Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
C PER
C PER Center for Advanced Power
Engineering Research 2017 Summer Research Planning Workshop
Energy Storage Technologies and Application Roadmap
Presented By:
Johan Enslin Zucker Family Graduate Education Center (ZFGEC)
Clemson University Restoration Institute (CURI)
C PER
Overview • Energy Storage – Global Growth Path
• Cost of Energy Storage
• Stacked Values and USE Cases
• Technology Capabilities
• Case Studies
– Tehachapi Energy Storage (SCE)
– Marshall Test Facility (Duke Energy)
• BESS Testing and Model Validation
• Roadmap Development with Value Chain
C PER
• 2015 growth 240% & 2017 growth expected 200% • Annual U.S. energy storage market projected to reach
1.7 GW by 2020 – with a value of $2.5B1 • Energy storage for solar systems expected to be an $8 B
market in 20262 • Acquisitions and mergers e.g. Siemens & AES (Fluence) • Energy storage is a key enabler for renewables, T&D grid
optimization and generation efficiency
1 Source: GTM Research 2 Lux Research Inc. 3 DOE (Energy Storage Exchange)
Global Energy Storage Development
- 171.05 GW 1,267 Projects
U.S. Energy Storage Development
- 24.2 GW with 570 MW in Battery Storage
Energy Storage: High Growth – High Potential
US Deployment Forecast, 2012- 2022E (MW)
C PER
Cost of Energy Storage
Source:- SolarPlaza
• Energy Storage is not cost effective in single USE cases • Stacked Values are crucial to make a cost effective
business case
Source: EPRI
C PER
Stacked Value Streams
Comparison of Storage Cost Compared to Individual Grid Service Benefits - No single business case
Benefit Stacking as a Simple Sum - Clear business case
*EPRI Energy Storage Valuation Tool
Energy Storage Service provider Opportunity
Integrate all possible services
C PER
Power-to-Power Use Cases
C PER
Application Requirements
C PER
Technology Capabilities
C PER
Tehachapi Energy Storage – Case Study • The project is strategically located in the Tehachapi Wind Resource Area.
– 4.5 GW of developed wind power by 2016 – State procurement target of 1.325 GW of energy storage capacity by 2020 – (CPUC AB 2514)
• Wind farm related grid reliability issues – Most of older wind farms in area are Type 1 turbines – 380 MW installed wind capacity (310 MW operation) – Absorb around 100 MVAr reactive power from system – No Low-Voltage-Ride-Through (LVRT) and reactive power support capability – Non-compliant with FERC - LGIP – Wind curtailment during high wind generation
• 66 kV line reliability – N-1 contingencies require
> 60 MW wind curtailment on daily basis – Angular stability concern during line trip – Existing SVC (14 MVAr) not reliable – Limited reactive power support on system
Configuration of Tehachapi Energy Storage Project 8MW/4hr Battery and 20 MVAr for 4 sec. STATCOM
Project investment is $35 M ($ 55 M final budget with M&V) ROI > 13% due to stacked values on USE cases:
• Transient stability mitigation for the N-1 contingency • 50 MW wind curtailment mitigation • Hourly wind dispatch of 50 MW wind farms • Voltage and frequency regulation • Avoided cost NPV = $3.2M p.a.
Ref:- Castaneda, J; Enslin, JHR; Elizondo, D; Abed, N; Teleke, S: “Application of STATCOM with Energy Storage for Wind Farm Integration” New Orleans, LA, USA, IEEE PES T&D Conference & Expo, 19-22 April 2010.
C PER
1 – Energy Time Shifting a) for system-level arbitrage b) for local operational constraint management c) based on forward-looking economic algorithm 2 – solar output PV smoothing and firming a) for local feeder voltage management b) solar-induced power swing mitigation 3 – active VAR / power factor management 4 – combined algorithms / optimization a) Combined Voltage Regulation, Energy time shifting and PV smoothing algorithms b) Use of distributed logic with economic, sub-station, forecasted and local input parameters
Battery container 750 kWh/250 kW Lithium Polymer Includes EMS.
