Upload
nam-sanchun
View
220
Download
0
Embed Size (px)
Citation preview
8/3/2019 CEC-500-2009-084
1/272
Arnold SchwarzeneggerGovernor
RENEWABLE ENERGYCOST OF GENERATION UPDATE
PIER
INTERIM
PROJECTREP
ORT
Prepared For:
California Energy CommissionPublic Interest Energy Research Program
Prepared By:KEMA, Inc.
August 2009CEC-500-2009-084
8/3/2019 CEC-500-2009-084
2/272
8/3/2019 CEC-500-2009-084
3/272
Prepared By:KEMA, Inc.Charles ODonnell, Pete Baumstark, Valerie Nibler, Karin Corfee, andKevin SullivanOakland, CA 94612Commission Contract No. 500-06-014Commission Work Authorization No: KEMA-06-020-P-R
Prepared For:
Public Interest Energy Research (PIER)
California Energy Commission
Cathy TurnerContract Manager
John Hingtgen, M.S.
Project Manager
Energy Generation Research Office
Kenneth Koyama
Office Manager
Energy Generation Research Office
Thom Kelly
Deputy Director
ENERGY RESEARCH & DEVELOPMENT DIVISION
Deputy Director
Melissa Jones
Executive Director
DISCLAIMER
This report was prepared as the result of work sponsored by the California Energy Commission. It does not necessarily represent the views of theEnergy Commission, its employees or the State of California. The Energy Commission, the State of California, its employees, contractors andsubcontractors make no warrant, express or implied, and assume no legal liability for the information in this report; nor does any party representthat the uses of this information will not infringe upon privately owned rights. This report has not been approved or disapproved by the CaliforniaEnergy Commission nor has the California Energy Commission passed upon the accuracy or adequacy of the information in this report.
8/3/2019 CEC-500-2009-084
4/272
8/3/2019 CEC-500-2009-084
5/272
i
Preface
TheCaliforniaEnergyCommissionsPublicInterestEnergyResearch(PIER)Programsupports
publicinterestenergyresearchanddevelopmentthatwillhelpimprovethequalityoflifein
Californiabybringingenvironmentallysafe,affordable,andreliableenergyservicesand
productstothemarketplace.
ThePIERProgramconductspublicinterestresearch,development,anddemonstration(RD&D)
projectstobenefitCalifornia.
ThePIERProgramstrivestoconductthemostpromisingpublicinterestenergyresearchby
partneringwithRD&Dentities,includingindividuals,businesses,utilities,andpublicor
privateresearchinstitutions.
PIERfundingeffortsarefocusedonthefollowingRD&Dprogramareas:
BuildingsEndUseEnergyEfficiency
EnergyInnovationsSmallGrants
EnergyRelatedEnvironmentalResearch
EnergySystemsIntegration
EnvironmentallyPreferredAdvancedGeneration
Industrial/Agricultural/WaterEndUseEnergyEfficiency
RenewableEnergyTechnologies
Transportation
RenewableEnergyCostofGenerationUpdateistheinterimreportfortheRenewableEnergyCost
ofGenerationUpdateproject(ContractNumber50006014,workauthorizationnumber
KEMA06020PR)conductedbyKEMA,Inc.Theinformationfromthisprojectcontributesto
PIERsRenewableEnergyTechnologiesProgram.
FormoreinformationaboutthePIERProgram,pleasevisittheEnergyCommissionswebsiteat
www.energy.ca.gov/research/orcontacttheEnergyCommissionat9166544878.
Acknowledgement
GerryBraun,PIERtechnicalconsultant,isacknowledgedforhisinvaluabletechnicalguidanceandreviewofthisproject.
Pleaseusethefollowingcitationforthisreport:
ODonnell,Charles,PeteBaumstark,ValerieNibler,KarinCorfee,andKevinSullivan(KEMA).
2009.RenewableEnergyCostofGenerationUpdate,PIERInterimProjectReport.CaliforniaEnergy
Commission.CEC5002009084.
8/3/2019 CEC-500-2009-084
6/272
ii
8/3/2019 CEC-500-2009-084
7/272
iii
Table of Contents
ExecutiveSummary........................................................................................................................... 11.0 Introduction.......................................................................................................................... 32.0 ProjectApproach................................................................................................................. 5
2.1. Task1: Technologies..................................................................................................... 52.2. Task2: CostDrivers...................................................................................................... 62.3. Task3: CurrentCosts.................................................................................................... 62.4. Task4: ExpectedCostTrajectories.............................................................................. 7
2.4.1. Method....................................................................................................................... 92.5. Task5:Price/CostReconciliation................................................................................. 102.6. Task6:CommunityandBuildingScaleRenewableEnergy Costs........................ 11
3.0 ProjectOutcomes................................................................................................................. 133.1. Technologies................................................................................................................... 13
3.1.1. TechnicalandAnalyticalCritiqueofReferenceDocuments.............................. 133.1.2. MethodforSelectingTechnologies........................................................................ 223.1.3. UtilityScaleTechnologies....................................................................................... 233.1.4. CommunityScaleTechnologies............................................................................. 243.1.5. BuildingScaleTechnologies.................................................................................... 24
3.2. Biomass............................................................................................................................ 243.2.1. TechnologyOverview.............................................................................................. 243.2.2. BiomassCombustionFluidizedBedBoiler........................................................ 273.2.3. BiomassCombustionStokerBoiler..................................................................... 353.2.4. BiomassCofiring....................................................................................................... 423.2.5. BiomassCoGasificationIGCC............................................................................... 47
3.3. Geothermal...................................................................................................................... 523.3.1. TechnologyOverview.............................................................................................. 523.3.2. GeothermalBinary................................................................................................. 593.3.3.
Geothermal
Flash
...................................................................................................
68
3.4. Hydropower.................................................................................................................... 72
3.4.1. TechnologyOverview.............................................................................................. 723.4.2. HydroDevelopedSitesWithoutPower............................................................. 753.4.3. HydroCapacityUpgradeforDevelopedSitesWithPower............................ 80
3.5. Solar.................................................................................................................................. 84
8/3/2019 CEC-500-2009-084
8/272
iv
3.5.1. TechnologyOverview.............................................................................................. 843.5.2. SolarParabolicTrough.......................................................................................... 863.5.3. SolarPhotovoltaic(SingleAxis).......................................................................... 96
3.6. Wind................................................................................................................................. 1023.6.1. TechnologyOverview.............................................................................................. 1023.6.2. OnshoreWindClass5........................................................................................... 1063.6.3. OnshoreWindClass3/4........................................................................................ 1173.6.4. OffshoreWindClass5........................................................................................... 117
3.7. Wave................................................................................................................................ 1233.7.1. TechnologyOverview.............................................................................................. 1233.7.2. OceanWave............................................................................................................... 125
3.8. IntegratedGasificationCombinedCycle................................................................... 1273.8.1. TechnologyOverview.............................................................................................. 1273.8.2. IGCCWithoutCarbonCapture(SingleorMultiple300MWTrains)...............1303.8.3. CarbonCaptureandSequestration........................................................................ 136
3.9. AdvancedNuclear......................................................................................................... 1383.9.1. TechnologyOverview.............................................................................................. 1383.9.2. WESTINGHOUSEAP1000................................................................................... 143
4.0 ConclusionsandRecommendations................................................................................. 1575.0 References............................................................................................................................. 1596.0 Glossary................................................................................................................................ 167AppendixA CostData
AppendixB ResponsestoWorkshopComments
List of Figures
Figure1.Utilityscalefluidizedbedgasifier........................................................................................ 25
Figure2.BiomassIGCCplantrepresentation...................................................................................... 26
Figure3.SchematicdiagramofbiomassIGCCprocess..................................................................... 26
Figure4.Utilityscalebiomassfluidizedbedgasifier......................................................................... 27
Figure5.Circulatingfluidizedbedschematicdiagram..................................................................... 28
Figure6.Bubblingfluidizedbedboiler................................................................................................ 30
8/3/2019 CEC-500-2009-084
9/272
v
Figure7.Stokerboilerschematicdiagram........................................................................................... 35
Figure8.Flowschematicforastokerboilerconfiguration................................................................ 37
Figure9.Biomasscofiringschematicforapulverizedcoalboilersystem...................................... 42
Figure10.
Primary
biomass
cofiring
locations
.....................................................................................
44
Figure11.ProcessflowdiagramforbiomassgasificationandconditioningforIGCCapplication
............................................................................................................................................................ 49
Figure12.Binarypowerplant................................................................................................................ 58
Figure13.Flashpowerplant.................................................................................................................. 58
Figure14.Financialimpactofdelayonexplorationcosts................................................................. 62
Figure15.Specificcostofpowerplantequipmentvs.resourcetemperature................................. 61
Figure16.
Economies
of
scale
.................................................................................................................
63
Figure17.Impoundmenthydropower................................................................................................. 73
Figure18.Diversionhydropowerfacility............................................................................................ 74
Figure19.Runofriverhydropowerfacility........................................................................................ 75
Figure20.Hydropowercostsfordevelopedsiteswithoutpower.................................................... 78
Figure21.Hydropowercostsforincreasingcapacity......................................................................... 82
Figure22.Solarparabolictroughelectricgeneratingsystem............................................................ 84
Figure23.Simplifiedmoltensaltstorageprocessdiagram............................................................... 85
Figure24.NellisAirForceBasePVinstallation.................................................................................. 86
Figure25.Majorcostcategoriesforparabolictroughplant.............................................................. 91
Figure26Capitalcostcomparison........................................................................................................ 94
Figure27.LevelizedO&Mcostcomparison........................................................................................ 95
Figure28.Solarmoduleretail/priceindex,125wattsandhigher..................................................... 99
Figure29.Solarpowergenerationplantsince2006over20%cheaper.......................................... 100
Figure30.Typicalturnkeysystemprice............................................................................................. 101
Figure31.Amodern1.5MWwindturbineinstalledinawindpowerplant............................... 102
Figure32.Californiawindresourcemap........................................................................................... 103
Figure33.WindresourcemapofNorthernCalifornia..................................................................... 104
Figure34.WindresourcemapofSouthernCalifornia..................................................................... 105
8/3/2019 CEC-500-2009-084
10/272
vi
Figure35.CapacityfactortrendsofCaliforniautilitywindsites................................................... 106
Figure36.Installedwindprojectcostsovertime.............................................................................. 109
Figure37.MetalpricesJan.2002Sept.2007(LondonMetalExchange)..................................... 111
Figure38.
U.S.
dollar
vs.
euro,
Jan.
1999
through
April
2009
(European
Central
Bank)
.............
