Upload
abhishek-singh
View
48
Download
0
Embed Size (px)
Citation preview
CE 561
Construction Project Management
Small Residential Building Project
FALL - 2016
ABHISHEK KUMAR SINGH
200116822
Table of Contents
SL No. Report Name
1 Grouped by Project and Sorted by Activity ID
2 Gantt Chart for activities grouped by WBS and Sorted by Activity ID
3 Activity Network Layout of the Project
4 Activity Table & Gantt Chart Schedule for Critical Activities
5 Gantt Chart Schedule for Critical Activities
6 Gantt Chart Schedule for activities Sorted by Early Start & Free Float
7 Report for Budgeted Cost
8 Daily Histogram and cumulative curve for Labor cost
9 Daily Histogram and cumulative curve for Material Cost
10 Monthly Histogram and Cumulative curve for Total Cost
11 Updated Schedule Report and Gantt Chart Table
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
R
R.1
A1000 Finalize Plans & Develop estimate with owner, architect
20.00 01-Nov-16 08:00 AM
23-Nov-16 05:00 PM
01-Nov-16 08:00 AM
23-Nov-16 05:00 PM
0.00 0.00
A1010 Sign Contract & Notice to proceed
A1000 1.00 24-Nov-16 08:00 AM
24-Nov-16 05:00 PM
24-Nov-16 08:00 AM
24-Nov-16 05:00 PM
0.00 0.00
R.1.1
A1110 Secure Foundation Permit A1010 1.00 25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
0.00 0.00
A1120 Secure Framing Permit A1010 1.00 25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
0.00 0.00
A1130 Secure Electrical Permit A1010 1.00 25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
0.00 0.00
A1140 Secure Plumbing Permit A1010 1.00 25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
0.00 0.00
A1150 Secure HVAC Permit A1010 1.00 25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
0.00 0.00
A1160 Secure miscellaneous permits A1010 1.00 25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
0.00 0.00
Subtotal 1.00 25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
25-Nov-16 08:00 AM
25-Nov-16 05:00 PM
0.00 0.00
Subtotal 22.00 01-Nov-16 08:00 AM
25-Nov-16 05:00 PM
01-Nov-16 08:00 AM
25-Nov-16 05:00 PM
0.00 0.00
R.S
A1020 Clear and grub lot A1110, A1120, A1130, A1140, A1150,
1.00 26-Nov-16 08:00 AM
26-Nov-16 05:00 PM
26-Nov-16 08:00 AM
26-Nov-16 05:00 PM
0.00 0.00
Abhishek Singh
© Oracle Corporation Page 1 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1030 Install temporary power service A1020 1.00 28-Nov-16 08:00 AM
28-Nov-16 05:00 PM
28-Nov-16 08:00 AM
28-Nov-16 05:00 PM
0.00 0.00
A1040 Install underground utilities A1030 1.00 29-Nov-16 08:00 AM
29-Nov-16 05:00 PM
29-Nov-16 08:00 AM
29-Nov-16 05:00 PM
0.00 0.00
Subtotal 3.00 26-Nov-16 08:00 AM
29-Nov-16 05:00 PM
26-Nov-16 08:00 AM
29-Nov-16 05:00 PM
0.00 0.00
R.2
A1170 Excavate for foundations A1040 3.00 30-Nov-16 08:00 AM
02-Dec-16 05:00 PM
30-Nov-16 08:00 AM
02-Dec-16 05:00 PM
0.00 0.00
A1180 Form basement walls A1170 13.00 03-Dec-16 08:00 AM
17-Dec-16 05:00 PM
03-Dec-16 08:00 AM
17-Dec-16 05:00 PM
0.00 0.00
A1190 Place concrete for foundations & basement walls
A1180 12.00 19-Dec-16 08:00 AM
31-Dec-16 05:00 PM
19-Dec-16 08:00 AM
31-Dec-16 05:00 PM
0.00 0.00
A1200 Cure basement walls for 7 days A1190 7.00 02-Jan-17 08:00 AM
09-Jan-17 05:00 PM
02-Jan-17 08:00 AM
09-Jan-17 05:00 PM
0.00 0.00
A1210 Strip basement wall forms A1200 2.00 10-Jan-17 08:00 AM
11-Jan-17 05:00 PM
10-Jan-17 08:00 AM
11-Jan-17 05:00 PM
0.00 0.00
A1220 Waterproof / insulate bsement walls
A1210 2.00 12-Jan-17 08:00 AM
13-Jan-17 05:00 PM
12-Jan-17 08:00 AM
13-Jan-17 05:00 PM
0.00 0.00
A1230 Perform foundation inspection A1170, A1220
1.00 14-Jan-17 08:00 AM
14-Jan-17 05:00 PM
14-Jan-17 08:00 AM
14-Jan-17 05:00 PM
0.00 0.00
A1240 Backfill foundation A1230 2.00 16-Jan-17 08:00 AM
17-Jan-17 05:00 PM
16-Jan-17 08:00 AM
17-Jan-17 05:00 PM
0.00 0.00
Subtotal 42.00 30-Nov-16 08:00 AM
17-Jan-17 05:00 PM
30-Nov-16 08:00 AM
17-Jan-17 05:00 PM
0.00 0.00
R.3
A1250 Install 1st floor joists A1240 2.00 18-Jan-17 08:00 AM
19-Jan-17 05:00 PM
18-Jan-17 08:00 AM
19-Jan-17 05:00 PM
0.00 0.00
Abhishek Singh
© Oracle Corporation Page 2 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1260 Lay 1st floor decking A1250 2.00 20-Jan-17 08:00 AM
21-Jan-17 05:00 PM
20-Jan-17 08:00 AM
21-Jan-17 05:00 PM
0.00 0.00
A1270 Frame 1st floor walls A1260 4.00 23-Jan-17 08:00 AM
26-Jan-17 05:00 PM
23-Jan-17 08:00 AM
26-Jan-17 05:00 PM
0.00 0.00
A1280 Frame 1st floor corners A1270 1.00 27-Jan-17 08:00 AM
27-Jan-17 05:00 PM
27-Jan-17 08:00 AM
27-Jan-17 05:00 PM
0.00 0.00
A1290 Install 2nd floor joist A1280 2.00 28-Jan-17 08:00 AM
30-Jan-17 05:00 PM
28-Jan-17 08:00 AM
30-Jan-17 05:00 PM
0.00 0.00
A1300 Frame 2nd Floor decking A1290 2.00 31-Jan-17 08:00 AM
01-Feb-17 05:00 PM
31-Jan-17 08:00 AM
01-Feb-17 05:00 PM
0.00 0.00
A1310 Frame 2nd floor walls A1300 3.00 02-Feb-17 08:00 AM
04-Feb-17 05:00 PM
02-Feb-17 08:00 AM
04-Feb-17 05:00 PM
0.00 0.00
A1320 Frame 2nd floor corners A1310 2.00 06-Feb-17 08:00 AM
07-Feb-17 05:00 PM
06-Feb-17 08:00 AM
07-Feb-17 05:00 PM
0.00 0.00
A1330 Complete roof framing A1320 3.00 08-Feb-17 08:00 AM
10-Feb-17 05:00 PM
08-Feb-17 08:00 AM
10-Feb-17 05:00 PM
0.00 0.00
A1340 Conduct framing inspection A1330 1.00 11-Feb-17 08:00 AM
11-Feb-17 05:00 PM
11-Feb-17 08:00 AM
11-Feb-17 05:00 PM
0.00 0.00
Subtotal 22.00 18-Jan-17 08:00 AM
11-Feb-17 05:00 PM
18-Jan-17 08:00 AM
11-Feb-17 05:00 PM
0.00 0.00
R.4
A1350 Install 1st Floor Sheathing A1340 3.00 13-Feb-17 08:00 AM
15-Feb-17 05:00 PM
13-Feb-17 08:00 AM
15-Feb-17 05:00 PM
0.00 0.00
A1360 Install 2nd Floor Sheathing A1350 3.00 16-Feb-17 08:00 AM
18-Feb-17 05:00 PM
16-Feb-17 08:00 AM
18-Feb-17 05:00 PM
0.00 0.00
A1370 Install roof decking A1330 3.00 11-Feb-17 08:00 AM
14-Feb-17 05:00 PM
16-Feb-17 08:00 AM
18-Feb-17 05:00 PM
4.00 0.00
A1380 Install felt, flashing, and shingles A1440 3.00 25-Feb-17 08:00 AM
28-Feb-17 05:00 PM
25-Feb-17 08:00 AM
28-Feb-17 05:00 PM
0.00 0.00
A1390 Hang 1st floor exterior doors A1380 1.00 01-Mar-17 08:00 AM
01-Mar-17 05:00 PM
01-Mar-17 08:00 AM
01-Mar-17 05:00 PM
0.00 0.00
Abhishek Singh
© Oracle Corporation Page 3 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1400 Install 1st floor windows A1390 3.00 02-Mar-17 08:00 AM
04-Mar-17 05:00 PM
02-Mar-17 08:00 AM
04-Mar-17 05:00 PM
0.00 0.00
A1410 Install 2nd floor windows A1400 3.00 06-Mar-17 08:00 AM
08-Mar-17 05:00 PM
06-Mar-17 08:00 AM
08-Mar-17 05:00 PM
0.00 0.00
Subtotal 22.00 11-Feb-17 08:00 AM
08-Mar-17 05:00 PM
13-Feb-17 08:00 AM
08-Mar-17 05:00 PM
0.00 0.00
R.6
A1420 Complete Exterior Brick A1410 16.00 09-Mar-17 08:00 AM
27-Mar-17 05:00 PM
13-Mar-17 08:00 AM
30-Mar-17 05:00 PM
3.00 0.00
A1430 Complete exterior siding A1420 3.00 28-Mar-17 08:00 AM
30-Mar-17 05:00 PM
31-Mar-17 08:00 AM
03-Apr-17 05:00 PM
3.00 0.00
Subtotal 19.00 09-Mar-17 08:00 AM
30-Mar-17 05:00 PM
13-Mar-17 08:00 AM
03-Apr-17 05:00 PM
3.00 0.00
R.7
A1440 Rough-in-plumbing A1370, A1360
5.00 20-Feb-17 08:00 AM
24-Feb-17 05:00 PM
20-Feb-17 08:00 AM
24-Feb-17 05:00 PM
0.00 0.00
A1450 Conduct Rough-in-plumbing inspection
A1440 1.00 25-Feb-17 08:00 AM
25-Feb-17 05:00 PM
18-Mar-17 08:00 AM
18-Mar-17 05:00 PM
18.00 0.00
A1460 Place concrete for basement floor
A1450 11.00 27-Feb-17 08:00 AM
10-Mar-17 05:00 PM
04-Apr-17 08:00 AM
15-Apr-17 05:00 PM
31.00 31.00
A1470 Rough-in electrical A1370, A1360
5.00 20-Feb-17 08:00 AM
24-Feb-17 05:00 PM
27-Feb-17 08:00 AM
03-Mar-17 05:00 PM
6.00 0.00
A1480 Conduct Rough-in-electrical inspection
A1470 1.00 25-Feb-17 08:00 AM
25-Feb-17 05:00 PM
04-Mar-17 08:00 AM
04-Mar-17 05:00 PM
6.00 0.00
A1490 Rough-in HVAC A1480 3.00 27-Feb-17 08:00 AM
01-Mar-17 05:00 PM
06-Mar-17 08:00 AM
08-Mar-17 05:00 PM
6.00 0.00
A1500 Conduct Rough-in-HVAC inspection
A1490 1.00 02-Mar-17 08:00 AM
02-Mar-17 05:00 PM
28-Mar-17 08:00 AM
28-Mar-17 05:00 PM
22.00 22.00
Abhishek Singh
© Oracle Corporation Page 4 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1510 Rough-in communication - phone, cables, computer, alarm
A1370 2.00 15-Feb-17 08:00 AM
16-Feb-17 05:00 PM
07-Mar-17 08:00 AM
08-Mar-17 05:00 PM
17.00 17.00
Subtotal 21.00 15-Feb-17 08:00 AM
10-Mar-17 05:00 PM
20-Feb-17 08:00 AM
15-Apr-17 05:00 PM
31.00 0.00
R.8
R.8.1
A1520 Place wall insulation - 1st floor A1350, A1360, A1470, A1490, A1510, A1410
1.00 09-Mar-17 08:00 AM
09-Mar-17 05:00 PM
09-Mar-17 08:00 AM
09-Mar-17 05:00 PM
0.00 0.00
A1530 Place wall insulation - 2nd floor A1520 1.00 10-Mar-17 08:00 AM
10-Mar-17 05:00 PM
08-Apr-17 08:00 AM
08-Apr-17 05:00 PM
25.00 1.00
A1540 Place ceiling insulation - 2nd floor A1530, A1590
1.00 17-Mar-17 08:00 AM
17-Mar-17 05:00 PM
14-Apr-17 08:00 AM
14-Apr-17 05:00 PM
24.00 0.00
A1550 Conduct insulation inspection A1540 1.00 18-Mar-17 08:00 AM
18-Mar-17 05:00 PM
15-Apr-17 08:00 AM
15-Apr-17 05:00 PM
24.00 24.00
Subtotal 9.00 09-Mar-17 08:00 AM
18-Mar-17 05:00 PM
09-Mar-17 08:00 AM
15-Apr-17 05:00 PM
24.00 0.00
R.8.2
A1560 Install Drywall - 1st floor walls A1520 2.00 08-Mar-17 08:00 AM
09-Mar-17 05:00 PM
08-Mar-17 08:00 AM
09-Mar-17 05:00 PM
0.00 0.00
A1570 Install drywall - 1st floor overhead
A1560 2.00 10-Mar-17 08:00 AM
11-Mar-17 05:00 PM
10-Mar-17 08:00 AM
11-Mar-17 05:00 PM
0.00 0.00
A1580 Install drywall 2nd floor walls A1570, A1530
2.00 13-Mar-17 08:00 AM
14-Mar-17 05:00 PM
10-Apr-17 08:00 AM
11-Apr-17 05:00 PM