Inverter/Controls Storage Management System (SMS) 1.25 MVA capacity/1.0 MVAR capacity
1.2 MW solar facility
1000 kVA transformer Steps up 480 V inverter output to 12.47 kV
Marshall Steam Station, Sherrills Ford, NC
System Attributes
Major system components: • 750 kWh / 250 kW system capacity • Kokam Superior Lithium Polymer Batteries • 1.25 MVA S&C Electric Company Inverter (SMS) • 1 MW PV solar test installation • Real-time control link to EPIC at UNCC
Interconnection: • Located on a 12.47 kV distribution circuit • Separate but adjacent medium-voltage interconnection from 1 MW solar facility • Located at the end of a distribution feeder
• Installed and in service July 2012
• Remote control and operation
• Battery and inverter independently sourced • Both vendors to Duke
• Located at the Marshall solar test site where multiple solar technologies are being field tested on a sealed coal-ash landfill • Develop and test new optimized control algorithms in cooperation with EPIC
Energy Storage – Stacked Value Algorithms
Applications Developed and Tested
C PER
PhaseStation
Regulator
Line
Regulator 1
Line
Regulator 2
A 3 15 14
B 4 15 9
C 4 15 14
A 2 5 6
B 4 5 10
C 4 5 10
No Voltage
Support
(1/26/2015)
BESS Voltage
Support
(1/27/2015)
Tap Operations
250 kW 750 kWh
Station Regulator
Line Regulator 1
Line Regulator 2
Voltage Support Algorithm Field Testing Results Development of Stacked Value Proposition for Storage
C PER
Battery
Saver Mode
Energy Arbitrage
(PLS)
PVCF
Accurate Prediction
of Feeder Peak Load
for Peak Load
Shaving
Charging Battery
during minimal
feeder load
Firmed PV
Station Output
PV Smoothing & Energy Time Shift Field Testing Results
Development of Stacked Value Proposition for Storage
C PER
Expert Energy Management System
Cloud State Pattern Recognition and Optimization
The framework is as follows-
• Characterize Cloud Cover Days.
• Criteria is built to identify each defined day type.
• Optimization routine
• Weather forecasts to identify next day cloud state
• Identify day type and adopt optimal values
C PER
Energy Storage Validation and Testing • Validate performance, efficiency, ancillary services.
• Demonstrate virtual inertia, primary and secondary frequency response.
1 MW, 510 kWh
Static Losses
Charge Discharge
Charge Discharge
Zoom in on low power levels
C PER
Example of Roadmap Development • Need and USE Case Development • Technology Assessment • Economic and Incentive Assessment • Financial and Stack-values
Assessment • Environmental Impact Assessment • Legal and Regulatory Assessment
Source:- “South Africa Energy Storage Technology and Market Assessment”, for USTDA, Activity Number: 2015-11032A, 2017.
Monitoring and Control· Energy Conversion
· System Control
· Grid Communication
Component
(cell & stack)
Manufacturing
Materials
Manufacturing
Raw Material
Mining and
Refining
Balance of Plant Systems / Container Assembly· Battery Management
· Safety / Containment
· Environmental Controls
Energy Storage Module
Module & Pack
Assembly
ESS System Integration and Construction
ESS Operation
ESS
Maintenance
and Renewal ES
S D
eco
mm
isio
nin
g a
nd
Re
cyclin
g
ESS Project Development and Finance
Energy Storage Value Chain
C PER
Conclusions
• Large growth in global energy storage deployments
• Energy Storage needs to be deployed to attract stacked values
• Technology and Energy Management System are key factors in
attracting stacked values with positive business case.
• Energy storage need to be validated and tested
• Roadmap with energy storage life-cycle analysis is key for positive
value chain.
C PER
Thank You. Questions?
Contact: Dr. Johan Enslin
Executive Director and
Duke Energy Smart Grid Endowed Chair
[email protected]; 843-730-5117
www.clemsonenergy.com