112
Figure39.2007Projectcapacityfactorsbycommercialoperationdate......................................... 112
Figure40.Onshorecapacityfactorbyinstalledyearandclass....................................................... 113
Figure41.AnnualandcumulativegrowthinU.S.windpowercapacity..................................... 114
Figure42.Averagecumulativewindandwholesalepowerpricesovertime.............................. 114
Figure43.Installedwindprojectcostsasafunctionofprojectsize:20062007projects.............115
Figure44.Europeanoffshorewindinstallations............................................................................... 118
Figure45.Europeanoffshorewindgrowthandprojections........................................................... 120
Figure46.Offshorecapacityfactorbyinstalledyear........................................................................ 122
Figure47.Pointabsorber...................................................................................................................... 124
Figure48.Oscillatingwatercolumn................................................................................................... 124
Figure49.Overtopping......................................................................................................................... 124
Figure50.Attenuator............................................................................................................................. 125
Figure51.TypicaloxygenblownIGCCprocess............................................................................... 128
Figure 52. Actual installation (Buggenum, The Netherlands) with typical technological
componentsindicated................................................................................................................... 129
Figure53.BureauofReclamationconstructioncosttrends............................................................. 134
Figure54.Actualvs.PredictedNuclearReactorCapitalCosts...................................................... 139
Figure55:PowerCapitalCostIndexNuclearandNonNuclearConstruction......................... 141
Figure56.Generationsofnuclearenergy........................................................................................... 149
List of Tables
Table1.RecentCalifornialegislationthatmayaffectcostofgeneration.......................................... 1
Table2.Costdriveranalysisworksheetexample................................................................................. 9
Table3.Comparisonbetween2009KEMAanalysisand2007IEPR................................................ 16
8/3/2019 CEC-500-2009-084
11/272
vii
Table4.Comparisonof2009analysiswiththeCPUCGHGmodeldata........................................ 18
Table5.Comparisonbetween2009analysiswiththeRETI1AData............................................... 20
Table6.CentralplanttechnologylistforCOGmodelingproject..................................................... 23
Table7.
Installed
CFB
boiler
capacity
by
country
...............................................................................
29
Table8.Recentcarbonsteelpricing...................................................................................................... 31
Table9.Recentcarbonsteelpricing...................................................................................................... 38
Table10.Biomassstokerinstalledcostranges2009dollarsperkWinstalled............................. 41
Table11.Coalfiredgenerationplantswithbiomasscofiring........................................................... 43
Table12.PotentialbinarygeothermalplantdevelopmentinCalifornia(mostlikelysources)....64
Table13.CaliforniaandNevadaexistingbinaryplantswithcapacityfactor................................ 65
Table14.FixedandvariableO&Mforbinarygeothermalpowerplants........................................ 66
Table15.PotentialflashgeothermalplantdevelopmentinCalifornia(mostlikelysources).......69
Table16.CaliforniaandNevadaexistingflashplantswithcapacityfactor................................... 70
Table17.FixedandvariableO&Mforflashgeothermalpowerplants........................................... 71
Table18.Parabolictroughcostcomparison......................................................................................... 89
Table19.Assessmentofparabolictroughandpowertowersolartechnology.............................. 91
Table20.Comparisonoftotalinvestmentcostestimates($/kWe):SunLabvs.S&L..................... 94
Table21.CSPplantcapitalcostbreakdowns,2005............................................................................. 95
Table22.AnnualCSPO&Mcostbreakdowns,2005.......................................................................... 96
Table23.Californiautilitywindplantinstallationssince2003....................................................... 108
Table24.Sizedistributionandnumberofturbinesovertime........................................................ 113
Table25.Oceanwaveenergycostdata.............................................................................................. 127
Table26.GasificationbasedpowerplantprojectsunderconsiderationintheU.S.beyond2010
.......................................................................................................................................................... 131
Table27.Expectednewnuclearpowerplantapplications.............................................................. 145
Table28.OperatorsofU.S.reactors.................................................................................................... 147
Table29.Nucleardecommissioningcosts.......................................................................................... 154
Table30.Nuclearplantconstructionspendingprofile(%oftotalinstantcostperyear)...........156
8/3/2019 CEC-500-2009-084
12/272
viii
8/3/2019 CEC-500-2009-084
13/272
ix
Abstract
This2009reportupdatesthecostofgeneratingelectricityfortechnologiesifbuiltinCalifornia.
CaliforniaEnergyCommissionstaffprovidesfactorsthataffectcosts,includingcost
assumptions,for15renewabletechnologies,coalintegratedgasification,combinedcycle,and
nuclearpowergenerationalternativesforutilityscalegenerationtechnologies.Thesecostsare
usefulinevaluatingthefinancialfeasibilityofagenerationtechnologyandforcomparingthe
costsofbuildingandoperatingoneparticularenergytechnologywithanother.Theseestimates
updatethe2007costofgeneration,basedonempiricaldatacollectedfromoperatingfacilities,
researchfromprimarysources,actualcostsandsurveysofexpectedcostsfromexpertsinthe
field,andreferencedocuments.Thisreportdetailsarangeofinstantandinstalledcostswith
projectedcostsbasedontwoyearsofsignificantgrowthinrenewabletechnologies,changesin
materialcosts,andinflation.
Keywords:Renewableenergy,costofgeneration,biomass,geothermal,hydropower,solar,
parabolictrough,photovoltaic,PV,thermalsolar,windenergy,oceanwave,integrated
gasificationcombinedcycle,IGCC,nuclear
8/3/2019 CEC-500-2009-084
14/272
x
8/3/2019 CEC-500-2009-084
15/272
1
Executive Summary
ThisstudyexaminesthecostsofrenewableelectricitygenerationinCaliforniatosupportthe
costofgenerationmodelingworkoftheElectricityAnalysisOffice. Inadditiontorenewable
electricitycostofgenerationassessment,nuclearandintegratedgasificationcombinedcycle
generation
are
also
examined.
The
California
Energy
Commission
is
tasked
with
developing
robustcostofgenerationestimates,backedbysolidresearchleveragingthefullassessmentof
previousresearchonthecostofgeneration,costdriversandtrends,andexpectedcost
trajectoriesforfuturecosts. AllofthesedataarethenusedbytheEnergyCommissionto
estimatethelevelizedcostofgenerationbytechnology.1
Inthelastseveralyears,Californiahasexperiencedtremendousactivityintherenewable
energymarket,largelydrivenbyseveralkeypiecesoflegislation. Thefollowingtableoutlines
somerecentlegislationthathasbeenadoptedthatislikelytohaveasignificantimpactonthe
costofgenerationforrenewablesaswellasconventionalgeneration.
Table 1. Recent California Legislation That May Affect Cost of Generation
Bill Author YearPassed
Summary
SB1 Murray
(Chapter
132)
2006 SB 1 establishes in statute the California Solar Initiative with a
goal of 3,000 megawatts of new solar produced electricity by
the end of 2016. The California Solar Initiative Program has a
$3.35 billion budget that will be administered by the California
Public Utilities Commission, Energy Commission, and publicly
owned utilities.
SB 107 Simitian
(Chapter
464)
2006 SB 107 accelerates Californias Renewables Portfolio
Standard targets by requiring Californias retail sellers of
electricity to increase renewable energy purchases by at least1 percent per year with a target of 20 percent renewable
energy by 2010. It also requires the publicly owned utilities to
file reports with the Energy Commission that outline their
specific Renewables Portfolio Standard goals and progress
towards the goals.
SB
1250
Perata
(Chapter
512)
2006 SB 1250, combined with SB 107, continues the authorization
of the Energy Commissions ongoing use of public goods
charge funds for the period of 2007-2012 for the continued
operation of the Energy Commissions Renewable Energy
Program.
AB2189
Blakeslee(Chapter
747)
2006 AB 2189 modifies the Renewables Portfolio Standardeligibility requirements for small hydroelectric generation
facilities regarding efficiency improvements that result in
increased capacity.
1Levelizedcostistheconstantannualcostthatisequivalentonapresentvaluebasistotheactualannual
costs,whicharethemselvesvariable.
8/3/2019 CEC-500-2009-084
16/272
2
Bill Author YearPassed
Summary
AB 32 Nez 2006 Global Warming Solutions Act sets mandatory targets for
greenhouse gas emission reductions. Commits to reducing
greenhouse gas emissions to 2000 levels by 2010 (11 percent
below business as usual), to 1990 levels by 2020 (25 percentbelow business as usual), and 80 percent below 1990 levels
by 2050. Requires the California Air Resources Board and
the Energy Commission to determine baselines and create
systems to track greenhouse gas emissions.
Source: California Energy Commission
TheambitiousgoalsaRenewablesPortfolioStandardof20percentby2010and33percentby
2020,3,000megawatts(MW)ofphotovoltaicsinstalledwithinadecade,andan11percent
reductioningreenhousegasemissionsby2010areambitiousbutachievable.
TheEnergyCommissionsworkinthepreviousintegratedenergypolicyreportsconfirmthat
thetechnicalpotentialforrenewablesinCaliforniaandtheWesternElectricityCoordinatingCouncilregiondwarfsthesegoals. Inaddition,developersofrenewableenergypowerplants
andthesolarphotovoltaicindustryhaverespondedtoincreaseddemandforrenewableenergy
withenthusiasm. TheEnergyCommissionintendstobridgetheestablishedpolicybackdrop
andthesurgingrenewablemarkettoconverttechnicalpotentialintoreality.
KEMA,Inc.(KEMA)performedadetailedassessmentofthegenerationtechnologiesthatmight
beavailableinthenext20years. Foreachtechnology,KEMAassessedcostdriversandtrends
todevelopinputvariablesfortheEnergyCommissionslevelizedcostmodel. Toprovidethis
information,researchersperformedthefollowing:
Literaturereview
and
identification
of
renewable
energy
and
two
non
renewable
energy
technologieslikelytobedeployedinCaliforniaoverthenext20years,alongwith
identificationofthescaleatwhichtheyarelikelytobedeployed.
Costdriversandtrendanalysisforeachlikelycontributingtechnologyandanalysisof
factorsthatdeterminetherange(high,average,andlow)ofexpectedcosts.
Costmodelinputforutilityscaletechnologies,includingcurrentnominalcostsand
plausibleminimumandmaximumcostsforeachutilityscaletechnology,brokendown
intoinputvariablesthatareusedintheEnergyCommissionslevelizedcostanalysis.
Expectedpathsforfuturecostsforutilityscalegenerationtechnologies,plusa
discussionoffactorsthatdeterminethesecosts,asthebasisforcalculatinglevelized
energycosts.
Thefourtopicslistedaboveareaddressedforutilityscaletechnologiesintheinterimproject
report. Thefinalprojectreportwillalsoaddresscommunityandbuildingscaletechnologiesas
wellassummarizekeyfindingsandrecommendations.
8/3/2019 CEC-500-2009-084
17/272
3
1.0 Introduction
RenewableenergydeploymentinCaliforniaisexpectedtoaccelerateintheneartermin
responsetolegislationidentifyingsupplyportfoliotargetsandclimatemitigationtargets.
