CE 561 Construction Project Management Small Residential Building Project FALL - 2016 ABHISHEK KUMAR SINGH 200116822

CE 561 - Term Project on Primavera P6

Embed Size (px)

Citation preview

Page 1: CE 561 - Term Project on Primavera P6

CE 561

Construction Project Management

Small Residential Building Project

FALL - 2016

ABHISHEK KUMAR SINGH

200116822

Page 2: CE 561 - Term Project on Primavera P6

Table of Contents

SL No. Report Name

1 Grouped by Project and Sorted by Activity ID

2 Gantt Chart for activities grouped by WBS and Sorted by Activity ID

3 Activity Network Layout of the Project

4 Activity Table & Gantt Chart Schedule for Critical Activities

5 Gantt Chart Schedule for Critical Activities

6 Gantt Chart Schedule for activities Sorted by Early Start & Free Float

7 Report for Budgeted Cost

8 Daily Histogram and cumulative curve for Labor cost

9 Daily Histogram and cumulative curve for Material Cost

10 Monthly Histogram and Cumulative curve for Total Cost

11 Updated Schedule Report and Gantt Chart Table

Page 3: CE 561 - Term Project on Primavera P6

Grouped by WBS and Sorted by Activity ID

WBS

Activity ID Activity Name Predecessors OriginalDuration

Early Start

Early Finish

Late Start Late Finish

Total Float Free Float

R

R.1

A1000 Finalize Plans & Develop estimate with owner, architect

20.00 01-Nov-16 08:00 AM

23-Nov-16 05:00 PM

01-Nov-16 08:00 AM

23-Nov-16 05:00 PM

0.00 0.00

A1010 Sign Contract & Notice to proceed

A1000 1.00 24-Nov-16 08:00 AM

24-Nov-16 05:00 PM

24-Nov-16 08:00 AM

24-Nov-16 05:00 PM

0.00 0.00

R.1.1

A1110 Secure Foundation Permit A1010 1.00 25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

0.00 0.00

A1120 Secure Framing Permit A1010 1.00 25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

0.00 0.00

A1130 Secure Electrical Permit A1010 1.00 25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

0.00 0.00

A1140 Secure Plumbing Permit A1010 1.00 25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

0.00 0.00

A1150 Secure HVAC Permit A1010 1.00 25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

0.00 0.00

A1160 Secure miscellaneous permits A1010 1.00 25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