24.00 0.00
A1590 Install drywall 2nd floor overhead A1580 2.00 15-Mar-17 08:00 AM
16-Mar-17 05:00 PM
12-Apr-17 08:00 AM
13-Apr-17 05:00 PM
24.00 0.00
Abhishek Singh
© Oracle Corporation Page 5 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1600 Tape & Float 1st floor drywall A1570 1.00 13-Mar-17 08:00 AM
13-Mar-17 05:00 PM
13-Mar-17 08:00 AM
13-Mar-17 05:00 PM
0.00 0.00
A1610 Tape & Float 2nd floor drywall A1600, A1590
1.00 17-Mar-17 08:00 AM
17-Mar-17 05:00 PM
25-Apr-17 08:00 AM
25-Apr-17 05:00 PM
33.00 33.00
Subtotal 9.00 08-Mar-17 08:00 AM
17-Mar-17 05:00 PM
08-Mar-17 08:00 AM
25-Apr-17 05:00 PM
33.00 0.00
R.8.3
A1620 Texture all except entry & kitchen- 1st floor
A1600 1.00 14-Mar-17 08:00 AM
14-Mar-17 05:00 PM
14-Mar-17 08:00 AM
14-Mar-17 05:00 PM
0.00 0.00
A1630 Paint all except entry & kitchen - 1st floor
A1620 1.00 15-Mar-17 08:00 AM
15-Mar-17 05:00 PM
15-Mar-17 08:00 AM
15-Mar-17 05:00 PM
0.00 0.00
A1640 Hang wallpaper entry & kitchen - 1st floor
A1630 1.00 16-Mar-17 08:00 AM
16-Mar-17 05:00 PM
16-Mar-17 08:00 AM
16-Mar-17 05:00 PM
0.00 0.00
A1650 Texture all - 2nd floor A1620 1.00 15-Mar-17 08:00 AM
15-Mar-17 05:00 PM
24-Apr-17 08:00 AM
24-Apr-17 05:00 PM
34.00 0.00
A1660 Paint all - 2nd floor A1650 1.00 16-Mar-17 08:00 AM
16-Mar-17 05:00 PM
25-Apr-17 08:00 AM
25-Apr-17 05:00 PM
34.00 34.00
A1670 Paint exterior siding & trim work A1430 4.00 31-Mar-17 08:00 AM
04-Apr-17 05:00 PM
04-Apr-17 08:00 AM
07-Apr-17 05:00 PM
3.00 0.00
Subtotal 19.00 14-Mar-17 08:00 AM
04-Apr-17 05:00 PM
14-Mar-17 08:00 AM
25-Apr-17 05:00 PM
18.00 0.00
R.8.4
A1680 Install 1st floor - kitchen cabinets A1640 2.00 17-Mar-17 08:00 AM
18-Mar-17 05:00 PM
17-Mar-17 08:00 AM
18-Mar-17 05:00 PM
0.00 0.00
A1690 Install 1st floor - master bath & guest cabinets
A1680 1.00 20-Mar-17 08:00 AM
20-Mar-17 05:00 PM
20-Mar-17 08:00 AM
20-Mar-17 05:00 PM
0.00 0.00
A1700 Install 2nd floor - hall bath & provate bath cabinets
A1690 1.00 21-Mar-17 08:00 AM
21-Mar-17 05:00 PM
22-Mar-17 08:00 AM
22-Mar-17 05:00 PM
1.00 0.00
Abhishek Singh
© Oracle Corporation Page 6 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1710 install chair rails, crown moldings,trim
A1700 2.00 22-Mar-17 08:00 AM
23-Mar-17 05:00 PM
14-Apr-17 08:00 AM
15-Apr-17 05:00 PM
20.00 20.00
Subtotal 6.00 17-Mar-17 08:00 AM
23-Mar-17 05:00 PM
17-Mar-17 08:00 AM
15-Apr-17 05:00 PM
20.00 0.00
R.8.5
A1720 Complete 1st floor - kitchen plumbing
A1450, A1680
1.00 20-Mar-17 08:00 AM
20-Mar-17 05:00 PM
20-Mar-17 08:00 AM
20-Mar-17 05:00 PM
0.00 0.00
A1730 Complete 1st floor - master bath & guest plumbing
A1690, A1720
2.00 21-Mar-17 08:00 AM
22-Mar-17 05:00 PM
21-Mar-17 08:00 AM
22-Mar-17 05:00 PM
0.00 0.00
A1740 Complete 2nd floor - hall bath & private bath plumbing
A1730, A1700
2.00 23-Mar-17 08:00 AM
24-Mar-17 05:00 PM
23-Mar-17 08:00 AM
24-Mar-17 05:00 PM
0.00 0.00
A1750 Conduct finish plumbing inspection
A1740 1.00 25-Mar-17 08:00 AM
25-Mar-17 05:00 PM
25-Mar-17 08:00 AM
25-Mar-17 05:00 PM
0.00 0.00
Subtotal 6.00 20-Mar-17 08:00 AM
25-Mar-17 05:00 PM
20-Mar-17 08:00 AM
25-Mar-17 05:00 PM
0.00 0.00
R.8.6
A1760 Complete 1st Floor circuits to service panel
A1480, A1740
1.00 25-Mar-17 08:00 AM
25-Mar-17 05:00 PM
29-Mar-17 08:00 AM
29-Mar-17 05:00 PM
3.00 0.00
A1770 Complete 2nd Floor circuits to service panel
A1760 1.00 27-Mar-17 08:00 AM
27-Mar-17 05:00 PM
30-Mar-17 08:00 AM
30-Mar-17 05:00 PM
3.00 0.00
A1780 Conduct finish electrical inspection
A1770 1.00 28-Mar-17 08:00 AM
28-Mar-17 05:00 PM
31-Mar-17 08:00 AM
31-Mar-17 05:00 PM
3.00 3.00
A1790 Complete communications wiring- phone, cable, computer alarm
A1750 2.00 27-Mar-17 08:00 AM
28-Mar-17 05:00 PM
27-Mar-17 08:00 AM
28-Mar-17 05:00 PM
0.00 0.00
Subtotal 3.00 25-Mar-17 08:00 AM
28-Mar-17 05:00 PM
27-Mar-17 08:00 AM
31-Mar-17 05:00 PM
3.00 0.00
Abhishek Singh
© Oracle Corporation Page 7 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
R.8.7
A1800 Complete 1st floor - zone 1 HVAC
A1500, A1790
1.00 29-Mar-17 08:00 AM
29-Mar-17 05:00 PM
29-Mar-17 08:00 AM
29-Mar-17 05:00 PM
0.00 0.00
A1810 Complete 2nd floor - zone 2 HVAC
A1800 1.00 30-Mar-17 08:00 AM
30-Mar-17 05:00 PM
30-Mar-17 08:00 AM
30-Mar-17 05:00 PM
0.00 0.00
A1820 Conduct HVAC inspection A1810 1.00 31-Mar-17 08:00 AM
31-Mar-17 05:00 PM
31-Mar-17 08:00 AM
31-Mar-17 05:00 PM
0.00 0.00
Subtotal 3.00 29-Mar-17 08:00 AM
31-Mar-17 05:00 PM
29-Mar-17 08:00 AM
31-Mar-17 05:00 PM
0.00 0.00
R.8.8
A1830 Tile entry, kitchen & bath A1780, A1820
3.00 01-Apr-17 08:00 AM
04-Apr-17 05:00 PM
01-Apr-17 08:00 AM
04-Apr-17 05:00 PM
0.00 0.00
A1840 Carpet 1st floor A1830 2.00 05-Apr-17 08:00 AM
06-Apr-17 05:00 PM
05-Apr-17 08:00 AM
06-Apr-17 05:00 PM
0.00 0.00
A1850 Carpet 2nd floor A1840 2.00 07-Apr-17 08:00 AM
08-Apr-17 05:00 PM
07-Apr-17 08:00 AM
08-Apr-17 05:00 PM
0.00 0.00
A1860 Install Appliances A1850 1.00 10-Apr-17 08:00 AM
10-Apr-17 05:00 PM
10-Apr-17 08:00 AM
10-Apr-17 05:00 PM
0.00 0.00
Subtotal 8.00 01-Apr-17 08:00 AM
10-Apr-17 05:00 PM
01-Apr-17 08:00 AM
10-Apr-17 05:00 PM
0.00 0.00
Subtotal 29.00 08-Mar-17 08:00 AM
10-Apr-17 05:00 PM
08-Mar-17 08:00 AM
25-Apr-17 05:00 PM
13.00 0.00
R.9
A1870 Pour concrete driveway and sidewalks
A1670 2.00 05-Apr-17 08:00 AM
06-Apr-17 05:00 PM
08-Apr-17 08:00 AM
10-Apr-17 05:00 PM
3.00 3.00
A1880 Install backyard fence A1870, A1860
2.00 11-Apr-17 08:00 AM
12-Apr-17 05:00 PM
11-Apr-17 08:00 AM
12-Apr-17 05:00 PM
0.00 0.00
Abhishek Singh
© Oracle Corporation Page 8 of 9
Grouped by WBS and Sorted by Activity ID
WBS
Activity ID Activity Name Predecessors OriginalDuration
Early Start
Early Finish
Late Start Late Finish
Total Float Free Float
A1890 Sod & complete plantings - frontyard
A1880 2.00 13-Apr-17 08:00 AM
14-Apr-17 05:00 PM
13-Apr-17 08:00 AM
14-Apr-17 05:00 PM
0.00 0.00
A1900 Sod & complete plantings - backyard
A1890 1.00 15-Apr-17 08:00 AM
15-Apr-17 05:00 PM
15-Apr-17 08:00 AM
15-Apr-17 05:00 PM
0.00 0.00
Subtotal 10.00 05-Apr-17 08:00 AM
15-Apr-17 05:00 PM
08-Apr-17 08:00 AM
15-Apr-17 05:00 PM
0.00 0.00
R.5
A1910 Complete final inspection for certificate of occupancy
A1900, A1820, A1780, A1750, A1710, A1550, A1460
1.00 17-Apr-17 08:00 AM
17-Apr-17 05:00 PM
17-Apr-17 08:00 AM
17-Apr-17 05:00 PM
0.00 0.00
A1920 Cleanup for occupancy A1860, A1910
1.00 18-Apr-17 08:00 AM
18-Apr-17 05:00 PM
18-Apr-17 08:00 AM
18-Apr-17 05:00 PM
0.00 0.00
A1930 Perform final walk - through inspection
A1920 1.00 19-Apr-17 08:00 AM
19-Apr-17 05:00 PM
19-Apr-17 08:00 AM
19-Apr-17 05:00 PM
0.00 0.00
A1940 Complete punch list items A1930 5.00 20-Apr-17 08:00 AM
25-Apr-17 05:00 PM
20-Apr-17 08:00 AM
25-Apr-17 05:00 PM
0.00 0.00
Subtotal 8.00 17-Apr-17 08:00 AM
25-Apr-17 05:00 PM
17-Apr-17 08:00 AM
25-Apr-17 05:00 PM
0.00 0.00
Subtotal 151.00 01-Nov-16 08:00 AM
25-Apr-17 05:00 PM
01-Nov-16 08:00 AM
25-Apr-17 05:00 PM
0.00 0.00
Abhishek Singh
© Oracle Corporation Page 9 of 9
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
25-Apr-17 05:00 PM, Residential Construction
25-Nov-16 05:00 PM, General Conditions
Finalize Plans & Develop estimate with owner, architect
Sign Contract & Notice to proceed25-Nov-16 05:00 PM, Apply For Permits
Secure Foundation Permit
Secure Framing Permit
Secure Electrical Permit
Secure Plumbing Permit
Secure HVAC Permit
Secure miscellaneous permits29-Nov-16 05:00 PM, Site Work
Clear and grub lot
Install temporary power service
Install underground utilities
17-Jan-17 05:00 PM, Foundation
Excavate for foundations
Form basement walls
Place concrete for foundations & basement walls
Cure basement walls for 7 days
Strip basement wall forms
Waterproof / insulate bsement walls
Perform foundation inspection
Backfill foundation11-Feb-17 05:00 PM, Framing
Install 1st floor joists
Lay 1st floor decking
Frame 1st floor walls
Frame 1st floor corners
Install 2nd floor joist
Frame 2nd Floor decking
Frame 2nd floor walls
Frame 2nd floor corners
Complete roof framing
Conduct framing inspection08-Mar-17 05:00 PM, Dry In
Install 1st Floor Sheathing
Install 2nd Floor Sheathing
Install roof decking
Install felt, flashing, and shingles
Hang 1st floor exterior doors
Install 1st floor windows
Install 2nd floor windows30-Mar-17 05:00 PM, Exterior Finishes
Complete Exterior Brick
Complete exterior siding10-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete
Rough-in-plumbing
Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
Conduct Rough-in-plumbing inspection
Place concrete for basement floor
Rough-in electrical
Conduct Rough-in-electrical inspection
Rough-in HVAC
Conduct Rough-in-HVAC inspection
Rough-in communication - phone, cables, computer, alarm10-Apr-17 05:00 PM, Interior Finishes
18-Mar-17 05:00 PM, Insulation
Place wall insulation - 1st floor
Place wall insulation - 2nd floor
Place ceiling insulation - 2nd floor
Conduct insulation inspection17-Mar-17 05:00 PM, Drywall
Install Drywall - 1st floor walls
Install drywall - 1st floor overhead
Install drywall 2nd floor walls
Install drywall 2nd floor overhead
Tape & Float 1st floor drywall
Tape & Float 2nd floor drywall04-Apr-17 05:00 PM, Paint & Wall Paper
Texture all except entry & kitchen - 1st floor
Paint all except entry & kitchen - 1st floor
Hang wallpaper entry & kitchen - 1st floor