Relatedpolicydevelopmentmustbebasedonthebestpossibleeconomicinformation,
especiallythecostofbulkrenewableenergyelectricitygeneration. Inaddition,twonon
renewableenergytechnologiesareexaminedinsupportofthecostofgenerationmodeling
workoftheElectricityAnalysisOfficeandascomparisonstotherenewableenergy
technologies. Thetwononrenewableenergytechnologiesincludedinthisreportarenuclear
andintegratedgasificationcombinedcycle(IGCC). Toprovidethisinformation,four
fundamentaltopicswereaddressed:
Literaturereviewandidentificationofrenewableenergyandtwononrenewableenergy
technologieslikelytobedeployedinCaliforniaoverthenext20years,alongwith
identificationoftheinfrastructurescalesatwhichtheyarelikelytobedeployed.
Costdriversandtrendanalysisforeachlikelycontributingtechnologyandquantitative
analysisoffactorsthatdeterminetherangeofexpectedcosts.
Costmodelinputforutilityscaletechnologies,includingcurrentnominalcostsand
plausibleminimumandmaximumcostsforeachutilityscaletechnology,brokendown
intocategoriesthatareusedinCaliforniaEnergyCommission(EnergyCommission)
levelizedcostanalysis.
Expectedpathsforfuturecostsforutilityscalegenerationtechnologies,plus
quantitativediscussionoffactorsthatdeterminethesecosts,asthebasisforcalculating
levelizedenergycosts.
Thefourtopicslistedaboveareaddressedforutilityscaletechnologiesintheinterimproject
report. Thefinalprojectreportwillalsoaddresscommunityandbuildingscaletechnologies
andthefollowingtwotopics:
Reconciliationofcurrentlyquotedforwardenergypricesandcurrentlyestimated
levelizedcosts,discussingtherelativeimpactofvariousfactorsotherthanovernight
constructioncostthatdeterminepricing. Reconciliationherereferstoexplainingthe
differencesbetweenpricesandcosts,identifyingthefactorsthataccountforthe
differences,andprovidingestimatesofthesizesofthesefactors.
Costsandcosttrajectoriesforcommunityandbuildingscalerenewableenergytechnologies,alongwithminimumandmaximumcostsandtrajectoriesforthesescales.
Theprojectwasundertakentoachievethefollowingobjectives:
Criticallyreview,adjustandaugmentthecontentofAppendixBofEnergyCommission
Report#CEC2002007011SF,December2007(ComparativeCostsofCaliforniaCentral
8/3/2019 CEC-500-2009-084
18/272
4
StationElectricityGenerationTechnologies,KleinandRednam)inordertocreate
comparableinformationforthe2009IntegratedEnergyPolicyReport(IEPR).
UpdaterenewableenergyandnonrenewableenergyinputsforuseintheEnergy
CommissionsCostofGenerationModel,usedinpreparingthe2009IEPR.
Reconcile
price
and
cost
information
for
representative
utility
scale
power
purchases.
Estimatecostsandtrajectoriesforcommunityandbuildingscaletechnologies.
Thefollowingsectiondescribestheprojectapproachfollowedbyasectiononprojectoutcomes.
TheProjectOutcomessectionofthereportincludesanintroductiontothetechnologiesthat
wereselectedwiththesectionsfollowingorganizedbytechnology.
8/3/2019 CEC-500-2009-084
19/272
5
2.0 Project Approach
Thissectiondiscussesthetaskstheresearchteamundertookandwhattheteamdidto
accomplishtheprojectobjectives.
2.1. Task 1: Technologies
Theresearchteamundertookthefollowingactivities:
Conductedatechnicalandanalyticalcritiqueofreferencedocuments,including:
ComparativeCostsofCaliforniaCentralStationElectricityGeneration
Technologies2publishedbytheCaliforniaEnergyCommissioninDecember
2007.
CostsandsupplycurvesgeneratedinsupportofCaliforniaPublicUtilities
Commission(CPUC)GreenhouseGas(GHG)ModelingProject.Finalresultsand
GHGCalculatorv2bfromE3.3
CostsestimatesfoundandusedintheRETIPhase1Aand1BreportsbyBlack&
VeatchinRenewableEnergyTransmissionInitiativePhase1A.4
RecommendedutilityscaleREtechnologiesforcostanalysiswithtechnicalandmarket
justification. UtilityscaleREtechnologiesaregenerallydefinedasthoseover20MW.
Identifiedtheprimaryexistingcommercialembodimentofeachutilityscaletechnology
inCalifornia.Thetermcommercialembodimentisintendedtodescribethemost
prevalentcommerciallyavailableapplicationofatechnology.Asanexample,inthecase
ofsolarthermalpower,theprimaryexistingapplicationisconcentratingparabolic
troughcollectors,
augmented
by
natural
gas
fired
boilers
and
supplying
heat
to
steam
Rankinepowerplantsinthe50MWto80MWsizerange.
Identifiedtheexpectedprimarycommercialembodimentin2018.
TheresearchteamwillrevisitTask1forthecommunityandbuildingscaletechnologiesinthe
secondphaseoftheprojectandincludefindingsinthefinalprojectreport.
2Klein,JoelandAnithaRednam.ComparativeCostsofCaliforniaCentralStationElectricityGeneration
Technologies.CaliforniaEnergyCommission,ElectricitySupplyAnalysisDivision,CEC2002007011,
December2007.http://www.energy.ca.gov/2007publications/CEC2002007011/CEC2002007011
SF.PDF.
3GHGCalculatorv2b,updatedon5/13/08.http://www.ethree.com/CPUC_GHG_Model.html.
4Black&Veatch.RenewableEnergyTransmissionInitiativePhase1A(DraftReport).Black&Veatch,RETI
StakeholderSteeringCommittee,ProjectNumber149148.0010,March2008.
http://www.energy.ca.gov/2008publications/RETI10002008001/RETI10002008001D.PDF.
8/3/2019 CEC-500-2009-084
20/272
6
Pleasealsonotethatthisstudyprovidesestimatesforcostofgenerationtechnologiesbutdoes
notprovidelevelizedlifecyclecostestimatesforthevariousenergytechnologies.5
2.2. Task 2: Cost Drivers
ForeachoftheutilityscaletechnologiesidentifiedinTask1,theresearchteamidentified:
MarketandindustrychangessinceAugust2007thathavemateriallyaffectedcosts.
Currenttrendsthatwillmateriallyaffectfuturecosts.
PrimarygeneralandCaliforniaspecificcostdrivers(e.g.,plantscale,globalindustry
manufacturingscale,resourcequality,plantlocation,capacityfactorincaseofstorage
coupledplants,overnightcost).
2.3. Task 3: Current Costs
ForeachoftheutilityscaletechnologiesidentifiedinTask1,theresearchteamidentified:
Nominal2009costsintheformatrequiredfortheEnergyCommissionslevelizedCost
ofGenerationmodel.
Plausibleminimum,average,andmaximumcostswithtechnicaljustification. Tothe
extentpossible,plausiblemaximumisdefinedasacostmorethanonecompetitive
playerwouldbewillingtopay,andplausibleminimumisdefinedasistheleastcost
recordedabsenthiddensubsidies. Insomecases,uniquesitecharacteristicswerealso
considered.
Theprocessforcompilingdataoftheplausibleminimum,average,andmaximumcostcases
wasdiscussedbetweentheresearchteamandEnergyCommissionstaff. Establishingranges
betweenminimum,average,andmaximumcostscircumscribestherangeofmarketcoststhatwouldreasonablybeencounteredintheactualdevelopment,construction,andoperation
withineachtechnology.
Foreachtechnology,sizerangeswereidentifiedfortotalplantcapacitytodetermineminimum,
average,andmaximumplantcapacitiesinmegawatts(MW). Plantcapacityfactorsandforced
outagerateswerealsodefinedusingminimum,average,andmaximumvalues,reflectingthe
rangesidentifiedthroughresearchedvalues. NorthAmericanEnergyReliabilityCorporation
(NERC)/GeneratingAvailabilityDataSystem(GADS)fleetreliabilitydatawereusedfor
technologieswheredatawasavailable,andinthecaseofwind,solar,andbiomasstechnologies,
otherresearchsourceswereidentified. Plantheatratesandfuelusagedataweresimilarly
modeledforlow/average/highcases,basedonactualoperatingplantcharacteristics;datawas
compiledforeachfossiltechnologyfuelusagereflectinginservicevaluesforgeneratingplants.
5Levelizedlifecyclecostestimatesincludethetotalcostofaprojectfromconstructiontoretirementand
decommissioning.Theresearchteamscostestimatesfornuclearenergydonotincludenuclearplant
decommissioningandwastedisposalcosts.
8/3/2019 CEC-500-2009-084
21/272
7
Fuelcostestimateswerederivedwithrangesforeachfueltypebasedonpublishedstudiesand
datafromcoal,naturalgas,uranium,andbiomass.
Overnightandinstalledcapitalcostvaluesforminimum,average,andmaximumcostswere
definedthroughtwoapproaches. Forovernightcosts,capitalcostrangesweredeveloped
throughdocumented
plant
cost
histories
and
adjusted
for
capacity
scaling
effects,
noting
that
theovernightcostperkilowattdependsonthetotalcapacityoftheplant. Furtheradjustments
toovernightcostweremadetoreflectthecostdriveranalysis,showinglearningeffectsof
cumulativegeneration. Theseexperiencecurveeffectswerereflectedontheyeartoyear
overnightcostswithinthegenerationtechnologydataset.
Forinstalledcapitalcostvalues,thelow/average/highcasesweredevelopedprimarilythrough
theuseofdifferingconstructiontimedurationswheresuchdatacouldbeverifiedbythe
researchteam. Thisdatareflectstheuncertaintyinconcepttocompletiontimeforeach
technologyandresultsincostimpactduetoadditionalinterestcostsandallowanceforfunds
usedduringconstructioncharges(AFUDC).
Theuseandapplicationofrenewableenergyandothertaxincentiveswerealsoconsideredand
modeledwiththeinputdatasettodeveloplow/average/highcostdatavalues. Thesetax
incentiveswereappliedforeachtechnology,basedontheircurrentvalidityandspecific
applicationforeachtechnology.
Thedatasetcontainscellsforlow/average/highvaluesforeachinputtothecostofgeneration
model,andeachspecificinputismodeledwithitsownlow/average/highcostrange. Onemay
notdrawtheconclusionthatthesecostsarespecifictoaparticularsizeprojectforexample,
thelowplantcapacityautomaticallygeneratesthehighestoperatingcost. Instead,thedatasets
werecompiledsothateachtechnologydimension(e.g.,capacity,forcedoutagerate,heatrate,
overnightcost)
has
its
own
low/average/high
range
and
is
not
associated
with
arelative
capacityorsizeproject.Inthatway,thedataismodeledsuchthattherangeofinputsdefining
low/average/highcostsreflectboundariesforeachtechnology;andtheminimumcost
representsthelowestplausiblerangeofcost,andthemaximumcostrepresentsthehighest
plausiblerangeofcostforeachtechnology.
