Upload
friendbce
View
314
Download
7
Embed Size (px)
DESCRIPTION
500mw bhel boiler
Citation preview
5/26/2018 CC Pump Manual-Full (Original)
1/109
HAYWARD TYLER
ENGINEERED PRODUCTS
BHARAT HEAVY ELECTRICALS LTD
(BHEL)
Kahalgaon Power Station
SERIAL NUMBERS
EP/03/10757A,B,C,D,E & F
EP/04/10794A,B & C
3 X 500 MW BOILER CIRCULATING PUMPS
5/26/2018 CC Pump Manual-Full (Original)
2/109
FOREWORD
Each section contains an itemised Contents List.
The major illustrations of the Pump and Motor are
included at the rear of Section 7. Additional
illustrations of particular features are incorporated
in the text.
This instruction manual provides comprehensive
installation, operating and maintenance information
of a Hayward Tyler Glandless, Wet Stator, Motor
Pump Unit, referred to in the text as the circulator.
The General Contents list shows that the manual is
divided into eight main sections. Paragraph
references are consecutive throughout each section,
and are preceded by the appropriate section
number. For example 5.1. designates:-
Note! Where a customer boiler layout drawing is
shown, this is used in good faith. However,
Hayward Tyler can accept no responsibility for any
errors or consequences that may result.
Hayward Tyler Manuals are for guidance only and
we reserve the right to update, revise and modify
this manual in accordance with our continuous
research and development programme.
Section 5, Commissioning.
5.1. Pre-Start Check List.
Hayward Tyler Engineered Products Ltd.
1 Kimpton RoadRevised manuals will not automatically be issued,
however, should they be required, Hayward Tylermay be contacted and arrangements can be made.
Luton
BedfordshireENGLAND
LU1 3LD
Telephone: +44 (0) 1582 731144
Email: [email protected]
Fax: +44 (0) 1582 452198
i
5/26/2018 CC Pump Manual-Full (Original)
3/109
GENERAL CONTENTS
BOILER CIRCULATING PUMP INSTRUCTION AND MAINTENANCE MANUAL
SECTION 1 TECHNICAL DATA
SECTION 2 STORAGE
SECTION 3 DESCRIPTION
SECTION 4 INSTALLATION
SECTION 5 COMMISSIONING
SECTION 6 OPERATION
SECTION 7 MAINTENANCE
SECTION 8 STUD TENSIONING
ii
5/26/2018 CC Pump Manual-Full (Original)
4/109
SECTION 1
TECHNICAL DATA
1. 0
CONTENTS
PARAGRAPH PAGE
1.1 GENERAL 1.1
1.2 CHARACTERISTICS 1.1
1.3 MOTOR CHARACTERISTICS 1.2
1.4 CLEARANCES AND SETTINGS 1.2
1.5 HEAT EXCHANGER 1.3
1.6 INSTRUMENTATION 1.3
1.7 TORQUE LOADINGS 1.3
1.8 WEIGHTS (APPROXIMATE) 1.3
ILLUSTRATIONS
FIGURE 1/1 MOTOR ASSEMBLY 1.4
FIGURE 1/2 WINDING RESISTANCE DIAGRAM 1.5
FIGURE 1/3 PUMP PERFORMANCE CURVE 1.6
FIGURE 1/4 MOTOR PERFORMANCE CURVE 1.7
5/26/2018 CC Pump Manual-Full (Original)
5/109
SECTION 1
TECHNICAL DATA
1. 1
1.1 GENERAL
Unit Serial Nos: EP/03/10757 A B C D E F & EP/04/10794 A B
Customer Order No: 0130645 & 0140593
Service: Boiler Water Circulating Pump with
Motor below Pump.
Number Supplied: 9
Electrical: 3300V - 3 Phase - 50Hz
1.2 CHARACTERISTICS
Type: Single Suction - Double Discharge
Size: (2 x 13) x 16 x 19H Volute
Design Pressure: 214 kg/cm2
Design Temperature: 370C
Hydrostatic Test pressure: 321 kg/cm2
Suction Pressure: 197.4 kg/cm2
Specific Gravity at pump suction 0.542
N.P.S.H. required: 15 m (3% head drop)
Quantity Pumped: 3135 m3/hr
Differential Head: 32.37 m
Pump Efficiency: 83 % Cold 83 % Hot
kW Absorbed: 333.1 Cold 180.5 Hot
1.3 MOTOR CHARACTERISTICS
Type: Wet Stator Squirrel Cage Induction
Output: 360 kW
Service Factor: 1.0
Winding Insulation: XLP
Motor Case Design Pressure 214 kg/cm2
Motor Case Design Temperature 368oC
Speed: 1450 RPM.