Texture all - 2nd floor
Paint all - 2nd floor
Paint exterior siding & trim work23-Mar-17 05:00 PM, Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath & guest cabinets
Install 2nd floor - hall bath & provate bath cabinets
install chair rails, crown moldings, trim25-Mar-17 05:00 PM, Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath & guest plumbing
Complete 2nd floor - hall bath & private bath plumbing
Conduct finish plumbing inspection28-Mar-17 05:00 PM, FInish Electrical
Complete 1st Floor circuits to service panel
Complete 2nd Floor circuits to service panel
Conduct finish electrical inspection
Complete communications wiring - phone, cable, computer alarm31-Mar-17 05:00 PM, Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection10-Apr-17 05:00 PM, Carpet, Tile & Appliances
Tile entry, kitchen & bath
Carpet 1st floor
Carpet 2nd floor
Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 3 TASK filter: All Activities
© Oracle Corporation
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
Install Appliances15-Apr-17 05:00 PM, Landscping and Grounds Work
Pour concrete driveway and sidewalks
Install backyard fence
Sod & complete plantings - frontyard
Sod & complete plantings - backyard25-Apr-17 05:00 PM, Final Acceptance
Complete final inspection for certificate of occupancy
Cleanup for occupancy
Perform final walk - through inspection
Complete punch list items
Abhishek Singh Gantt Chart for Activities Grouped by WBS and Sorted by Activity ID
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 3 of 3 TASK filter: All Activities
© Oracle Corporation
Project: R Residential ConstructionWBS: R.1 General Conditions
WBS: R.S Site Work
WBS: R.2 Foundation
WBS: R.3 Framing
WBS: R.4 Dry In
WBS: R.6 Exterior Finishes
WBS: R.7 Utility Rough B97Ins and Complete Concrete
WBS: R.8 Interior Finishes
WBS: R.9 Landscping and Grounds Work
WBS: R.5 Final Acceptance
WBS: R.1.1 Apply For Permits
WBS: R.8.1 Insulation
WBS: R.8.2 Drywall
WBS: R.8.3 Paint & Wall Paper
WBS: R.8.4 Cabinets
WBS: R.8.5 Finish Plumbing
WBS: R.8.6 FInish Electrical
WBS: R.8.7 Finish HVAC
WBS: R.8.8 Carpet, Tile & Appliances
A1010Sign Cont ract & Noti ce
to p roc eed
A 10 00F inal ize P la ns &
Dev elop e stimate wi th own er, arc hi tect
A1160Secure miscell ane ous perm its
A1150Secure HVA C Permit
A1140Secure Plum bing
Permi t
A1130Secure Elec trica l
Permi t
A1120Secure Fr aming Permi t
A1110Secure Fo und at ion
Permi t
A1040Inst al l underground
utili t ies
A1030Inst all temporary
power serv ice
A1020Clear and grub lot
A1240Backf i ll f oundation
A1230Perf orm f oundatio n
inspect ion
A1220Waterproo f / ins ulate
bseme nt wall s
A 12 10S trip basemen t wall
f o rm s
A 12 00Cure basemen t wall s
f o r 7 day s
A1190Pl ace concr et e f or
f o undations &
basem ent wal ls
A1180Form basement wall s
A1170Excav ate f or
f oundations
A1340Conduct f raming
inspect ion
A1330Com plete roof f ramin g
A1320Frame 2nd f l oor
corn ers
A 13 10F rame 2nd f l oor wa ll s
A 13 00F rame 2nd Floor
decking
A12 90Inst al l 2nd f loor joist
A12 80Frame 1st f loor
corners
A1270Frame 1st f loor wall s
A1260Lay 1st f l oor decking
A1250Inst all 1st f loor joists
A 14 10I nst all 2nd f lo or
windows
A 14 00Inst all 1st f lo or
windows
A13 90Hang 1s t f loor exterior
doors
A13 80Inst al l f elt, fl ashing,
and shingles
A1360Inst al l 2nd Floor
Sheathing
A1350Inst all 1st Floor
Sheath in g
A1370Inst all roof decking
A1430Com plete ext erior
siding
A1420Com plete Exterior
Brick
A1440Rough-in-plumbing
A1510Rough-in
communication - phone, cables,
A 15 00Conduct
Rough-in-HVA C inspection
A14 90Rough-in HVA C
A14 80Conduct
Rough-in-electrical inspection
A1470Rough-in elect rical
A14 60Pl ace concr et e f or
basem ent f l oor
A14 50Conduct
Rough-in-plumbing
inspection
A1520Place wal l i ns ulat ion -
1st f lo or
A15 50Conduct insulati on
inspection
A1540Place ceil ing insulation
- 2nd f l oor
A1530Place wal l i ns ulation -
2nd f lo or
A1600Tape & F loat 1st f loor
dry wall
A1570Inst all dr y wall - 1st
f loor over head
A1560Inst all Drywall - 1 st
f loor wal ls
A1610Tape & Float 2nd fl oor
dry wall
A1590Inst al l dry wall 2nd
f loor ov erhead
A1580Inst all dry wall 2nd
f loor walls
A16 40Hang wallpaper entry &
kitchen - 1s t f loor
A1630Paint all except entry
& kit chen - 1st f loor
A1620Texture al l except entry
& kit chen - 1st f loor
A1670Paint exteri or siding &
trim wor k
A16 60Paint all - 2 nd f loor
A1650Texture al l - 2nd f loor
A 16 90Inst all 1st f lo or - mas ter ba th & g ues t
cabinets
A 16 80Inst all 1st f lo or - kitch en cabinets
A1710insta ll chair r ai ls , crown moldings, trim
A 17 00I nst all 2nd f lo or - hall bath & pro v ate bath
cabinets
A1750Conduct f inish plum bing inspect ion
A1740Com plete 2nd f l oor - hall ba th & pr iv at e ba th
plum bing
A 17 30Com plete 1st f loor - mas ter ba th & g ues t
plum bing
A 17 20Com plete 1st f loor - kitch en plumb ing
A1790Com plete communicatio ns wiring
- phone, cable,
A1780Conduct f inish
elect ri cal inspection
A1770Com plete 2nd F loor
ci rcuits to servi ce panel
A1760Com plete 1st F loor
ci rcu it s t o servi ce panel
A1820Conduct HVAC
inspection
A1810Complete 2nd f l oor -
zone 2 HVAC
A1800Complete 1st fl oor -
zone 1 HVAC
A 18 60I nst all Appliance s
A 18 50Carp et 2nd fl o or
A 18 40Carp et 1st f l oor
A18 30Tile entry, kitchen &
bath
A1900Sod & com plete
plant ings - backy ard
A1890Sod & com plete
plant in gs - f ronty ard
A1880Inst all bac ky ard f enc e
A1870Pour concrete
driv eway and sidewalks
A19 40Complete punch list
items
A1930Perf orm f inal walk -
through inspection
A1920Cleanup f or occupancy
A1910Complete f inal
inspection f or cert if icate of
Abhishek Singh Activity Network Layout
Activity IDActivity Name Page 1 of 2 © Oracle Corporation
Activity ID Activity Name Original
Duration
Residential ConstructionResidential Construction 151.00
General ConditionsGeneral Conditions 22.00
A1000 Finalize Plans & Develop estimate with owner, architect20.00
A1010 Sign Contract & Notice to proceed 1.00
Apply For PermitsApply For Permits 1.00
A1110 Secure Foundation Permit 1.00
A1120 Secure Framing Permit 1.00
A1130 Secure Electrical Permit 1.00
A1140 Secure Plumbing Permit 1.00
A1150 Secure HVAC Permit 1.00
A1160 Secure miscellaneous permits 1.00
Site WorkSite Work 3.00
A1020 Clear and grub lot 1.00
A1030 Install temporary power service 1.00
A1040 Install underground utilities 1.00
FoundationFoundation 42.00
A1170 Excavate for foundations 3.00
A1180 Form basement walls 13.00
A1190 Place concrete for foundations & basement walls12.00
A1200 Cure basement walls for 7 days 7.00
A1210 Strip basement wall forms 2.00
A1220 Waterproof / insulate bsement walls 2.00
A1230 Perform foundation inspection 1.00
A1240 Backfill foundation 2.00
FramingFraming 22.00
A1250 Install 1st floor joists 2.00
A1260 Lay 1st floor decking 2.00
A1270 Frame 1st floor walls 4.00
A1280 Frame 1st floor corners 1.00
A1290 Install 2nd floor joist 2.00
A1300 Frame 2nd Floor decking 2.00
A1310 Frame 2nd floor walls 3.00
A1320 Frame 2nd floor corners 2.00
A1330 Complete roof framing 3.00
A1340 Conduct framing inspection 1.00
Dry InDry In 21.00
A1350 Install 1st Floor Sheathing 3.00
A1360 Install 2nd Floor Sheathing 3.00
A1380 Install felt, flashing, and shingles 3.00
A1390 Hang 1st floor exterior doors 1.00
A1400 Install 1st floor windows 3.00
A1410 Install 2nd floor windows 3.00
Exterior FinishesExterior Finishes 0.00
Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete Concrete5.00
A1440 Rough-in-plumbing 5.00
Interior FinishesInterior Finishes 29.00
InsulationInsulation 1.00
A1520 Place wall insulation - 1st floor 1.00
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
25-Apr-17 05:00 PM, Residential Construction
25-Nov-16 05:00 PM, General Conditions
Finalize Plans & Develop estimate with owner, architect
Sign Contract & Notice to proceed25-Nov-16 05:00 PM, Apply For Permits
Secure Foundation Permit
Secure Framing Permit
Secure Electrical Permit
Secure Plumbing Permit
Secure HVAC Permit
Secure miscellaneous permits29-Nov-16 05:00 PM, Site Work
Clear and grub lot
Install temporary power service
Install underground utilities
17-Jan-17 05:00 PM, Foundation
Excavate for foundations
Form basement walls
Place concrete for foundations & basement walls
Cure basement walls for 7 days
Strip basement wall forms
Waterproof / insulate bsement walls
Perform foundation inspection
Backfill foundation11-Feb-17 05:00 PM, Framing
Install 1st floor joists
Lay 1st floor decking
Frame 1st floor walls
Frame 1st floor corners
Install 2nd floor joist
Frame 2nd Floor decking
Frame 2nd floor walls
Frame 2nd floor corners
Complete roof framing
Conduct framing inspection08-Mar-17 05:00 PM, Dry In
Install 1st Floor Sheathing
Install 2nd Floor Sheathing
Install felt, flashing, and shingles
Hang 1st floor exterior doors
Install 1st floor windows
Install 2nd floor windows
24-Feb-17 05:00 PM, Utility Rough B97Ins and Complete Concrete
Rough-in-plumbing10-Apr-17 05:00 PM, Interior Finishes
09-Mar-17 05:00 PM, Insulation
Place wall insulation - 1st floor
Abhishek Singh Activity Table and Gantt Chart for Critical Path Activities
Page 1 of 2 TASK filter: Critical.