2.4. Task 4: Expected Cost Trajectories
Theresearchteamdevelopedaspreadsheetmodelusingcostdriverinformationtoestimate
futurecosttrajectories(costsexpectedineachyearfrom20092029)oftherecommendedutility
scaletechnologiesidentifiedinTask1.
Thespreadsheetmodeltodevelopexpectedcosttrajectoriesforeachtechnologywasdeveloped
usingtheconceptoflearningeffectsandtheexperiencecurve. Experiencecurvesareusedin
developingtechnologypolicybecausetheyshowthemarketeffectsofincreasedcumulative
production. Asthemarketadoptsanewenergytechnology,manufacturersgaineconomiesof
scaleduetoincreasedproduction,andtheylearnhowtoimprovethetechnology. Bothofthese
factorsovertimecanlowerunitcostsofproduction.
8/3/2019 CEC-500-2009-084
22/272
8
Theprimarydefinitionofexperiencecurveeffectsiscapturedinwhatistermedtheprogress
ratioforatechnology. Simplyput,theprogressratioistheexpectedpercentagedecreasein
unitcost,basedonadoublingofcumulativeoutputofthattechnology. Asanexample,a
technologythathasaprogressratioof0.90wouldindicatethatadoublingofinstalledunitsfor
thattechnologychoicewouldresultina10%unitcostreduction.6
Energytechnologiesgenerallyhavetechnologyprogressratiosintherangefrom0.70to1.00,
withthelowernumberindicatingarapidlearningrateandloweringofunitcostsovertime
(newtechnologydeployment)andprogressratiosclosetounityreflectingextremelymature
technologieswithonlysmall,incrementallearningeffects.
Theresearchteamnotedthatitispossiblefortechnologiestoexhibitchangesinprogressratios
overtime,duetoseveralfactors:
DisruptiveTechnologyAdvancesbreakthroughdevelopmentsinatechnologythat
significantlyaffectunitcostand/orpaceoflearningforamanufacturer.
Price
Subsidies
Artificial
price
subsidies
can
alter
the
balance
between
experience
and
learning,andmitigatelearningeffects,sincethepricesignalisnotatruecompetitive
marketsignal.
ChangesinMacroeconomicFundamentalsTheycanaffectsupply/demandbalance
andadoptionratesoftechnologies,enhancingorinhibitinglearningeffectsofadditional
production.
Thesechangesovertimedemonstratethatonevalueforprogressratioandexperienceeffectsis
generallynotsuitableformodelingtheexperiencecurveovertime,especiallyforthose
technologieswithhighlearningeffects. Theresearchteamthusmodeledarangeoflearning
effects,withdocumentedprogressratiosforeachtechnologymodifiedthroughtheuseofkey
costdriversthatwereidentifiedforeachtechnologychoice.
Inthemodelingoftheselearningeffects,thetechnologyprogressratioandexperienceeffects,
whichtypicallyrangefrom0.70to1.00,weremodifiedthroughtheuseofcostdriverratesof
changeratios. Thesecostdriverratiosbeginatunity(1.00)asabasecase,whichreflectsthe
normal,expectedexperiencecurve,andtheratioscanbeweightedasgreaterthanunity,which
implyalesserlearningeffect,orlessthanunity,whichimplyagreater,acceleratedlearning
effectthanthenormalexperiencecurve.
Costdriversweresubjectivelyevaluatedbasedontwofactors: importanceweighting(how
importantthedriveristothetechnologycostimprovement)andlow/highrangestoreflectthe
subjectivevariationinlearningeffect. Foreachtechnologyandtheresearchedtechnology
6InternationalEnergyAgency.ExperienceCurvesforEnergyTechnologyPolicy.OrganizationofEconomic
CooperationandDevelopment(OECD),2000.
8/3/2019 CEC-500-2009-084
23/272
9
progressratio,eachcostdriverwasmodeledatunityfortheaveragecaseandthenmodifiedfor
thelow/highcasesbasedontheresearchteamtechnicalfindingsandjudgment.
Amodifiedprogressratio,calculatedastheproductoftheexpectedtechnologyexperience
curve(shownasTechnologyProgressRatiointheexamplebelow)andtheweightedaverage
costdriver
effect,
combines
the
effects
of
the
baseline
technology
experience
curve
and
identifiedcostdriversthatmighteitheraccelerateordeceleratethecostimprovements
associatedwithanincreaseinthecumulativeinstalledbaseforeachtechnology. Thismodified
progressratioisusedforfinalcostmodelingforeachtechnology.
Theweightedaveragecasesforlow/average/highcostdrivereffectsusingthemodified
progressratiowerethenmodeledusingthestandardexperiencecurveequationandyearover
yearpricechangesidentified. Thesepricechangeswereusedtodeveloptheforecasted
overnightcostsforeachtechnology.
2.4.1. Method
Theexperiencecurveeffectsandcostdriversweredevelopedforeachtechnologybycombining
theexpectedvariabilityinidentifiedcostdriverswiththepublisheddatareflectingtheexpected
learningcurveeffectsforeachrenewableenergytechnology,aspublishedbytheU.S.
DepartmentofEnergy(DOE)andotherindustrysources. Theresearchteammodifiedthe
experiencecurveeffectsbytheweightedimpacteachcostdrivercouldhaveonthetechnology
anditscosttrajectory.
AmodelwasdevelopedtocalculatetheseimpactsandisshownbelowinTable2:
Table 2. Cost Driver Analysis Worksheet Example
Cost Driver Analysis
Technology: Onshore Wind 7
Technology Progress Ratio: 0.900
Rate of Change
Cost Driver Percentage Low Average High
1 Turbine Costs 75.0% 0.95 1.00 1.10
2 Reliability 10.0% 0.97 1.00 1.04
3 Permitting/Site Selection 5.0% 0.98 1.00 1.02
4 Land Acquisition 5.0% 0.99 1.00 1.01
5 Transmission Costs 5.0% 0.97 1.00 1.10
Total and Averages: 100.0% 0.96 1.00 1.09
Modified Progress Ratio: 0.86 0.90 0.98
Source: KEMA
Forexample,theabovesheetshowsthecalculationsmadefortheonshorewindrenewable
technology. Thetechnologyprogressratioforonshorewindisidentifiedas0.90asabaseline
8/3/2019 CEC-500-2009-084
24/272
10
fromindustrypublisheddata.7 Thisbaselinevalueforexperiencecurveeffectsisthen
subjectivelyadjustedbyeachcostdriverratio,andthenaweightedaverageistakenthattakes
thesubjectiveeffectsofthesecostdriversintoaccount.
Thecalculatedweightedaverageisthenshownasthemodifiedprogressratio,ortheexpected
rangein
learning
curve
effects
with
additional
cumulative
capacity
over
time.
In
the
case
above,theexpectedrangeinmodifiedprogressratioisfromalowvalueof0.86toahighvalue
of0.98,whichimpliesthatwithadoublingofoverallinstalledcapacity,theexpecteddecrease
incostswouldbebetween2%and14%,withanaverageexpecteddecreaseof10%.
Thenextstepincomputingexperiencecurveeffectsandoverallcosttrajectoriesisdeveloping
reliableestimatesforcumulativeinstalledcapacityforeachtechnology. Thiswasdonethrough
twoprimaryresearchsources:theEnergyInformationAdministrations(EIA)AnnualEnergy
Outlookfor20098andEuropeanWindEnergyAssociations(EWEA)PurePowerreport,9
whichprovidesglobaldataforoffshorewindtechnologyadoption. Cumulativeinstalled
capacityforecastswerecompiledforeachtechnologyusingthisreferencesourcedata.
Theoverallcosttrajectorydevelopedinayearoveryearfashionwascomputedusingthe
standardexperiencecurveformula:
1_
__
Y
Y
GenerationCumulative
GenerationCumulativeRatioCost ^ln
2
_Pr_ RatioogressModified
Thiscostratiowasdevelopedinthecostdriverdataworksheetsforeachtechnologyandthen
usedtoadjusttheforecastedyearlycostsforeachtechnology.
2.5. Task 5: Price/Cost Reconciliation
Inalaterphaseoftheproject,theresearchteamwill:
AnalyzepubliclyavailablepricinginformationforrepresentativeutilityscaleREpower
purchasesinCalifornia.
Reconcilerepresentativepricesandestimatedlevelizedlifecyclecosts,includingthe
relativeimpactoffactorsotherthancostthatdeterminepricing,e.g.,stateandfederal
incentivesandtaxpolicies,financingassumptions,andthecostofcredit.
TheprojectoutcomesfromtheresearchteamsanalysisforTask5willbepresentedinthefinal
projectreport.
7U.S.DOE.EnergyInformationAdministration.LearningCurveEffectsforNewTechnologies.
8U.S.DepartmentofEnergy.EnergyInformationAdministration. AnnualEnergyOutlook2009
(AEO2009).DOE/EIA0383(2009),March2009.
9Zervos,Arthourous,ChristianKjaer,.PurePower:WindEnergyScenariosupto2030.EuropeanWind
EnergyAssociation,March2008.
8/3/2019 CEC-500-2009-084
25/272
11
2.6. Task 6: Community and Building Scale Renewable EnergyCosts
Inalaterphaseoftheproject,theresearchteamwill:
IdentifysourcesofrelevantU.S.costinformationforrenewableenergyheatingand
coolingtechnologies.
Estimatenominalcostsandexpectedcosttrajectoriesforrecommendedcommunity and
buildingscaleREtechnologies.
Presentplausibleminimumandmaximumcostsandcosttrajectoriesforsame,with
explanationoffactorsthatvaryandcausecoststovary.
TheprojectoutcomesfromtheresearchteamsanalysisforTask6willbepresentedinthefinal
projectreport.
8/3/2019 CEC-500-2009-084
26/272
12
8/3/2019 CEC-500-2009-084
27/272
13
3.0 Project Outcomes
Thissectionpresentstheresearchresults. ThetechnologiesselectedinTask1arepresentedin
Section3.1alongwithadescriptionofthemethodforselectingthetechnologies. Notethatthe
communityandbuildingscaletechnologieswillbeincludedinthefinalprojectreport. The
sectionsfollowing3.1areorganizedbytechnologyandincludeoutcomesfromTasks2,3,and4.
3.1. Technologies
Theresearchteamconductedatechnicalandanalyticalcritiqueofreferencedocumentsinorder
torecommendtechnologiesforcostanalysis. Theinterimprojectreportincludestheresearch
teamsrecommendationsforutilityscaletechnologies(i.e.,>20MW). Thefinalprojectreport
willincluderecommendedcommunityscaleREtechnologies(i.e.,120MW)andbuilding
scaleREtechnologies(i.e.,
8/3/2019 CEC-500-2009-084
28/272
14
Transmissioncosts
Integrationcosts
Environmentalbenefitsandotherexternalities
Generationcostsarealwaysconsideredsincetheygenerallyformthebasisofcostestimation.