Hot Duty Cold Test
Motor Efficiency: 89.5 % 89.5 %
kW Input: 201.7 372.2
Power Factor: 74.0 82.5
Overall Efficiency: 74.3 % 74.3 %
Full Load Current: 85 amps
Motor Starting Current: 410 amps
5/26/2018 CC Pump Manual-Full (Original)
6/109
SECTION 1
TECHNICAL DATA
1. 2
1.4 CLEARANCES & SETTINGS (mm)
Initial Maximum
Impeller Wear Ring Clearance : 1.46 1.58 2.03
Journal Bearing Clearance : 0.20 - 0.38 0.55
Reverse Thrust Wear Ring Clearance :
0.42 - 0.52 0.76
Rotor End Float: 0.50 - 0.80 1.50
Impeller Setting (Dimension Z): 572.5 571.5 mm
1.5 INSTRUMENTATION:
Temperature Switches: Ashcroft Model T.461-T20-030-69C-XNH:
20-950C with 6096 mm capillary. 15amp. 125 to 250 Volt AC.
Alarm Setting 60C Trip Setting at 65C
Thermometer:Ashcroft Model 600A-03-C41-B01-A1-L07-BS-
XNG
0-1200C CD1
Pressure Gauge:Ashcroft Model 60-1379SSL-04L-XNH-XNG
0-250 Kg/cm2 CD1.
Flowmeter:KDG Mobrey Series 250 Rotameter
Model 250-50-CX-M12-TO-S6-Z6
Relay Mains supply: 220V 50/60 Hz
Contact Cut Off Capacity: Max 250V/4A/500VA
Thermocouples: Type K Dual Element Ungrounded
1.6 TORQUE LOADINGS:- Refer to Figure 1/1, Schedule of Torque Loadings
1.7 WEIGHTS (Approximate)
Pump Case 3425 kg
Motor Complete 6020 kg
Heat Exchanger 410 kg
5/26/2018 CC Pump Manual-Full (Original)
7/109
SECTION 1
TECHNICAL DATA
1. 3
TOTAL 9855 kg
5/26/2018 CC Pump Manual-Full (Original)
8/109
SECTION 1
TECHNICAL DATA
1. 4
Figure 1/1 Motor Assembly
5/26/2018 CC Pump Manual-Full (Original)
9/109
5/26/2018 CC Pump Manual-Full (Original)
10/109
SECTION 1
TECHNICAL DATA
1. 6
Fi ure 1/3 Pum Performance Curve
5/26/2018 CC Pump Manual-Full (Original)
11/109
5/26/2018 CC Pump Manual-Full (Original)
12/109
SECTION 2
STORAGE
CONTENTS
PARAGRAPH PAGE
2.1 ENVIRONMENT 2.2
2.2 STORAGE - GENERAL 2.2
2.3 INHIBITOR 2.2
2.4 HEAT EXCHANGER 2.2
2.5 EXTERIOR SURFACES 2.2
2.6 STANDARD STORAGE CHECKS FOR STORAGE UP TO 3 YEARS 2.3
2.7 STORAGE PERIODS GREATER THAN 3 YEARS 2.4
2.8 PREPARATION FOR STORAGE AFTER USE 2.4
2.9 INSPECTION RECORD CARDS 2.4
ILLUSTRATIONS
FIGURE 2/1 MOTOR STORAGE / TRANSIT DETAILS 2.1
FIGURE 2/2 PUMP CASE STORAGE DETAILS 2.2
FIGURE 2/3 INHIBITOR FILLING VALVE 2.3
FIGURE 2/4 ROTATING THE ROTOR ASSEMBLY 2.5
FIGURE 2/5 INSPECTION RECORD CARD 2.6
FIGURE 2/6 CHECK LIST 2.7
2.0
5/26/2018 CC Pump Manual-Full (Original)
13/109
SECTION 2
STORAGE
Figure 2/1 Typical Motor Transit/Storage Details
2.1
5/26/2018 CC Pump Manual-Full (Original)
14/109
SECTION 2
STORAGE
2.1 ENVIRONMENT
The storage area must have a hard standing
floor that will be capable of supporting the
weight of the units.
2.2 STORAGE GENERAL
2.2.1 Pump Case (Fig. 2/2)
1) The pump case internal cast areas and all
machined faces must be cleaned and a
suitable removable solvent rust
preventative, with a minimum effective
life of 6 months, applied. Recommendedrust preventatives are, Jenolac J400 or
Shell Ensis Fluid 264, or their
equivalents.
2) All pump case openings must be closed
with covers. These covers to be secured
to the weld preparations with steel
banding and the pump case main flange
with the existing studs and nuts supplied
on the pump flange.
2.2.2 Motors (Fig. 2/1)
1) The motor and transit assembly must be
stored in a vertical position standing on
the motor cover end.
NOTE:
When the terminal box protrudes
below the motor cover stand, rest the
motor cover on balks of timber of
sufficient height to keep the terminal
box clear off the ground (Fig. 2/1)
2) The motor apertures must be blanked off
with flanges secured with studs, bolts andnuts (Fig. 2/1).
3) The motor and transit assembly must be
filled to the top of the transit canister with
inhibitor of the appropriate concentration,
through the filling connector located in
the temporary transit flange, sealing off
the motor heat exchanger bottom outlet.
2.3 INHIBITOR
Inhibitor is to be produced from a pre-mixed
concentration of mono-propylene glycol anddistilled water in a 50/50 solution by volume.