© Oracle Corporation
Activity ID Activity Name Original
DurationDrywallDrywall 5.00
A1560 Install Drywall - 1st floor walls 2.00
A1570 Install drywall - 1st floor overhead 2.00
A1600 Tape & Float 1st floor drywall 1.00
Paint & Wall PaperPaint & Wall Paper 3.00
A1620 Texture all except entry & kitchen - 1st floor 1.00
A1630 Paint all except entry & kitchen - 1st floor 1.00
A1640 Hang wallpaper entry & kitchen - 1st floor 1.00
CabinetsCabinets 3.00
A1680 Install 1st floor - kitchen cabinets 2.00
A1690 Install 1st floor - master bath & guest cabinets 1.00
Finish PlumbingFinish Plumbing 6.00
A1720 Complete 1st floor - kitchen plumbing 1.00
A1730 Complete 1st floor - master bath & guest plumbing2.00
A1740 Complete 2nd floor - hall bath & private bath plumbing2.00
A1750 Conduct finish plumbing inspection 1.00
FInish ElectricalFInish Electrical 2.00
A1790 Complete communications wiring - phone, cable, computer alarm2.00
Finish HVACFinish HVAC 3.00
A1800 Complete 1st floor - zone 1 HVAC 1.00
A1810 Complete 2nd floor - zone 2 HVAC 1.00
A1820 Conduct HVAC inspection 1.00
Carpet, Tile & AppliancesCarpet, Tile & Appliances 8.00
A1830 Tile entry, kitchen & bath 3.00
A1840 Carpet 1st floor 2.00
A1850 Carpet 2nd floor 2.00
A1860 Install Appliances 1.00
Landscping and Grounds WorkLandscping and Grounds Work 5.00
A1880 Install backyard fence 2.00
A1890 Sod & complete plantings - frontyard 2.00
A1900 Sod & complete plantings - backyard 1.00
Final AcceptanceFinal Acceptance 8.00
A1910 Complete final inspection for certificate of occupancy1.00
A1920 Cleanup for occupancy 1.00
A1930 Perform final walk - through inspection 1.00
A1940 Complete punch list items 5.00
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
13-Mar-17 05:00 PM, Drywall
Install Drywall - 1st floor walls
Install drywall - 1st floor overhead
Tape & Float 1st floor drywall16-Mar-17 05:00 PM, Paint & Wall Paper
Texture all except entry & kitchen - 1st floor
Paint all except entry & kitchen - 1st floor
Hang wallpaper entry & kitchen - 1st floor20-Mar-17 05:00 PM, Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath & guest cabinets25-Mar-17 05:00 PM, Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath & guest plumbing
Complete 2nd floor - hall bath & private bath plumbing
Conduct finish plumbing inspection28-Mar-17 05:00 PM, FInish Electrical
Complete communications wiring - phone, cable, computer alarm31-Mar-17 05:00 PM, Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection10-Apr-17 05:00 PM, Carpet, Tile & Appliances
Tile entry, kitchen & bath
Carpet 1st floor
Carpet 2nd floor
Install Appliances15-Apr-17 05:00 PM, Landscping and Grounds Work
Install backyard fence
Sod & complete plantings - frontyard
Sod & complete plantings - backyard25-Apr-17 05:00 PM, Final Acceptance
Complete final inspection for certificate of occupancy
Cleanup for occupancy
Perform final walk - through inspection
Complete punch list items
Abhishek Singh Activity Table and Gantt Chart for Critical Path Activities
Page 2 of 2 TASK filter: Critical.
© Oracle Corporation
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
25-Apr-17 05:00 PM, Residential Construction
25-Nov-16 05:00 PM, General Conditions
Finalize Plans & Develop estimate with owner, architect
Sign Contract & Notice to proceed25-Nov-16 05:00 PM, Apply For Permits
Secure Foundation Permit
Secure Framing Permit
Secure Electrical Permit
Secure Plumbing Permit
Secure HVAC Permit
Secure miscellaneous permits29-Nov-16 05:00 PM, Site Work
Clear and grub lot
Install temporary power service
Install underground utilities
17-Jan-17 05:00 PM, Foundation
Excavate for foundations
Form basement walls
Place concrete for foundations & basement walls
Cure basement walls for 7 days
Strip basement wall forms
Waterproof / insulate bsement walls
Perform foundation inspection
Backfill foundation11-Feb-17 05:00 PM, Framing
Install 1st floor joists
Lay 1st floor decking
Frame 1st floor walls
Frame 1st floor corners
Install 2nd floor joist
Frame 2nd Floor decking
Frame 2nd floor walls
Frame 2nd floor corners
Complete roof framing
Conduct framing inspection08-Mar-17 05:00 PM, Dry In
Install 1st Floor Sheathing
Install 2nd Floor Sheathing
Install felt, flashing, and shingles
Hang 1st floor exterior doors
Install 1st floor windows
Install 2nd floor windows
24-Feb-17 05:00 PM, Utility Rough B97Ins and Complete Concrete
Rough-in-plumbing10-Apr-17 05:00 PM, Interior Finishes
09-Mar-17 05:00 PM, Insulation
Place wall insulation - 1st floor
Abhishek Singh Critical Path Activities
Page 1 of 2 TASK filter: Critical.
© Oracle Corporation
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
13-Mar-17 05:00 PM, Drywall
Install Drywall - 1st floor walls
Install drywall - 1st floor overhead
Tape & Float 1st floor drywall16-Mar-17 05:00 PM, Paint & Wall Paper
Texture all except entry & kitchen - 1st floor
Paint all except entry & kitchen - 1st floor
Hang wallpaper entry & kitchen - 1st floor20-Mar-17 05:00 PM, Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath & guest cabinets25-Mar-17 05:00 PM, Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath & guest plumbing
Complete 2nd floor - hall bath & private bath plumbing
Conduct finish plumbing inspection28-Mar-17 05:00 PM, FInish Electrical
Complete communications wiring - phone, cable, computer alarm31-Mar-17 05:00 PM, Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection10-Apr-17 05:00 PM, Carpet, Tile & Appliances
Tile entry, kitchen & bath
Carpet 1st floor
Carpet 2nd floor
Install Appliances15-Apr-17 05:00 PM, Landscping and Grounds Work
Install backyard fence
Sod & complete plantings - frontyard
Sod & complete plantings - backyard25-Apr-17 05:00 PM, Final Acceptance
Complete final inspection for certificate of occupancy
Cleanup for occupancy
Perform final walk - through inspection
Complete punch list items
Abhishek Singh Critical Path Activities
Page 2 of 2 TASK filter: Critical.
© Oracle Corporation
Activity ID Activity Name OriginalDuration
Free FloatRemaining
Duration
Residential ConstructionResidential Construction 151.00 0.00151.00
General ConditionsGeneral Conditions 22.00 0.0022.00
A1000 Finalize Plans & Develop estimate with owner, architect20.00 0.0020.00
A1010 Sign Contract & Notice to proceed 1.00 0.00 1.00
Apply For PermitsApply For Permits 1.00 0.00 1.00
A1110Secure Foundation Permit 1.00 0.00 1.00
A1120Secure Framing Permit 1.00 0.00 1.00
A1130Secure Electrical Permit 1.00 0.00 1.00
A1140Secure Plumbing Permit 1.00 0.00 1.00
A1150Secure HVAC Permit 1.00 0.00 1.00
A1160Secure miscellaneous permits 1.00 0.00 1.00
Site WorkSite Work 3.00 0.00 3.00
A1020 Clear and grub lot 1.00 0.00 1.00
A1030 Install temporary power service 1.00 0.00 1.00
A1040 Install underground utilities 1.00 0.00 1.00
FoundationFoundation 42.00 0.0042.00
A1170 Excavate for foundations 3.00 0.00 3.00
A1180 Form basement walls 13.00 0.0013.00
A1190 Place concrete for foundations & basement walls12.00 0.0012.00
A1200 Cure basement walls for 7 days 7.00 0.00 7.00
A1210 Strip basement wall forms 2.00 0.00 2.00
A1220 Waterproof / insulate bsement walls 2.00 0.00 2.00
A1230 Perform foundation inspection 1.00 0.00 1.00
A1240 Backfill foundation 2.00 0.00 2.00
FramingFraming 22.00 0.0022.00
A1250 Install 1st floor joists 2.00 0.00 2.00
A1260 Lay 1st floor decking 2.00 0.00 2.00
A1270 Frame 1st floor walls 4.00 0.00 4.00
A1280 Frame 1st floor corners 1.00 0.00 1.00
A1290 Install 2nd floor joist 2.00 0.00 2.00
A1300 Frame 2nd Floor decking 2.00 0.00 2.00
A1310 Frame 2nd floor walls 3.00 0.00 3.00
A1320 Frame 2nd floor corners 2.00 0.00 2.00
A1330 Complete roof framing 3.00 0.00 3.00
A1340 Conduct framing inspection 1.00 0.00 1.00
Dry InDry In 22.00 0.0022.00
A1370 Install roof decking 3.00 0.00 3.00
A1350 Install 1st Floor Sheathing 3.00 0.00 3.00
A1360 Install 2nd Floor Sheathing 3.00 0.00 3.00
A1380 Install felt, flashing, and shingles 3.00 0.00 3.00
A1390 Hang 1st floor exterior doors 1.00 0.00 1.00
A1400 Install 1st floor windows 3.00 0.00 3.00
A1410 Install 2nd floor windows 3.00 0.00 3.00
Exterior FinishesExterior Finishes 19.00 0.0019.00
A1420 Complete Exterior Brick 16.00 0.0016.00
A1430 Complete exterior siding 3.00 0.00 3.00
Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete Concrete21.00 0.0021.00
A1510 Rough-in communication - phone, cables, computer, alarm2.00 17.00 2.00
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
25-Apr-17 05:00 PM, Residential Construction
25-Nov-16 05:00 PM, General Conditions
Finalize Plans & Develop estimate with owner, architect
Sign Contract & Notice to proceed25-Nov-16 05:00 PM, Apply For Permits
Secure Foundation Permit
Secure Framing Permit
Secure Electrical Permit
Secure Plumbing Permit
Secure HVAC Permit
Secure miscellaneous permits29-Nov-16 05:00 PM, Site Work
Clear and grub lot
Install temporary power service
Install underground utilities
17-Jan-17 05:00 PM, Foundation
Excavate for foundations
Form basement walls
Place concrete for foundations & basement walls
Cure basement walls for 7 days
Strip basement wall forms
Waterproof / insulate bsement walls
Perform foundation inspection
Backfill foundation11-Feb-17 05:00 PM, Framing
Install 1st floor joists
Lay 1st floor decking
Frame 1st floor walls
Frame 1st floor corners
Install 2nd floor joist
Frame 2nd Floor decking
Frame 2nd floor walls
Frame 2nd floor corners
Complete roof framing
Conduct framing inspection08-Mar-17 05:00 PM, Dry In
Install roof decking
Install 1st Floor Sheathing
Install 2nd Floor Sheathing
Install felt, flashing, and shingles
Hang 1st floor exterior doors
Install 1st floor windows
Install 2nd floor windows30-Mar-17 05:00 PM, Exterior Finishes
Complete Exterior Brick
Complete exterior siding10-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete
Rough-in communication - phone, cables, computer, alarm
Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
Free FloatRemaining
DurationA1440 Rough-in-plumbing 5.00 0.00 5.00
A1470 Rough-in electrical 5.00 0.00 5.00
A1450 Conduct Rough-in-plumbing inspection 1.00 0.00 1.00
A1480 Conduct Rough-in-electrical inspection 1.00 0.00 1.00
A1490 Rough-in HVAC 3.00 0.00 3.00
A1460 Place concrete for basement floor 11.00 31.0011.00
A1500 Conduct Rough-in-HVAC inspection 1.00 22.00 1.00
Interior FinishesInterior Finishes 29.00 0.0029.00
InsulationInsulation 9.00 0.00 9.00
A1520Place wall insulation - 1st floor 1.00 0.00 1.00
A1530Place wall insulation - 2nd floor 1.00 1.00 1.00
A1540Place ceiling insulation - 2nd floor 1.00 0.00 1.00
A1550Conduct insulation inspection 1.00 24.00 1.00
DrywallDrywall 9.00 0.00 9.00
A1560Install Drywall - 1st floor walls 2.00 0.00 2.00
A1570Install drywall - 1st floor overhead 2.00 0.00 2.00
A1580Install drywall 2nd floor walls 2.00 0.00 2.00
A1600Tape & Float 1st floor drywall 1.00 0.00 1.00
A1590Install drywall 2nd floor overhead 2.00 0.00 2.00
A1610Tape & Float 2nd floor drywall 1.00 33.00 1.00
Paint & Wall PaperPaint & Wall Paper 19.00 0.0019.00
A1620Texture all except entry & kitchen - 1st floor1.00 0.00 1.00
A1630Paint all except entry & kitchen - 1st floor 1.00 0.00 1.00
A1650Texture all - 2nd floor 1.00 0.00 1.00
A1640Hang wallpaper entry & kitchen - 1st floor1.00 0.00 1.00
A1660Paint all - 2nd floor 1.00 34.00 1.00
A1670Paint exterior siding & trim work 4.00 0.00 4.00
CabinetsCabinets 6.00 0.00 6.00
A1680Install 1st floor - kitchen cabinets 2.00 0.00 2.00
A1690Install 1st floor - master bath & guest cabinets1.00 0.00 1.00
A1700Install 2nd floor - hall bath & provate bath cabinets1.00 0.00 1.00
A1710install chair rails, crown moldings, trim 2.00 20.00 2.00
Finish PlumbingFinish Plumbing 6.00 0.00 6.00
A1720Complete 1st floor - kitchen plumbing 1.00 0.00 1.00
A1730Complete 1st floor - master bath & guest plumbing2.00 0.00 2.00
A1740Complete 2nd floor - hall bath & private bath plumbing2.00 0.00 2.00
A1750Conduct finish plumbing inspection 1.00 0.00 1.00
FInish ElectricalFInish Electrical 3.00 0.00 3.00
A1760Complete 1st Floor circuits to service panel1.00 0.00 1.00
A1770Complete 2nd Floor circuits to service panel1.00 0.00 1.00
A1790Complete communications wiring - phone, cable, computer alarm2.00 0.00 2.00
A1780Conduct finish electrical inspection 1.00 3.00 1.00
Finish HVACFinish HVAC 3.00 0.00 3.00
A1800Complete 1st floor - zone 1 HVAC 1.00 0.00 1.00
A1810Complete 2nd floor - zone 2 HVAC 1.00 0.00 1.00
A1820Conduct HVAC inspection 1.00 0.00 1.00
Carpet, Tile & AppliancesCarpet, Tile & Appliances 8.00 0.00 8.00
A1830Tile entry, kitchen & bath 3.00 0.00 3.00
A1840Carpet 1st floor 2.00 0.00 2.00
A1850Carpet 2nd floor 2.00 0.00 2.00
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
Rough-in-plumbing
Rough-in electrical
Conduct Rough-in-plumbing inspection
Conduct Rough-in-electrical inspection
Rough-in HVAC
Place concrete for basement floor
Conduct Rough-in-HVAC inspection10-Apr-17 05:00 PM, Interior Finishes
18-Mar-17 05:00 PM, Insulation
Place wall insulation - 1st floor
Place wall insulation - 2nd floor
Place ceiling insulation - 2nd floor
Conduct insulation inspection17-Mar-17 05:00 PM, Drywall
Install Drywall - 1st floor walls
Install drywall - 1st floor overhead
Install drywall 2nd floor walls
Tape & Float 1st floor drywall
Install drywall 2nd floor overhead
Tape & Float 2nd floor drywall04-Apr-17 05:00 PM, Paint & Wall Paper
Texture all except entry & kitchen - 1st floor
Paint all except entry & kitchen - 1st floor
Texture all - 2nd floor
Hang wallpaper entry & kitchen - 1st floor
Paint all - 2nd floor
Paint exterior siding & trim work23-Mar-17 05:00 PM, Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath & guest cabinets
Install 2nd floor - hall bath & provate bath cabinets
install chair rails, crown moldings, trim25-Mar-17 05:00 PM, Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath & guest plumbing
Complete 2nd floor - hall bath & private bath plumbing
Conduct finish plumbing inspection28-Mar-17 05:00 PM, FInish Electrical
Complete 1st Floor circuits to service panel
Complete 2nd Floor circuits to service panel
Complete communications wiring - phone, cable, computer alarm
Conduct finish electrical inspection31-Mar-17 05:00 PM, Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection10-Apr-17 05:00 PM, Carpet, Tile & Appliances
Tile entry, kitchen & bath
Carpet 1st floor
Carpet 2nd floor
Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
Free FloatRemaining
DurationA1860Install Appliances 1.00 0.00 1.00
Landscping and Grounds WorkLandscping and Grounds Work 10.00 0.0010.00
A1870 Pour concrete driveway and sidewalks 2.00 3.00 2.00
A1880 Install backyard fence 2.00 0.00 2.00
A1890 Sod & complete plantings - frontyard 2.00 0.00 2.00
A1900 Sod & complete plantings - backyard 1.00 0.00 1.00
Final AcceptanceFinal Acceptance 8.00 0.00 8.00
A1910 Complete final inspection for certificate of occupancy1.00 0.00 1.00
A1920 Cleanup for occupancy 1.00 0.00 1.00
A1930 Perform final walk - through inspection 1.00 0.00 1.00
A1940 Complete punch list items 5.00 0.00 5.00
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
Install Appliances15-Apr-17 05:00 PM, Landscping and Grounds Work
Pour concrete driveway and sidewalks
Install backyard fence
Sod & complete plantings - frontyard
Sod & complete plantings - backyard25-Apr-17 05:00 PM, Final Acceptance
Complete final inspection for certificate of occupancy
Cleanup for occupancy
Perform final walk - through inspection
Complete punch list items
Abhishek Singh Gantt Chart Schedule for Activities Grouped by WBS and Sorted by Early Start and Free Float
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 3 of 3 TASK filter: All Activities
© Oracle Corporation
Report for the Budgeted Cost
WBS
Activity ID Activity Name OriginalDuration
BudgetedLabor Cost
BudgetedMaterial Cost
Budgeted TotalCost
R Residential Construction
R.1 General Conditions
A1000 Finalize Plans & Develop estimate with owner, architect
20.00 $5,220.00 $0.00 $5,220.00
A1010 Sign Contract & Notice to proceed
1.00 $750.00 $0.00 $750.00
R.1.1 Apply For Permits
A1110 Secure Foundation Permit 1.00 $0.00 $0.00 $0.00
A1120 Secure Framing Permit 1.00 $0.00 $0.00 $0.00
A1130 Secure Electrical Permit 1.00 $0.00 $0.00 $0.00
A1140 Secure Plumbing Permit 1.00 $0.00 $0.00 $0.00
A1150 Secure HVAC Permit 1.00 $0.00 $0.00 $0.00
A1160 Secure miscellaneous permits 1.00 $0.00 $0.00 $0.00
Subtotal 1.00 $0.00 $0.00 $0.00
Subtotal 22.00 $5,970.00 $0.00 $5,970.00
R.S Site Work
A1020 Clear and grub lot 1.00 $150.00 $0.00 $150.00
A1030 Install temporary power service 1.00 $150.00 $0.00 $150.00
A1040 Install underground utilities 1.00 $450.00 $0.00 $450.00
Subtotal 3.00 $750.00 $0.00 $750.00
R.2 Foundation
Abhishek Singh Residential Building Project
© Oracle Corporation Page 1 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name OriginalDuration
BudgetedLabor Cost
BudgetedMaterial Cost
Budgeted TotalCost
A1170 Excavate for foundations 3.00 $450.00 $0.00 $450.00
A1180 Form basement walls 13.00 $2,600.00 $0.00 $2,600.00
A1190 Place concrete for foundations & basement walls
12.00 $2,400.00 $0.00 $2,400.00
A1200 Cure basement walls for 7 days 7.00 $0.00 $0.00 $0.00
A1210 Strip basement wall forms 2.00 $400.00 $0.00 $400.00
A1220 Waterproof / insulate bsement walls
2.00 $400.00 $0.00 $400.00
A1230 Perform foundation inspection 1.00 $0.00 $500.00 $500.00
A1240 Backfill foundation 2.00 $300.00 $0.00 $300.00
Subtotal 42.00 $6,550.00 $500.00 $7,050.00
R.3 Framing
A1250 Install 1st floor joists 2.00 $400.00 $0.00 $400.00
A1260 Lay 1st floor decking 2.00 $400.00 $0.00 $400.00
A1270 Frame 1st floor walls 4.00 $800.00 $0.00 $800.00
A1280 Frame 1st floor corners 1.00 $200.00 $0.00 $200.00
A1290 Install 2nd floor joist 2.00 $400.00 $0.00 $400.00
A1300 Frame 2nd Floor decking 2.00 $400.00 $0.00 $400.00
A1310 Frame 2nd floor walls 3.00 $600.00 $0.00 $600.00
A1320 Frame 2nd floor corners 2.00 $400.00 $0.00 $400.00
A1330 Complete roof framing 3.00 $600.00 $0.00 $600.00
A1340 Conduct framing inspection 1.00 $0.00 $500.00 $500.00
Subtotal 22.00 $4,200.00 $500.00 $4,700.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 2 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name OriginalDuration
BudgetedLabor Cost
BudgetedMaterial Cost
Budgeted TotalCost
R.4 Dry In
A1350 Install 1st Floor Sheathing 3.00 $600.00 $0.00 $600.00
A1360 Install 2nd Floor Sheathing 3.00 $600.00 $0.00 $600.00
A1370 Install roof decking 3.00 $600.00 $0.00 $600.00
A1380 Install felt, flashing, and shingles 3.00 $300.00 $0.00 $300.00
A1390 Hang 1st floor exterior doors 1.00 $200.00 $0.00 $200.00
A1400 Install 1st floor windows 3.00 $600.00 $0.00 $600.00
A1410 Install 2nd floor windows 3.00 $600.00 $0.00 $600.00
Subtotal 22.00 $3,500.00 $0.00 $3,500.00
R.6 Exterior Finishes
A1420 Complete Exterior Brick 16.00 $2,400.00 $0.00 $2,400.00
A1430 Complete exterior siding 3.00 $600.00 $0.00 $600.00
Subtotal 19.00 $3,000.00 $0.00 $3,000.00
R.7 Utility Rough B97Ins and Complete Concrete
A1440 Rough-in-plumbing 5.00 $1,500.00 $0.00 $1,500.00
A1450 Conduct Rough-in-plumbing inspection
1.00 $0.00 $500.00 $500.00
A1460 Place concrete for basement floor
11.00 $2,200.00 $0.00 $2,200.00
A1470 Rough-in electrical 5.00 $750.00 $0.00 $750.00
A1480 Conduct Rough-in-electrical inspection
1.00 $0.00 $500.00 $500.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 3 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name OriginalDuration
BudgetedLabor Cost
BudgetedMaterial Cost
Budgeted TotalCost
A1490 Rough-in HVAC 3.00 $450.00 $0.00 $450.00
A1500 Conduct Rough-in-HVAC inspection
1.00 $0.00 $500.00 $500.00
A1510 Rough-in communication - phone, cables, computer, alarm
2.00 $300.00 $0.00 $300.00
Subtotal 21.00 $5,200.00 $1,500.00 $6,700.00
R.8 Interior Finishes