Treatmentoftransmissioncosts,integrationcosts,andenvironmentalbenefitsisnotconsistent
andtreatmentofexternalitiesisevenlesscommon.
Thethreestudiesarebrieflydescribedbelowfollowedbycomparisontablesofkeyinput
assumptions.
2007 Cost of Generation Report
TheEnergyCommissionsCostofGenerationReport(COG)provideslevelizedcostestimates
forvariouscentralstationgenerationtechnologiesinCalifornia. Thelevelizedcostestimates
weredevelopedusingtheEnergyCommissionsCostofGenerationModelwhichwasinitially
developedtosupportthe2003Integrated
Energy
Policy
Report(IEPR). The2007Costof
GenerationReportusedanewlyrefinedCostofGenerationModeltoestimatethelevelized
costsofenergyforthreeclassesofdevelopers:investorownedutilities,publiclyownedutilities,
andmerchantplants. Thereportsummarizesthelevelizedcostestimatesinaclearandconcise
mannerforeightconventionaltechnologiesandtwentyrenewabletechnologiesforthethree
classesofdevelopers. Italsodocumentskeyinputassumptionsandcomparesthe2007input
assumptionstothoseusedinthe2003IEPRforecastandEIAestimates. Ageneraldescription
oftheEnergyCommissionsModelandmethodisprovidedaswellasuserinstructionsand
explanationofthescreeningandsensitivityanalysiscomponentsoftheModel.
CPUC 2008 GHG Modeling Project
ThecostandsupplycurvesgeneratedbytheCaliforniaPublicUtilitiesCommission(CPUC)
GHGModelingProjectin2008provideabenchmarkforwhichtocomparethekeyassumptions
andlevelizedcostestimatesprovidedinthisstudy. TheanalysisusedaGHGcalculator
developedbyE3andreviewedthroughthestakeholderprocessundertheCPUCGHGdocket
R.0604009.
TheCPUCisscheduledtocompletethefirstphaseoftheimplementationanalysisinearly2009.
Theintentistoconductarenewablepenetrationbarrieranalysisandtodevelopplausible
resourceportfoliosforCaliforniaIndependentSystemOperator(CaliforniaISO)toanalyze
further.13 Inaddition,theanalysiswillestimatenetcostandrateimpacts,lookingatcostand
rateimpacts
of
the
33%
Renewables
Portfolio
Standard
(RPS)
portfolio
relative
to
a20%
RPS
referencecasebaseline. ThoughtheresultsoftheCPUC2009analysisarenotyetavailable,
KEMAassessedthestudybasedonpubliclyavailablepresentations.14 AccordingtoaCPUC
13Thestudydoesnotrecommendoptimalrenewableresourceportfolios.
14CPUC,Aspen,E3,andPlexos. 33%ImplementationAnalysisWorkingGroupMeeting.CPUC,2008.
8/3/2019 CEC-500-2009-084
29/272
15
presentation,RETIprovidedusefulinputsforthe2008CPUCGHGModelingProjectandthe
pendingCPUC33%ImplementationAnalysis.
TheE3calculatorconsidersfactorssuchasintegrationcostsandrenewableimpactonwholesale
prices. Thestudyperformedasensitivityanalysisthatdeterminedfourkeydriversofresultsin
theelectricity
sector:
Loadgrowthassumptions.
Fuelprices.
EEachievements.
Carbondioxide(CO2)marketcosts.
InclusionofCO2marketcostshasbecomeincreasinglyimportantforplanningpurposesin
California. AccordingtoE3,CO2costsaretreatedasanexogenousinputtothemodel. The
analystusingtheGHGcalculatorinputsaCO2price,aswellasanyassumptionsaboutoffset
prices,andwhetherCO2permitsareauctionedorallocated,amongotherCO2marketdesign
questions.CO2costsarethencalculatedandallocatedtoloadservingentitiesdifferentlybased
ontheselectedscenario. CO2costsaretrackedonlyforretailprovidersandCO2coststo
existinggeneratorsarenottracked.
RETI 1A 2008 and IB 2009 Studies
AccordingtotheRETIReport,RETIsgoalistoidentifytransmissionfacilitieslikelytobe
requiredtomeeta33%RPSrequirementbytheyear2020. TheRETIIB2009studydeveloped
informationforrankingpotentialrenewableresourcesgroupedbygeographicproximity,
developmenttimeframe,sharedtransmissionconstraints,andeconomicbenefits. Italso
estimatedthe
value
of
energy
by
considering
time
of
day
and
capacity
value
of
resource
(contributiontosystemreliability). Itthenconductedahighlevelscreeninganalysisranking
therenewablezonesbycosteffectiveness,environmentalconcerns,developmentandschedule
uncertainty,andotherfactors. Therenewablesresourcesrankingbygroupingisintendedto
assistintransmissionplanning.
TheRETIanalysishasnotyetincludedintegratedcostsinitsmethod. However,itappearsthat
thereisaplantoincludethesecostsmaybeincludedinfutureRETIanalysesshouldthe
informationbedevelopedinanappropriatemannerthatitwarrantsinclusioninthecost
estimates. Forinstance,furtherinformationonintegrationcostsareneededtosupport
estimatesonthecosttointegrateintermittentwindandsolarresources.
TransmissioncostscalculatedbyBlack&VeatchandusedinthePhase1economicranking
assumesimultaneousdeliveryofthefullnameplategeneratingcapacityofeverycompetitive
renewableenergyzone(CREZ).Thisconservativeapproachisappropriateforahighlevel
screeninganalysisyetwithoutdoubtoverstatestheamountandcostofthetransmission
facilitiesnecessarytomeetcurrentstateGHGandrenewableenergygoals.
8/3/2019 CEC-500-2009-084
30/272
16
ThemethodemployedbytheRETIteamincludesscenarioanalysistoanalyzetheeffectsof
differentpolicyscenarios,resourceportfoliosandtechnologyoptionsandcosts. Thismethod
allowedtheRETIanalysistoassesstheimpactsofuncertaintyontherankingprocess. TheRETI
analysisalsoappearstoincludecarboncostsbasedonaGHGadder.
Comparison of 2009 Analysis With the 2007 IEPR Data
Thefollowingtableprovidesacomparisonofthekeyassumptionspresentedinthe2007IEPR
andKEMAs2009analysis.
Table 3. Comparison between 2009 KEMA analysis and 2007 IEPR
Technology Gross
Capacity
(MW)
Capacity
Factor (%)
Instant Cost
($/KW)
Fixed O&M
($/kW-Yr)
Variable O&M
($/MWh)
2009
KEMA
2007
IEPR
2009
KEMA
2007
IEPR
2009
KEMA
2007
IEPR
2009
KEMA
2007
IEPR
2009
KEMA
2007
IEPR
Biomass Combustion -
Fluidized Bed Boiler28 25 85% 85% $3,200 $3,156 $99.50 $150.26 $4.47 $3.11
Biomass Combustion -
Stoker Boiler38 25 85% 85% $2,600 $2,899 $160.00 $134.72 $6.98 $3.11
Biomass Cofiring 20 N/A 90% N/A $500 N/A $15.00 N/A $1.27 N/A
Biomass - IGCC 30 21.25 75% 85% $2,950 $3,121 $150.00 155.44 $4.00 3.11
Geothermal - Binary 15 50 90% 95% $4,046 $3,093 $47.44 $72.54 $4.55 $4.66
Geothermal - Flash 30 50 94% 93% $3,676 $2,866 $58.38 $82.90 $5.06 $4.58
Hydro Small Scale or
Developed Sites15 10 30% 52% $1,730 $4,125 $17.57 $13.47 $3.48 $3.11
Hydro Capacity
Upgrade80 N/A 30% N/A $771 N/A $12.59 N/A $2.39 N/A
Solar - Parabolic Trough 250 63.5 27% 27% $3,687 $4,021 $68.00 $62.18 $0.00 $0.00
Solar - Parabolic Trough
with Storage250 N/A 65% N/A $5,406 N/A $68.00 N/A $10.30 N/A
Solar - Photovoltaic
(Single Axis)25 1 27% 22% $4,550 $9,611 $68.00 $24.87 $0.00 $0.00
Onshore Wind - Class 5 100 N/A 42% N/A $1,990 N/A $13.70 N/A $5.50 N/A
Onshore Wind
Class 3/450 50 37% 34% $1,990 $1,959 $13.70 $31.09 $5.50 $0.00
Offshore Wind - Class 5
(2018 start date)100 N/A 45% N/A $5,588 N/A $27.40 N/A $11.00 N/A
Ocean Wave (2018 start
date)40 0.75 26% 15% $2,587 $7,203 $36.00 $31.09 $12.00 $25.91
Coal - IGCC 300 575 80% 60% $2,250 $2,198 $41.70 $36.27 $6.67 $3.11
Nuclear: Westinghouse-
AP1000960 1000 86% 85% $4,000 $2,950 $147.70 $140.00 $5.27 $5.00
Source: KEMA and 2007 Integrated Energy Policy Report
8/3/2019 CEC-500-2009-084
31/272
17
NotestoTable:IfN/Aislisted,nodatawasavailable. Thehydrodevelopedsitescategoryisanalogoustothe
hydrosmallscalecategoryusedinthe2007IEPR. Grosscapacityreferstothegrosselectricalgenerationoutput,
Capacityfactorreferstothefullloadequivalentoperationalpercentageforaunit,andinstantcostreferstothe
costtobuildaunitimmediately(withoutconstructioninterestorescalationeffects). Theinstantcostfornuclear
energydoesnotincludedecommissioningornuclearwastedisposalcosts.
Keyobservationsinclude:
Thehydroelectricfordevelopedsiteswithoutpowerdiscrepancyininstantcostsis
primarilyduetoestimatedlicensingandmitigationcosts. KEMAexaminedtheIdaho
NationalLaboratory(INL)databaseofpotentialsitesandfoundthattheaverage
mitigationcostsweresubstantiallylessthanwhatwasestimatedin2007.
Thecapacityfactorforthehydrowasdeterminedthroughananalysisofexisting
hydroelectricplantsinCalifornia. Throughthisanalysis,theaveragecapacityfactorwas
foundtobemuchlowerthanthe2007IEPRestimate.
Solarphotovoltaic(PV)singleaxisinstantcostshavedecreasedsubstantiallysincethe
2007IEPR. Thesedecreasingcosttrendsareconsistentwithseveralresearchand
financialsourcesaswellassignificanteconomiesofscaleassociatedwiththechange
froma1megawatt(MW)unittoa25MWinstallation. Section3.5.3providesfurther
documentationofKEMAsassumptionsandsourcedocuments.