0.00 0.00

Subtotal 1.00 25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

25-Nov-16 08:00 AM

25-Nov-16 05:00 PM

0.00 0.00

Subtotal 22.00 01-Nov-16 08:00 AM

25-Nov-16 05:00 PM

01-Nov-16 08:00 AM

25-Nov-16 05:00 PM

0.00 0.00

R.S

A1020 Clear and grub lot A1110, A1120, A1130, A1140, A1150,

1.00 26-Nov-16 08:00 AM

26-Nov-16 05:00 PM

26-Nov-16 08:00 AM

26-Nov-16 05:00 PM

0.00 0.00

Abhishek Singh

© Oracle Corporation Page 1 of 9

Page 4: CE 561 - Term Project on Primavera P6

Grouped by WBS and Sorted by Activity ID

WBS

Activity ID Activity Name Predecessors OriginalDuration

Early Start

Early Finish

Late Start Late Finish

Total Float Free Float

A1030 Install temporary power service A1020 1.00 28-Nov-16 08:00 AM

28-Nov-16 05:00 PM

28-Nov-16 08:00 AM

28-Nov-16 05:00 PM

0.00 0.00

A1040 Install underground utilities A1030 1.00 29-Nov-16 08:00 AM

29-Nov-16 05:00 PM

29-Nov-16 08:00 AM

29-Nov-16 05:00 PM

0.00 0.00

Subtotal 3.00 26-Nov-16 08:00 AM

29-Nov-16 05:00 PM

26-Nov-16 08:00 AM

29-Nov-16 05:00 PM

0.00 0.00

R.2

A1170 Excavate for foundations A1040 3.00 30-Nov-16 08:00 AM

02-Dec-16 05:00 PM

30-Nov-16 08:00 AM

02-Dec-16 05:00 PM

0.00 0.00

A1180 Form basement walls A1170 13.00 03-Dec-16 08:00 AM

17-Dec-16 05:00 PM

03-Dec-16 08:00 AM

17-Dec-16 05:00 PM

0.00 0.00

A1190 Place concrete for foundations & basement walls

A1180 12.00 19-Dec-16 08:00 AM

31-Dec-16 05:00 PM

19-Dec-16 08:00 AM

31-Dec-16 05:00 PM

0.00 0.00

A1200 Cure basement walls for 7 days A1190 7.00 02-Jan-17 08:00 AM

09-Jan-17 05:00 PM

02-Jan-17 08:00 AM

09-Jan-17 05:00 PM

0.00 0.00

A1210 Strip basement wall forms A1200 2.00 10-Jan-17 08:00 AM

11-Jan-17 05:00 PM

10-Jan-17 08:00 AM

11-Jan-17 05:00 PM

0.00 0.00

A1220 Waterproof / insulate bsement walls

A1210 2.00 12-Jan-17 08:00 AM

13-Jan-17 05:00 PM

12-Jan-17 08:00 AM

13-Jan-17 05:00 PM

0.00 0.00

A1230 Perform foundation inspection A1170, A1220

1.00 14-Jan-17 08:00 AM

14-Jan-17 05:00 PM

14-Jan-17 08:00 AM

14-Jan-17 05:00 PM

0.00 0.00

A1240 Backfill foundation A1230 2.00 16-Jan-17 08:00 AM

17-Jan-17 05:00 PM

16-Jan-17 08:00 AM

17-Jan-17 05:00 PM

0.00 0.00

Subtotal 42.00 30-Nov-16 08:00 AM

17-Jan-17 05:00 PM

30-Nov-16 08:00 AM

17-Jan-17 05:00 PM

0.00 0.00

R.3

A1250 Install 1st floor joists A1240 2.00 18-Jan-17 08:00 AM

19-Jan-17 05:00 PM

18-Jan-17 08:00 AM

19-Jan-17 05:00 PM

0.00 0.00

Abhishek Singh

© Oracle Corporation Page 2 of 9

Page 5: CE 561 - Term Project on Primavera P6

Grouped by WBS and Sorted by Activity ID

WBS

Activity ID Activity Name Predecessors OriginalDuration

Early Start

Early Finish

Late Start Late Finish

Total Float Free Float

A1260 Lay 1st floor decking A1250 2.00 20-Jan-17 08:00 AM

21-Jan-17 05:00 PM

20-Jan-17 08:00 AM

21-Jan-17 05:00 PM

0.00 0.00

A1270 Frame 1st floor walls A1260 4.00 23-Jan-17 08:00 AM

26-Jan-17 05:00 PM

23-Jan-17 08:00 AM

26-Jan-17 05:00 PM

0.00 0.00

A1280 Frame 1st floor corners A1270 1.00 27-Jan-17 08:00 AM

27-Jan-17 05:00 PM

27-Jan-17 08:00 AM

27-Jan-17 05:00 PM

0.00 0.00

A1290 Install 2nd floor joist A1280 2.00 28-Jan-17 08:00 AM

30-Jan-17 05:00 PM

28-Jan-17 08:00 AM

30-Jan-17 05:00 PM

0.00 0.00

A1300 Frame 2nd Floor decking A1290 2.00 31-Jan-17 08:00 AM

01-Feb-17 05:00 PM

31-Jan-17 08:00 AM

01-Feb-17 05:00 PM

0.00 0.00

A1310 Frame 2nd floor walls A1300 3.00 02-Feb-17 08:00 AM

04-Feb-17 05:00 PM

02-Feb-17 08:00 AM

04-Feb-17 05:00 PM

0.00 0.00

A1320 Frame 2nd floor corners A1310 2.00 06-Feb-17 08:00 AM

07-Feb-17 05:00 PM

06-Feb-17 08:00 AM

07-Feb-17 05:00 PM

0.00 0.00

A1330 Complete roof framing A1320 3.00 08-Feb-17 08:00 AM

10-Feb-17 05:00 PM

08-Feb-17 08:00 AM

10-Feb-17 05:00 PM

0.00 0.00

A1340 Conduct framing inspection A1330 1.00 11-Feb-17 08:00 AM

11-Feb-17 05:00 PM

11-Feb-17 08:00 AM

11-Feb-17 05:00 PM

0.00 0.00

Subtotal 22.00 18-Jan-17 08:00 AM

11-Feb-17 05:00 PM

18-Jan-17 08:00 AM

11-Feb-17 05:00 PM

0.00 0.00

R.4

A1350 Install 1st Floor Sheathing A1340 3.00 13-Feb-17 08:00 AM

15-Feb-17 05:00 PM

13-Feb-17 08:00 AM

15-Feb-17 05:00 PM

0.00 0.00

A1360 Install 2nd Floor Sheathing A1350 3.00 16-Feb-17 08:00 AM

18-Feb-17 05:00 PM

16-Feb-17 08:00 AM

18-Feb-17 05:00 PM

0.00 0.00

A1370 Install roof decking A1330 3.00 11-Feb-17 08:00 AM

14-Feb-17 05:00 PM

16-Feb-17 08:00 AM

18-Feb-17 05:00 PM

4.00 0.00

A1380 Install felt, flashing, and shingles A1440 3.00 25-Feb-17 08:00 AM

28-Feb-17 05:00 PM

25-Feb-17 08:00 AM

28-Feb-17 05:00 PM

0.00 0.00

A1390 Hang 1st floor exterior doors A1380 1.00 01-Mar-17 08:00 AM

01-Mar-17 05:00 PM

01-Mar-17 08:00 AM

01-Mar-17 05:00 PM

0.00 0.00

Abhishek Singh

© Oracle Corporation Page 3 of 9

Page 6: CE 561 - Term Project on Primavera P6

Grouped by WBS and Sorted by Activity ID

WBS

Activity ID Activity Name Predecessors OriginalDuration

Early Start

Early Finish

Late Start Late Finish

Total Float Free Float

A1400 Install 1st floor windows A1390 3.00 02-Mar-17 08:00 AM

04-Mar-17 05:00 PM

02-Mar-17 08:00 AM

04-Mar-17 05:00 PM

0.00 0.00

A1410 Install 2nd floor windows A1400 3.00 06-Mar-17 08:00 AM

08-Mar-17 05:00 PM

06-Mar-17 08:00 AM

08-Mar-17 05:00 PM

0.00 0.00

Subtotal 22.00 11-Feb-17 08:00 AM

08-Mar-17 05:00 PM

13-Feb-17 08:00 AM

08-Mar-17 05:00 PM

0.00 0.00

R.6

A1420 Complete Exterior Brick A1410 16.00 09-Mar-17 08:00 AM

27-Mar-17 05:00 PM

13-Mar-17 08:00 AM

30-Mar-17 05:00 PM

3.00 0.00

A1430 Complete exterior siding A1420 3.00 28-Mar-17 08:00 AM

30-Mar-17 05:00 PM

31-Mar-17 08:00 AM

03-Apr-17 05:00 PM

3.00 0.00

Subtotal 19.00 09-Mar-17 08:00 AM

30-Mar-17 05:00 PM

13-Mar-17 08:00 AM

03-Apr-17 05:00 PM

3.00 0.00

R.7

A1440 Rough-in-plumbing A1370, A1360

5.00 20-Feb-17 08:00 AM

24-Feb-17 05:00 PM

20-Feb-17 08:00 AM

24-Feb-17 05:00 PM

0.00 0.00

A1450 Conduct Rough-in-plumbing inspection

A1440 1.00 25-Feb-17 08:00 AM

25-Feb-17 05:00 PM

18-Mar-17 08:00 AM

18-Mar-17 05:00 PM

18.00 0.00

A1460 Place concrete for basement floor

A1450 11.00 27-Feb-17 08:00 AM

10-Mar-17 05:00 PM

04-Apr-17 08:00 AM

15-Apr-17 05:00 PM

31.00 31.00

A1470 Rough-in electrical A1370, A1360

5.00 20-Feb-17 08:00 AM

24-Feb-17 05:00 PM

27-Feb-17 08:00 AM

03-Mar-17 05:00 PM

6.00 0.00

A1480 Conduct Rough-in-electrical inspection

A1470 1.00 25-Feb-17 08:00 AM

25-Feb-17 05:00 PM

04-Mar-17 08:00 AM

04-Mar-17 05:00 PM

6.00 0.00

A1490 Rough-in HVAC A1480 3.00 27-Feb-17 08:00 AM

01-Mar-17 05:00 PM

06-Mar-17 08:00 AM

08-Mar-17 05:00 PM

6.00 0.00

A1500 Conduct Rough-in-HVAC inspection

A1490 1.00 02-Mar-17 08:00 AM

02-Mar-17 05:00 PM

28-Mar-17 08:00 AM

28-Mar-17 05:00 PM

22.00 22.00

Abhishek Singh

© Oracle Corporation Page 4 of 9

Page 7: CE 561 - Term Project on Primavera P6

Grouped by WBS and Sorted by Activity ID

WBS

Activity ID Activity Name Predecessors OriginalDuration

Early Start

Early Finish

Late Start Late Finish

Total Float Free Float

A1510 Rough-in communication - phone, cables, computer, alarm

A1370 2.00 15-Feb-17 08:00 AM

16-Feb-17 05:00 PM

07-Mar-17 08:00 AM

08-Mar-17 05:00 PM

17.00 17.00

Subtotal 21.00 15-Feb-17 08:00 AM

10-Mar-17 05:00 PM

20-Feb-17 08:00 AM

15-Apr-17 05:00 PM

31.00 0.00

R.8

R.8.1

A1520 Place wall insulation - 1st floor A1350, A1360, A1470, A1490, A1510, A1410

1.00 09-Mar-17 08:00 AM

09-Mar-17 05:00 PM

09-Mar-17 08:00 AM

09-Mar-17 05:00 PM

0.00 0.00

A1530 Place wall insulation - 2nd floor A1520 1.00 10-Mar-17 08:00 AM

10-Mar-17 05:00 PM

08-Apr-17 08:00 AM

08-Apr-17 05:00 PM

25.00 1.00

A1540 Place ceiling insulation - 2nd floor A1530, A1590

1.00 17-Mar-17 08:00 AM

17-Mar-17 05:00 PM

14-Apr-17 08:00 AM

14-Apr-17 05:00 PM

24.00 0.00

A1550 Conduct insulation inspection A1540 1.00 18-Mar-17 08:00 AM

18-Mar-17 05:00 PM

15-Apr-17 08:00 AM

15-Apr-17 05:00 PM

24.00 24.00

Subtotal 9.00 09-Mar-17 08:00 AM

18-Mar-17 05:00 PM

09-Mar-17 08:00 AM

15-Apr-17 05:00 PM

24.00 0.00

R.8.2

A1560 Install Drywall - 1st floor walls A1520 2.00 08-Mar-17 08:00 AM

09-Mar-17 05:00 PM

08-Mar-17 08:00 AM

09-Mar-17 05:00 PM

0.00 0.00

A1570 Install drywall - 1st floor overhead

A1560 2.00 10-Mar-17 08:00 AM

11-Mar-17 05:00 PM

10-Mar-17 08:00 AM

11-Mar-17 05:00 PM

0.00 0.00

A1580 Install drywall 2nd floor walls A1570, A1530

2.00 13-Mar-17 08:00 AM

14-Mar-17 05:00 PM

10-Apr-17 08:00 AM

11-Apr-17 05:00 PM

24.00 0.00

A1590 Install drywall 2nd floor overhead A1580 2.00 15-Mar-17 08:00 AM

16-Mar-17 05:00 PM

12-Apr-17 08:00 AM

13-Apr-17 05:00 PM

24.00 0.00

Abhishek Singh

© Oracle Corporation Page 5 of 9

Page 8: CE 561 - Term Project on Primavera P6

Grouped by WBS and Sorted by Activity ID

WBS

Activity ID Activity Name Predecessors OriginalDuration

Early Start

Early Finish

Late Start Late Finish

Total Float Free Float

A1600 Tape & Float 1st floor drywall A1570 1.00 13-Mar-17 08:00 AM

13-Mar-17 05:00 PM

13-Mar-17 08:00 AM

13-Mar-17 05:00 PM

0.00 0.00

A1610 Tape & Float 2nd floor drywall A1600, A1590

1.00 17-Mar-17 08:00 AM

17-Mar-17 05:00 PM

25-Apr-17 08:00 AM

25-Apr-17 05:00 PM

33.00 33.00

Subtotal 9.00 08-Mar-17 08:00 AM

17-Mar-17 05:00 PM

08-Mar-17 08:00 AM

25-Apr-17 05:00 PM

33.00 0.00

R.8.3

A1620 Texture all except entry & kitchen- 1st floor

A1600 1.00 14-Mar-17 08:00 AM

14-Mar-17 05:00 PM

14-Mar-17 08:00 AM

14-Mar-17 05:00 PM

0.00 0.00

A1630 Paint all except entry & kitchen - 1st floor

A1620 1.00 15-Mar-17 08:00 AM

15-Mar-17 05:00 PM

15-Mar-17 08:00 AM

15-Mar-17 05:00 PM

0.00 0.00

A1640 Hang wallpaper entry & kitchen - 1st floor

A1630 1.00 16-Mar-17 08:00 AM

16-Mar-17 05:00 PM

16-Mar-17 08:00 AM

16-Mar-17 05:00 PM

0.00 0.00

A1650 Texture all - 2nd floor A1620 1.00 15-Mar-17 08:00 AM

15-Mar-17 05:00 PM

24-Apr-17 08:00 AM

24-Apr-17 05:00 PM

34.00 0.00

A1660 Paint all - 2nd floor A1650 1.00 16-Mar-17 08:00 AM

16-Mar-17 05:00 PM

25-Apr-17 08:00 AM

25-Apr-17 05:00 PM

34.00 34.00

A1670 Paint exterior siding & trim work A1430 4.00 31-Mar-17 08:00 AM

04-Apr-17 05:00 PM

04-Apr-17 08:00 AM

07-Apr-17 05:00 PM

3.00 0.00

Subtotal 19.00 14-Mar-17 08:00 AM

04-Apr-17 05:00 PM

14-Mar-17 08:00 AM

25-Apr-17 05:00 PM

18.00 0.00

R.8.4

A1680 Install 1st floor - kitchen cabinets A1640 2.00 17-Mar-17 08:00 AM

18-Mar-17 05:00 PM

17-Mar-17 08:00 AM

18-Mar-17 05:00 PM

0.00 0.00

A1690 Install 1st floor - master bath & guest cabinets

