CE-401CE 1.0 Bar Chart 2015

Embed Size (px)

Citation preview

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    1/49

    .CONSTRUCTION PLANNING

    & MANAGEMENT

    COURSE OBJECTIVE

    To enable the students learn network

    techniques, construction planning

    practices, construction equipments &

    methods along with quality control in

    construction

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    2/49

    COURSE CONTENTS

    Network technique! "#$%

    B'ic B'r Ch'rt( Networkin)( CPM 'n*

    PERT 'n* Cot Mo*e+ Technique,

    Introduction to network techniques,

    Use of CP and P!"T for planning,

    scheduling and control of construction

    works.

    #etwork scheduling and bar chart. !rrors

    in networks. Types of nodes and node

    numbering systems.

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    3/49

    COURSE CONTENTS

    Contruction P+'nnin)! "-.% Planning for construction and site facilities

    using networks.

    Preparation of construction schedules for$ob. aterials, equipment, labor and

    budgets using CP.

    Construction %uality Control andinspection.

    ignificance of 'ariability and estimation of

    risk. Construction cost control.

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    4/49

    Contruction Equi/0ent 'n* Metho*! "1.%!quipments for earth construction and application.

    Concrete construction. (ggregate production,

    concrete) production, handling and placement, mi*ers,

    'ibrators and temperature control.

    Book+ ri'asta'a U. . -Construction Planning and management - /0001. 2algotia

    Publishers, #ew 3elhi+ Peurifoy, ". 4., -Construction Planning, !quipments and ethods - /0051 c

    2raw 6ills, Tokyo+ rinath 4.., -P!"T and CP Principles and (pplications7 899:1 (ffiliated !ast;

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    5/49

    CONSTRUCTIONPLANNING &

    MANAGEMENT

    PROJECT SC2E3ULING!

    IMPORTANCE( STEPS 4OR BAR

    C2ART( GANTT C2ART

    CONSTRUCTION LABOR! T5PES(

    PRO3UCTIVIT5( MULTIS6ILLING &SOCIAL ASPECTS

    CONSTRUCTION E7UIPMENTS!

    I3ENTI4ICATION( ACTUAL OUTPUT(

    EMPLO5MENT COST( AC7UISITION

    OPTIONS 4ILE3 VISITS

    BASICS8 PROJECT P2ASES( PROJECT

    3ELIVER5 S5STEM( PROJECT TEAM

    CONSTRUCTION MATERIAL!

    MANAGEMENT( PROVISIONING

    STEPS( INVENTOR5

    CRITICAL PAT2 MET2O3S! PROJECT

    PLANNING( EVENT TIMES( CRITICAL

    PAT2S( ACTIVIT5 TIES( ACTIVIT5

    4LOATS

    PERT TEC2NI7UE! UNCERTAINLT5(

    PROJECT PLANNING( PROBABILIT5

    O4 COMPLETION

    COST MO3EL! 3IRECT

    IN3IRECT COST( TIME9

    COMPRESSION

    TEC2NI7UES

    7UALIT5 CONTROL IN

    COSNTRUCTION!INSPECTION( TOTAL 7UALT5

    CONTROL( ISO :$$$(

    7UALIT5 ASSURANCE

    PROGRAM( RIS6

    CONTAINMENT

    SA4ET5 IN

    CONSTRUCTION

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    6/49

    P+'nnin) & Sche*u+in)

    I;

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    7/49

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    8/49

    Nee* ;or Sche*u+in) >

    =wner =wner "equirement

    Communication of the Construction Plan

    onitor and measure progress

    2eneral Contractor>ub Contractors>uper'isor !stablish production goals

    anage Change

    Communication of the construction plan

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    9/49

    T

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    10/49

    4or0't o; Sche*u+e

    ummary schedule

    hows ma$or work elements, such as 3esign,

    Ci'il, !lectrical, commissioning1

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    11/49

    B'r Ch'rt

    3e'eloped by 6enry 2antt =ften called a 2antt Chart

    3efinition( graphical description of a pro$ect consisting

    of well;defined collection of tasks

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    12/49

    (cti'ities are represented by bars inproportion to their duration.(n acti'ity is a task or closely related group of

    tasks whose performance contributes to thecompletion of the o'erall pro$ect !*ample) !*ca'ate foundation