The mono-propylene glycol must contain
corrosion inhibitors and meet BS6580 or
equivalent. A tolerance of 5% on the normal
glycol/water mix may be applied.
The distilled water used must have a
conductivity of less than 10 reciprocal
megohms (microsiemens) per centimetre.
Check the specific gravity of the inhibitor to
ensure the correct concentration.
The specific gravity of the mixture at 20C isas follows:-
Mixture by%Volume Specific Gravity
45% MPG /55% Water 1.036
50% MPG /50% Water 1.038
55% MPG /45% Water 1.040
MPG = Mono-propylene Glycol
2.4 HEAT EXCHANGERFigure 2/2 Pump Case Storage DetailsThe heat exchanger should be stored as
instructed by the manufacturers.
The heat exchanger interconnecting pipe work
and the fill and drain assemblies must also be
filled with the same inhibitor as the motor,
blank flanges being used to seal both ends.
2.5 EXTERIOR SURFACES
All exterior surfaces of the motor must be
maintained in a good painted condition.
Scratched or damaged paintwork must berepainted.
2.2
5/26/2018 CC Pump Manual-Full (Original)
15/109
SECTION 2
STORAGE
CAUTION:
To rotate the assembly in a clockwise
direction may damage the impeller nut
locking screw.
2.6 STANDARD STORAGE CHECKS FOR
STORAGE UP TO 3 YEARS
A visual examination and inspection of the
motor and transit assembly must be made at
least every three months as follows:-
b) If the shaft cannot be rotated or is
very difficult to turn, the motor mustbe stripped down and inspected as
outlined in Section 7.NOTE:
When stored by the contractor, or by an
agency, a record card should be kept of the
intervals between inspections and the results
of the following inspection checks recorded.
8) Check the inhibitor level in the motor and
transit assembly. The level of inhibitor
must not fall below the level of the
impeller. Top up if necessary.
2.6.1 MOTOR9) Check the glycol/water concentration by
measuring the specific gravity of the
inhibitor. The inhibitor is considered
acceptable if it conforms to the
concentration and tolerance given in
paragraph 2.3.
1) The motor is stored vertically resting on
the motor cover - not horizontally.
2) The exterior paintwork is in good
condition. Repaint where necessary.3) All flanges and joints are tightly secured
and no leakage of the inhibitor has taken
place.
10) Replace the transit inspection cover
when the inspection is satisfied.
2.6.1.2 Topping up/Draining Inhibitor (Fig 2/3)4)
1) Remove the access cover plug.a) All studs, bolts and nuts are present
and in sound condition. 2) Attach a hose leading from a pumping
device to the hose tube of the inhibitor
filling valve.b) The phosphate, or any other plating,
applied to these items has not
deteriorated.3) Unscrew the filling valve screw by two
turns. This action opens the valve to allow
the pumped liquid to enter the motor.
5) Measure and record the ambient
temperature of the storage area.
4) When the sufficient inhibitor has been
pumped in, turn screw to close the valve.6) Check and record the insulation resistance
of the stator windings as follows:
a) Remove the terminal box cover. 5) Remove the hose from the inhibitor
filling valve.b) Check the insulation resistance at the
terminal stems using a l000V megger.
Record the result.NOTE:
If the motor is to be drained, allow the
liquid to flow out of the valve hose tube.
Ensure disposal of inhibitor is carried
out in accordance with local
regulations.
IMPORTANT: -
If any insulation resistance value falls below
200 megohms at 20C this, and any previous
readings, with dates, must be reported to
Hayward Tyler for comment.
c) Fit the terminal box cover.
7)
a) Remove the inspection cover from the
top of the transit canister (Fig.2/1).
Fit impeller wrench onto the impeller
nut and rotate the rotating assembly
seven complete revolutions in an anti-
clockwise direction when viewed from
the pump-end.
Fi ure 2/3 Inhibitor Fillin Valve
2.3
5/26/2018 CC Pump Manual-Full (Original)
16/109
SECTION 2
STORAGE
2.6.1.3 Pump Case and Transit Assemblies
2.8 PREPARATION FOR STORAGE
AFTER USE.Inspect the pump assembly and check the
following: -
1) Remove the motor from the pump caseand drain the motor as described in
Section 7.
1) No extensive corrosion has occurred on
the internal pump cast or machined areas.
2) The protective coating is satisfactory.
Re-apply if necessary. 2) Disassemble the motor cover and clean
out any loose material, sediment etc.3) Visually examine the assembly for
damage. 3) Disassemble the motor as described in
Section 7.4) Check that the pump case protective
flanges are correctly fitted and secure. 4) Check all fittings and clearances and
general condition (Section 1). Fit spare
parts as necessary.2.6.2 Stud Tensioning Equipment
After use, the stud tensioning componentsmust be thoroughly cleaned, examined for
damage and a rust preventative lubricant
applied to all surfaces.
5) Reassemble the motor as described inSection 7.
6) Using special wrench provided on the
impeller nut, check that the shaft rotates
freely, approximately seven revolutions in
an anti-clockwisedirection.