R.8.1 Insulation
A1520 Place wall insulation - 1st floor 1.00 $300.00 $0.00 $300.00
A1530 Place wall insulation - 2nd floor 1.00 $300.00 $0.00 $300.00
A1540 Place ceiling insulation - 2nd floor 1.00 $300.00 $0.00 $300.00
A1550 Conduct insulation inspection 1.00 $0.00 $500.00 $500.00
Subtotal 9.00 $900.00 $500.00 $1,400.00
R.8.2 Drywall
A1560 Install Drywall - 1st floor walls 2.00 $400.00 $0.00 $400.00
A1570 Install drywall - 1st floor overhead
2.00 $400.00 $0.00 $400.00
A1580 Install drywall 2nd floor walls 2.00 $400.00 $0.00 $400.00
A1590 Install drywall 2nd floor overhead 2.00 $400.00 $0.00 $400.00
A1600 Tape & Float 1st floor drywall 1.00 $200.00 $0.00 $200.00
A1610 Tape & Float 2nd floor drywall 1.00 $200.00 $0.00 $200.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 4 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name OriginalDuration
BudgetedLabor Cost
BudgetedMaterial Cost
Budgeted TotalCost
Subtotal 9.00 $2,000.00 $0.00 $2,000.00
R.8.3 Paint & Wall Paper
A1620 Texture all except entry & kitchen- 1st floor
1.00 $100.00 $0.00 $100.00
A1630 Paint all except entry & kitchen - 1st floor
1.00 $100.00 $0.00 $100.00
A1640 Hang wallpaper entry & kitchen - 1st floor
1.00 $100.00 $0.00 $100.00
A1650 Texture all - 2nd floor 1.00 $100.00 $0.00 $100.00
A1660 Paint all - 2nd floor 1.00 $100.00 $0.00 $100.00
A1670 Paint exterior siding & trim work 4.00 $400.00 $0.00 $400.00
Subtotal 19.00 $900.00 $0.00 $900.00
R.8.4 Cabinets
A1680 Install 1st floor - kitchen cabinets 2.00 $300.00 $0.00 $300.00
A1690 Install 1st floor - master bath & guest cabinets
1.00 $150.00 $0.00 $150.00
A1700 Install 2nd floor - hall bath & provate bath cabinets
1.00 $150.00 $0.00 $150.00
A1710 install chair rails, crown moldings,trim
2.00 $300.00 $0.00 $300.00
Subtotal 6.00 $900.00 $0.00 $900.00
R.8.5 Finish Plumbing
A1720 Complete 1st floor - kitchen plumbing
1.00 $300.00 $0.00 $300.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 5 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name OriginalDuration
BudgetedLabor Cost
BudgetedMaterial Cost
Budgeted TotalCost
A1730 Complete 1st floor - master bath & guest plumbing
2.00 $600.00 $0.00 $600.00
A1740 Complete 2nd floor - hall bath & private bath plumbing
2.00 $600.00 $0.00 $600.00
A1750 Conduct finish plumbing inspection
1.00 $0.00 $500.00 $500.00
Subtotal 6.00 $1,500.00 $500.00 $2,000.00
R.8.6 FInish Electrical
A1760 Complete 1st Floor circuits to service panel
1.00 $150.00 $0.00 $150.00
A1770 Complete 2nd Floor circuits to service panel
1.00 $150.00 $0.00 $150.00
A1780 Conduct finish electrical inspection
1.00 $0.00 $500.00 $500.00
A1790 Complete communications wiring- phone, cable, computer alarm
2.00 $300.00 $0.00 $300.00
Subtotal 3.00 $600.00 $500.00 $1,100.00
R.8.7 Finish HVAC
A1800 Complete 1st floor - zone 1 HVAC
1.00 $150.00 $0.00 $150.00
A1810 Complete 2nd floor - zone 2 HVAC
1.00 $150.00 $0.00 $150.00
A1820 Conduct HVAC inspection 1.00 $0.00 $500.00 $500.00
Subtotal 3.00 $300.00 $500.00 $800.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 6 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name OriginalDuration
BudgetedLabor Cost
BudgetedMaterial Cost
Budgeted TotalCost
R.8.8 Carpet, Tile & Appliances
A1830 Tile entry, kitchen & bath 3.00 $450.00 $0.00 $450.00
A1840 Carpet 1st floor 2.00 $300.00 $0.00 $300.00
A1850 Carpet 2nd floor 2.00 $300.00 $0.00 $300.00
A1860 Install Appliances 1.00 $150.00 $0.00 $150.00
Subtotal 8.00 $1,200.00 $0.00 $1,200.00
Subtotal 29.00 $8,300.00 $2,000.00 $10,300.00
R.9 Landscping and Grounds Work
A1870 Pour concrete driveway and sidewalks
2.00 $400.00 $0.00 $400.00
A1880 Install backyard fence 2.00 $300.00 $0.00 $300.00
A1890 Sod & complete plantings - frontyard
2.00 $600.00 $0.00 $600.00
A1900 Sod & complete plantings - backyard
1.00 $300.00 $0.00 $300.00
Subtotal 10.00 $1,600.00 $0.00 $1,600.00
R.5 Final Acceptance
A1910 Complete final inspection for certificate of occupancy
1.00 $0.00 $500.00 $500.00
A1920 Cleanup for occupancy 1.00 $0.00 $0.00 $200.00
A1930 Perform final walk - through inspection
1.00 $200.00 $0.00 $200.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 7 of 8
Report for the Budgeted Cost
WBS
Activity ID Activity Name OriginalDuration
BudgetedLabor Cost
BudgetedMaterial Cost
Budgeted TotalCost
A1940 Complete punch list items 5.00 $750.00 $0.00 $750.00
Subtotal 8.00 $950.00 $500.00 $1,650.00
Subtotal 151.00 $40,020.00 $5,000.00 $45,220.00
Abhishek Singh Residential Building Project
© Oracle Corporation Page 8 of 8
Oct 17 Oct 24 Oct 31 Nov 07 Nov 14 Nov 21 Nov 28 Dec 05 Dec 12 Dec 19 Dec 26 Jan 02 Jan 09 Jan 16 Jan 23 Jan 30 Feb 06 Feb 13 Feb 20 Feb 27 Mar 06 Mar 13 Mar 20 Mar 27 Apr 03 Apr 10 Apr 17 Apr 24 May 01 May 08 May 15May 22
$200.00
$400.00
$600.00
$800.00
$1,000.00
$9,000.00
$18,000.00
$27,000.00
$36,000.00
$45,000.00
Abhishek Singh Daily Histogram and Cumulative curve for Labor cost
Budgeted Labor Cost Page 1 of 1 TASK filter: All Activities
© Oracle Corporation
Oct 17 Oct 24 Oct 31 Nov 07 Nov 14 Nov 21 Nov 28 Dec 05 Dec 12 Dec 19 Dec 26 Jan 02 Jan 09 Jan 16 Jan 23 Jan 30 Feb 06 Feb 13 Feb 20 Feb 27 Mar 06 Mar 13 Mar 20 Mar 27 Apr 03 Apr 10 Apr 17 Apr 24 May 01 May 08 May 15May 22
$200.00
$400.00
$600.00
$800.00
$1,000.00
$2,000.00
$4,000.00
$6,000.00
$8,000.00
$10,000.00
Abhishek Singh Daily Histogram and Cumulative curve for Material cost
Budgeted Material Cost Page 1 of 1 TASK filter: All Activities
© Oracle Corporation
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
$800.00
$1,600.00
$2,400.00
$3,200.00
$4,000.00
$10,000.00
$20,000.00
$30,000.00
$40,000.00
$50,000.00
Abhishek Singh Monthly Histogram and Cumulative curve for Total Cost
Budgeted Total Cost Page 1 of 1 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name
Residential ConstructionResidential Construction
General ConditionsGeneral ConditionsA1000 Finalize Plans & Develop estimate with owner, architect
A1010 Sign Contract & Notice to proceed
Apply For PermitsApply For Permits
A1110 Secure Foundation Permit
A1120 Secure Framing Permit
A1130 Secure Electrical Permit
A1140 Secure Plumbing Permit
A1150 Secure HVAC Permit
A1160 Secure miscellaneous permits
Site WorkSite WorkA1020 Clear and grub lot
A1030 Install temporary power service
A1040 Install underground utilities
FoundationFoundationA1170 Excavate for foundations
A1180 Form basement walls
A1190 Place concrete for foundations & basement walls
A1200 Cure basement walls for 7 days
A1210 Strip basement wall forms
A1220 Waterproof / insulate bsement walls
A1230 Perform foundation inspection
A1240 Backfill foundation
FramingFramingA1250 Install 1st floor joists
A1260 Lay 1st floor decking
A1270 Frame 1st floor walls
A1280 Frame 1st floor corners
A1290 Install 2nd floor joist
A1300 Frame 2nd Floor decking
A1310 Frame 2nd floor walls
A1320 Frame 2nd floor corners
A1330 Complete roof framing
A1340 Conduct framing inspection
Dry InDry InA1350 Install 1st Floor Sheathing
A1360 Install 2nd Floor Sheathing
A1370 Install roof decking
A1380 Install felt, flashing, and shingles
A1390 Hang 1st floor exterior doors
A1400 Install 1st floor windows
A1410 Install 2nd floor windows
Exterior FinishesExterior FinishesA1420 Complete Exterior Brick
A1430 Complete exterior siding
Utility Rough B97Ins and Complete ConcreteUtility Rough B97Ins and Complete ConcreteA1440 Rough-in-plumbing
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
10-May-17 05:00 PM, Residential Construction
10-Dec-16 05:00 PM, General Conditions
Finalize Plans & Develop estimate with owner, architect
Sign Contract & Notice to proceed10-Dec-16 05:00 PM, Apply For Permits
Secure Foundation Permit
Secure Framing Permit
Secure Electrical Permit
Secure Plumbing Permit
Secure HVAC Permit
Secure miscellaneous permits14-Dec-16 05:00 PM, Site Work
Clear and grub lot
Install temporary power service
Install underground utilities
01-Feb-17 05:00 PM, Foundation
Excavate for foundations
Form basement walls
Place concrete for foundations & basement walls
Cure basement walls for 7 days
Strip basement wall forms
Waterproof / insulate bsement walls
Perform foundation inspection
Backfill foundation27-Feb-17 05:00 PM, Framing
Install 1st floor joists
Lay 1st floor decking
Frame 1st floor walls
Frame 1st floor corners
Install 2nd floor joist
Frame 2nd Floor decking
Frame 2nd floor walls
Frame 2nd floor corners
Complete roof framing
Conduct framing inspection23-Mar-17 05:00 PM, Dry In
Install 1st Floor Sheathing
Install 2nd Floor Sheathing
Install roof decking
Install felt, flashing, and shingles
Hang 1st floor exterior doors
Install 1st floor windows
Install 2nd floor windows14-Apr-17 05:00 PM, Exterior Finishes
Complete Exterior Brick
Complete exterior siding25-Mar-17 05:00 PM, Utility Rough B97Ins and Complete Concrete
Rough-in-plumbing
Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name
A1450 Conduct Rough-in-plumbing inspection
A1460 Place concrete for basement floor
A1470 Rough-in electrical
A1480 Conduct Rough-in-electrical inspection
A1490 Rough-in HVAC
A1500 Conduct Rough-in-HVAC inspection
A1510 Rough-in communication - phone, cables, computer, alarm
Interior FinishesInterior FinishesInsulationInsulation
A1520 Place wall insulation - 1st floor
A1530 Place wall insulation - 2nd floor
A1540 Place ceiling insulation - 2nd floor
A1550 Conduct insulation inspection
DrywallDrywall
A1560 Install Drywall - 1st floor walls
A1570 Install drywall - 1st floor overhead
A1580 Install drywall 2nd floor walls
A1590 Install drywall 2nd floor overhead
A1600 Tape & Float 1st floor drywall
A1610 Tape & Float 2nd floor drywall
Paint & Wall PaperPaint & Wall Paper
A1620 Texture all except entry & kitchen - 1st floor
A1630 Paint all except entry & kitchen - 1st floor
A1640 Hang wallpaper entry & kitchen - 1st floor
A1650 Texture all - 2nd floor
A1660 Paint all - 2nd floor
A1670 Paint exterior siding & trim work