A1680 1.00 20-Mar-17 08:00 AM

20-Mar-17 05:00 PM

20-Mar-17 08:00 AM

20-Mar-17 05:00 PM

0.00 0.00

A1700 Install 2nd floor - hall bath & provate bath cabinets

A1690 1.00 21-Mar-17 08:00 AM

21-Mar-17 05:00 PM

22-Mar-17 08:00 AM

22-Mar-17 05:00 PM

1.00 0.00

Abhishek Singh

© Oracle Corporation Page 6 of 9

Page 9: CE 561 - Term Project on Primavera P6

Grouped by WBS and Sorted by Activity ID

WBS

Activity ID Activity Name Predecessors OriginalDuration

Early Start

Early Finish

Late Start Late Finish

Total Float Free Float

A1710 install chair rails, crown moldings,trim

A1700 2.00 22-Mar-17 08:00 AM

23-Mar-17 05:00 PM

14-Apr-17 08:00 AM

15-Apr-17 05:00 PM

20.00 20.00

Subtotal 6.00 17-Mar-17 08:00 AM

23-Mar-17 05:00 PM

17-Mar-17 08:00 AM

15-Apr-17 05:00 PM

20.00 0.00

R.8.5

A1720 Complete 1st floor - kitchen plumbing

A1450, A1680

1.00 20-Mar-17 08:00 AM

20-Mar-17 05:00 PM

20-Mar-17 08:00 AM

20-Mar-17 05:00 PM

0.00 0.00

A1730 Complete 1st floor - master bath & guest plumbing

A1690, A1720

2.00 21-Mar-17 08:00 AM

22-Mar-17 05:00 PM

21-Mar-17 08:00 AM

22-Mar-17 05:00 PM

0.00 0.00

A1740 Complete 2nd floor - hall bath & private bath plumbing

A1730, A1700

2.00 23-Mar-17 08:00 AM

24-Mar-17 05:00 PM

23-Mar-17 08:00 AM

24-Mar-17 05:00 PM

0.00 0.00

A1750 Conduct finish plumbing inspection

A1740 1.00 25-Mar-17 08:00 AM

25-Mar-17 05:00 PM

25-Mar-17 08:00 AM

25-Mar-17 05:00 PM

0.00 0.00

Subtotal 6.00 20-Mar-17 08:00 AM

25-Mar-17 05:00 PM

20-Mar-17 08:00 AM

25-Mar-17 05:00 PM

0.00 0.00

R.8.6

A1760 Complete 1st Floor circuits to service panel

A1480, A1740

1.00 25-Mar-17 08:00 AM

25-Mar-17 05:00 PM

29-Mar-17 08:00 AM

29-Mar-17 05:00 PM

3.00 0.00

A1770 Complete 2nd Floor circuits to service panel

A1760 1.00 27-Mar-17 08:00 AM

27-Mar-17 05:00 PM

30-Mar-17 08:00 AM

30-Mar-17 05:00 PM

3.00 0.00

A1780 Conduct finish electrical inspection

A1770 1.00 28-Mar-17 08:00 AM

28-Mar-17 05:00 PM

31-Mar-17 08:00 AM

31-Mar-17 05:00 PM

3.00 3.00

A1790 Complete communications wiring- phone, cable, computer alarm

A1750 2.00 27-Mar-17 08:00 AM

28-Mar-17 05:00 PM

27-Mar-17 08:00 AM

28-Mar-17 05:00 PM

0.00 0.00

Subtotal 3.00 25-Mar-17 08:00 AM

28-Mar-17 05:00 PM

27-Mar-17 08:00 AM

31-Mar-17 05:00 PM

3.00 0.00

Abhishek Singh

© Oracle Corporation Page 7 of 9

Page 10: CE 561 - Term Project on Primavera P6

Grouped by WBS and Sorted by Activity ID

WBS

Activity ID Activity Name Predecessors OriginalDuration

Early Start

Early Finish

Late Start Late Finish

Total Float Free Float

R.8.7

A1800 Complete 1st floor - zone 1 HVAC

A1500, A1790

1.00 29-Mar-17 08:00 AM

29-Mar-17 05:00 PM

29-Mar-17 08:00 AM

29-Mar-17 05:00 PM

0.00 0.00

A1810 Complete 2nd floor - zone 2 HVAC

A1800 1.00 30-Mar-17 08:00 AM

30-Mar-17 05:00 PM

30-Mar-17 08:00 AM

30-Mar-17 05:00 PM

0.00 0.00

A1820 Conduct HVAC inspection A1810 1.00 31-Mar-17 08:00 AM

31-Mar-17 05:00 PM

31-Mar-17 08:00 AM

31-Mar-17 05:00 PM

0.00 0.00

Subtotal 3.00 29-Mar-17 08:00 AM

31-Mar-17 05:00 PM

29-Mar-17 08:00 AM

31-Mar-17 05:00 PM

0.00 0.00

R.8.8

A1830 Tile entry, kitchen & bath A1780, A1820

3.00 01-Apr-17 08:00 AM

04-Apr-17 05:00 PM

01-Apr-17 08:00 AM

04-Apr-17 05:00 PM

0.00 0.00

A1840 Carpet 1st floor A1830 2.00 05-Apr-17 08:00 AM

06-Apr-17 05:00 PM

05-Apr-17 08:00 AM

06-Apr-17 05:00 PM

0.00 0.00

A1850 Carpet 2nd floor A1840 2.00 07-Apr-17 08:00 AM

08-Apr-17 05:00 PM

07-Apr-17 08:00 AM

08-Apr-17 05:00 PM

0.00 0.00

A1860 Install Appliances A1850 1.00 10-Apr-17 08:00 AM

10-Apr-17 05:00 PM

10-Apr-17 08:00 AM

10-Apr-17 05:00 PM

0.00 0.00

Subtotal 8.00 01-Apr-17 08:00 AM

10-Apr-17 05:00 PM

01-Apr-17 08:00 AM

10-Apr-17 05:00 PM

0.00 0.00

Subtotal 29.00 08-Mar-17 08:00 AM

10-Apr-17 05:00 PM

08-Mar-17 08:00 AM

25-Apr-17 05:00 PM

13.00 0.00

R.9

A1870 Pour concrete driveway and sidewalks

A1670 2.00 05-Apr-17 08:00 AM

06-Apr-17 05:00 PM

08-Apr-17 08:00 AM

10-Apr-17 05:00 PM

3.00 3.00

A1880 Install backyard fence A1870, A1860

2.00 11-Apr-17 08:00 AM

12-Apr-17 05:00 PM

11-Apr-17 08:00 AM

12-Apr-17 05:00 PM

0.00 0.00

Abhishek Singh

© Oracle Corporation Page 8 of 9

Page 11: CE 561 - Term Project on Primavera P6

Grouped by WBS and Sorted by Activity ID

WBS

Activity ID Activity Name Predecessors OriginalDuration

Early Start

Early Finish

Late Start Late Finish

Total Float Free Float

A1890 Sod & complete plantings - frontyard

A1880 2.00 13-Apr-17 08:00 AM

14-Apr-17 05:00 PM

13-Apr-17 08:00 AM

14-Apr-17 05:00 PM

0.00 0.00

A1900 Sod & complete plantings - backyard

A1890 1.00 15-Apr-17 08:00 AM

15-Apr-17 05:00 PM

15-Apr-17 08:00 AM

15-Apr-17 05:00 PM

0.00 0.00

Subtotal 10.00 05-Apr-17 08:00 AM

15-Apr-17 05:00 PM

08-Apr-17 08:00 AM

15-Apr-17 05:00 PM

0.00 0.00

R.5

A1910 Complete final inspection for certificate of occupancy

A1900, A1820, A1780, A1750, A1710, A1550, A1460

1.00 17-Apr-17 08:00 AM

17-Apr-17 05:00 PM

17-Apr-17 08:00 AM

17-Apr-17 05:00 PM

0.00 0.00

A1920 Cleanup for occupancy A1860, A1910

1.00 18-Apr-17 08:00 AM

18-Apr-17 05:00 PM

18-Apr-17 08:00 AM

18-Apr-17 05:00 PM

0.00 0.00

A1930 Perform final walk - through inspection

A1920 1.00 19-Apr-17 08:00 AM

19-Apr-17 05:00 PM

19-Apr-17 08:00 AM

19-Apr-17 05:00 PM

0.00 0.00

A1940 Complete punch list items A1930 5.00 20-Apr-17 08:00 AM

25-Apr-17 05:00 PM

20-Apr-17 08:00 AM

25-Apr-17 05:00 PM

0.00 0.00

Subtotal 8.00 17-Apr-17 08:00 AM

25-Apr-17 05:00 PM

17-Apr-17 08:00 AM

25-Apr-17 05:00 PM

0.00 0.00

Subtotal 151.00 01-Nov-16 08:00 AM

25-Apr-17 05:00 PM

01-Nov-16 08:00 AM

25-Apr-17 05:00 PM

0.00 0.00

Abhishek Singh

© Oracle Corporation Page 9 of 9

Page 12: CE 561 - Term Project on Primavera P6

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08

October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

25-Apr-17 05:00 PM, Residential Construction

25-Nov-16 05:00 PM, General Conditions

Finalize Plans & Develop estimate with owner, architect

Sign Contract & Notice to proceed25-Nov-16 05:00 PM, Apply For Permits

Secure Foundation Permit

Secure Framing Permit

Secure Electrical Permit

Secure Plumbing Permit

Secure HVAC Permit

Secure miscellaneous permits29-Nov-16 05:00 PM, Site Work

Clear and grub lot

Install temporary power service

Install underground utilities

17-Jan-17 05:00 PM, Foundation

Excavate for foundations

Form basement walls

Place concrete for foundations & basement walls

Cure basement walls for 7 days

Strip basement wall forms

Waterproof / insulate bsement walls

Perform foundation inspection

Backfill foundation11-Feb-17 05:00 PM, Framing

Install 1st floor joists

Lay 1st floor decking

Frame 1st floor walls

Frame 1st floor corners

Install 2nd floor joist

Frame 2nd Floor decking

Frame 2nd floor walls

Frame 2nd floor corners

Complete roof framing

Conduct framing inspection08-Mar-17 05:00 PM, Dry In

Install 1st Floor Sheathing

Install 2nd Floor Sheathing

Install roof decking

Install felt, flashing, and shingles

Hang 1st floor exterior doors

Install 1st floor windows

Install 2nd floor windows30-Mar-17 05:00 PM, Exterior Finishes

Complete Exterior Brick

Complete exterior siding10-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete

Rough-in-plumbing

Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID

Actual Level of Effort

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 1 of 3 TASK filter: All Activities

© Oracle Corporation

Page 13: CE 561 - Term Project on Primavera P6

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08

October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

Conduct Rough-in-plumbing inspection

Place concrete for basement floor

Rough-in electrical

Conduct Rough-in-electrical inspection

Rough-in HVAC

Conduct Rough-in-HVAC inspection

Rough-in communication - phone, cables, computer, alarm10-Apr-17 05:00 PM, Interior Finishes

18-Mar-17 05:00 PM, Insulation

Place wall insulation - 1st floor

Place wall insulation - 2nd floor

Place ceiling insulation - 2nd floor

Conduct insulation inspection17-Mar-17 05:00 PM, Drywall

Install Drywall - 1st floor walls

Install drywall - 1st floor overhead

Install drywall 2nd floor walls

Install drywall 2nd floor overhead

Tape & Float 1st floor drywall

Tape & Float 2nd floor drywall04-Apr-17 05:00 PM, Paint & Wall Paper

Texture all except entry & kitchen - 1st floor

Paint all except entry & kitchen - 1st floor

Hang wallpaper entry & kitchen - 1st floor

Texture all - 2nd floor

Paint all - 2nd floor

Paint exterior siding & trim work23-Mar-17 05:00 PM, Cabinets

Install 1st floor - kitchen cabinets

Install 1st floor - master bath & guest cabinets

Install 2nd floor - hall bath & provate bath cabinets

install chair rails, crown moldings, trim25-Mar-17 05:00 PM, Finish Plumbing

Complete 1st floor - kitchen plumbing

Complete 1st floor - master bath & guest plumbing

Complete 2nd floor - hall bath & private bath plumbing

Conduct finish plumbing inspection28-Mar-17 05:00 PM, FInish Electrical

Complete 1st Floor circuits to service panel

Complete 2nd Floor circuits to service panel

Conduct finish electrical inspection

Complete communications wiring - phone, cable, computer alarm31-Mar-17 05:00 PM, Finish HVAC

Complete 1st floor - zone 1 HVAC

Complete 2nd floor - zone 2 HVAC

Conduct HVAC inspection10-Apr-17 05:00 PM, Carpet, Tile & Appliances

Tile entry, kitchen & bath

Carpet 1st floor

Carpet 2nd floor

Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID

Actual Level of Effort

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 2 of 3 TASK filter: All Activities

© Oracle Corporation

Page 14: CE 561 - Term Project on Primavera P6

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08

October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

Install Appliances15-Apr-17 05:00 PM, Landscping and Grounds Work

Pour concrete driveway and sidewalks

Install backyard fence

Sod & complete plantings - frontyard

Sod & complete plantings - backyard25-Apr-17 05:00 PM, Final Acceptance

Complete final inspection for certificate of occupancy

Cleanup for occupancy

Perform final walk - through inspection

Complete punch list items

Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID

Actual Level of Effort

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 3 of 3 TASK filter: All Activities