The components must be then wrapped in
suitable waterproofed material and stored in
a clean, dry area.7) Check the insulation resistance of the
winding. This should not be below 200
megohms.2.7 STORAGE PERIODS GREATER
THAN THREE YEARS8) Fit the transit canister to the main flange
and stand the motor upright on the motor
cover.
Units that remain in store over three years
require special consideration and HaywardTyler Limited should be consulted for
specialist advice.9) Seal off all apertures with appropriate
transit flanges and gaskets.
Motor assemblies that are stripped must be
reassembled using new gaskets, the details
recorded on the storage record card stating that
it has been stripped and listing any relevant
findings.
10) Fill the motor with a pre-mixed
concentration of inhibitor, in accordance
with paragraph 3, through the filling
connection in the transit flange, sealing
the motor heat exchanger bottom outlet.
CAUTION: 11) Fit the transit canister inspection cover.Precautions must be taken prior to use that
the unit is pressure tight. 12) Re-check the insulation resistance of the
motor windings.
13) Check that the storage conforms to Para
2.2.
2.9 INSPECTION RECORD CARD
(Fig. 2/5 and Fig 2/6)
A typical inspection record card and check list
is given on the following pages.
2.4
5/26/2018 CC Pump Manual-Full (Original)
17/109
SECTION 2
STORAGE
Fi ure 2/4 Rotatin the Rotor Assembl
2.5
5/26/2018 CC Pump Manual-Full (Original)
18/109
SECTION 2
STORAGE
Fi ure 2/5 Ins ection Record Card
2.6
5/26/2018 CC Pump Manual-Full (Original)
19/109
SECTION 2
STORAGE
2.7
Fi ure 2/6 Check List
5/26/2018 CC Pump Manual-Full (Original)
20/109
5/26/2018 CC Pump Manual-Full (Original)
21/109
SECTION 3
DESCRIPTION
3.1 GENERAL 3.2 PUMP
The Hayward Tyler Glandless Motor
Circulator Pump is designed for recirculating
boiler water through the boiler water systems
of fossil fuel or liquid cooled nuclear reactorpower stations and similar applications.
The pump comprises a single suction and
double discharge branch casing, welded into
the boiler system pipe work at the suction and
discharge branches with the suction branchuppermost.
The circulators consist of a single stage
centrifugal pump and a wet stator induction
motor, which are mounted within a common
pressure vessel. The vessel consists of three
main parts, a pump casing, motor housing and
motor cover.
Within the pump cavity rotates a key driven,
mixed flow type impeller, mounted on the end
of the extended motor shaft. 'Renewable wear
rings are fitted to both the impeller and pump
case. The impeller wear ring is the harder
component to prevent galling
The motor is suspended beneath the pump
casing and is filled with cold boiler water at
full system pressure. No seal exists between
the pump and motor, but provision is made to
thermally isolate the pump from the motor in
the following respect: -
3.3 MOTOR
The motor is a squirrel cage, wet stator,
induction motor, the stator wound with aspecial water tight insulated cable. The phase
joints and lead connections are also moulded in
an insulated material. The motor is joined to
the pump casing by a pressure tight flange joint
and a motor cover completes the pressure tight
shell.
1) Thermal Conduction. Because the pump
temperature is so high, usually above 340C
and the motor temperature is limited to
about 55C, a simple restriction, in the form
of a 'neck', is provided to minimise heat
conduction. The motor shell contains all the moving parts,
except for the impeller. Below the impeller is
situated an integral heat baffle which reduces
the heat flow, a combination of convection and
conduction, down the unit. A baffle wear ring-
cum-sleeve above the baffle forms a labyrinthwith the underside of the impeller to limit
sediment penetration into the motor. Should
foreign matter manage to pass the labyrinth
device into the motor enclosure, a filter located
at the base of the cover end bearing housing
strains it out.
2) Hot Water Diffusion. To minimise
diffusion of boiler water, a narrow annulus
surrounds the rotor shaft, between the hot
and cold regions. A baffle ring restrictssolids entering the annulus.
3) Motor Cooling. The motor cavity is
maintained at a low temperature by a heat
exchanger in a closed loop water circulation
system, thus extracting the heat conducted
from the pump.
The motor design is such that for ease of
maintenance, the stator shell, complete with the
stator pack, the rotor shaft, the journal bearing
housings and the thrust assembly, can be
withdrawn from the motor case in sequence.
Lifting lugs are supplied to secure hoists whenraising and lowering the motor.
In addition, this water circulates through the
stator and bearings, extracting the heat
generated in the windings and providing
bearing lubrication. An internal filter is
incorporated in the circulating system.
4) In emergency conditions, if low pressure
coolant to the heat exchanger fails, or is
inadequate to cope with heat flow from the
pump case, a cold purge can be applied to
the bottom of the motor to limit the
temperature rise.