    ?ar chart is usually graphed on a calendar

    Can be as simple or detailed as necessary

    B'r Ch'rt

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    13/49

    E'0/+e B'r Ch'rt9

    Cu+ertTi0e

    June Ju+< Au)ut Se/te0@er Octo@er

    Ec''tion &B'ck;i++

    Pi++in)

    A@ut0ent No, -

    A@ut0ent No,1

    Stee+ )ir*er

    Concrete 3eck

    4inihin)O/er'tion

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    14/49

    Cul'ert

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    15/49

    Contructin) ' B'r Ch'rt

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    16/49

    Cot +o'*e* Contruction

    Sche*u+e

    http)>>www.pro$ectrisk.com

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    17/49

    M'n92our +o'*e* Sche*u+e

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    18/49

    4abor chedule

    http)>>hafeeDrm.hubpages.com

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    19/49

    Ste/ to Contruct ' B'r Ch'rt

    Identify (cti'ities

    !stimate (cti'ity 3uration

    3e'elop (cti'ity equence Construct ?ar Chart

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    20/49

    -, I*enti;ic'tion o; Actiitie

    Use the

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    21/49

    Work Breakdown Structure

    Hierarchical organization of a system Continued until sub-system is reduced to a

    manageable unit.

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    22/49

    Work Breakdown Structure Hierarchical organization of a system Continued until sub-

    system is reduced to a manageable unit.

    ?uilding E/

    Foundation tructure Interior

    !*ca'ation Footings

    Isolated Footings Continuous Footings

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    23/49

    Sewage Pumping Station-WBS

    P ci'il

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    24/49

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    25/49

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    26/49

    8. !stimate (cti'ity 3uration

    6ow to estimate duration) From companyGs historic records

    From asking superintendent or foreman

    From standard estimating guide

    From calculation using the 4abor 6our

    Producti'ity equation

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    27/49

    4abor;6our Producti'ity ethod

    Total labor;hours required for an acti'ity H

    labor;hours >Unit * no. of units

    Total days H

    Total days H

    total labor hours

    labor;hours > day

    total labor hours

    crew siDe * hrs>day

    :. !stimate (cti'ity 3uration

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    28/49

    Find the duration days1 of an interior and

    e*terior painting acti'ities with quantities of 9m8and ::JK m8respecti'ely, using crews of //

    m8>hours and / m8>hours for the interior and

    e*terior painting acti'ities respecti'ely. (ssume

    three shifts of K;h for each acti'ity.

    So+ution

    Interior painting duration H 9 > 8*// H /5.K or /J days

    !*terior painting duration H ::JK > 8* / H /9 daysTotal work hours H 8J days

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    29/49

    equencing needs to take into account therelationships between acti'ities.

    There are four types of relationships thatneed to be taken into account.

    -, Ph

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    30/49

    1, S';et

    !*ists when simultaneous performance of two

    acti'ities can result in a safety haDard i.e., in

    multi;story construction it is at times unsafe forcrews to be working under one another1

    , Reource!

    3ue to limited resource a'ailability, two acti'ities

    may not be able to use a resource at the sametime i.e., a crane cannot be used for both

    pouring walls and erecting steel1D, Pre;erenti'+!