© Oracle Corporation

Page 15: CE 561 - Term Project on Primavera P6

Project: R Residential ConstructionWBS: R.1 General Conditions

WBS: R.S Site Work

WBS: R.2 Foundation

WBS: R.3 Framing

WBS: R.4 Dry In

WBS: R.6 Exterior Finishes

WBS: R.7 Utility Rough B97Ins and Complete Concrete

WBS: R.8 Interior Finishes

WBS: R.9 Landscping and Grounds Work

WBS: R.5 Final Acceptance

WBS: R.1.1 Apply For Permits

WBS: R.8.1 Insulation

WBS: R.8.2 Drywall

WBS: R.8.3 Paint & Wall Paper

WBS: R.8.4 Cabinets

WBS: R.8.5 Finish Plumbing

WBS: R.8.6 FInish Electrical

WBS: R.8.7 Finish HVAC

WBS: R.8.8 Carpet, Tile & Appliances

A1010Sign Cont ract & Noti ce

to p roc eed

A 10 00F inal ize P la ns &

Dev elop e stimate wi th own er, arc hi tect

A1160Secure miscell ane ous perm its

A1150Secure HVA C Permit

A1140Secure Plum bing

Permi t

A1130Secure Elec trica l

Permi t

A1120Secure Fr aming Permi t

A1110Secure Fo und at ion

Permi t

A1040Inst al l underground

utili t ies

A1030Inst all temporary

power serv ice

A1020Clear and grub lot

A1240Backf i ll f oundation

A1230Perf orm f oundatio n

inspect ion

A1220Waterproo f / ins ulate

bseme nt wall s

A 12 10S trip basemen t wall

f o rm s

A 12 00Cure basemen t wall s

f o r 7 day s

A1190Pl ace concr et e f or

f o undations &

basem ent wal ls

A1180Form basement wall s

A1170Excav ate f or

f oundations

A1340Conduct f raming

inspect ion

A1330Com plete roof f ramin g

A1320Frame 2nd f l oor

corn ers

A 13 10F rame 2nd f l oor wa ll s

A 13 00F rame 2nd Floor

decking

A12 90Inst al l 2nd f loor joist

A12 80Frame 1st f loor

corners

A1270Frame 1st f loor wall s

A1260Lay 1st f l oor decking

A1250Inst all 1st f loor joists

A 14 10I nst all 2nd f lo or

windows

A 14 00Inst all 1st f lo or

windows

A13 90Hang 1s t f loor exterior

doors

A13 80Inst al l f elt, fl ashing,

and shingles

A1360Inst al l 2nd Floor

Sheathing

A1350Inst all 1st Floor

Sheath in g

A1370Inst all roof decking

A1430Com plete ext erior

siding

A1420Com plete Exterior

Brick

A1440Rough-in-plumbing

A1510Rough-in

communication - phone, cables,

A 15 00Conduct

Rough-in-HVA C inspection

A14 90Rough-in HVA C

A14 80Conduct

Rough-in-electrical inspection

A1470Rough-in elect rical

A14 60Pl ace concr et e f or

basem ent f l oor

A14 50Conduct

Rough-in-plumbing

inspection

A1520Place wal l i ns ulat ion -

1st f lo or

A15 50Conduct insulati on

inspection

A1540Place ceil ing insulation

- 2nd f l oor

A1530Place wal l i ns ulation -

2nd f lo or

A1600Tape & F loat 1st f loor

dry wall

A1570Inst all dr y wall - 1st

f loor over head

A1560Inst all Drywall - 1 st

f loor wal ls

A1610Tape & Float 2nd fl oor

dry wall

A1590Inst al l dry wall 2nd

f loor ov erhead

A1580Inst all dry wall 2nd

f loor walls

A16 40Hang wallpaper entry &

kitchen - 1s t f loor

A1630Paint all except entry

& kit chen - 1st f loor

A1620Texture al l except entry

& kit chen - 1st f loor

A1670Paint exteri or siding &

trim wor k

A16 60Paint all - 2 nd f loor

A1650Texture al l - 2nd f loor

A 16 90Inst all 1st f lo or - mas ter ba th & g ues t

cabinets

A 16 80Inst all 1st f lo or - kitch en cabinets

A1710insta ll chair r ai ls , crown moldings, trim

A 17 00I nst all 2nd f lo or - hall bath & pro v ate bath

cabinets

A1750Conduct f inish plum bing inspect ion

A1740Com plete 2nd f l oor - hall ba th & pr iv at e ba th

plum bing

A 17 30Com plete 1st f loor - mas ter ba th & g ues t

plum bing

A 17 20Com plete 1st f loor - kitch en plumb ing

A1790Com plete communicatio ns wiring

- phone, cable,

A1780Conduct f inish

elect ri cal inspection

A1770Com plete 2nd F loor

ci rcuits to servi ce panel

A1760Com plete 1st F loor

ci rcu it s t o servi ce panel

A1820Conduct HVAC

inspection

A1810Complete 2nd f l oor -

zone 2 HVAC

A1800Complete 1st fl oor -

zone 1 HVAC

A 18 60I nst all Appliance s

A 18 50Carp et 2nd fl o or

A 18 40Carp et 1st f l oor

A18 30Tile entry, kitchen &

bath

A1900Sod & com plete

plant ings - backy ard

A1890Sod & com plete

plant in gs - f ronty ard

A1880Inst all bac ky ard f enc e

A1870Pour concrete

driv eway and sidewalks

A19 40Complete punch list

items

A1930Perf orm f inal walk -

through inspection

A1920Cleanup f or occupancy

A1910Complete f inal

inspection f or cert if icate of

Abhishek Singh Activity Network Layout

Activity IDActivity Name Page 1 of 2 © Oracle Corporation

Page 16: CE 561 - Term Project on Primavera P6

Activity ID Activity Name Original

Duration

Residential ConstructionResidential Construction 151.00

General ConditionsGeneral Conditions 22.00

A1000 Finalize Plans & Develop estimate with owner, architect20.00

A1010 Sign Contract & Notice to proceed 1.00

Apply For PermitsApply For Permits 1.00

A1110 Secure Foundation Permit 1.00

A1120 Secure Framing Permit 1.00

A1130 Secure Electrical Permit 1.00

A1140 Secure Plumbing Permit 1.00

A1150 Secure HVAC Permit 1.00

A1160 Secure miscellaneous permits 1.00

Site WorkSite Work 3.00

A1020 Clear and grub lot 1.00

A1030 Install temporary power service 1.00

A1040 Install underground utilities 1.00

FoundationFoundation 42.00

A1170 Excavate for foundations 3.00

A1180 Form basement walls 13.00

A1190 Place concrete for foundations & basement walls12.00

A1200 Cure basement walls for 7 days 7.00

A1210 Strip basement wall forms 2.00

A1220 Waterproof / insulate bsement walls 2.00

A1230 Perform foundation inspection 1.00

A1240 Backfill foundation 2.00

FramingFraming 22.00

A1250 Install 1st floor joists 2.00

A1260 Lay 1st floor decking 2.00

A1270 Frame 1st floor walls 4.00

A1280 Frame 1st floor corners 1.00

A1290 Install 2nd floor joist 2.00

A1300 Frame 2nd Floor decking 2.00

A1310 Frame 2nd floor walls 3.00

A1320 Frame 2nd floor corners 2.00

A1330 Complete roof framing 3.00

A1340 Conduct framing inspection 1.00

Dry InDry In 21.00

A1350 Install 1st Floor Sheathing 3.00

A1360 Install 2nd Floor Sheathing 3.00

A1380 Install felt, flashing, and shingles 3.00

A1390 Hang 1st floor exterior doors 1.00

A1400 Install 1st floor windows 3.00

A1410 Install 2nd floor windows 3.00

Exterior FinishesExterior Finishes 0.00

Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete Concrete5.00

A1440 Rough-in-plumbing 5.00

Interior FinishesInterior Finishes 29.00

InsulationInsulation 1.00

A1520 Place wall insulation - 1st floor 1.00

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

25-Apr-17 05:00 PM, Residential Construction

25-Nov-16 05:00 PM, General Conditions

Finalize Plans & Develop estimate with owner, architect

Sign Contract & Notice to proceed25-Nov-16 05:00 PM, Apply For Permits

Secure Foundation Permit

Secure Framing Permit

Secure Electrical Permit

Secure Plumbing Permit

Secure HVAC Permit

Secure miscellaneous permits29-Nov-16 05:00 PM, Site Work

Clear and grub lot

Install temporary power service

Install underground utilities

17-Jan-17 05:00 PM, Foundation

Excavate for foundations

Form basement walls

Place concrete for foundations & basement walls

Cure basement walls for 7 days

Strip basement wall forms

Waterproof / insulate bsement walls

Perform foundation inspection

Backfill foundation11-Feb-17 05:00 PM, Framing

Install 1st floor joists

Lay 1st floor decking

Frame 1st floor walls

Frame 1st floor corners

Install 2nd floor joist

Frame 2nd Floor decking

Frame 2nd floor walls

Frame 2nd floor corners

Complete roof framing

Conduct framing inspection08-Mar-17 05:00 PM, Dry In

Install 1st Floor Sheathing

Install 2nd Floor Sheathing

Install felt, flashing, and shingles

Hang 1st floor exterior doors

Install 1st floor windows

Install 2nd floor windows

24-Feb-17 05:00 PM, Utility Rough B97Ins and Complete Concrete

Rough-in-plumbing10-Apr-17 05:00 PM, Interior Finishes

09-Mar-17 05:00 PM, Insulation

Place wall insulation - 1st floor

Abhishek Singh Activity Table and Gantt Chart for Critical Path Activities

Page 1 of 2 TASK filter: Critical.

© Oracle Corporation

Page 17: CE 561 - Term Project on Primavera P6

Activity ID Activity Name Original

DurationDrywallDrywall 5.00

A1560 Install Drywall - 1st floor walls 2.00

A1570 Install drywall - 1st floor overhead 2.00

A1600 Tape & Float 1st floor drywall 1.00

Paint & Wall PaperPaint & Wall Paper 3.00

A1620 Texture all except entry & kitchen - 1st floor 1.00

A1630 Paint all except entry & kitchen - 1st floor 1.00

A1640 Hang wallpaper entry & kitchen - 1st floor 1.00

CabinetsCabinets 3.00

A1680 Install 1st floor - kitchen cabinets 2.00

A1690 Install 1st floor - master bath & guest cabinets 1.00

Finish PlumbingFinish Plumbing 6.00

A1720 Complete 1st floor - kitchen plumbing 1.00

A1730 Complete 1st floor - master bath & guest plumbing2.00

A1740 Complete 2nd floor - hall bath & private bath plumbing2.00

A1750 Conduct finish plumbing inspection 1.00

FInish ElectricalFInish Electrical 2.00

A1790 Complete communications wiring - phone, cable, computer alarm2.00

Finish HVACFinish HVAC 3.00

A1800 Complete 1st floor - zone 1 HVAC 1.00

A1810 Complete 2nd floor - zone 2 HVAC 1.00

A1820 Conduct HVAC inspection 1.00

Carpet, Tile & AppliancesCarpet, Tile & Appliances 8.00

A1830 Tile entry, kitchen & bath 3.00

A1840 Carpet 1st floor 2.00

A1850 Carpet 2nd floor 2.00

A1860 Install Appliances 1.00

Landscping and Grounds WorkLandscping and Grounds Work 5.00

A1880 Install backyard fence 2.00

A1890 Sod & complete plantings - frontyard 2.00

A1900 Sod & complete plantings - backyard 1.00

Final AcceptanceFinal Acceptance 8.00

A1910 Complete final inspection for certificate of occupancy1.00

A1920 Cleanup for occupancy 1.00

A1930 Perform final walk - through inspection 1.00

A1940 Complete punch list items 5.00

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

13-Mar-17 05:00 PM, Drywall

Install Drywall - 1st floor walls

Install drywall - 1st floor overhead

Tape & Float 1st floor drywall16-Mar-17 05:00 PM, Paint & Wall Paper

Texture all except entry & kitchen - 1st floor

Paint all except entry & kitchen - 1st floor

Hang wallpaper entry & kitchen - 1st floor20-Mar-17 05:00 PM, Cabinets

Install 1st floor - kitchen cabinets

Install 1st floor - master bath & guest cabinets25-Mar-17 05:00 PM, Finish Plumbing

Complete 1st floor - kitchen plumbing

Complete 1st floor - master bath & guest plumbing

Complete 2nd floor - hall bath & private bath plumbing

Conduct finish plumbing inspection28-Mar-17 05:00 PM, FInish Electrical

Complete communications wiring - phone, cable, computer alarm31-Mar-17 05:00 PM, Finish HVAC

Complete 1st floor - zone 1 HVAC

Complete 2nd floor - zone 2 HVAC

Conduct HVAC inspection10-Apr-17 05:00 PM, Carpet, Tile & Appliances

Tile entry, kitchen & bath

Carpet 1st floor

Carpet 2nd floor

Install Appliances15-Apr-17 05:00 PM, Landscping and Grounds Work

Install backyard fence

Sod & complete plantings - frontyard

Sod & complete plantings - backyard25-Apr-17 05:00 PM, Final Acceptance

Complete final inspection for certificate of occupancy

Cleanup for occupancy

Perform final walk - through inspection

Complete punch list items

Abhishek Singh Activity Table and Gantt Chart for Critical Path Activities

Page 2 of 2 TASK filter: Critical.

© Oracle Corporation

Page 18: CE 561 - Term Project on Primavera P6

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08

October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

25-Apr-17 05:00 PM, Residential Construction

25-Nov-16 05:00 PM, General Conditions

Finalize Plans & Develop estimate with owner, architect

Sign Contract & Notice to proceed25-Nov-16 05:00 PM, Apply For Permits

Secure Foundation Permit

Secure Framing Permit

Secure Electrical Permit

Secure Plumbing Permit

Secure HVAC Permit

Secure miscellaneous permits29-Nov-16 05:00 PM, Site Work

Clear and grub lot

Install temporary power service

Install underground utilities

17-Jan-17 05:00 PM, Foundation

Excavate for foundations

Form basement walls

Place concrete for foundations & basement walls

Cure basement walls for 7 days

Strip basement wall forms

Waterproof / insulate bsement walls

Perform foundation inspection

Backfill foundation11-Feb-17 05:00 PM, Framing

Install 1st floor joists

Lay 1st floor decking

Frame 1st floor walls

Frame 1st floor corners

Install 2nd floor joist

Frame 2nd Floor decking

Frame 2nd floor walls

Frame 2nd floor corners

Complete roof framing

Conduct framing inspection08-Mar-17 05:00 PM, Dry In

Install 1st Floor Sheathing

Install 2nd Floor Sheathing

Install felt, flashing, and shingles

Hang 1st floor exterior doors

Install 1st floor windows

Install 2nd floor windows

24-Feb-17 05:00 PM, Utility Rough B97Ins and Complete Concrete

Rough-in-plumbing10-Apr-17 05:00 PM, Interior Finishes

09-Mar-17 05:00 PM, Insulation

Place wall insulation - 1st floor

Abhishek Singh Critical Path Activities

Page 1 of 2 TASK filter: Critical.

© Oracle Corporation

Page 19: CE 561 - Term Project on Primavera P6

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08

October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

13-Mar-17 05:00 PM, Drywall

Install Drywall - 1st floor walls

Install drywall - 1st floor overhead

Tape & Float 1st floor drywall16-Mar-17 05:00 PM, Paint & Wall Paper

Texture all except entry & kitchen - 1st floor

Paint all except entry & kitchen - 1st floor

Hang wallpaper entry & kitchen - 1st floor20-Mar-17 05:00 PM, Cabinets

Install 1st floor - kitchen cabinets

Install 1st floor - master bath & guest cabinets25-Mar-17 05:00 PM, Finish Plumbing

Complete 1st floor - kitchen plumbing

Complete 1st floor - master bath & guest plumbing

Complete 2nd floor - hall bath & private bath plumbing

Conduct finish plumbing inspection28-Mar-17 05:00 PM, FInish Electrical

Complete communications wiring - phone, cable, computer alarm31-Mar-17 05:00 PM, Finish HVAC

Complete 1st floor - zone 1 HVAC

Complete 2nd floor - zone 2 HVAC

Conduct HVAC inspection10-Apr-17 05:00 PM, Carpet, Tile & Appliances

Tile entry, kitchen & bath

Carpet 1st floor

Carpet 2nd floor

Install Appliances15-Apr-17 05:00 PM, Landscping and Grounds Work

Install backyard fence

Sod & complete plantings - frontyard

Sod & complete plantings - backyard25-Apr-17 05:00 PM, Final Acceptance

Complete final inspection for certificate of occupancy

Cleanup for occupancy

Perform final walk - through inspection

Complete punch list items

Abhishek Singh Critical Path Activities

Page 2 of 2 TASK filter: Critical.

© Oracle Corporation

Page 20: CE 561 - Term Project on Primavera P6

Activity ID Activity Name OriginalDuration

Free FloatRemaining

Duration

Residential ConstructionResidential Construction 151.00 0.00151.00

General ConditionsGeneral Conditions 22.00 0.0022.00

A1000 Finalize Plans & Develop estimate with owner, architect20.00 0.0020.00

A1010 Sign Contract & Notice to proceed 1.00 0.00 1.00

Apply For PermitsApply For Permits 1.00 0.00 1.00

A1110Secure Foundation Permit 1.00 0.00 1.00

A1120Secure Framing Permit 1.00 0.00 1.00

A1130Secure Electrical Permit 1.00 0.00 1.00

A1140Secure Plumbing Permit 1.00 0.00 1.00

A1150Secure HVAC Permit 1.00 0.00 1.00

A1160Secure miscellaneous permits 1.00 0.00 1.00

Site WorkSite Work 3.00 0.00 3.00

A1020 Clear and grub lot 1.00 0.00 1.00

A1030 Install temporary power service 1.00 0.00 1.00

A1040 Install underground utilities 1.00 0.00 1.00

FoundationFoundation 42.00 0.0042.00

A1170 Excavate for foundations 3.00 0.00 3.00

A1180 Form basement walls 13.00 0.0013.00

A1190 Place concrete for foundations & basement walls12.00 0.0012.00

A1200 Cure basement walls for 7 days 7.00 0.00 7.00

A1210 Strip basement wall forms 2.00 0.00 2.00

A1220 Waterproof / insulate bsement walls 2.00 0.00 2.00

A1230 Perform foundation inspection 1.00 0.00 1.00

A1240 Backfill foundation 2.00 0.00 2.00

FramingFraming 22.00 0.0022.00

A1250 Install 1st floor joists 2.00 0.00 2.00

A1260 Lay 1st floor decking 2.00 0.00 2.00

A1270 Frame 1st floor walls 4.00 0.00 4.00

A1280 Frame 1st floor corners 1.00 0.00 1.00

A1290 Install 2nd floor joist 2.00 0.00 2.00

A1300 Frame 2nd Floor decking 2.00 0.00 2.00

A1310 Frame 2nd floor walls 3.00 0.00 3.00

A1320 Frame 2nd floor corners 2.00 0.00 2.00

A1330 Complete roof framing 3.00 0.00 3.00

A1340 Conduct framing inspection 1.00 0.00 1.00

Dry InDry In 22.00 0.0022.00

A1370 Install roof decking 3.00 0.00 3.00

A1350 Install 1st Floor Sheathing 3.00 0.00 3.00

A1360 Install 2nd Floor Sheathing 3.00 0.00 3.00

A1380 Install felt, flashing, and shingles 3.00 0.00 3.00

A1390 Hang 1st floor exterior doors 1.00 0.00 1.00

A1400 Install 1st floor windows 3.00 0.00 3.00

A1410 Install 2nd floor windows 3.00 0.00 3.00

Exterior FinishesExterior Finishes 19.00 0.0019.00

A1420 Complete Exterior Brick 16.00 0.0016.00

A1430 Complete exterior siding 3.00 0.00 3.00

Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete Concrete21.00 0.0021.00

A1510 Rough-in communication - phone, cables, computer, alarm2.00 17.00 2.00

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

25-Apr-17 05:00 PM, Residential Construction

25-Nov-16 05:00 PM, General Conditions

Finalize Plans & Develop estimate with owner, architect

Sign Contract & Notice to proceed25-Nov-16 05:00 PM, Apply For Permits

Secure Foundation Permit

Secure Framing Permit

Secure Electrical Permit

Secure Plumbing Permit

Secure HVAC Permit

Secure miscellaneous permits29-Nov-16 05:00 PM, Site Work

Clear and grub lot

Install temporary power service

Install underground utilities

17-Jan-17 05:00 PM, Foundation

Excavate for foundations

Form basement walls

Place concrete for foundations & basement walls

Cure basement walls for 7 days

Strip basement wall forms

Waterproof / insulate bsement walls

Perform foundation inspection

Backfill foundation11-Feb-17 05:00 PM, Framing

Install 1st floor joists

Lay 1st floor decking

Frame 1st floor walls

Frame 1st floor corners

Install 2nd floor joist

Frame 2nd Floor decking

Frame 2nd floor walls

Frame 2nd floor corners

Complete roof framing

Conduct framing inspection08-Mar-17 05:00 PM, Dry In

Install roof decking

Install 1st Floor Sheathing

Install 2nd Floor Sheathing

Install felt, flashing, and shingles

Hang 1st floor exterior doors

Install 1st floor windows

Install 2nd floor windows30-Mar-17 05:00 PM, Exterior Finishes

Complete Exterior Brick

Complete exterior siding10-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete

Rough-in communication - phone, cables, computer, alarm

Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float

Actual Level of Effort

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 1 of 3 TASK filter: All Activities

© Oracle Corporation

Page 21: CE 561 - Term Project on Primavera P6

Activity ID Activity Name OriginalDuration

Free FloatRemaining

DurationA1440 Rough-in-plumbing 5.00 0.00 5.00

A1470 Rough-in electrical 5.00 0.00 5.00

A1450 Conduct Rough-in-plumbing inspection 1.00 0.00 1.00

A1480 Conduct Rough-in-electrical inspection 1.00 0.00 1.00

A1490 Rough-in HVAC 3.00 0.00 3.00

A1460 Place concrete for basement floor 11.00 31.0011.00

A1500 Conduct Rough-in-HVAC inspection 1.00 22.00 1.00

Interior FinishesInterior Finishes 29.00 0.0029.00

InsulationInsulation 9.00 0.00 9.00

A1520Place wall insulation - 1st floor 1.00 0.00 1.00

A1530Place wall insulation - 2nd floor 1.00 1.00 1.00

A1540Place ceiling insulation - 2nd floor 1.00 0.00 1.00

A1550Conduct insulation inspection 1.00 24.00 1.00

DrywallDrywall 9.00 0.00 9.00

A1560Install Drywall - 1st floor walls 2.00 0.00 2.00

A1570Install drywall - 1st floor overhead 2.00 0.00 2.00

A1580Install drywall 2nd floor walls 2.00 0.00 2.00

A1600Tape & Float 1st floor drywall 1.00 0.00 1.00

A1590Install drywall 2nd floor overhead 2.00 0.00 2.00

A1610Tape & Float 2nd floor drywall 1.00 33.00 1.00

Paint & Wall PaperPaint & Wall Paper 19.00 0.0019.00

A1620Texture all except entry & kitchen - 1st floor1.00 0.00 1.00

A1630Paint all except entry & kitchen - 1st floor 1.00 0.00 1.00

A1650Texture all - 2nd floor 1.00 0.00 1.00

A1640Hang wallpaper entry & kitchen - 1st floor1.00 0.00 1.00

A1660Paint all - 2nd floor 1.00 34.00 1.00

A1670Paint exterior siding & trim work 4.00 0.00 4.00

CabinetsCabinets 6.00 0.00 6.00

A1680Install 1st floor - kitchen cabinets 2.00 0.00 2.00

A1690Install 1st floor - master bath & guest cabinets1.00 0.00 1.00

A1700Install 2nd floor - hall bath & provate bath cabinets1.00 0.00 1.00

A1710install chair rails, crown moldings, trim 2.00 20.00 2.00

Finish PlumbingFinish Plumbing 6.00 0.00 6.00

A1720Complete 1st floor - kitchen plumbing 1.00 0.00 1.00

A1730Complete 1st floor - master bath & guest plumbing2.00 0.00 2.00

A1740Complete 2nd floor - hall bath & private bath plumbing2.00 0.00 2.00

A1750Conduct finish plumbing inspection 1.00 0.00 1.00

FInish ElectricalFInish Electrical 3.00 0.00 3.00

A1760Complete 1st Floor circuits to service panel1.00 0.00 1.00

A1770Complete 2nd Floor circuits to service panel1.00 0.00 1.00

A1790Complete communications wiring - phone, cable, computer alarm2.00 0.00 2.00

A1780Conduct finish electrical inspection 1.00 3.00 1.00

Finish HVACFinish HVAC 3.00 0.00 3.00

A1800Complete 1st floor - zone 1 HVAC 1.00 0.00 1.00

A1810Complete 2nd floor - zone 2 HVAC 1.00 0.00 1.00

A1820Conduct HVAC inspection 1.00 0.00 1.00

Carpet, Tile & AppliancesCarpet, Tile & Appliances 8.00 0.00 8.00

A1830Tile entry, kitchen & bath 3.00 0.00 3.00

A1840Carpet 1st floor 2.00 0.00 2.00

A1850Carpet 2nd floor 2.00 0.00 2.00

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

Rough-in-plumbing

Rough-in electrical

Conduct Rough-in-plumbing inspection

Conduct Rough-in-electrical inspection

Rough-in HVAC

Place concrete for basement floor

Conduct Rough-in-HVAC inspection10-Apr-17 05:00 PM, Interior Finishes

18-Mar-17 05:00 PM, Insulation

Place wall insulation - 1st floor

Place wall insulation - 2nd floor

Place ceiling insulation - 2nd floor

Conduct insulation inspection17-Mar-17 05:00 PM, Drywall

Install Drywall - 1st floor walls

Install drywall - 1st floor overhead

Install drywall 2nd floor walls

Tape & Float 1st floor drywall

Install drywall 2nd floor overhead

Tape & Float 2nd floor drywall04-Apr-17 05:00 PM, Paint & Wall Paper

Texture all except entry & kitchen - 1st floor

Paint all except entry & kitchen - 1st floor

Texture all - 2nd floor

Hang wallpaper entry & kitchen - 1st floor

Paint all - 2nd floor

Paint exterior siding & trim work23-Mar-17 05:00 PM, Cabinets

Install 1st floor - kitchen cabinets

Install 1st floor - master bath & guest cabinets

Install 2nd floor - hall bath & provate bath cabinets

install chair rails, crown moldings, trim25-Mar-17 05:00 PM, Finish Plumbing

Complete 1st floor - kitchen plumbing

Complete 1st floor - master bath & guest plumbing

Complete 2nd floor - hall bath & private bath plumbing

Conduct finish plumbing inspection28-Mar-17 05:00 PM, FInish Electrical

Complete 1st Floor circuits to service panel

Complete 2nd Floor circuits to service panel

Complete communications wiring - phone, cable, computer alarm

Conduct finish electrical inspection31-Mar-17 05:00 PM, Finish HVAC

Complete 1st floor - zone 1 HVAC

Complete 2nd floor - zone 2 HVAC

Conduct HVAC inspection10-Apr-17 05:00 PM, Carpet, Tile & Appliances

Tile entry, kitchen & bath

Carpet 1st floor

Carpet 2nd floor

Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float

Actual Level of Effort

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 2 of 3 TASK filter: All Activities

© Oracle Corporation

Page 22: CE 561 - Term Project on Primavera P6

Activity ID Activity Name OriginalDuration

Free FloatRemaining

DurationA1860Install Appliances 1.00 0.00 1.00

Landscping and Grounds WorkLandscping and Grounds Work 10.00 0.0010.00

A1870 Pour concrete driveway and sidewalks 2.00 3.00 2.00

A1880 Install backyard fence 2.00 0.00 2.00

A1890 Sod & complete plantings - frontyard 2.00 0.00 2.00

A1900 Sod & complete plantings - backyard 1.00 0.00 1.00

Final AcceptanceFinal Acceptance 8.00 0.00 8.00

A1910 Complete final inspection for certificate of occupancy1.00 0.00 1.00

A1920 Cleanup for occupancy 1.00 0.00 1.00

A1930 Perform final walk - through inspection 1.00 0.00 1.00

A1940 Complete punch list items 5.00 0.00 5.00

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

Install Appliances15-Apr-17 05:00 PM, Landscping and Grounds Work

Pour concrete driveway and sidewalks

Install backyard fence

Sod & complete plantings - frontyard

Sod & complete plantings - backyard25-Apr-17 05:00 PM, Final Acceptance

Complete final inspection for certificate of occupancy

Cleanup for occupancy

Perform final walk - through inspection

Complete punch list items

Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float

Actual Level of Effort

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 3 of 3 TASK filter: All Activities