NOTE:
A high pressure cold purge is to be used
only as an emergency. (para 6.3.8)
3.1
5/26/2018 CC Pump Manual-Full (Original)
22/109
SECTION 3
DESCRIPTION
Figure 3/1 Auxiliary Cooling Circuit
3.2
5/26/2018 CC Pump Manual-Full (Original)
23/109
SECTION 3
DESCRIPTION
3.3.1 Auxiliary Cooling Circuit (Fig. 3/1)
3.3.3 Internal FilterThe motor is provided with its own auxiliary
closed circuit, which besides cooling the motor
lubricates the bearings. The water is
continuously circulated through the bearings,
motor windings and an external heat exchanger(cooler), by an auxiliary impeller at the thrust
bearing end of the motor shaft.
A stainless steel woven wire strainer, fitted at the
base of the reverse thrust seat, filters the liquid in
the motor before it is circulated through the
bearings after passing through the heat exchanger
(cooler).
The filter should be cleaned at normal
maintenance periods, removing any accumulation
of foreign matter in the motor cover.
When the motor is stationary, thermosyphon
circulation takes place to remove conducted heat
from the pump end of the motor.
3.3.4 Main Flange Joints3.3.2 Bearings
The pressure joints at the pump and motor cover
flanges employ spiral edge wound gaskets,
specially designed for very high pressure and
temperature. The main pump/motor flange
gasket is housed in stainless steel overlay,
recessed into the joint face.
The motor rotor shaft is supported by water
lubricated tilting pad type radial and thrust
bearings mounted on the stator shell, thus making
the motor internals into a separate construction
independent of the motor pressure vessel.
3.3.2.1 Journal BearingsThe studs and nuts securing the flanges are made
from special high tensile steel and, because
torque tightening these nuts is inadequate, the
studs are hydraulically stretched and the nuts
tightened down by hand. When the hydraulic
tension in the stud is released, the load is
transferred to the nut giving the required
tightness.
The journal bearings of the circulator are
the water lubricated Michell type located at
the ends of the motor shaft, i.e. pump-end
and cover-end. Each bearing comprises a
hardened steel sleeve on the shaft running
in six radially located tilting pads whose
bearing surfaces are lined with a composite
material. The bearing surfaces must never
be allowed to operate in a dry condition.Stud tensioning equipment is supplied with each
circulator order.
3.3.2.2 Thrust Bearing 3.3.5 Terminal GlandA main thrust bearing is situated below the
cover-end journal bearing and takes the full
hydraulic thrust of the pump. This bearing,
also of the Michell water lubricated type, is
formed by a steel thrust disc, with a
composite bearing surface, on the bottom of
the rotor shaft running on stationary
hardened steel tilting pads.
The electrical supply to the motor is taken
through special high pressure single lead cable
terminal glands of the high temperature, safety
type.
The seal is effected by a terminal gland
moulding, together with o-rings located between
an insulating sleeve and an inner casing, and
between the inner casing and the motor case.
The addition of a cone-shaped collar within the
terminal moulding, plus the design of the inner
casing, prevents any possibility of a glandblowout at high temperatures. However, if the
motor is subjected to sustained overheating, a
slight leakage may occur into the terminal box.
The thrust disc is also designed to operate
as an auxiliary impeller to circulate the
internal water content of the motor.
3.3.2.3 Reverse Thrust Bearing
The weight of the rotating assembly, as well
as the down thrust imposed at start-up and
shut-down, are taken by a reverse thrust
bearing located on a reverse thrust housing
which forms the bottom of the cover
housing cylinder.
The reverse thrust housing also includes a
composites reverse thrust wear ring and is
the mounting for the internal filter.
3.3
5/26/2018 CC Pump Manual-Full (Original)
24/109
SECTION 3
DESCRIPTION
Fi ure 3/2 Terminal Gland
3.4
5/26/2018 CC Pump Manual-Full (Original)
25/109
SECTION 3
DESCRIPTION
3.4 TERMINAL BOX
Robust fabricated steel terminal boxes are
provided on the side of the motor casing for
connecting the power supply to the motor.
Each phase supply cable for the motor enters a
box at its base and should be sealed by a cable
gland. Each phase notation is identified by a
colour coding, Red, Yellow or Blue.
Bursting discs are fitted to the wall of the
terminal boxes to relieve excessive pressure
build up within the box should a flash over
occur at the terminals.
Desiccators are fitted to absorb atmospheric
moisture that may decrease the electrical
resistance to ground. Each assembly is
completely enclosed by a bolted on cover.
3.5 HEAT EXCHANGER
A heat exchanger (cooler) must be fitted to
dissipate the heat generated by the motor and
the heat transferred from the pump casing.
High pressure outlet and inlet raised facings are
situated at the bottom and top of the motor case
respectively for connection to high pressure
heat exchanger / motor case stub pipes.
Interconnecting pipework must be short and
direct with the heat exchanger mounted as high
as possible to promote good thermosyphon
circulation when the unit is on hot standby.
3.6 ALARM SYSTEMS
3.6.1 Thermometer
The thermometer instrument is mounted adjacent
to the motor, and gives visual indication of the
motor temperature.
3.6.2 Temperature Switches
Two temperature switches, remotely mounted,
are provided for actuating the alarm. When a
pre-set temperature is reached, the alarm circuit
is energised via one of the switches. Should the
motor temperature continue to rise, the second
switch is activated to de-energise the motor.