    6ow the contractor wishes certain acti'ities to be

    1, Et'@+ih the Sequence O;

    =ork "continue*

    3 th B Ch t 4i + 3 i &

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    31/49

    3r'w the B'r Ch'rt 4in'+ 3ei)n &

    =ork Or*er ;or ' Bui+*in)F

    4in'+ 3ei)n & =ork Or*er

    3ei)n=ork

    Or*er

    Site

    Sure

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    32/49

    !stimate (cti'ity 3urationActiit< 3ecri/tion

    A Site Sure

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    33/49

    !stablish equence of

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    34/49

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    35/49

    BAR C2ART

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    36/49

    (nother !*ample

    ?ar Chart

    Immediate EstimatedActivity Predecessor Completion Time

    A None 90B A 15C B 5D G 20E D 21

    F A 25G C,F 14H D 28I A 30J D,I 45

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    37/49

    A

    :$

    09

    B-.

    4

    1.

    I

    $

    -$.

    C

    .

    --.

    G

    -D

    -1:

    3

    1$

    -D:

    E

    1-

    2

    1

    J

    D.

    -:D

    -:D

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    38/49

    2antt chart can be used as a 'isual aid fortracking the progress of pro$ect acti'ities.

    (ppropriate percentage of a bar is shaded todocument the completed work.

    The manager can easily see if the pro$ect isprogressing on schedule with respect to theearliest possible completiontimes1.

    G'ntt Ch'rt 9 Monitorin) Pro?ect

    Pro)re

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    39/49

    A

    :$

    B-.

    4

    1.

    I

    $

    C

    .

    G

    -D

    3

    1$

    E

    1-

    2

    1

    J

    D.

    -:D

    -:D

    -.

    onitoring Pro$ect Progress

    The shaded bars represent

    completed work ?L 3(L /:@.

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    40/49

    A*'nt')e o; B'r Ch'rt

    Misual representation of entire pro$ect.

    !asy to construct and read.

    Traditional ethod;#o computer needed. Progress achie'ed at site e*pressed in

    terms of percentage.

    !asily produced by all schedulingsoftware.

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    41/49

    4imitation /) Time Uncertainties

    =nly one time for the completion of

    pro$ect) ometimes uncertainties in determination of

    Pro$ect. #o pessimistic and optimistic times1

    Can be used for con'entional pro$ects with

    set times not for comple* " & 3 Pro$ects.

    =nly pro$ects with Fair degree of certainty

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    42/49

    LIMITATION 1 9LAC6 3EGREE O4

    3ETAILS

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    43/49

    Mi+etone

    6e< 3'te(! board meetings,key dates mark significant pieces of

    pro$ect

    ey 3eadlines)

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    44/49

    (cti'ity Interrelationship

    #o interrelationship) If ( is delayed by / week, what happens for ? & C)

    Cannot be clearly portrayed

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    45/49

    T'k A

    T'k B

    T'k C

    T'k 3

    / 8

    : @

    5J

    K 0 /9

    (fter defining

    Interrelationship)

    #etwork diagram

    can be prepared

    /

    :

    5

    K

    8

    @

    J

    0 /9

    8.9

    8.9 /.@

    :.9

    8.9 /.@

    : cannot tart until / finish,

    cannot start until : finishes

    /.9

    8.9 :.9 .9

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    46/49

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    47/49

    #etwork 3iagram

    Clearly shows interrelationship between

    e'ents.

    Can be used for highly complicated

    pro$ects with large acti'ities.

    Indicate time required in between two

    milestones or acti'ities. 6elpful in

    rescheduling, if required. If uncertainties are required, it allows

    probability theory for time estimations

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    48/49

    Importance of Planning &

    cheduling Failure to plan and schedule leads to e*cessi'e labor cost,

    equipment waiting time, delays, waiting for materials,

    lack of coordination, and management inability to

    react to une*pected e'ents weather, equipment

    breakdowns, shortages1

    Producti'ity 4oss

  • 7/25/2019 CE-401CE 1.0 Bar Chart 2015

    49/49

    Presentation (ssignment

    -,$ 3ee+o/ the =BS ;or the 4o++owin) Pro?ect!

    2roup / & K; 6ighway Construction

    2roup 8 & 0 ; ?ridge Construction

    2roup : & /9 ; ultistory ?uilding Construction

    2roup & // ; "ailway Track Construction

    2roup @ & /8 ;