CabinetsCabinets
A1680 Install 1st floor - kitchen cabinets
A1690 Install 1st floor - master bath & guest cabinets
A1700 Install 2nd floor - hall bath & provate bath cabinets
A1710 install chair rails, crown moldings, trim
Finish PlumbingFinish Plumbing
A1720 Complete 1st floor - kitchen plumbing
A1730 Complete 1st floor - master bath & guest plumbing
A1740 Complete 2nd floor - hall bath & private bath plumbing
A1750 Conduct finish plumbing inspection
FInish ElectricalFInish Electrical
A1760 Complete 1st Floor circuits to service panel
A1770 Complete 2nd Floor circuits to service panel
A1780 Conduct finish electrical inspection
A1790 Complete communications wiring - phone, cable, computer alarm
Finish HVACFinish HVAC
A1800 Complete 1st floor - zone 1 HVAC
A1810 Complete 2nd floor - zone 2 HVAC
A1820 Conduct HVAC inspection
Carpet, Tile & AppliancesCarpet, Tile & Appliances
A1830 Tile entry, kitchen & bath
A1840 Carpet 1st floor
A1850 Carpet 2nd floor
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
Conduct Rough-in-plumbing inspection
Place concrete for basement floor
Rough-in electrical
Conduct Rough-in-electrical inspection
Rough-in HVAC
Conduct Rough-in-HVAC inspection
Rough-in communication - phone, cables, computer, alarm25-Apr-17 05:00 PM, Interior Finishes
03-Apr-17 05:00 PM, Insulation
Place wall insulation - 1st floor
Place wall insulation - 2nd floor
Place ceiling insulation - 2nd floor
Conduct insulation inspection01-Apr-17 05:00 PM, Drywall
Install Drywall - 1st floor walls
Install drywall - 1st floor overhead
Install drywall 2nd floor walls
Install drywall 2nd floor overhead
Tape & Float 1st floor drywall
Tape & Float 2nd floor drywall19-Apr-17 05:00 PM, Paint & Wall Paper
Texture all except entry & kitchen - 1st floor
Paint all except entry & kitchen - 1st floor
Hang wallpaper entry & kitchen - 1st floor
Texture all - 2nd floor
Paint all - 2nd floor
Paint exterior siding & trim work07-Apr-17 05:00 PM, Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath & guest cabinets
Install 2nd floor - hall bath & provate bath cabinets
install chair rails, crown moldings, trim10-Apr-17 05:00 PM, Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath & guest plumbing
Complete 2nd floor - hall bath & private bath plumbing
Conduct finish plumbing inspection12-Apr-17 05:00 PM, FInish Electrical
Complete 1st Floor circuits to service panel
Complete 2nd Floor circuits to service panel
Conduct finish electrical inspection
Complete communications wiring - phone, cable, computer alarm15-Apr-17 05:00 PM, Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection25-Apr-17 05:00 PM, Carpet, Tile & Appliances
Tile entry, kitchen & bath
Carpet 1st floor
Carpet 2nd floor
Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name
A1860 Install Appliances
Landscping and Grounds WorkLandscping and Grounds WorkA1870 Pour concrete driveway and sidewalks
A1880 Install backyard fence
A1890 Sod & complete plantings - frontyard
A1900 Sod & complete plantings - backyard
Final AcceptanceFinal AcceptanceA1910 Complete final inspection for certificate of occupancy
A1920 Cleanup for occupancy
A1930 Perform final walk - through inspection
A1940 Complete punch list items
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22
October 2016 November 2016 December 2016 January 2017 February 2017 March 2017 April 2017 May 2017
Install Appliances01-May-17 05:00 PM, Landscping and Grounds Work
Pour concrete driveway and sidewalks
Install backyard fence
Sod & complete plantings - frontyard
Sod & complete plantings - backyard10-May-17 05:00 PM, Final Acceptance
Complete final inspection for certificate of occupancy
Cleanup for occupancy
Perform final walk - through inspection
Complete punch list items
Actual Level of Effort Primary Baseline Actual Work R... Updated Project Schedule with Activity Table
Actual Level of Effort
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 3 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost
R Residential ConstructionR Residential Construction 164.00 139.00 01-Nov-16 08:00 AM 25-Apr-17 05:00 PM 02-Nov-16 08:00 AM A
10-May-17 05:00 PM 0.00 $45,220.00
R.1 General ConditionsR.1 General Conditions 35.00 10.00 01-Nov-16 08:00 AM 25-Nov-16 05:00 PM 02-Nov-16 08:00 AM A10-Dec-16 05:00 PM 0.00 $5,970.00
A1010 Sign Contract & Notice to proceed 1.00 1.00 24-Nov-16 08:00 AM 24-Nov-16 05:00 PM 09-Dec-16 08:00 AM 09-Dec-16 05:00 PM 0.00 $750.00
A1000 Finalize Plans & Develop estimate with owner, architect 20.00 8.00 01-Nov-16 08:00 AM 23-Nov-16 05:00 PM 02-Nov-16 08:00 AM A08-Dec-16 05:00 PM -13.00 $5,220.00
R.1.1 Apply For PermitsR.1.1 Apply For Permits 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1160 Secure miscellaneous permits 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1150 Secure HVAC Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1140 Secure Plumbing Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1130 Secure Electrical Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1120 Secure Framing Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
A1110 Secure Foundation Permit 1.00 1.00 25-Nov-16 08:00 AM 25-Nov-16 05:00 PM 10-Dec-16 08:00 AM 10-Dec-16 05:00 PM 0.00 $0.00
R.S Site WorkR.S Site Work 3.00 3.00 26-Nov-16 08:00 AM 29-Nov-16 05:00 PM 12-Dec-16 08:00 AM 14-Dec-16 05:00 PM 0.00 $750.00
A1040 Install underground utilities 1.00 1.00 29-Nov-16 08:00 AM 29-Nov-16 05:00 PM 14-Dec-16 08:00 AM 14-Dec-16 05:00 PM 0.00 $450.00
A1030 Install temporary power service 1.00 1.00 28-Nov-16 08:00 AM 28-Nov-16 05:00 PM 13-Dec-16 08:00 AM 13-Dec-16 05:00 PM 0.00 $150.00
A1020 Clear and grub lot 1.00 1.00 26-Nov-16 08:00 AM 26-Nov-16 05:00 PM 12-Dec-16 08:00 AM 12-Dec-16 05:00 PM 0.00 $150.00
R.2 FoundationR.2 Foundation 42.00 42.00 30-Nov-16 08:00 AM 17-Jan-17 05:00 PM 15-Dec-16 08:00 AM 01-Feb-17 05:00 PM 0.00 $7,050.00
A1240 Backfill foundation 2.00 2.00 16-Jan-17 08:00 AM 17-Jan-17 05:00 PM 31-Jan-17 08:00 AM 01-Feb-17 05:00 PM 0.00 $300.00
A1230 Perform foundation inspection 1.00 1.00 14-Jan-17 08:00 AM 14-Jan-17 05:00 PM 30-Jan-17 08:00 AM 30-Jan-17 05:00 PM 0.00 $500.00
A1220 Waterproof / insulate bsement walls 2.00 2.00 12-Jan-17 08:00 AM 13-Jan-17 05:00 PM 27-Jan-17 08:00 AM 28-Jan-17 05:00 PM 0.00 $400.00
A1210 Strip basement wall forms 2.00 2.00 10-Jan-17 08:00 AM 11-Jan-17 05:00 PM 25-Jan-17 08:00 AM 26-Jan-17 05:00 PM 0.00 $400.00
A1200 Cure basement walls for 7 days 7.00 7.00 02-Jan-17 08:00 AM 09-Jan-17 05:00 PM 17-Jan-17 08:00 AM 24-Jan-17 05:00 PM 0.00 $0.00
A1190 Place concrete for foundations & basement walls 12.00 12.00 19-Dec-16 08:00 AM 31-Dec-16 05:00 PM 03-Jan-17 08:00 AM 16-Jan-17 05:00 PM 0.00 $2,400.00
A1180 Form basement walls 13.00 13.00 03-Dec-16 08:00 AM 17-Dec-16 05:00 PM 19-Dec-16 08:00 AM 02-Jan-17 05:00 PM 0.00 $2,600.00
A1170 Excavate for foundations 3.00 3.00 30-Nov-16 08:00 AM 02-Dec-16 05:00 PM 15-Dec-16 08:00 AM 17-Dec-16 05:00 PM 0.00 $450.00
R.3 FramingR.3 Framing 22.00 22.00 18-Jan-17 08:00 AM 11-Feb-17 05:00 PM 02-Feb-17 08:00 AM 27-Feb-17 05:00 PM 0.00 $4,700.00
A1340 Conduct framing inspection 1.00 1.00 11-Feb-17 08:00 AM 11-Feb-17 05:00 PM 27-Feb-17 08:00 AM 27-Feb-17 05:00 PM 0.00 $500.00
A1330 Complete roof framing 3.00 3.00 08-Feb-17 08:00 AM 10-Feb-17 05:00 PM 23-Feb-17 08:00 AM 25-Feb-17 05:00 PM 0.00 $600.00
A1320 Frame 2nd floor corners 2.00 2.00 06-Feb-17 08:00 AM 07-Feb-17 05:00 PM 21-Feb-17 08:00 AM 22-Feb-17 05:00 PM 0.00 $400.00
A1310 Frame 2nd floor walls 3.00 3.00 02-Feb-17 08:00 AM 04-Feb-17 05:00 PM 17-Feb-17 08:00 AM 20-Feb-17 05:00 PM 0.00 $600.00
A1300 Frame 2nd Floor decking 2.00 2.00 31-Jan-17 08:00 AM 01-Feb-17 05:00 PM 15-Feb-17 08:00 AM 16-Feb-17 05:00 PM 0.00 $400.00
A1290 Install 2nd floor joist 2.00 2.00 28-Jan-17 08:00 AM 30-Jan-17 05:00 PM 13-Feb-17 08:00 AM 14-Feb-17 05:00 PM 0.00 $400.00
A1280 Frame 1st floor corners 1.00 1.00 27-Jan-17 08:00 AM 27-Jan-17 05:00 PM 11-Feb-17 08:00 AM 11-Feb-17 05:00 PM 0.00 $200.00
A1270 Frame 1st floor walls 4.00 4.00 23-Jan-17 08:00 AM 26-Jan-17 05:00 PM 07-Feb-17 08:00 AM 10-Feb-17 05:00 PM 0.00 $800.00
A1260 Lay 1st floor decking 2.00 2.00 20-Jan-17 08:00 AM 21-Jan-17 05:00 PM 04-Feb-17 08:00 AM 06-Feb-17 05:00 PM 0.00 $400.00
A1250 Install 1st floor joists 2.00 2.00 18-Jan-17 08:00 AM 19-Jan-17 05:00 PM 02-Feb-17 08:00 AM 03-Feb-17 05:00 PM 0.00 $400.00
R.4 Dry InR.4 Dry In 22.00 22.00 11-Feb-17 08:00 AM 08-Mar-17 05:00 PM 27-Feb-17 08:00 AM 23-Mar-17 05:00 PM 0.00 $3,500.00
A1410 Install 2nd floor windows 3.00 3.00 06-Mar-17 08:00 AM 08-Mar-17 05:00 PM 21-Mar-17 08:00 AM 23-Mar-17 05:00 PM 0.00 $600.00
A1400 Install 1st floor windows 3.00 3.00 02-Mar-17 08:00 AM 04-Mar-17 05:00 PM 17-Mar-17 08:00 AM 20-Mar-17 05:00 PM 0.00 $600.00
A1390 Hang 1st floor exterior doors 1.00 1.00 01-Mar-17 08:00 AM 01-Mar-17 05:00 PM 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 0.00 $200.00
A1380 Install felt, flashing, and shingles 3.00 3.00 25-Feb-17 08:00 AM 28-Feb-17 05:00 PM 13-Mar-17 08:00 AM 15-Mar-17 05:00 PM 0.00 $300.00
A1360 Install 2nd Floor Sheathing 3.00 3.00 16-Feb-17 08:00 AM 18-Feb-17 05:00 PM 03-Mar-17 08:00 AM 06-Mar-17 05:00 PM 0.00 $600.00
A1350 Install 1st Floor Sheathing 3.00 3.00 13-Feb-17 08:00 AM 15-Feb-17 05:00 PM 28-Feb-17 08:00 AM 02-Mar-17 05:00 PM 0.00 $600.00
A1370 Install roof decking 3.00 3.00 11-Feb-17 08:00 AM 14-Feb-17 05:00 PM 27-Feb-17 08:00 AM 01-Mar-17 05:00 PM 0.00 $600.00
R.6 Exterior FinishesR.6 Exterior Finishes 19.00 19.00 09-Mar-17 08:00 AM 30-Mar-17 05:00 PM 24-Mar-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $3,000.00
A1430 Complete exterior siding 3.00 3.00 28-Mar-17 08:00 AM 30-Mar-17 05:00 PM 12-Apr-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $600.00
A1420 Complete Exterior Brick 16.00 16.00 09-Mar-17 08:00 AM 27-Mar-17 05:00 PM 24-Mar-17 08:00 AM 11-Apr-17 05:00 PM 0.00 $2,400.00