Oceanwaveisanewtechnologyresourcecategoryatthecentralscaleprojectlevelthat
isscheduledtobecomeaviableresourceinthe2018timeframe. Theinstantcostsarenot
directlycomparablebetweena40MWsystemandthe0.75MWpilotprojectthatwas
includedinthe2007IEPRanalysis.
The2007IEPRanalysisdidnotcoverClass5windspecifically. Rather,theyincluded
onebroadwindcategorythatalignscloselywithClass3and4. Thedataalignsquite
nicelybetweenthetwostudies. Costsperunitofcapacityandenergyareexpectedto
declineasmachinesizeandoutputperunitincreases.
Offshorewindisanewcategoryinthe2009analysisandisscheduledtocomeonlineinthe
2018timeframe. Offshorewindinstantcostsareestimatedtobeapproximatelytwicethatof
onshorewind.
ThecoalIGCCcapacityfactorissubstantiallyhigherintheKEMA2009analysis. Thischangeis
basedonactualplantdataandwarrantedbecauseastechnologiesmaturecapacityfactorstend
toincrease.
Theinstantcostofnuclearishigherinthe2009analysisversusthe2007IEPRestimate. The
KEMAdataisbasedontheWestinghouseAP1000system,and,asdiscussedinSection3.8of
thisreport,thenucleardataiswellsubstantiatedbyseveralresearchandfinancialsources. In
addition,theinformationisconsistentwithdataavailablefrommajoroperatorssuchasFlorida
PowerandLight,GeorgiaPower,andSouthCarolinaElectricandGasCompany.
The2009IEPRcostofgenerationreportwilladdtothepreviousanalysesofrenewable
resourcesinthefollowingmanner:
8/3/2019 CEC-500-2009-084
32/272
18
Thecostestimateswillbepresentedasarange(high,mid,low)ofestimatestoreflectthe
uncertaintyandotherfactorsthataffectprojectcosts.
Installedcostshavebeenaddedthatincludethecarryingcostofcapitalduringthe
averageconstructionperiods.
Include
explicitly
cost
trajectories
affected
by
specific
influences
into
the
future.
Clearlyincludingfinancingandotherconstructionrelatedcostsbeyondengineering
estimates.
Providingexplicitreferencedocumentationforrenewabletechnologies.
Assessingofcostsforcommunityorbuildingscaletechnologies.
Comparison of 2009 Analysis With the CPUC GHG Modeling Project
KEMAs2009analysisiscomparedtothedatathatwaspresentedintheCPUCGHGmodeling
projectinthefollowingtable.
Table 4. Comparison of 2009 analysis with the CPUC GHG model data
TechnologyGross Capacity
(MW)*
CapacityFactor (%)
Instant Cost($/KW)
Fixed O&M($/kW-Yr)
Variable O&M($/MWh)
2009KEMA
CPUCE3 Data2008$
2009KEMA
CPUCE3
Data2008$
2009KEMA
CPUCE3
Data2008$
2009KEMA
CPUCE3 Data2008$
2009KEMA
CPUCE3
Data2008$
Biomass1
1 85% $3,737 $107.50 $0.01
BiomassCombustion -Fluidized Bed Boiler
28 85% $3,200 $ 99.50 $ 4.47
BiomassCombustion - StokerBoiler
38 85% $2,600 $160.00 $ 6.98
Biomass Cofiring 20 90% $500 $ 15.00 $ 1.27
Biomass - IGCC 30 75% $2,950 $150.00 $ 4.00
Geothermal2
1 90% $3,011 $154.92 $ -
Geothermal - Binary 15 90% $4,046 $47.44 $ 4.55
Geothermal - Flash 30 94% $3,676 $58.38 $ 5.06
Hydro - Small Scaleor Developed Sites
15 1 30% 50% $1,730 $2,402 $17.57 $13.40 $ 3.48 $3.30
Hydro CapacityUpgrade
80 N/A 30% N/A $771 N/A $12.59 N/A $2.39 N/A
Solar - ParabolicTrough
250 1 27% 40% $3,687 $2,696 $68.00 $49.63 $ - $ -
Solar - ParabolicTrough with Storage
250 N/A 65% N/A $5,406 N/A $68.00 N/A $10.30 N/A
8/3/2019 CEC-500-2009-084
33/272
19
TechnologyGross Capacity
(MW)*
CapacityFactor (%)
Instant Cost($/KW)
Fixed O&M($/kW-Yr)
Variable O&M($/MWh)
Solar - Photovoltaic(Single Axis)
25 27% $4,550 $68.00 $ -
Wind3 1 37% $1,931 $ 28.51
Onshore Wind -Class 5
100 42% $1,990 $13.70 $ 5.50
Onshore Wind -Class 3/4
50 37% $1,990 $13.70 $ 5.50
Offshore Wind -Class 5 (2018 startdate)
100 N/A 45% N/A $5,588 N/A $27.40 N/A $11.00 N/A
Ocean Wave (2018start date)
40 N/A 26% N/A $2,587 N/A $36.00 N/A $12.00 N/A
Coal - IGCC 300 1 80% 85% $2,250 $2,388 $41.70 $ 36.36 $ 6.67 $2.75
Nuclear:Westinghouse -AP1000
960 1 86% 85% $4,000 $3,333 $147.70 $ 63.88 $ 5.27 $0.47
Notes: Source for CPUC E3 data is GHG Calculator v2b (May 2008).15
1) Biomass is listed as generic category in the CPUC GHG Model
2) Geothermal is listed as generic category in the CPUC GHG Model
3) Wind is listed as a generic category (no Class is listed)
* Capacity MW was listed as 1 MW in all cases
Source: KEMA and CPUC
Keyobservationsinclude:
CostcharacterizationsandheatratesintheGHGmodelcomeprimarilyfromtheEIA
2007AnnualEnergyOutlookReport.16
Directcomparisonofdataisdifficultduetolackofdataonunitsizeassumptions.
TheCPUCdatadoesnotincludesolarsingleaxisPVsystems,despiterecent
announcementsinCaliforniaforlargerscalecentralizedPVsystemapplications.
TheCPUCsolarthermalinstantcostestimatesaresubstantiallylowerthanthe2007
IEPR,a2006NationalRenewableEnergyLaboratory(NREL)studyandKEMAs2009
estimate
for
reasons
that
are
not
easy
to
identify.
KEMAs
cost
data
is
based
on
a
2006
NREL/Black&Veatchstudyandindependentresearchoncapitalcostsofprojectsin
SpainandtheUnitedStates. Costestimatesanddiscussionofmajormarketdriversare
includedinSection3.5.2.
15http://www.ethree.com/CPUC_GHG_Model.html. E3GHGCalculatorv2b,May2008.
16U.S.DOE.EnergyInformationAdministration.AssumptionstotheAnnualEnergyOutlook.2007.
8/3/2019 CEC-500-2009-084
34/272
20
KEMAsClass3and4winddataalignscloselywiththeCPUCdata. E3benchmarked
windcoststoarecentAmericanWindEnergyAssociation(AWEA)study.
AllcostsintheGHGmodelwereinflatedby25%peryearfortwoyearstoreflectthe
recentrapidinflationinconstructioncosts. Giventherecentdownturnintheeconomy,
thisassumptionmaynolongerbeappropriate.
TheCPUCGHGmodelincludessitespecifictransmissioninterconnectiondistancesfor
geothermal,solarthermal,windandhydro. Conversely,KEMAs2009assessment
includestransmissioncostsandvoltageconversionfromthegenerationplanttothe
localfirstpointofinterconnectiontothetransmissionordistributionnetwork.
TheCPUCdataincludeswindandsmallhydroincludefirmingresourcecostsbasedon
costofCTsneededtoreach90%availabilityonpeak. KEMAsassessmentdoesnot
includefirmingresourcecosts.
Comparison of 2009 Analysis With the RETI Project (Phase 1A and 1B)
The2009analysisiscomparedtothedatathatwaspresentedinRETI1Areportinthefollowing
table.
Table 5. Comparison between 2009 Analysis with the RETI 1A Data
Technology Gross
Capacity
(MW)
Capacity
Factor (%)
Instant Cost
($/KW)
Fixed O&M
($/kW-Yr)
Variable O&M
($/MWh)
2009 RETI
1A
2009 RETI
1A
2009 RETI
1A
2009 RETI
1A
2009 RET
1A
Solid Biomass1
35 80% $4,000 $83 $11.0
Biomass Combustion -
Fluidized Bed Boiler*28 85% $3,200 $99.50 $4.47
Biomass Combustion -
Stoker Boiler*38 85% $2,600 $160.00 $6.98
Biomass Cofiring 20 35 90% 85% $500 $400 $15.00 $10 $1.27 $0.00
Biomass - IGCC 30 N/A 75% N/A $2,950 N/A $150.00 N/A $4.00 N/A
Geothermal2
30 80% $4,000 $0 $27.5
Geothermal Binary 15 90% $4,046 $47.44 $4.55
Geothermal - Flash 30 94% $3,676 $58.38 $5.06
Hydro - Developed Sites
or New as listed in RETI15
8/3/2019 CEC-500-2009-084
35/272
21
Technology Gross
Capacity
(MW)
Capacity
Factor (%)
Instant Cost
($/KW)
Fixed O&M
($/kW-Yr)
Variable O&M
($/MWh)
Solar - Parabolic Trough
with Storage250 N/A 65% N/A $5,406 N/A $68.00 N/A $10.30 N/A
Solar - Photovoltaic
(Single Axis)25 20 27% 28% $4,550 $7,000 $68.00 $35 $0.00 $0.00
Wind3
100 32% $2,150 $50 $0.00
Onshore Wind - Class 5** 100 42% $1,990 $13.70 $5.50
Onshore Wind - Class 3/4 50 37% $1,990 $13.70 $5.50
Offshore Wind - Class 5 100 200 45% 40% $5,588 $5,500 $27.40 $88.00 $11.00 $0
Ocean Wave 40 100 26% 35% $2,587 $4,000 $36.00 $210 $12.00 $11.0
Coal IGCC 300 N/A 80% N/A $2,250 N/A $41.70 N/A $6.67 N/A
Nuclear: Westinghouse -
AP1000960 N/A 86% N/A $4,000 N/A $147.70 N/A $5.27 N/A
Notes:
1) RETI 1A Solid Biomass.
2) Only one category of geothermal is listed in the RETI 1A Report.
3) Only one category of onshore wind is listed in the RETI 1A Report.
If ranges were presented in RETI 1A data, midpoints are listed in the table
Source: KEMA, Black & Veatch RETI 1A Report, 2008
Keyobservationsincludethefollowing:
Forthemostpart,theKEMAanalysisisfairlyconsistentwiththeRETIdata.
InformationonunderlyingassumptionsinRETIreportonthetwohydrocategoriesis
limited. Therefore,itisdifficulttoassesswhycostestimatesvarybetweenKEMA2009
dataandtheRETIIAdata.
TheRETIIAinstantcostdataforsolarparabolictroughappearstoalignnicelywith
KEMAsdata.
