CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust Experiment (CDE) Science and Calibration David James University of Colorado/LASP 303-492-5208 [email protected]

CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

Embed Size (px)

Citation preview

Page 1: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name1

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James1

GATS

Cosmic Dust Experiment (CDE)Science and Calibration

David James

University of Colorado/LASP

303-492-5208

[email protected]

Page 2: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name2

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James2

GATS

Science Goals

Monitor the cosmic dust flux variability :

CDE measures dust flux using an impact detector.

Measurement at S/C is directly related to dust input to the mesosphere.

Page 3: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name3

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James3

GATS

Dust Detection using PVDF

Depolarization induced current

PVDF Film Al/Ni Contacts

DepolarizationCavity

VolumePolarization P

m

v

VolumePolarization P

VolumePolarization P

Page 4: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name4

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James4

GATS

Calibration and Validation Plan

Calibration is performed in two steps:

• Electronics (DN to charge)– Performed at LASP 9/16-9/20

• PVDF Detectors (Charge to mass, given velocity)– SDC calibration with dust accelerator in Heidelberg, Germany is complete– Proposed CDE calibration in early 2006

Page 5: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name5

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James5

GATS

E-box Calibration

Calibration of Electronics was performed at LASP before (abbreviated) and after the environmental (full) testing

• Tested full dynamic range of each signal chain 104-1010e charges at 21 individual values (100 events at each of the 21 values injected externally).

• Tested over full range of E-box temperatures (-26 to 50oC)– Full calibration at -26, 0, 15, 30, 50°C– Pre-Environmental Calibration at 20oC

• Repeated for all 14 channels

• Total Calibration generated 14 x 5 x 21 = 1476 data sets of 100 hits.

Page 6: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name6

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James6

GATS

Calibration Setup – External Charge Injection

Injection Circuit to Simulate Detector Signal

Environmental Chamber

Data Collection

Page 7: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name7

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James7

GATS

Sample CDE Calibration Curves

Page 8: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name8

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James8

GATS

Simpson-Tuzzolino Curve

]/[][018.3][ 33.117 skmvgmeN ×=

Page 9: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name9

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James9

GATS

CDE will maximize impact rates

CDE detector area ~ 0.1 m2

300 hits/day @ 0.1 m threshold

3 hits/day @ 1.0 m threshold

Science requirement:

100 hits/week → 0.7 m threshold

mass

Page 10: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name10

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James10

GATS

15 km/s

10

PVDF Detectors

13

100 hits/week on ~ 0.1 m2

2

100 hits/day

To meet science requirement of 100 hits/week must have a noise floor of 106 electrons.

Page 11: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name11

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James11

GATS

Noise floor well below required 106 electrons.

CDE satisfies its science requirements!

CDE Noise Characterization

9*105 e level

Page 12: CDE CDR, September 14, 2004 Your Position, Your Name 1 GATS CDE Pre-Ship Review October 6, 2005 Science and Calibration David James 1 GATS Cosmic Dust

CDE CDR, September 14, 2004

Your Position, Your Name12

GATS CDE Pre-Ship Review October 6, 2005

Science and Calibration David James12

GATS

Calibration Summary

Charge injection calibration has been completed and is ready for integration into ground processing software

Determination of noise floor via zero threshold noise collection verifies that CDE meets science requirements

CDE is ready to ship and meets science requirements