CCC Commissioning

Django Manglunki, AB/OP

PS-SPS Days 18/1/2006

Page 2: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 2

Outline

• Constraints and boundary limits

• Reminder of room and consoles layout

• Project status as of today

• Schedule/Resources for TI, PS complex, SPS, Cryogenics, LHC HWC

• Conclusions

Page 3: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 3

Constraints and boundary limits• Restart of existing

accelerator chain and technical services

• TI operates 24/7

• LEIR early February

• LHC sector test mid-November

Page 4: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 4

Room layout: 4 similar but not identical islets

~50 19”screens for controls, local fixed displays, administration and access on outer tables

4 large 46” screens for general purpose fixed displays

3 19”screens for laptops and mail/web on central tables

19” cabinet for rackable HW (access, intercom, beam inhibits, radiation alarms …)

5 IP-touch phones

1 colourprinter

Page 5: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 5

Project status as of today• TS works finished except:

– Finishing paint (27/1)– Heating/AC (27/1?)– Blinds and lighting controls (20/1)– CCC Access control operational but administration needed

(cards distribution + EDH authorizations)

Picture January 16th 2006Simulation December 3rd 2004

Page 6: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 6

Project status as of today (2)• CO works:

– Most hardware installed– Configuration in progress, TI islet will be delivered 19/1– Other islets to follow; end January 27th

• Video signals– Last HW delivery mid February– System operational end February

• Communications– All phones installed, operational– Server configuration started 13/1, finishing 27/1,

tests start with TI 30/1– SPS intercom February

• Fast analog signals– First HW batch delivered last week (11/1)– Observation of signals mid-April

Page 7: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 7

Project status as of today (3)

• PS complex access– Configuration and test under way– Switch control from CSA on week-end

February 4-5 (LEIR starts February 6th!)– Radio protection alarms: Hardware being installed

• SPS Access– racks in 867 for configuration;move to CCC 20/1– Test access control from CCC 2nd fortnight March

Page 8: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 8

Schedule/resources for TI

• CCC Cold checkout starts January 23rd

– Configure and test application programs– Configure and test room functions (lighting

and blinds controls…)– Configure and test communications (30-31/1)– Additional 2 TI technicians 8 hours/day

• Move in from MCR on February 1st

– 1 TI + 1 PS/PSB 24/7 until PS shifts start

Page 9: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 9

Schedule/resources for PS complex• CCC Cold checkout starts February 13th

– Configure and test application programs– Configure and test communications– 2 PS/PSB technicians 8 hours/day– Until PS/PSB shifts start, access given by PSB

technician on TI shift• PS magnet tests start 20/2• PSB/PS closed 6/3

– PSB HW tests– Additional 2 PS/PSB tech 8 hours/day

• PS shifts start 20/3– 3 tech on shift 24/7– Only 1 TI tech

Page 10: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 10

Schedule/resources for SPS• CCC Cold checkout starts March 6th

– Configure and test communications– Configure and test application programs– Test access control

• Give access only during working hours

– 2 SPS technicians 8 hours/day

• SPS shifts start 3/4 for HW tests– 2 tech on shift 24/7

• Request of SPS OP in February– for TI8/CNGS tests!

Page 11: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 11

Schedule/resources for Cryogenics

• CCC Cold checkout starts March 6th in parallel with operations/tests from local control rooms– Configure and test application programs– Configure and test communications– 1 AT/ACR technician + 1 AB/CO 8 hours/day

• First operation from CCC expected in June

Page 12: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 12

Schedule/resources for LHC HWC• CCC Cold checkout starts September 4th

– Test access control– Configure and test application programs– Configure and test communications– 3 LHC OP or EiC , 16 hours/day

• HWC gradually moves from FCR to CCC in October/November

• Sector test from CCC end November

Page 13: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 13

Overall schedule January – April 2006

Page 14: CCC Commissioning Django Manglunki, AB/OP PS-SPS Days 18/1/2006

CCC Commissioning PS-SPS DAYS 18/1/ 2006D. Manglunki, AB/OP 14

Conclusion

• Good collaboration needed between all parts (AB/OP, AB/CO, TS/CSE, TS/EL, TS/CV, AT/ACR, TS/HDO, IT/CS…) for validation of CCC functionalities

• So far so good, February 1st is still the delivery date: 14 days to go!