TheinstantcostforsolarPVsingleaxissystemsissignificantlylowerintheKEMA
studythantheRETIanalysis. TheKEMAdataisstronglysupportedbyrecentdeclining
pricetrendsasdiscussedinSection3.5.3.
8/3/2019 CEC-500-2009-084
36/272
22
Summary
MoreandmorestudiesthatassesscostofachievingRPSgoalsaretakingmacroeconomicand
externalitybenefitsintoaccount. Forinstance,somestudiesarenowassessingmacroeconomic
benefitsofrenewablegenerationincludingbenefitsassociatedwithgrowthintheclean
technologyindustryandemployment. Externalitiesshouldalsopotentiallybeexaminedeither
onaqualitativeorquantitativebasis. Forinstance,thebenefitassociatedwithrenewablesinhelpingtoserveasahedgeagainstthepriceoffossilfuelcouldpotentiallybequantified.
Futurestudiesshouldconsiderincluding:
CO2abatementcosts.
Qualitativeorquantitativeassessmentofotherkeyissuesthatmayinfluencecostsof
generationincluding:
Environmentalsensitivity.
Landuseconstraints.
Permittingrisk.
Transmissionconstraintsandequityissuesrelatedtowhobearsthecostofnew
transmission.
Systemintegrationcosts.
Systemdiversity.
Taxcreditavailabilityandstructure.
Financingavailability.
Macroeconomicbenefits(jobscreation,security,fueldiversity,etc.).
Natural
gas
price
and
wholesale
price
effects
associated
with
increased
penetrationofrenewables.
Otherriskfactors.
3.1.2. Method for Selecting Technologies
Theresearchteamusedthefollowingscreeningcriteriatoselectthemajorityoftechnologiesfor
costanalysis:
Isthetechnologycommerciallyavailableandinuseonanylevelotherthana
demonstrationphase?
ArethereanumberofprojectsinuseintheUnitedStatesorabroadthatusethis
technology?
IsthisaviabletechnologyforuseinCaliforniaorinneighboringstates? Ifso,whatis
theproductionpotential?
ArethereanyregulatoryissuesorotherrestrictionsforuseinCalifornia?
8/3/2019 CEC-500-2009-084
37/272
23
Isthereanyactualcostdataavailablefortheexistinginstallationsthatcanbeusedinthe
study?
Costanalysisforthetechnologiesthatpassedthesescreeningtechnologieswasconductedto
providedatastartingin2009(i.e.,currentstartdata). Inseveralcases,technologiesthatarenot
currentlycommerciallyavailablewereselectedforcostanalysis. Thesetechnologieswere
includedbecausethereissubstantialdemonstrationprojectactivityorsufficientinterestinthese
technologiestoexpectthatthesetechnologiescouldbecommerciallyavailableanddominantin
10yearstime. Sincenocostdatafromcommercialinstallationsisreadilyavailableforthese
technologies,theauthorsexpectgreateruncertaintyaroundthecosts. Theauthorshave
identifiedthesetechnologiesinthetablebelowwithadatastartdateof2018. Theutilityscale
technologiesfallingintothiscategoryareBiomassCoGasificationIGCC,OffshoreWind(Class
5),andOceanWave.
3.1.3. Utility-Scale Technologies
Theutility
scale
technologies
recommended
for
cost
analysis
are
shown
in
Table
6below.
Table 6. Central plant technology list for COG modeling project
Technology List Gross Capacity
(MW)
Data Start Date
Biomass
Biomass Combustion - Fluidized Bed Boiler 28 Current
Biomass Combustion - Stoker Boiler 38 Current
Biomass Cofiring 20 Current
Biomass Co-Gasification IGCC 30 2018
Geothermal
Geothermal - Binary 15 CurrentGeothermal - Flash 30 Current
Hydropower
Hydro - Small Scale (developed sites without power) 15 Current
Hydro - Capacity upgrade for developed sites with
power
80 Current
Solar
Solar - Parabolic Trough 250 Current
Solar - Photovoltaic (Single Axis) 25 Current
Wind
Onshore Wind - Class 5 100 Current
Onshore Wind - Class 3/4 50 Current
Offshore Wind - Class 5 100 2018
Wave
Ocean Wave 40 2018
Integrated Gasification Combined-Cycle
IGCC without carbon capture 300 Current
Nuclear
8/3/2019 CEC-500-2009-084
38/272
24
Technology List Gross Capacity
(MW)
Data Start Date
Westinghouse - AP1000 960 Current
Source: KEMA
3.1.4. Community-Scale Technologies
Communityscaletechnologieswillbediscussedinthefinalprojectreport.
3.1.5. Building-Scale Technologies
Buildingscaletechnologieswillbediscussedinthefinalprojectreport.
3.2. Biomass
3.2.1. Technology Overview
Theuseofbiomasstechnologyhasbeenapartoftheenergylandscapeforcenturiesandhas
becomeatechnologyofincreasingimportanceinthecurrentenergymix,bothinCalifornia,the
UnitedStates,andtherestoftheworld.
Biomass,ortheuseofplantbasedhemicellulosematerial,agriculturalvegetation,or
agriculturalwastesasfuel,hasthreeprimarytechnologypathways:
Pyrolysistransformationofbiomassfeedstockmaterialsintofuel(oftenliquidbiofuel)
byapplyingheatinthepresenceofacatalyst.
Combustiontransformationofbiomassfeedstockmaterialsintoenergythroughthe
directburningofthosefeedstocksusingavarietyofburner/boilertechnologiesalsoused
toburnmaterialssuchascoal,oilandnaturalgas.
Gasificationtransformationofbiomassfeedstockmaterialsintosyntheticgasthrough
thepartialoxidationanddecompositionofthosefeedstocksinareactorvesseland
oxidationprocess.
Ofthesetechnologypathways,thetwoprimaryembodimentsofelectricityproduction
technologyarefoundinthedirectcombustionandgasificationapproachestobiomass
combustionintoelectricityandenergy. Activeresearchintopyrolysisforbiofuelproductionis
activeandongoingbutisnotyetatcommercialscale.
Combustiontechnologiesarewidespread,andincludethefollowinggeneralapproaches:
StokerBoilerCombustionusessimilartechnologyforcoalfiredstokerboilersto
combustbiomassmaterials,eitherusingatravelinggrateoravibratingbed. Whilea
verymature,centuryoldtechnology,stokerboilerdesignshaveseentechnology
improvementsrecentlytoimprovebiomasscombustion,particularlyemissions
reductionsandincreasedcombustionefficiencies.
8/3/2019 CEC-500-2009-084
39/272
25
BiomassCofiringusesbiomassfuelburnedwithcoalproductsincurrenttechnology
pulverizedcoalboilersusedinutilityscaleelectricityproduction. Biomasscofiringisa
maturetechnologyinEuropeandisincreasinglybeingadoptedintheUnitedStates,
sinceitcansignificantlyenhancetheuseofbiomass,reducenetcarbonemissionsin
powergeneration,andhasshowngoodreliabilityinservice.
FluidizedBed(FB)Combustionusesaspecialformofcombustionwherethebiomass
fuelissuspendedinamixofsilicaandlimestonethroughtheapplicationofairthrough
thesilica/limestonebed. Fluidizedbedcombustionboilersareclassifiedeitheras
bubblingbed(FB)orcirculatingfluidizedbed(CFB)units.
Figure 1. Utility-scale fluidized bed gasifier
Source: Energy Products of Idaho
Gasificationtechnologies,whilerelativelyrecentintheirevolution,aregrowinginscopeand
scaleastheyareincreasinglybeingdevelopedandusedthroughouttheworld. Several
differentformsofgasificationtechnologiesexisttoday:
BiomassIntegratedGasificationCombinedCycle(IGCC)similartothecoalbased
IGCCprocess,exceptthebiomassfuelisgasifiedinareactorvesselpriortoits
8/3/2019 CEC-500-2009-084
40/272
26
introductionandcombustioninagasturbinegeneratorset. Gasturbinesdevelopedfor
coalbasedIGCCarewellsuitedforbiomassIGCCbecausebothgasifiedfuelsareof
sufficientBTUheatingvaluecontent. BiomassIGCCplantsarenowbeingintroducedas
technologydemonstrationunits.
Figure 2. Biomass IGCC plant representation
Source: KEMA
Figure 3. Schematic diagram of biomass IGCC process
Source: U.S. Department of Energy
(www.fossil.energy.gov/programs/powersystems/gasification/howgasificationworks.html)
8/3/2019 CEC-500-2009-084
41/272
27
BiomassfluidizedbedgasificationusingaFBorCFBgasificationreactortoconvert
biomassfeedstocksintosyntheticfuelgas,whichisthenburnedinaconventionalcoal
ornaturalgasfiredutilityboiler. Thistechnologyisnotbeingadoptedforthecostof
generationstudybecausethecurrentcommercialembodimentisdirectfluidizedbed
combustionofbiomassforelectricalpowergeneration.
Figure 4. Utility-scale biomass fluidized bed gasifier
Source : Foster Wheeler
3.2.2. Biomass Combustion Fluidized Bed Boiler
Technical and Market Justification
Forbiomassfuels,fluidizedbedcombustionisrapidlyemergingasasystemofchoiceformany
powergenerationapplications. Theinherentfuelversatilityoffluidizedbedsystemsprovidesa
plantoperatortheabilitytoburnmanydifferentbiomassresourcetypes,includingthose
feedstockswithsignificantmoisturevariations. Themajorreasonforthisisthatthefluidized
bedcarryingmedium(typicallyamixofsilicasandand/oralumina)providesathermalflywheel
8/3/2019 CEC-500-2009-084
42/272
28
effectthatmaintainsconstantheatoutputandfluegasqualityevenwhenburningfuelsof
varyingmoisturecontent.17
Fluidizedbedboilersarecharacterizedaseitherbubblingbed(FB)orcirculatingfluidizedbed
(CFB),andthisisbasedonhowthebedmaterialisusedwithintheboiler. Inabubblingbed
(FB)unit,
the
bed
material
stays
within
afixed
zone
in
the
boiler,
while
in
acirculating
fluidized
bed(CFB)unit,thematerialissuspendedaboveanairzoneandiscirculatedthroughareturn
loopbacktothecombustionzonebymeansofamassorcyclonicseparator.
Figure 5. Circulating fluidized bed schematic diagram
Source: Babcock & Wilcox Image (www.babcock.com/products/boilers/images/cfb.gif)
Forboth
FB
and
CFB
units,
due
to
the
high
quality
combustion
and
near
complete
carbon
burnout(99100%)ofbiomassfuelsources,ashiscarriedoverintothefluegasstream,requiring
theadditionofpostcombustionashremovalequipmentsuchascyclonesandbaghouses. The
17Overend,R.P.BiomassConversionTechnologies.Golden,CO:NationalRenewableEnergyLaboratory,
2002.