3.6.3 Thermocouples
A thermocouple is provided for measuring motor
cavity temperature. Two thermocouples are also
supplied with weld on pads for measuring the
skin temperature of the pump case and suction
manifold. These are to be installed on site by the
user.
3.6.4 Instrument Pockets
Temperature switch, thermometer and
thermocouple pockets are provided where
required.
3.6.5 Differential Pressure Transmitter with
manifold
These are to be connected to the process
connections in the pump case by the user.
(Customer supply)
3.6.6 Pressure Gauge
A pressure gauge is remotely mounted to the
motor case.
3.6.7 Flow Meter
A flow meter is supplied to be fitted in the low
pressure cooling water return line by the user.
3.6.8 Ground Detection Relays
The motor windings should be protected by
ground detection relays, sufficiently sensitive to
detect the development of a pinhole or minor
crack in the stator winding insulation.
3.5
5/26/2018 CC Pump Manual-Full (Original)
26/109
SECTION 4
INSTALLATION
CONTENTS
PARAGRAPH PAGE
4.1 GENERAL 4.2
4.2 PUMP CASE INSTALLATION 4.2
4.3 PREPARATION FOR MOTOR INSTALLATION 4.2
4.4 MOTOR INSTALLATION 4.4
4.5 FITTING THE HEAT EXCHANGER 4.5
4.6 FILLING THE CIRCULATOR WITH BOILER COLD 4.6
4.7 HYDROTESTING BOILER WITH CIRCULATOR INSTALLED 4.6
4.8 ELECTRICAL CONNECTIONS 4.8
4.9 MOTOR PROTECTION 4.9
ILLUSTRATIONS
FIGURE 4/1 PUMP CASE INSTALLATION 4.1
FIGURE 4/2 MOTOR INSTALLATION 4.3
FIGURE 4/3 TERMINAL BOX 4.7
FIGURE 4/4 BURSTING DISC ASSEMBLY 4.8
FIGURE 4/5 EARTH LEAKAGE PROTECTION CIRCUIT DIAGRAM 4.10
4.0
5/26/2018 CC Pump Manual-Full (Original)
27/109
SECTION 4
INSTALLATION
Fi ure 4/1 Pum Case Installation
4.1
5/26/2018 CC Pump Manual-Full (Original)
28/109
SECTION 4
INSTALLATION
3) The cables, leading to the motor, should be
flexible and looped immediately prior to
entering the terminal boxes. The looping
should be sufficient to accommodate unit
movement caused by expansion and
contraction of the boiler pipe work.
4.1 GENERAL
WARNING
The Hayward Tyler boiler circulating pump is
a precision piece of heavy machinery.
It should only be installed under the
supervision of a qualified professional engineer
who should ensure that the staff directly
concerned are adequately trained and have
read and understood this manual.
4.2 PUMP CASE INSTALLATION (FIG 4/1)
1) Remove the pump case flange and branch
covers and clean the pump branches.
When installing the circulators the following
conditions MUST be observed.2) Attach shackles and slings to the casing
eyebolts. A plate on the pump case
indicates the front of the pump.1) The system pipe work should be adequately
supported to accept the weight of the
circulator.3) Raise the case to meet the system pipe
work, with the suction branch uppermost.
2) When mounted, the pump should
accommodate movement in the pipe work
due to thermal expansion without imposingexcessive loads on the casing and branches.
4) Ensure that the main motor/case flange is
horizontal to within 1. Tack weld to thesystem pipe work and re-check the
horizontal limits.
3) Sufficient clearance should be allowed
beneath the motor to permit lowering of the
motor from the pump case for maintenance.
(See Section 7 Fig. 7/35.). If removable
floors or girders etc. are fitted after the
motor is installed, ensure that the terminal
boxes or low pressure cooling water supply
lines will not foul them when the boiler is on
load and the circulator moves downwards
due to thermal expansion.
5) Complete the weld to the procedure
approved by the boiler manufacturer and test
radiographically for flaws.
6) On completion of a satisfactory
radiographic test, fit any pressure
differential transmitters using the stub pipes
on the pump case branches.
7) Fit the blanking off plate until the motor is
installed.NOTE:
Two long lift hoists should be used to
raise the pump or motor, each hoist being
capable of taking the full weight of the
pump or motor
4.3 PREPARATION FOR MOTOR
INSTALLATION
CAUTION:
The motor should be stored, topped-up with
inhibitor for as long as possible. If it is
necessary to install the motor before boiler
water is available, install in the inhibited
condition to provide additional protection for
the motor internal components. However,
the inhibitor must then be drained
immediately before mounting the heat
exchanger.
4) The pump should be positioned so that the
N.P.S.H. available exceeds the N.P.S.H.
specified in the Technical Data - Section 1).
NOTE:
When operating at temperature, sub
cooling of the inlet water is normally
present and this gives a considerableincrease in the N.P.S.H. available. The
worst condition is normally operating
cold. We do not recommend motor installation on
a Hot Boiler.4.1.2 Installation Notes
1) Hose down internally, the pump case, the
valves and adjacent-piping, to ensure the
removal of all loose debris.