R.7 Utility Rough B97Ins and Complete ConcreteR.7 Utility Rough B97Ins and Complete Concrete 21.00 21.00 15-Feb-17 08:00 AM 10-Mar-17 05:00 PM 02-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $6,700.00
A1460 Place concrete for basement floor 11.00 11.00 27-Feb-17 08:00 AM 10-Mar-17 05:00 PM 14-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $2,200.00
Abhishek Singh Updated Project Schedule with Activity Table
Page 1 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost
A1500 Conduct Rough-in-HVAC inspection 1.00 1.00 02-Mar-17 08:00 AM 02-Mar-17 05:00 PM 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 0.00 $500.00
A1490 Rough-in HVAC 3.00 3.00 27-Feb-17 08:00 AM 01-Mar-17 05:00 PM 14-Mar-17 08:00 AM 16-Mar-17 05:00 PM 0.00 $450.00
A1480 Conduct Rough-in-electrical inspection 1.00 1.00 25-Feb-17 08:00 AM 25-Feb-17 05:00 PM 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 0.00 $500.00
A1450 Conduct Rough-in-plumbing inspection 1.00 1.00 25-Feb-17 08:00 AM 25-Feb-17 05:00 PM 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 0.00 $500.00
A1470 Rough-in electrical 5.00 5.00 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 07-Mar-17 08:00 AM 11-Mar-17 05:00 PM 0.00 $750.00
A1440 Rough-in-plumbing 5.00 5.00 20-Feb-17 08:00 AM 24-Feb-17 05:00 PM 07-Mar-17 08:00 AM 11-Mar-17 05:00 PM 0.00 $1,500.00
A1510 Rough-in communication - phone, cables, computer, alarm 2.00 2.00 15-Feb-17 08:00 AM 16-Feb-17 05:00 PM 02-Mar-17 08:00 AM 03-Mar-17 05:00 PM 0.00 $300.00
R.8 Interior FinishesR.8 Interior Finishes 29.00 29.00 08-Mar-17 08:00 AM 10-Apr-17 05:00 PM 23-Mar-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $10,300.00
R.8.1 InsulationR.8.1 Insulation 9.00 9.00 09-Mar-17 08:00 AM 18-Mar-17 05:00 PM 24-Mar-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $1,400.00
A1550 Conduct insulation inspection 1.00 1.00 18-Mar-17 08:00 AM 18-Mar-17 05:00 PM 03-Apr-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $500.00
A1540 Place ceiling insulation - 2nd floor 1.00 1.00 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 01-Apr-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $300.00
A1530 Place wall insulation - 2nd floor 1.00 1.00 10-Mar-17 08:00 AM 10-Mar-17 05:00 PM 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 0.00 $300.00
A1520 Place wall insulation - 1st floor 1.00 1.00 09-Mar-17 08:00 AM 09-Mar-17 05:00 PM 24-Mar-17 08:00 AM 24-Mar-17 05:00 PM 0.00 $300.00
R.8.2 DrywallR.8.2 Drywall 9.00 9.00 08-Mar-17 08:00 AM 17-Mar-17 05:00 PM 23-Mar-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $2,000.00
A1610 Tape & Float 2nd floor drywall 1.00 1.00 17-Mar-17 08:00 AM 17-Mar-17 05:00 PM 01-Apr-17 08:00 AM 01-Apr-17 05:00 PM 0.00 $200.00
A1590 Install drywall 2nd floor overhead 2.00 2.00 15-Mar-17 08:00 AM 16-Mar-17 05:00 PM 30-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $400.00
A1580 Install drywall 2nd floor walls 2.00 2.00 13-Mar-17 08:00 AM 14-Mar-17 05:00 PM 28-Mar-17 08:00 AM 29-Mar-17 05:00 PM 0.00 $400.00
A1600 Tape & Float 1st floor drywall 1.00 1.00 13-Mar-17 08:00 AM 13-Mar-17 05:00 PM 28-Mar-17 08:00 AM 28-Mar-17 05:00 PM 0.00 $200.00
A1570 Install drywall - 1st floor overhead 2.00 2.00 10-Mar-17 08:00 AM 11-Mar-17 05:00 PM 25-Mar-17 08:00 AM 27-Mar-17 05:00 PM 0.00 $400.00
A1560 Install Drywall - 1st floor walls 2.00 2.00 08-Mar-17 08:00 AM 09-Mar-17 05:00 PM 23-Mar-17 08:00 AM 24-Mar-17 05:00 PM 0.00 $400.00
R.8.3 Paint & Wall PaperR.8.3 Paint & Wall Paper 19.00 19.00 14-Mar-17 08:00 AM 04-Apr-17 05:00 PM 29-Mar-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $900.00
A1670 Paint exterior siding & trim work 4.00 4.00 31-Mar-17 08:00 AM 04-Apr-17 05:00 PM 15-Apr-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $400.00
A1660 Paint all - 2nd floor 1.00 1.00 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $100.00
A1640 Hang wallpaper entry & kitchen - 1st floor 1.00 1.00 16-Mar-17 08:00 AM 16-Mar-17 05:00 PM 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 0.00 $100.00
A1650 Texture all - 2nd floor 1.00 1.00 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 0.00 $100.00
A1630 Paint all except entry & kitchen - 1st floor 1.00 1.00 15-Mar-17 08:00 AM 15-Mar-17 05:00 PM 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 0.00 $100.00
A1620 Texture all except entry & kitchen - 1st floor 1.00 1.00 14-Mar-17 08:00 AM 14-Mar-17 05:00 PM 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 0.00 $100.00
R.8.4 CabinetsR.8.4 Cabinets 6.00 6.00 17-Mar-17 08:00 AM 23-Mar-17 05:00 PM 01-Apr-17 08:00 AM 07-Apr-17 05:00 PM 0.00 $900.00
A1710 install chair rails, crown moldings, trim 2.00 2.00 22-Mar-17 08:00 AM 23-Mar-17 05:00 PM 06-Apr-17 08:00 AM 07-Apr-17 05:00 PM 0.00 $300.00
A1700 Install 2nd floor - hall bath & provate bath cabinets 1.00 1.00 21-Mar-17 08:00 AM 21-Mar-17 05:00 PM 05-Apr-17 08:00 AM 05-Apr-17 05:00 PM 0.00 $150.00
A1690 Install 1st floor - master bath & guest cabinets 1.00 1.00 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 04-Apr-17 08:00 AM 04-Apr-17 05:00 PM 0.00 $150.00
A1680 Install 1st floor - kitchen cabinets 2.00 2.00 17-Mar-17 08:00 AM 18-Mar-17 05:00 PM 01-Apr-17 08:00 AM 03-Apr-17 05:00 PM 0.00 $300.00
R.8.5 Finish PlumbingR.8.5 Finish Plumbing 6.00 6.00 20-Mar-17 08:00 AM 25-Mar-17 05:00 PM 04-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $2,000.00
A1750 Conduct finish plumbing inspection 1.00 1.00 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $500.00
A1740 Complete 2nd floor - hall bath & private bath plumbing 2.00 2.00 23-Mar-17 08:00 AM 24-Mar-17 05:00 PM 07-Apr-17 08:00 AM 08-Apr-17 05:00 PM 0.00 $600.00
A1730 Complete 1st floor - master bath & guest plumbing 2.00 2.00 21-Mar-17 08:00 AM 22-Mar-17 05:00 PM 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 0.00 $600.00
A1720 Complete 1st floor - kitchen plumbing 1.00 1.00 20-Mar-17 08:00 AM 20-Mar-17 05:00 PM 04-Apr-17 08:00 AM 04-Apr-17 05:00 PM 0.00 $300.00
R.8.6 FInish ElectricalR.8.6 FInish Electrical 3.00 3.00 25-Mar-17 08:00 AM 28-Mar-17 05:00 PM 10-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $1,100.00
A1790 Complete communications wiring - phone, cable, computer alarm 2.00 2.00 27-Mar-17 08:00 AM 28-Mar-17 05:00 PM 11-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $300.00
A1780 Conduct finish electrical inspection 1.00 1.00 28-Mar-17 08:00 AM 28-Mar-17 05:00 PM 12-Apr-17 08:00 AM 12-Apr-17 05:00 PM 0.00 $500.00
A1770 Complete 2nd Floor circuits to service panel 1.00 1.00 27-Mar-17 08:00 AM 27-Mar-17 05:00 PM 11-Apr-17 08:00 AM 11-Apr-17 05:00 PM 0.00 $150.00
A1760 Complete 1st Floor circuits to service panel 1.00 1.00 25-Mar-17 08:00 AM 25-Mar-17 05:00 PM 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 0.00 $150.00
R.8.7 Finish HVACR.8.7 Finish HVAC 3.00 3.00 29-Mar-17 08:00 AM 31-Mar-17 05:00 PM 13-Apr-17 08:00 AM 15-Apr-17 05:00 PM 0.00 $800.00
A1820 Conduct HVAC inspection 1.00 1.00 31-Mar-17 08:00 AM 31-Mar-17 05:00 PM 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 0.00 $500.00
A1810 Complete 2nd floor - zone 2 HVAC 1.00 1.00 30-Mar-17 08:00 AM 30-Mar-17 05:00 PM 14-Apr-17 08:00 AM 14-Apr-17 05:00 PM 0.00 $150.00
A1800 Complete 1st floor - zone 1 HVAC 1.00 1.00 29-Mar-17 08:00 AM 29-Mar-17 05:00 PM 13-Apr-17 08:00 AM 13-Apr-17 05:00 PM 0.00 $150.00
R.8.8 Carpet, Tile & AppliancesR.8.8 Carpet, Tile & Appliances 8.00 8.00 01-Apr-17 08:00 AM 10-Apr-17 05:00 PM 17-Apr-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $1,200.00
A1860 Install Appliances 1.00 1.00 10-Apr-17 08:00 AM 10-Apr-17 05:00 PM 25-Apr-17 08:00 AM 25-Apr-17 05:00 PM 0.00 $150.00
A1850 Carpet 2nd floor 2.00 2.00 07-Apr-17 08:00 AM 08-Apr-17 05:00 PM 22-Apr-17 08:00 AM 24-Apr-17 05:00 PM 0.00 $300.00
A1840 Carpet 1st floor 2.00 2.00 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 20-Apr-17 08:00 AM 21-Apr-17 05:00 PM 0.00 $300.00
Abhishek Singh Updated Project Schedule with Activity Table
Page 2 of 3 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original Duration Remaining Duration BL Project Start BL Project Finish Start Finish Variance - BL1 Finish Date Budgeted Total Cost
A1830 Tile entry, kitchen & bath 3.00 3.00 01-Apr-17 08:00 AM 04-Apr-17 05:00 PM 17-Apr-17 08:00 AM 19-Apr-17 05:00 PM 0.00 $450.00
R.9 Landscping and Grounds WorkR.9 Landscping and Grounds Work 10.00 10.00 05-Apr-17 08:00 AM 15-Apr-17 05:00 PM 20-Apr-17 08:00 AM 01-May-17 05:00 PM 0.00 $1,600.00
A1900 Sod & complete plantings - backyard 1.00 1.00 15-Apr-17 08:00 AM 15-Apr-17 05:00 PM 01-May-17 08:00 AM 01-May-17 05:00 PM 0.00 $300.00
A1890 Sod & complete plantings - frontyard 2.00 2.00 13-Apr-17 08:00 AM 14-Apr-17 05:00 PM 28-Apr-17 08:00 AM 29-Apr-17 05:00 PM 0.00 $600.00
A1880 Install backyard fence 2.00 2.00 11-Apr-17 08:00 AM 12-Apr-17 05:00 PM 26-Apr-17 08:00 AM 27-Apr-17 05:00 PM 0.00 $300.00
A1870 Pour concrete driveway and sidewalks 2.00 2.00 05-Apr-17 08:00 AM 06-Apr-17 05:00 PM 20-Apr-17 08:00 AM 21-Apr-17 05:00 PM 0.00 $400.00
R.5 Final AcceptanceR.5 Final Acceptance 8.00 8.00 17-Apr-17 08:00 AM 25-Apr-17 05:00 PM 02-May-17 08:00 AM 10-May-17 05:00 PM 0.00 $1,650.00
A1940 Complete punch list items 5.00 5.00 20-Apr-17 08:00 AM 25-Apr-17 05:00 PM 05-May-17 08:00 AM 10-May-17 05:00 PM 0.00 $750.00
A1930 Perform final walk - through inspection 1.00 1.00 19-Apr-17 08:00 AM 19-Apr-17 05:00 PM 04-May-17 08:00 AM 04-May-17 05:00 PM 0.00 $200.00
A1920 Cleanup for occupancy 1.00 1.00 18-Apr-17 08:00 AM 18-Apr-17 05:00 PM 03-May-17 08:00 AM 03-May-17 05:00 PM 0.00 $200.00
A1910 Complete final inspection for certificate of occupancy 1.00 1.00 17-Apr-17 08:00 AM 17-Apr-17 05:00 PM 02-May-17 08:00 AM 02-May-17 05:00 PM 0.00 $500.00
Abhishek Singh Updated Project Schedule with Activity Table
Page 3 of 3 TASK filter: All Activities
© Oracle Corporation