© Oracle Corporation

Page 23: CE 561 - Term Project on Primavera P6

Report for the Budgeted Cost

WBS

Activity ID Activity Name OriginalDuration

BudgetedLabor Cost

BudgetedMaterial Cost

Budgeted TotalCost

R Residential Construction

R.1 General Conditions

A1000 Finalize Plans & Develop estimate with owner, architect

20.00 $5,220.00 $0.00 $5,220.00

A1010 Sign Contract & Notice to proceed

1.00 $750.00 $0.00 $750.00

R.1.1 Apply For Permits

A1110 Secure Foundation Permit 1.00 $0.00 $0.00 $0.00

A1120 Secure Framing Permit 1.00 $0.00 $0.00 $0.00

A1130 Secure Electrical Permit 1.00 $0.00 $0.00 $0.00

A1140 Secure Plumbing Permit 1.00 $0.00 $0.00 $0.00

A1150 Secure HVAC Permit 1.00 $0.00 $0.00 $0.00

A1160 Secure miscellaneous permits 1.00 $0.00 $0.00 $0.00

Subtotal 1.00 $0.00 $0.00 $0.00

Subtotal 22.00 $5,970.00 $0.00 $5,970.00

R.S Site Work

A1020 Clear and grub lot 1.00 $150.00 $0.00 $150.00

A1030 Install temporary power service 1.00 $150.00 $0.00 $150.00

A1040 Install underground utilities 1.00 $450.00 $0.00 $450.00

Subtotal 3.00 $750.00 $0.00 $750.00

R.2 Foundation

Abhishek Singh Residential Building Project

© Oracle Corporation Page 1 of 8

Page 24: CE 561 - Term Project on Primavera P6

Report for the Budgeted Cost

WBS

Activity ID Activity Name OriginalDuration

BudgetedLabor Cost

BudgetedMaterial Cost

Budgeted TotalCost

A1170 Excavate for foundations 3.00 $450.00 $0.00 $450.00

A1180 Form basement walls 13.00 $2,600.00 $0.00 $2,600.00

A1190 Place concrete for foundations & basement walls

12.00 $2,400.00 $0.00 $2,400.00

A1200 Cure basement walls for 7 days 7.00 $0.00 $0.00 $0.00

A1210 Strip basement wall forms 2.00 $400.00 $0.00 $400.00

A1220 Waterproof / insulate bsement walls

2.00 $400.00 $0.00 $400.00

A1230 Perform foundation inspection 1.00 $0.00 $500.00 $500.00

A1240 Backfill foundation 2.00 $300.00 $0.00 $300.00

Subtotal 42.00 $6,550.00 $500.00 $7,050.00

R.3 Framing

A1250 Install 1st floor joists 2.00 $400.00 $0.00 $400.00

A1260 Lay 1st floor decking 2.00 $400.00 $0.00 $400.00

A1270 Frame 1st floor walls 4.00 $800.00 $0.00 $800.00

A1280 Frame 1st floor corners 1.00 $200.00 $0.00 $200.00

A1290 Install 2nd floor joist 2.00 $400.00 $0.00 $400.00

A1300 Frame 2nd Floor decking 2.00 $400.00 $0.00 $400.00

A1310 Frame 2nd floor walls 3.00 $600.00 $0.00 $600.00

A1320 Frame 2nd floor corners 2.00 $400.00 $0.00 $400.00

A1330 Complete roof framing 3.00 $600.00 $0.00 $600.00

A1340 Conduct framing inspection 1.00 $0.00 $500.00 $500.00

Subtotal 22.00 $4,200.00 $500.00 $4,700.00

Abhishek Singh Residential Building Project

© Oracle Corporation Page 2 of 8

Page 25: CE 561 - Term Project on Primavera P6

Report for the Budgeted Cost

WBS

Activity ID Activity Name OriginalDuration

BudgetedLabor Cost

BudgetedMaterial Cost

Budgeted TotalCost

R.4 Dry In

A1350 Install 1st Floor Sheathing 3.00 $600.00 $0.00 $600.00

A1360 Install 2nd Floor Sheathing 3.00 $600.00 $0.00 $600.00

A1370 Install roof decking 3.00 $600.00 $0.00 $600.00

A1380 Install felt, flashing, and shingles 3.00 $300.00 $0.00 $300.00

A1390 Hang 1st floor exterior doors 1.00 $200.00 $0.00 $200.00

A1400 Install 1st floor windows 3.00 $600.00 $0.00 $600.00

A1410 Install 2nd floor windows 3.00 $600.00 $0.00 $600.00

Subtotal 22.00 $3,500.00 $0.00 $3,500.00

R.6 Exterior Finishes

A1420 Complete Exterior Brick 16.00 $2,400.00 $0.00 $2,400.00

A1430 Complete exterior siding 3.00 $600.00 $0.00 $600.00

Subtotal 19.00 $3,000.00 $0.00 $3,000.00

R.7 Utility Rough B97Ins and Complete Concrete

A1440 Rough-in-plumbing 5.00 $1,500.00 $0.00 $1,500.00

A1450 Conduct Rough-in-plumbing inspection

1.00 $0.00 $500.00 $500.00

A1460 Place concrete for basement floor

11.00 $2,200.00 $0.00 $2,200.00

A1470 Rough-in electrical 5.00 $750.00 $0.00 $750.00

A1480 Conduct Rough-in-electrical inspection

1.00 $0.00 $500.00 $500.00

Abhishek Singh Residential Building Project

© Oracle Corporation Page 3 of 8

Page 26: CE 561 - Term Project on Primavera P6

Report for the Budgeted Cost

WBS

Activity ID Activity Name OriginalDuration

BudgetedLabor Cost

BudgetedMaterial Cost

Budgeted TotalCost

A1490 Rough-in HVAC 3.00 $450.00 $0.00 $450.00

A1500 Conduct Rough-in-HVAC inspection

1.00 $0.00 $500.00 $500.00

A1510 Rough-in communication - phone, cables, computer, alarm

2.00 $300.00 $0.00 $300.00

Subtotal 21.00 $5,200.00 $1,500.00 $6,700.00

R.8 Interior Finishes

R.8.1 Insulation

A1520 Place wall insulation - 1st floor 1.00 $300.00 $0.00 $300.00

A1530 Place wall insulation - 2nd floor 1.00 $300.00 $0.00 $300.00

A1540 Place ceiling insulation - 2nd floor 1.00 $300.00 $0.00 $300.00

A1550 Conduct insulation inspection 1.00 $0.00 $500.00 $500.00

Subtotal 9.00 $900.00 $500.00 $1,400.00

R.8.2 Drywall

A1560 Install Drywall - 1st floor walls 2.00 $400.00 $0.00 $400.00

A1570 Install drywall - 1st floor overhead

2.00 $400.00 $0.00 $400.00

A1580 Install drywall 2nd floor walls 2.00 $400.00 $0.00 $400.00

A1590 Install drywall 2nd floor overhead 2.00 $400.00 $0.00 $400.00

A1600 Tape & Float 1st floor drywall 1.00 $200.00 $0.00 $200.00

A1610 Tape & Float 2nd floor drywall 1.00 $200.00 $0.00 $200.00

Abhishek Singh Residential Building Project

© Oracle Corporation Page 4 of 8

Page 27: CE 561 - Term Project on Primavera P6

Report for the Budgeted Cost

WBS

Activity ID Activity Name OriginalDuration

BudgetedLabor Cost

BudgetedMaterial Cost

Budgeted TotalCost

Subtotal 9.00 $2,000.00 $0.00 $2,000.00

R.8.3 Paint & Wall Paper

A1620 Texture all except entry & kitchen- 1st floor

1.00 $100.00 $0.00 $100.00

A1630 Paint all except entry & kitchen - 1st floor

1.00 $100.00 $0.00 $100.00

A1640 Hang wallpaper entry & kitchen - 1st floor

1.00 $100.00 $0.00 $100.00

A1650 Texture all - 2nd floor 1.00 $100.00 $0.00 $100.00

A1660 Paint all - 2nd floor 1.00 $100.00 $0.00 $100.00

A1670 Paint exterior siding & trim work 4.00 $400.00 $0.00 $400.00

Subtotal 19.00 $900.00 $0.00 $900.00

R.8.4 Cabinets

A1680 Install 1st floor - kitchen cabinets 2.00 $300.00 $0.00 $300.00

A1690 Install 1st floor - master bath & guest cabinets

1.00 $150.00 $0.00 $150.00

A1700 Install 2nd floor - hall bath & provate bath cabinets

1.00 $150.00 $0.00 $150.00

A1710 install chair rails, crown moldings,trim

2.00 $300.00 $0.00 $300.00

Subtotal 6.00 $900.00 $0.00 $900.00

R.8.5 Finish Plumbing

A1720 Complete 1st floor - kitchen plumbing

1.00 $300.00 $0.00 $300.00

Abhishek Singh Residential Building Project

© Oracle Corporation Page 5 of 8

Page 28: CE 561 - Term Project on Primavera P6

Report for the Budgeted Cost

WBS

Activity ID Activity Name OriginalDuration

BudgetedLabor Cost

BudgetedMaterial Cost

Budgeted TotalCost

A1730 Complete 1st floor - master bath & guest plumbing

2.00 $600.00 $0.00 $600.00

A1740 Complete 2nd floor - hall bath & private bath plumbing

2.00 $600.00 $0.00 $600.00

A1750 Conduct finish plumbing inspection

1.00 $0.00 $500.00 $500.00

Subtotal 6.00 $1,500.00 $500.00 $2,000.00

R.8.6 FInish Electrical

A1760 Complete 1st Floor circuits to service panel

1.00 $150.00 $0.00 $150.00

A1770 Complete 2nd Floor circuits to service panel

1.00 $150.00 $0.00 $150.00

A1780 Conduct finish electrical inspection

1.00 $0.00 $500.00 $500.00

A1790 Complete communications wiring- phone, cable, computer alarm

2.00 $300.00 $0.00 $300.00

Subtotal 3.00 $600.00 $500.00 $1,100.00

R.8.7 Finish HVAC

A1800 Complete 1st floor - zone 1 HVAC

1.00 $150.00 $0.00 $150.00

A1810 Complete 2nd floor - zone 2 HVAC

1.00 $150.00 $0.00 $150.00

A1820 Conduct HVAC inspection 1.00 $0.00 $500.00 $500.00

Subtotal 3.00 $300.00 $500.00 $800.00

Abhishek Singh Residential Building Project

© Oracle Corporation Page 6 of 8

Page 29: CE 561 - Term Project on Primavera P6

Report for the Budgeted Cost

WBS

Activity ID Activity Name OriginalDuration

BudgetedLabor Cost

BudgetedMaterial Cost

Budgeted TotalCost

R.8.8 Carpet, Tile & Appliances

A1830 Tile entry, kitchen & bath 3.00 $450.00 $0.00 $450.00

A1840 Carpet 1st floor 2.00 $300.00 $0.00 $300.00

A1850 Carpet 2nd floor 2.00 $300.00 $0.00 $300.00

A1860 Install Appliances 1.00 $150.00 $0.00 $150.00

Subtotal 8.00 $1,200.00 $0.00 $1,200.00

Subtotal 29.00 $8,300.00 $2,000.00 $10,300.00

R.9 Landscping and Grounds Work

A1870 Pour concrete driveway and sidewalks

2.00 $400.00 $0.00 $400.00

A1880 Install backyard fence 2.00 $300.00 $0.00 $300.00

A1890 Sod & complete plantings - frontyard

2.00 $600.00 $0.00 $600.00

A1900 Sod & complete plantings - backyard

1.00 $300.00 $0.00 $300.00

Subtotal 10.00 $1,600.00 $0.00 $1,600.00

R.5 Final Acceptance

A1910 Complete final inspection for certificate of occupancy

1.00 $0.00 $500.00 $500.00

A1920 Cleanup for occupancy 1.00 $0.00 $0.00 $200.00

A1930 Perform final walk - through inspection

1.00 $200.00 $0.00 $200.00

Abhishek Singh Residential Building Project

© Oracle Corporation Page 7 of 8

Page 30: CE 561 - Term Project on Primavera P6

Report for the Budgeted Cost

WBS

Activity ID Activity Name OriginalDuration

BudgetedLabor Cost

BudgetedMaterial Cost

Budgeted TotalCost

A1940 Complete punch list items 5.00 $750.00 $0.00 $750.00

Subtotal 8.00 $950.00 $500.00 $1,650.00

Subtotal 151.00 $40,020.00 $5,000.00 $45,220.00

Abhishek Singh Residential Building Project

© Oracle Corporation Page 8 of 8

Page 31: CE 561 - Term Project on Primavera P6

Oct 17 Oct 24 Oct 31 Nov 07 Nov 14 Nov 21 Nov 28 Dec 05 Dec 12 Dec 19 Dec 26 Jan 02 Jan 09 Jan 16 Jan 23 Jan 30 Feb 06 Feb 13 Feb 20 Feb 27 Mar 06 Mar 13 Mar 20 Mar 27 Apr 03 Apr 10 Apr 17 Apr 24 May 01 May 08 May 15May 22

$200.00

$400.00

$600.00

$800.00

$1,000.00

$9,000.00

$18,000.00

$27,000.00

$36,000.00

$45,000.00

Abhishek Singh Daily Histogram and Cumulative curve for Labor cost

Budgeted Labor Cost Page 1 of 1 TASK filter: All Activities

© Oracle Corporation

Page 32: CE 561 - Term Project on Primavera P6

Oct 17 Oct 24 Oct 31 Nov 07 Nov 14 Nov 21 Nov 28 Dec 05 Dec 12 Dec 19 Dec 26 Jan 02 Jan 09 Jan 16 Jan 23 Jan 30 Feb 06 Feb 13 Feb 20 Feb 27 Mar 06 Mar 13 Mar 20 Mar 27 Apr 03 Apr 10 Apr 17 Apr 24 May 01 May 08 May 15May 22

$200.00

$400.00

$600.00

$800.00

$1,000.00

$2,000.00

$4,000.00

$6,000.00

$8,000.00

$10,000.00

Abhishek Singh Daily Histogram and Cumulative curve for Material cost

Budgeted Material Cost Page 1 of 1 TASK filter: All Activities

© Oracle Corporation

Page 33: CE 561 - Term Project on Primavera P6

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22

October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

$800.00

$1,600.00

$2,400.00

$3,200.00

$4,000.00

$10,000.00

$20,000.00

$30,000.00

$40,000.00

$50,000.00

Abhishek Singh Monthly Histogram and Cumulative curve for Total Cost

Budgeted Total Cost Page 1 of 1 TASK filter: All Activities

© Oracle Corporation

Page 34: CE 561 - Term Project on Primavera P6

Activity ID Activity Name

Residential ConstructionResidential Construction

General ConditionsGeneral ConditionsA1000 Finalize Plans & Develop estimate with owner, architect

A1010 Sign Contract & Notice to proceed

Apply For PermitsApply For Permits

A1110 Secure Foundation Permit

A1120 Secure Framing Permit

A1130 Secure Electrical Permit

A1140 Secure Plumbing Permit

A1150 Secure HVAC Permit

A1160 Secure miscellaneous permits

Site WorkSite WorkA1020 Clear and grub lot

A1030 Install temporary power service

A1040 Install underground utilities

FoundationFoundationA1170 Excavate for foundations

A1180 Form basement walls

A1190 Place concrete for foundations & basement walls

A1200 Cure basement walls for 7 days

A1210 Strip basement wall forms

A1220 Waterproof / insulate bsement walls

A1230 Perform foundation inspection

A1240 Backfill foundation

FramingFramingA1250 Install 1st floor joists

A1260 Lay 1st floor decking

A1270 Frame 1st floor walls

A1280 Frame 1st floor corners

A1290 Install 2nd floor joist

A1300 Frame 2nd Floor decking

A1310 Frame 2nd floor walls

A1320 Frame 2nd floor corners

A1330 Complete roof framing

A1340 Conduct framing inspection

Dry InDry InA1350 Install 1st Floor Sheathing

A1360 Install 2nd Floor Sheathing

A1370 Install roof decking

A1380 Install felt, flashing, and shingles

A1390 Hang 1st floor exterior doors

A1400 Install 1st floor windows

A1410 Install 2nd floor windows

Exterior FinishesExterior FinishesA1420 Complete Exterior Brick

A1430 Complete exterior siding

Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete ConcreteA1440 Rough-in-plumbing

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22

October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

10-May-17 05:00 PM, Residential Construction

10-Dec-16 05:00 PM, General Conditions

Finalize Plans & Develop estimate with owner, architect

Sign Contract & Notice to proceed10-Dec-16 05:00 PM, Apply For Permits

Secure Foundation Permit

Secure Framing Permit

Secure Electrical Permit

Secure Plumbing Permit

Secure HVAC Permit

Secure miscellaneous permits14-Dec-16 05:00 PM, Site Work

Clear and grub lot

Install temporary power service

Install underground utilities

01-Feb-17 05:00 PM, Foundation

Excavate for foundations

Form basement walls

Place concrete for foundations & basement walls

Cure basement walls for 7 days

Strip basement wall forms

Waterproof / insulate bsement walls

Perform foundation inspection

Backfill foundation27-Feb-17 05:00 PM, Framing

Install 1st floor joists

Lay 1st floor decking

Frame 1st floor walls

Frame 1st floor corners

Install 2nd floor joist

Frame 2nd Floor decking

Frame 2nd floor walls

Frame 2nd floor corners

Complete roof framing

Conduct framing inspection23-Mar-17 05:00 PM, Dry In

Install 1st Floor Sheathing

Install 2nd Floor Sheathing

Install roof decking

Install felt, flashing, and shingles

Hang 1st floor exterior doors

Install 1st floor windows

Install 2nd floor windows14-Apr-17 05:00 PM, Exterior Finishes

Complete Exterior Brick

Complete exterior siding25-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete

Rough-in-plumbing

Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table

Actual Level of Effort

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 1 of 3 TASK filter: All Activities