The following conditions must be observed
when installing the circulator:
1) Ensure that the main system is free from
solids before mounting the circulators.2) Fully close the pump suction and discharge
valves.2) Permanent insulation should be applied
only to the pump case. No insulatingmaterial must be applied to the motor case
or to the main flange studs and nuts, as this
will cause the motor to overheat.
4.2
5/26/2018 CC Pump Manual-Full (Original)
29/109
SECTION 4
INSTALLATION
Fi ure 4/2 Motor Installation
4.3
5/26/2018 CC Pump Manual-Full (Original)
30/109
5/26/2018 CC Pump Manual-Full (Original)
31/109
SECTION 4
INSTALLATION
c) If, after fitting of the heat exchanger,
running the motor is reasonably
imminent, and sub-freezing
temperatures are not envisaged, the
motor and heat exchanger must be filled
with treated boiler water or condensate
within 3 hours of fitting.
f) Check the gaps every 10 mm, or less,
during the last 100 mm of the motor
raising sequence to ensure that the motor
does not 'cock' or rotate as it is raised.
Adjust the gap as necessary.
g) Continue raising the motor until an
increase in the effort required on thehoists indicates that the gasket is in
contact with the pump case face. At this
stage, the gap between the flange faces
should be approximately 2.5mm and
should be equal all round the flange.
4.5 FITTING THE HEAT EXCHANGER
(CUSTOMER SUPPLY)
1) Remove the blank flanges from the motor
high pressure outlet to cooler and fill and
drain connection.CAUTION:
If the gap is unequal, the gasket may
have come out of its recess. If the gap
is unequal, lower the motor
sufficiently to check the condition of
the gasket. If the gasket is damaged -
renew. Never use any substance onthe gasket to make it adhere to its
recess.
2) Ensure that the motor, the heat exchanger
and the high pressure pipe work and high
pressure purge lines, have been flushed free
from all obstructions and foreign matter.
3) Flush out the secondary cooling watersystem until clear water is discharged.
4) Mount the heat exchanger onto the motor
case brackets and proceed.h) Coat the stud threads with high
temperature anti-seize compound or
silicon grease and install the nuts by
hand.
a) Bring the heat exchanger parallel to the
motor supporting the weight with the
lifting tackle.NOTE:
b) Clamp the heat exchanger to the motor
by tightening up the securing bolts, nuts
and washers.
Do not coat the exposed extended
diameter threads of the studs as these
threads are for the tensioner
application. c) Ensure the motor / heat exchanger
interconnecting pipe work assembly is
correct for the circulator.i) Tighten the nuts, using the hydraulic studtensioner in accordance with the
instructions in Section 8. Remove the
lifting tackle and removable lifting lugs.
d) Offer up the interconnecting pipe work
to the heat exchanger and motor flanges
and complete all pipe welds and NDE in
accordance with site approved
procedures.
j) Thoroughly flush out the fill and drain
system piping, to the motor cover and
when satisfied that the piping is clean,
connect to the motor cover. 5) Install gauges and recorders for temperature
and pressure. Connect the low pressure
cooling systems to the heat exchanger.k) Install the heat exchanger: see Para. 4.5
l) Install the appropriate thermocouples,
the thermometer, pressure guage and
temperature alarm switches.
6) Fit temporary strainers to the low pressure
cooling systems, and then check that
circulation meets the heat exchangerspecification.
m) Connect the power supply cables to the
motor terminals, See 4.8.
7) Close the shut off valve in the high pressure
fill and purge line and blow down piping.n) Install the vibration pick up probes if
permanent vibration monitoring is
required.The motor and heat exchanger circuit must
now be refilled with inhibitor (See 4.4, Para.
13 (a) or (b) or with treated boiler water or
condensate.
13)
a) If, after fitting the heat exchanger,
running is not reasonably imminent, the
motor and heat exchanger circuit must
be refilled immediately with inhibitor.
b) If, after fitting the heat exchanger, sub-
freezing temperatures are envisaged themotor and heat exchanger circuit must
be refilled immediately with inhibitor.
4.5
5/26/2018 CC Pump Manual-Full (Original)
32/109
SECTION 4
INSTALLATION
5) After connecting the supply, open the heat
exchanger vent on the high pressure side, fill
the motor from the bottom and vent air from
the top, until clean air free water is
discharged from the vents.
4.6 FILLING THE CIRCULATOR WITH
BOILER COLD
Filling the circulator correctly is a prerequisite to
ensure satisfactory operation. If air is present in
the motor it could affect bearing lubrication and
precipitate bearing failure.
6) Close the vent on the high pressure side of
the heat exchanger.
7) Continue to fill the motor and vent any air
via the vent connections in the boiler system
pipe work.
If air pockets are present in the stator this would
affect dissipation of heat generated in the
windings, creating hot spots and consequent
degrading of the insulating material, and
ultimately cause winding failure.8) Isolate the now filled circulator.