8/3/2019 CEC-500-2009-084
43/272
29
postcombustioncontrolsallowparticulateremovaltoNewSourcePerformanceStandards
(NSPS)forPM10.
Fluidizedbedboilertechnologyhaslongbeenincommercialuse,withmuchmorewidespread
adoptioninEuropethanintheUnitedStates,duetoseveralreasons.18 First,fuelresourcesin
Europecan
vary
widely
in
quality
and
processing,
and
the
ability
of
fluidized
bed
boilers
to
handlewidelyvaryingfuelsisofadvantage. Second,fluidizedbedboilersexhibitsuperior
emissionsperformance,especiallynitrogenoxide(NOx)emissions,duetotheinherentlylow
firingtemperatureoftheboiler. Third,forcoalbasedfuels,theabilitytodirectlyinject
limestoneasasorbentprovidesexcellentsulfurandsulfurdioxide(SOx)reductionswithoutthe
needforexpensivepostcombustionscrubbingequipmentandsystems.
Marketadoptionoffluidizedbedboilertechnologyforbiomasshaslongbeenacommercial
reality,withbothbubblingbedandCFBunitsbeingusedforbiomasscogenerationthroughout
theUnitedStates,particularlyintheforestproductsandpaperindustry. AdoptionofCFB
technologyforutilityscalecoalandbiomasspowergenerationhasreachedworldwidegeneral
industryadoption,
as
shown
below:
Table 7. Installed CFB boiler capacity by country19
Country Installed Capacity (MW)
China 10,000
Czech Republic 1,400
Germany 1,800
Poland 3,310
India 1,200
United States 8,800
Source: Tavoulareas, Stratos. Advanced Power Generation Technologies An Overview
TechnologySelectionCriteria
Fluidizedbedcombustiontechnologyforgeneratingelectricpowerusingbiomassfuelwas
selectedforthecostofgenerationstudybytheresearchteambecauseofthefollowingfactors:
CommercialscaleBothbubblingbedandcirculatingfluidizedbedtechnologieshave
beendevelopedtoutilityscale,andcurrentcommercializedunitsfitwellwithinthe
overallsupplycurveconstraintsforbiomassthatcanlimitoverallgeneratingunitsize
potential.
18U.S.EnvironmentalProtectionAgency.CombinedHeatandPowerPartnership. BiomassCombined
HeatandPowerCatalogofTechnologies,September2007.
19Tavoulareas,Stratos.AdvancedPowerGenerationTechnologiesAnOverview.U.S.Agencyfor
InternationalDevelopment.ECOAsiaCleanDevelopmentProgram,August2008.
8/3/2019 CEC-500-2009-084
44/272
30
FuelflexibilityBiomasscombustioninfluidizedbedboilershasbeenwelldocumented
foravarietyofbiomassfuelfeedstocks. Theinherentstabilityinfluidizedbedboilers
whileburningfuelsofvaryingqualityisakeyadvantagewhenevaluatingchanging
biomassfuelsourcesoverthelifeofthegeneratingplant.
ReliabilityFluidizedbedcombustionisreliableandprovenoverdecadesofservice.
Whilerelativelynewintechnologywhencomparedtostoker ortraditionalfired
boilers,thereisrapidandgrowingadoptionoffluidizedbedboilertechnologyformid
sizedunits.
EmissionsperformanceFluidizedbedcombustionperformswellinreducingNOx
emissionsbecauseofthelowcombustiontemperaturesusedintheprocess. Inaddition,
thenearcompleteconversionofavailablecarbonresultsinlowercarbonmonoxide(CO)
emissions. Particulateemissionsaremanagedthroughpostcombustioncontrols,as
withtraditionalfiredunitsburningsolidfuels.
Figure 6. Bubbling fluidized bed boiler
Source: Energy Products of Idaho
8/3/2019 CEC-500-2009-084
45/272
31
Primary Commercial Embodiment
Today,theprimarycommercialembodimentofcirculatingfluidizedbedboilertechnologyisin
EuropeandChinaandgainingmomentumintheUnitedStates Forover20years,the
developmentofcirculatingandbubblingfluidizedbedtechnologyhasprogressedinEuropeto
thepointwherecirculatingfluidizedbedboilersareastandard,utilityscaletechnologytoday.
IntheUnitedStates,severalcompanieshaveprogressedwithstandardizeddesignsofcirculatingfluidizedbedboilerscombustingavarietyoffuels,frombiomasstocoaland
petroleumcoke.
InCalifornia,currentcommercialembodimentislimited,mainlybecauseofthelimitedability
topermitsolidfuelcombustionfacilities. However,thereiscurrentinterestinthecogeneration
andforestproductsindustrialbasetoexaminefluidizedbedcombustiontechnologyfor
repoweringexistingsolidfuelcombustionfacilitiestobiomassfuelconversion.20
Theresearchteambelievesthatfluidizedbedtechnologywillbecomecommerciallyembodied
inCaliforniatoenablethestatetoachieveitsbiomassenergygoalsby2018. Theinherentlyfuel
flexiblenatureoffluidizedbedcombustion,theintegrationofprimarypollutioncontrolsintothecombustionprocess,andthesmallfootprintareenablersofthistechnologyinCalifornia,as
beingdemonstratednowinEuropeandChina.
Cost Drivers
MarketandIndustryChanges
MarketandindustrychangessinceAugust2007havenotsignificantlyaffectedcostsfor
circulatingfluidizedbedboilertechnology. Materialcostincreaseshaveabatedduetothe
currenteconomicrecession,especiallyincarbonsteelandstainlesssteelcosts,whicharethe
primarycostcomponentsofcirculatingfluidizedbedboilermanufacturing.
CarbonsteelcostshavechangedsignificantlysinceAugust2007,butthenetchangeisnot
significant. Theattachedtablehighlightstherapidriseandthenfallofcarbonsteelpricing:21
Table 8. Recent carbon steel pricing
Year Average Carbon Steel Price ($/Ton)
2007 $717
2008 $1,004
2009 (April 2009 average annual price) $736
Source: Purchasing Magazine
20KEMASources:PersonalCommunicationwithEPI,FosterWheeler,March2009.
21PurchasingStaff.Steelplatepriceshaveplunged50%frommid2008peak.PurchasingMagazine.
April2009.www.purchasing.com/article/CA6654110.html?industryid=48389.
8/3/2019 CEC-500-2009-084
46/272
32
CurrentTrends
Currenttrendsthatwillmateriallyaffectfuturecostsare:
GlobaleconomicdownturnThebreadthanddepthofthecurrentrecessionhascaused
asignificantreductioninthenumberofnewboilerordersforbothpowergeneration
andindustrialmanufacturingcapacity. Thelengthofthecurrentrecessionandthepaceofrecoverywilldeterminetheescalationrateinrawmaterials,theuseofboiler
manufacturingcapacity,andthusfuturecosts.
SteelpriceabatementCurrentameliorationofworldwidesteelprices,bothforcarbon
andstainlesssteel,willhaveapricemoderatingeffectonstokerboilerpricesbothnow
andinthenearfuture. Longtermsteelcommoditypricesarecurrentlydifficultto
predict.
IndustrialproductionandeconomicgrowthinChinaByNovember2008,Chinalost
over30millionmanufacturingjobsinGuangzhouProvinceduetotheglobalrecession,
significantlycurtailingChineseeconomicgrossdomesticproduct(GDP)growth.
Enoughoftheglobaloutputforsteelandotherrawmaterials,usedincirculating
fluidizedbedboilerproduction,werebeingusedinChinathatsignificantescalationof
pricesresulted. ThepaceoftheeconomicrecoveryandstimulusinChinawill
determinerawmaterialpriceescalationandthuswillimpactcirculatingfluidizedbed
boilercosts.
EconomicstimulusBecausestimuluspackagesaredesignedtosupportenergy
technologies,suchascombinedheatandpower,cogeneration,andbiomass,stimulus
supportintheUnitedStatescouldhaveanescalatingeffectonbothmaterialsand
demandforcirculatingfluidizedbedboilers.
CostDrivers
Costdriversforbiomasscirculatingfluidizedbedboilertechnologiesareasfollows:
BiomassfueltypeanduniformityThetypeanduniformityofdeliveredbiomassfuel
supplyisaprimarycostdriverforanybiomasstechnology. Becauseofthevaried
natureofbiomassfuelfeedstocks,theirdeliveredmoisturecontentandheatingvalue
variations,andfuelprocessingissues,thehandlingandprocessingcostsofbiomass
fuelscanvarygreatly. Asaresult,thetypeandnatureofbiomassfuelscombustedcan
haveamaterialimpactonthecapitalcostoftheboilerislanddesign,aswellasthe
overallfuelhandlingandoperationscost.
Supplycurveforbiomassfuel,fueltransportandhandlingcostsTheavailabilityof
adequateandsufficientbiomassfuelresourceswithina100mileradiusoftheplant
locationisacriticaldriverforoperatingcost. Mostbiomassfuelistransportedbytruck
transporttoaplantsite,whichlimitstheeffectiveeconomicradiusfromtheplant
locationtoaggregatefuelsupplyatcommerciallyreasonableprices. Thevariednature
ofbiomassfuelfeedstocksalsonecessitatesspecialhandlingequipmentandlarger
8/3/2019 CEC-500-2009-084
47/272
33
numbersofdedicatedstaffthanforcoalfiredcombustionpowerplantsofequivalent
size.
BoilerislandcostCapitalcostoftheboilerislandisacriticalcostdriverthatcanentail
approximately4060%oftheoverallplantcost,dependingonthetypeofbiomass
combustedandtheneedforpostcombustionpollutioncontrols.22 Thedesignbasisfor
thetypeoffuelstobecombustedisanimportantcostdriver. Inaddition,theescalation
trendsforrawmaterialsusedinmanufactureoftheboilerisland,primarilysteelcost,
arefactorsthatcaninfluencedeliveredboilerislandcost.
LongtermfuelsupplycontractavailabilityMostcurrentbiomassfuelsupplycontracts
areofshorttermdurationandforfuelofsometimesvaryingquality. Akeycostdriver
topromotingbiomasscirculatingbedcombustioninCaliforniaistheabilitytodevelop
andachieveperformanceonlongterm(e.g.,fiveyearsdurationandlonger)fuelsupply
contractsforavailablefuelsources.
PlantscaleCurrentCFBtechnologyhasbeenproventoutilityscaleapplicationsofup
to
300
MW,
with
the
primary
commercial
embodiment
in
sizes
from
30
100
MW.
Developmentof800MWclasssupercriticalCFBcyclesisnowbeingstudiedfor
applicationsinChina,andtheoutcomeofthatresearcheffortwouldmateriallyaffectthe
capitalcostprofileandscaleofCFBtechnologyapplicationsforbiomass.23
EmissionscontrolcostsCostsespeciallyofpostcombustionemissionscontrol
technologies,suchasSCR/SNCRtechnologiesforNOxcontrol,andadditiona