© Oracle Corporation

Page 35: CE 561 - Term Project on Primavera P6

Activity ID Activity Name

A1450 Conduct Rough-in-plumbing inspection

A1460 Place concrete for basement floor

A1470 Rough-in electrical

A1480 Conduct Rough-in-electrical inspection

A1490 Rough-in HVAC

A1500 Conduct Rough-in-HVAC inspection

A1510 Rough-in communication - phone, cables, computer, alarm

Interior FinishesInterior FinishesInsulationInsulation

A1520 Place wall insulation - 1st floor

A1530 Place wall insulation - 2nd floor

A1540 Place ceiling insulation - 2nd floor

A1550 Conduct insulation inspection

DrywallDrywall

A1560 Install Drywall - 1st floor walls

A1570 Install drywall - 1st floor overhead

A1580 Install drywall 2nd floor walls

A1590 Install drywall 2nd floor overhead

A1600 Tape & Float 1st floor drywall

A1610 Tape & Float 2nd floor drywall

Paint & Wall PaperPaint & Wall Paper

A1620 Texture all except entry & kitchen - 1st floor

A1630 Paint all except entry & kitchen - 1st floor

A1640 Hang wallpaper entry & kitchen - 1st floor

A1650 Texture all - 2nd floor

A1660 Paint all - 2nd floor

A1670 Paint exterior siding & trim work

CabinetsCabinets

A1680 Install 1st floor - kitchen cabinets

A1690 Install 1st floor - master bath & guest cabinets

A1700 Install 2nd floor - hall bath & provate bath cabinets

A1710 install chair rails, crown moldings, trim

Finish PlumbingFinish Plumbing

A1720 Complete 1st floor - kitchen plumbing

A1730 Complete 1st floor - master bath & guest plumbing

A1740 Complete 2nd floor - hall bath & private bath plumbing

A1750 Conduct finish plumbing inspection

FInish ElectricalFInish Electrical

A1760 Complete 1st Floor circuits to service panel

A1770 Complete 2nd Floor circuits to service panel

A1780 Conduct finish electrical inspection

A1790 Complete communications wiring - phone, cable, computer alarm

Finish HVACFinish HVAC

A1800 Complete 1st floor - zone 1 HVAC

A1810 Complete 2nd floor - zone 2 HVAC

A1820 Conduct HVAC inspection

Carpet, Tile & AppliancesCarpet, Tile & Appliances

A1830 Tile entry, kitchen & bath

A1840 Carpet 1st floor

A1850 Carpet 2nd floor

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22

October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

Conduct Rough-in-plumbing inspection

Place concrete for basement floor

Rough-in electrical

Conduct Rough-in-electrical inspection

Rough-in HVAC

Conduct Rough-in-HVAC inspection

Rough-in communication - phone, cables, computer, alarm25-Apr-17 05:00 PM, Interior Finishes

03-Apr-17 05:00 PM, Insulation

Place wall insulation - 1st floor

Place wall insulation - 2nd floor

Place ceiling insulation - 2nd floor

Conduct insulation inspection01-Apr-17 05:00 PM, Drywall

Install Drywall - 1st floor walls

Install drywall - 1st floor overhead

Install drywall 2nd floor walls

Install drywall 2nd floor overhead

Tape & Float 1st floor drywall

Tape & Float 2nd floor drywall19-Apr-17 05:00 PM, Paint & Wall Paper

Texture all except entry & kitchen - 1st floor

Paint all except entry & kitchen - 1st floor

Hang wallpaper entry & kitchen - 1st floor

Texture all - 2nd floor

Paint all - 2nd floor

Paint exterior siding & trim work07-Apr-17 05:00 PM, Cabinets

Install 1st floor - kitchen cabinets

Install 1st floor - master bath & guest cabinets

Install 2nd floor - hall bath & provate bath cabinets

install chair rails, crown moldings, trim10-Apr-17 05:00 PM, Finish Plumbing

Complete 1st floor - kitchen plumbing

Complete 1st floor - master bath & guest plumbing

Complete 2nd floor - hall bath & private bath plumbing

Conduct finish plumbing inspection12-Apr-17 05:00 PM, FInish Electrical

Complete 1st Floor circuits to service panel

Complete 2nd Floor circuits to service panel

Conduct finish electrical inspection

Complete communications wiring - phone, cable, computer alarm15-Apr-17 05:00 PM, Finish HVAC

Complete 1st floor - zone 1 HVAC

Complete 2nd floor - zone 2 HVAC

Conduct HVAC inspection25-Apr-17 05:00 PM, Carpet, Tile & Appliances

Tile entry, kitchen & bath

Carpet 1st floor

Carpet 2nd floor

Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table

Actual Level of Effort

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 2 of 3 TASK filter: All Activities

© Oracle Corporation

Page 36: CE 561 - Term Project on Primavera P6

Activity ID Activity Name

A1860 Install Appliances

Landscping and Grounds WorkLandscping and Grounds WorkA1870 Pour concrete driveway and sidewalks

A1880 Install backyard fence

A1890 Sod & complete plantings - frontyard

A1900 Sod & complete plantings - backyard

Final AcceptanceFinal AcceptanceA1910 Complete final inspection for certificate of occupancy

A1920 Cleanup for occupancy

A1930 Perform final walk - through inspection

A1940 Complete punch list items

17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22

October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017

Install Appliances01-May-17 05:00 PM, Landscping and Grounds Work

Pour concrete driveway and sidewalks

Install backyard fence

Sod & complete plantings - frontyard

Sod & complete plantings - backyard10-May-17 05:00 PM, Final Acceptance

Complete final inspection for certificate of occupancy

Cleanup for occupancy

Perform final walk - through inspection

Complete punch list items

Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table

Actual Level of Effort

Primary Baseline

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 3 of 3 TASK filter: All Activities

© Oracle Corporation

Page 37: CE 561 - Term Project on Primavera P6

Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost

R Residential ConstructionR Residential Construction 164.00 139.00 01-Nov-16 08:00 AM 25-Apr-17 05:00 PM 02-Nov-16 08:00 AM A

10-May-17 05:00 PM 0.00 $45,220.00

R.1 General ConditionsR.1 General Conditions 35.00 10.00 01-Nov-16 08:00 AM 25-Nov-16 05:00 PM 02-Nov-16 08:00 AM A10-Dec-16 05:00 PM 0.00 $5,970.00

A1010 Sign Contract & Notice to proceed 1.00 1.00 24-Nov-16 08:00 AM 24-Nov-16 05:00 PM 09-Dec-16 08:00 AM 09-Dec-16 05:00 PM 0.00 $750.00

A1000 Finalize Plans & Develop estimate with owner, architect 20.00 8.00 01-Nov-16 08:00 AM 23-Nov-16 05:00 PM 02-Nov-16 08:00 AM A08-Dec-16 05:00 PM -13.00 $5,220.00

R.1.1 Apply For PermitsR.1.1 Apply For Permits 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00

A1160 Secure miscellaneous permits 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00

A1150 Secure HVAC Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00

A1140 Secure Plumbing Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00

A1130 Secure Electrical Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00

A1120 Secure Framing Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00

A1110 Secure Foundation Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00

R.S Site WorkR.S Site Work 3.00 3.00 26-Nov-16 08:00 AM 29-Nov-16 05:00 PM 12-Dec-16 08:00 AM 14-Dec-16 05:00 PM 0.00 $750.00

A1040 Install underground utilities 1.00 1.00 29-Nov-16 08:00 AM 29-Nov-16 05:00 PM 14-Dec-16 08:00 AM 14-Dec-16 05:00 PM 0.00 $450.00

A1030 Install temporary power service 1.00 1.00 28-Nov-16 08:00 AM 28-Nov-16 05:00 PM 13-Dec-16 08:00 AM 13-Dec-16 05:00 PM 0.00 $150.00

A1020 Clear and grub lot 1.00 1.00 26-Nov-16 08:00 AM 26-Nov-16 05:00 PM 12-Dec-16 08:00 AM 12-Dec-16 05:00 PM 0.00 $150.00

R.2 FoundationR.2 Foundation 42.00 42.00 30-Nov-16 08:00 AM 17-Jan-17 05:00 PM 15-Dec-16 08:00 AM 01-Feb-17 05:00 PM 0.00 $7,050.00

A1240 Backfill foundation 2.00 2.00 16-Jan-17 08:00 AM 17-Jan-17 05:00 PM 31-Jan-17 08:00 AM 01-Feb-17 05:00 PM 0.00 $300.00

A1230 Perform foundation inspection 1.00 1.00 14-Jan-17 08:00 AM 14-Jan-17 05:00 PM 30-Jan-17 08:00 AM 30-Jan-17 05:00 PM 0.00 $500.00

A1220 Waterproof / insulate bsement walls 2.00 2.00 12-Jan-17 08:00 AM 13-Jan-17 05:00 PM 27-Jan-17 08:00 AM 28-Jan-17 05:00 PM 0.00 $400.00

A1210 Strip basement wall forms 2.00 2.00 10-Jan-17 08:00 AM 11-Jan-17 05:00 PM 25-Jan-17 08:00 AM 26-Jan-17 05:00 PM 0.00 $400.00

A1200 Cure basement walls for 7 days 7.00 7.00 02-Jan-17 08:00 AM 09-Jan-17 05:00 PM 17-Jan-17 08:00 AM 24-Jan-17 05:00 PM 0.00 $0.00

A1190 Place concrete for foundations & basement walls 12.00 12.00 19-Dec-16 08:00 AM 31-Dec-16 05:00 PM 03-Jan-17 08:00 AM 16-Jan-17 05:00 PM 0.00 $2,400.00

A1180 Form basement walls 13.00 13.00 03-Dec-16 08:00 AM 17-Dec-16 05:00 PM 19-Dec-16 08:00 AM 02-Jan-17 05:00 PM 0.00 $2,600.00

A1170 Excavate for foundations 3.00 3.00 30-Nov-16 08:00 AM 02-Dec-16 05:00 PM 15-Dec-16 08:00 AM 17-Dec-16 05:00 PM 0.00 $450.00

R.3 FramingR.3 Framing 22.00 22.00 18-Jan-17 08:00 AM 11-Feb-17 05:00 PM 02-Feb-17 08:00 AM 27-Feb-17 05:00 PM 0.00 $4,700.00

A1340 Conduct framing inspection 1.00 1.00 11-Feb-17 08:00 AM 11-Feb-17 05:00 PM 27-Feb-17 08:00 AM 27-Feb-17 05:00 PM 0.00 $500.00

A1330 Complete roof framing 3.00 3.00 08-Feb-17 08:00 AM 10-Feb-17 05:00 PM 23-Feb-17 08:00 AM 25-Feb-17 05:00 PM 0.00 $600.00

A1320 Frame 2nd floor corners 2.00 2.00 06-Feb-17 08:00 AM 07-Feb-17 05:00 PM 21-Feb-17 08:00 AM 22-Feb-17 05:00 PM 0.00 $400.00

A1310 Frame 2nd floor walls 3.00 3.00 02-Feb-17 08:00 AM 04-Feb-17 05:00 PM 17-Feb-17 08:00 AM 20-Feb-17 05:00 PM 0.00 $600.00

A1300 Frame 2nd Floor decking 2.00 2.00 31-Jan-17 08:00 AM 01-Feb-17 05:00 PM 15-Feb-17 08:00 AM 16-Feb-17 05:00 PM 0.00 $400.00

A1290 Install 2nd floor joist 2.00 2.00 28-Jan-17 08:00 AM 30-Jan-17 05:00 PM 13-Feb-17 08:00 AM 14-Feb-17 05:00 PM 0.00 $400.00

A1280 Frame 1st floor corners 1.00 1.00 27-Jan-17 08:00 AM 27-Jan-17 05:00 PM 11-Feb-17 08:00 AM 11-Feb-17 05:00 PM 0.00 $200.00

A1270 Frame 1st floor walls 4.00 4.00 23-Jan-17 08:00 AM 26-Jan-17 05:00 PM 07-Feb-17 08:00 AM 10-Feb-17 05:00 PM 0.00 $800.00

A1260 Lay 1st floor decking 2.00 2.00 20-Jan-17 08:00 AM 21-Jan-17 05:00 PM 04-Feb-17 08:00 AM 06-Feb-17 05:00 PM 0.00 $400.00

A1250 Install 1st floor joists 2.00 2.00 18-Jan-17 08:00 AM 19-Jan-17 05:00 PM 02-Feb-17 08:00 AM 03-Feb-17 05:00 PM 0.00 $400.00

R.4 Dry InR.4 Dry In 22.00 22.00 11-Feb-17 08:00 AM 08-Mar-17 05:00 PM 27-Feb-17 08:00 AM 23-Mar-17 05:00 PM 0.00 $3,500.00

A1410 Install 2nd floor windows 3.00 3.00 06-Mar-17 08:00 AM 08-Mar-17 05:00 PM 21-Mar-17 08:00 AM 23-Mar-17 05:00 PM 0.00 $600.00

A1400 Install 1st floor windows 3.00 3.00 02-Mar-17 08:00 AM 04-Mar-17 05:00 PM 17-Mar-17 08:00 AM 20-Mar-17 05:00 PM 0.00 $600.00

A1390 Hang 1st floor exterior doors 1.00 1.00 01-Mar-17 08:00 AM 01-Mar-17 05:00 PM 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 0.00 $200.00

A1380 Install felt, flashing, and shingles 3.00 3.00 25-Feb-17 08:00 AM 28-Feb-17 05:00 PM 13-Mar-17 08:00 AM 15-Mar-17 05:00 PM 0.00 $300.00

A1360 Install 2nd Floor Sheathing 3.00 3.00 16-Feb-17 08:00 AM 18-Feb-17 05:00 PM 03-Mar-17 08:00 AM 06-Mar-17 05:00 PM 0.00 $600.00

A1350 Install 1st Floor Sheathing 3.00 3.00 13-Feb-17 08:00 AM 15-Feb-17 05:00 PM 28-Feb-17 08:00 AM 02-Mar-17 05:00 PM 0.00 $600.00

A1370 Install roof decking 3.00 3.00 11-Feb-17 08:00 AM 14-Feb-17 05:00 PM 27-Feb-17 08:00 AM 01-Mar-17 05:00 PM 0.00 $600.00

R.6 Exterior FinishesR.6 Exterior Finishes 19.00 19.00 09-Mar-17 08:00 AM 30-Mar-17 05:00 PM 24-Mar-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $3,000.00

A1430 Complete exterior siding 3.00 3.00 28-Mar-17 08:00 AM 30-Mar-17 05:00 PM 12-Apr-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $600.00

A1420 Complete Exterior Brick 16.00 16.00 09-Mar-17 08:00 AM 27-Mar-17 05:00 PM 24-Mar-17 08:00 AM 11-Apr-17 05:00 PM 0.00 $2,400.00

R.7 Utility Rough B97Ins and Complete ConcreteR.7 Utility Rough B97Ins and Complete Concrete 21.00 21.00 15-Feb-17 08:00 AM 10-Mar-17 05:00 PM 02-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $6,700.00

A1460 Place concrete for basement floor 11.00 11.00 27-Feb-17 08:00 AM 10-Mar-17 05:00 PM 14-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $2,200.00

Abhishek Singh Updated Project Schedule with Activity Table

Page 1 of 3 TASK filter: All Activities

© Oracle Corporation

Page 38: CE 561 - Term Project on Primavera P6

Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost

A1500 Conduct Rough-in-HVAC inspection 1.00 1.00 02-Mar-17 08:00 AM 02-Mar-17 05:00 PM 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 0.00 $500.00

A1490 Rough-in HVAC 3.00 3.00 27-Feb-17 08:00 AM 01-Mar-17 05:00 PM 14-Mar-17 08:00 AM 16-Mar-17 05:00 PM 0.00 $450.00

A1480 Conduct Rough-in-electrical inspection 1.00 1.00 25-Feb-17 08:00 AM 25-Feb-17 05:00 PM 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 0.00 $500.00

A1450 Conduct Rough-in-plumbing inspection 1.00 1.00 25-Feb-17 08:00 AM 25-Feb-17 05:00 PM 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 0.00 $500.00

A1470 Rough-in electrical 5.00 5.00 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 07-Mar-17 08:00 AM 11-Mar-17 05:00 PM 0.00 $750.00

A1440 Rough-in-plumbing 5.00 5.00 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 07-Mar-17 08:00 AM 11-Mar-17 05:00 PM 0.00 $1,500.00

A1510 Rough-in communication - phone, cables, computer, alarm 2.00 2.00 15-Feb-17 08:00 AM 16-Feb-17 05:00 PM 02-Mar-17 08:00 AM 03-Mar-17 05:00 PM 0.00 $300.00

R.8 Interior FinishesR.8 Interior Finishes 29.00 29.00 08-Mar-17 08:00 AM 10-Apr-17 05:00 PM 23-Mar-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $10,300.00

R.8.1 InsulationR.8.1 Insulation 9.00 9.00 09-Mar-17 08:00 AM 18-Mar-17 05:00 PM 24-Mar-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $1,400.00

A1550 Conduct insulation inspection 1.00 1.00 18-Mar-17 08:00 AM 18-Mar-17 05:00 PM 03-Apr-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $500.00

A1540 Place ceiling insulation - 2nd floor 1.00 1.00 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 01-Apr-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $300.00

A1530 Place wall insulation - 2nd floor 1.00 1.00 10-Mar-17 08:00 AM 10-Mar-17 05:00 PM 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $300.00

A1520 Place wall insulation - 1st floor 1.00 1.00 09-Mar-17 08:00 AM 09-Mar-17 05:00 PM 24-Mar-17 08:00 AM 24-Mar-17 05:00 PM 0.00 $300.00

R.8.2 DrywallR.8.2 Drywall 9.00 9.00 08-Mar-17 08:00 AM 17-Mar-17 05:00 PM 23-Mar-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $2,000.00

A1610 Tape & Float 2nd floor drywall 1.00 1.00 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 01-Apr-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $200.00

A1590 Install drywall 2nd floor overhead 2.00 2.00 15-Mar-17 08:00 AM 16-Mar-17 05:00 PM 30-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $400.00

A1580 Install drywall 2nd floor walls 2.00 2.00 13-Mar-17 08:00 AM 14-Mar-17 05:00 PM 28-Mar-17 08:00 AM 29-Mar-17 05:00 PM 0.00 $400.00

A1600 Tape & Float 1st floor drywall 1.00 1.00 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 28-Mar-17 08:00 AM 28-Mar-17 05:00 PM 0.00 $200.00

A1570 Install drywall - 1st floor overhead 2.00 2.00 10-Mar-17 08:00 AM 11-Mar-17 05:00 PM 25-Mar-17 08:00 AM 27-Mar-17 05:00 PM 0.00 $400.00

A1560 Install Drywall - 1st floor walls 2.00 2.00 08-Mar-17 08:00 AM 09-Mar-17 05:00 PM 23-Mar-17 08:00 AM 24-Mar-17 05:00 PM 0.00 $400.00

R.8.3 Paint & Wall PaperR.8.3 Paint & Wall Paper 19.00 19.00 14-Mar-17 08:00 AM 04-Apr-17 05:00 PM 29-Mar-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $900.00

A1670 Paint exterior siding & trim work 4.00 4.00 31-Mar-17 08:00 AM 04-Apr-17 05:00 PM 15-Apr-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $400.00

A1660 Paint all - 2nd floor 1.00 1.00 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $100.00

A1640 Hang wallpaper entry & kitchen - 1st floor 1.00 1.00 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $100.00

A1650 Texture all - 2nd floor 1.00 1.00 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 0.00 $100.00

A1630 Paint all except entry & kitchen - 1st floor 1.00 1.00 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 0.00 $100.00

A1620 Texture all except entry & kitchen - 1st floor 1.00 1.00 14-Mar-17 08:00 AM 14-Mar-17 05:00 PM 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 0.00 $100.00

R.8.4 CabinetsR.8.4 Cabinets 6.00 6.00 17-Mar-17 08:00 AM 23-Mar-17 05:00 PM 01-Apr-17 08:00 AM 07-Apr-17 05:00 PM 0.00 $900.00

A1710 install chair rails, crown moldings, trim 2.00 2.00 22-Mar-17 08:00 AM 23-Mar-17 05:00 PM 06-Apr-17 08:00 AM 07-Apr-17 05:00 PM 0.00 $300.00

A1700 Install 2nd floor - hall bath & provate bath cabinets 1.00 1.00 21-Mar-17 08:00 AM 21-Mar-17 05:00 PM 05-Apr-17 08:00 AM 05-Apr-17 05:00 PM 0.00 $150.00

A1690 Install 1st floor - master bath & guest cabinets 1.00 1.00 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 04-Apr-17 08:00 AM 04-Apr-17 05:00 PM 0.00 $150.00

A1680 Install 1st floor - kitchen cabinets 2.00 2.00 17-Mar-17 08:00 AM 18-Mar-17 05:00 PM 01-Apr-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $300.00

R.8.5 Finish PlumbingR.8.5 Finish Plumbing 6.00 6.00 20-Mar-17 08:00 AM 25-Mar-17 05:00 PM 04-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $2,000.00

A1750 Conduct finish plumbing inspection 1.00 1.00 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $500.00

A1740 Complete 2nd floor - hall bath & private bath plumbing 2.00 2.00 23-Mar-17 08:00 AM 24-Mar-17 05:00 PM 07-Apr-17 08:00 AM 08-Apr-17 05:00 PM 0.00 $600.00

A1730 Complete 1st floor - master bath & guest plumbing 2.00 2.00 21-Mar-17 08:00 AM 22-Mar-17 05:00 PM 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 0.00 $600.00

A1720 Complete 1st floor - kitchen plumbing 1.00 1.00 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 04-Apr-17 08:00 AM 04-Apr-17 05:00 PM 0.00 $300.00

R.8.6 FInish ElectricalR.8.6 FInish Electrical 3.00 3.00 25-Mar-17 08:00 AM 28-Mar-17 05:00 PM 10-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $1,100.00

A1790 Complete communications wiring - phone, cable, computer alarm 2.00 2.00 27-Mar-17 08:00 AM 28-Mar-17 05:00 PM 11-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $300.00

A1780 Conduct finish electrical inspection 1.00 1.00 28-Mar-17 08:00 AM 28-Mar-17 05:00 PM 12-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $500.00

A1770 Complete 2nd Floor circuits to service panel 1.00 1.00 27-Mar-17 08:00 AM 27-Mar-17 05:00 PM 11-Apr-17 08:00 AM 11-Apr-17 05:00 PM 0.00 $150.00

A1760 Complete 1st Floor circuits to service panel 1.00 1.00 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $150.00

R.8.7 Finish HVACR.8.7 Finish HVAC 3.00 3.00 29-Mar-17 08:00 AM 31-Mar-17 05:00 PM 13-Apr-17 08:00 AM 15-Apr-17 05:00 PM 0.00 $800.00

A1820 Conduct HVAC inspection 1.00 1.00 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 0.00 $500.00

A1810 Complete 2nd floor - zone 2 HVAC 1.00 1.00 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 14-Apr-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $150.00

A1800 Complete 1st floor - zone 1 HVAC 1.00 1.00 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 13-Apr-17 08:00 AM 13-Apr-17 05:00 PM 0.00 $150.00

R.8.8 Carpet, Tile & AppliancesR.8.8 Carpet, Tile & Appliances 8.00 8.00 01-Apr-17 08:00 AM 10-Apr-17 05:00 PM 17-Apr-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $1,200.00

A1860 Install Appliances 1.00 1.00 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 25-Apr-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $150.00

A1850 Carpet 2nd floor 2.00 2.00 07-Apr-17 08:00 AM 08-Apr-17 05:00 PM 22-Apr-17 08:00 AM 24-Apr-17 05:00 PM 0.00 $300.00

A1840 Carpet 1st floor 2.00 2.00 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 20-Apr-17 08:00 AM 21-Apr-17 05:00 PM 0.00 $300.00

Abhishek Singh Updated Project Schedule with Activity Table

Page 2 of 3 TASK filter: All Activities

© Oracle Corporation

Page 39: CE 561 - Term Project on Primavera P6

Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost

A1830 Tile entry, kitchen & bath 3.00 3.00 01-Apr-17 08:00 AM 04-Apr-17 05:00 PM 17-Apr-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $450.00

R.9 Landscping and Grounds WorkR.9 Landscping and Grounds Work 10.00 10.00 05-Apr-17 08:00 AM 15-Apr-17 05:00 PM 20-Apr-17 08:00 AM 01-May-17 05:00 PM 0.00 $1,600.00

A1900 Sod & complete plantings - backyard 1.00 1.00 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 01-May-17 08:00 AM 01-May-17 05:00 PM 0.00 $300.00

A1890 Sod & complete plantings - frontyard 2.00 2.00 13-Apr-17 08:00 AM 14-Apr-17 05:00 PM 28-Apr-17 08:00 AM 29-Apr-17 05:00 PM 0.00 $600.00

A1880 Install backyard fence 2.00 2.00 11-Apr-17 08:00 AM 12-Apr-17 05:00 PM 26-Apr-17 08:00 AM 27-Apr-17 05:00 PM 0.00 $300.00

A1870 Pour concrete driveway and sidewalks 2.00 2.00 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 20-Apr-17 08:00 AM 21-Apr-17 05:00 PM 0.00 $400.00

R.5 Final AcceptanceR.5 Final Acceptance 8.00 8.00 17-Apr-17 08:00 AM 25-Apr-17 05:00 PM 02-May-17 08:00 AM 10-May-17 05:00 PM 0.00 $1,650.00

A1940 Complete punch list items 5.00 5.00 20-Apr-17 08:00 AM 25-Apr-17 05:00 PM 05-May-17 08:00 AM 10-May-17 05:00 PM 0.00 $750.00

A1930 Perform final walk - through inspection 1.00 1.00 19-Apr-17 08:00 AM 19-Apr-17 05:00 PM 04-May-17 08:00 AM 04-May-17 05:00 PM 0.00 $200.00

A1920 Cleanup for occupancy 1.00 1.00 18-Apr-17 08:00 AM 18-Apr-17 05:00 PM 03-May-17 08:00 AM 03-May-17 05:00 PM 0.00 $200.00

A1910 Complete final inspection for certificate of occupancy 1.00 1.00 17-Apr-17 08:00 AM 17-Apr-17 05:00 PM 02-May-17 08:00 AM 02-May-17 05:00 PM 0.00 $500.00

Abhishek Singh Updated Project Schedule with Activity Table

Page 3 of 3 TASK filter: All Activities