9) Ensure that the terminal box is dry and with
the unit full of water below 20C or at
normal ambient temperature, using a 1,000
Volt Megger, check winding resistance to
ground at the terminals. The resistance
should exceed 200 megohms.
Due to the complexity of the passages in the
motor through which water must flow to displace
all air, it is necessary to fill the motor very slowly.
If air pockets are present in the stator this would
affect dissipation of heat generated in the
windings, creating hot spots and consequentdegrading of the insulating material, and
ultimately cause winding failure.
IF NOT, CALL HAYWARD TYLER.
DO NOT ATTEMPT TO RUN THE
MOTOR.The maximum filling rate is 2 litres /min.
The motor must NOT be filled via the pump
casing, but only through the filling connector
located at the motor cover.
4.7 HYDROTESTING BOILER WITH
CIRCULATOR INSTALLED
Treated Water or Condensate Available: -1) Isolate the circulator from the boiler by
closing appropriate discharge valves. Should the customer wish to hydrotest the
circulator, the hydrostatic test pressure must not
exceed the maximum specified in Section 1.2) Supply the low pressure side of the heat
exchanger as follows: -
Treated Water Not Available: -a) Open the supply valves in the low
pressure cooling water system. If the boiler is to be hydrotested at an early state
of construction, the pump casing can be pressure
tested without the motor once the blank off plate
is installed refer to para.4.2.
b) Flush out the piping for the supply of
low pressure treated boiler water, or
condensate, for filling the motor, until
clean air free water is discharged.4.7.1 Post Hydrostatic Test Procedure
NOTE:1) Boiler circulators are not to be drained, but
left filled to a level above the suction
downcomer.
The flushing must always be carried out
before introducing any water through the
lines to the motor and heat exchanger.
2) Freezing can be avoided by filling with
glycol in the concentration detailed inSection 2.
3) If the low pressure supply contains an
orifice, check that it is clean and that its flowrate is correct.
4) Adjust the flow rate to approximately 2
litres/min.
4.6
5/26/2018 CC Pump Manual-Full (Original)
33/109
SECTION 4
INSTALLATION
Fi ure 4/3 Terminal Box
4.7
5/26/2018 CC Pump Manual-Full (Original)
34/109
SECTION 4
INSTALLATION
4.8 ELECTRICAL CONNECTIONS
4.8.1 Power Supply to Motor
Refer to the terminal box arrangement shown in
Fig. 4/3.
WARNING:
Disconnect the power supply and the starter
before commencing any work.
CAUTION:
Ensure that the cable length will
accommodate expansion and removal of the
circulator.
Ensure that the voltage connected to the
circulator is the correct operating voltage as
stamped on the motor nameplate situated on
the bottom of the motor case.
1) Remove the nuts and washers, and thenremove the terminal box cover using lifting
gear, if necessary.
2) Feed the cable through the conduit entry
gland and connect to the terminals in the
phase rotation RED, YELLOW, BLUE (U,
V or W). When so connected the unit
will operate in the designed direction, i.e.
clockwise when viewed from above. All
connecting cables and links are marked with
appropriate phase colours.
3) Earth the circulator adequately. Earthing
studs are provided on the motor casingadjacent to the terminal box.
4) Ensure that all electrical connections
particularly at the terminal box entry gland
are secure.
5) Fit the bursting discs to the terminal box as
follows: -
NOTE:
The bursting discs are supplied as loose
items and are packed separately to
prevent damage in transit. They are
fitted to the terminal box on theinstallation of the motor.
a) Dismantle the bursting disc assembly
and discard the cardboard sheet fitted in
lieu of the disc.
b) Reassemble the bursting disc assembly
with the bursting disc in place, as
depicted in Fig. 4/4.
6) Fit the desiccators, also supplied as loose
equipment, as follows:-
a) Check that the desiccator crystals are
coloured blue.b) If pink, reactivate by placing the
desiccator in a well ventilated oven
where it should be maintained at a
temperature of 110oC until the colour
reverts to blue. The re-activating time is
between 1 and 2 hours.
c) Screw the desiccators into the terminal
box covers taking precautions not to
damage the desiccators.
7) Fit and secure the terminal box covers using
the nuts and washers previously removed.
Fi ure 4/4 Burstin Disc Assembl
4.8.2 Recommended Instrumentation
It is recommended that the following be
provided: -
1) Pump suction and discharge pressure
gauges.
2) Continuous record of motor voltage.
3) Continuous record of motor current.
4) Ground leakage relay to warn of very low
winding resistance in order to prevent
winding insulation failure.
5) Indication and record of downcomertemperature and pump case temperature.
This is required to avoid thermal shocks
when starting a pump on a hot boiler.
4.8
5/26/2018 CC Pump Manual-Full (Original)
35/109
SECTION 4
INSTALLATION
4.8.3 Alarm Circuits (Fig.4/5)
4.9.3 Starting Period ProtectionWARNING:Lethal voltage is present in the alarm system
when the motor is inoperative. To make the
circulator safe - open the isolator.
If the motor fails to start, trip out after a period
of approximately 5 seconds. The starting
current is based on a locked rotor test with an
allowance made for saturation of the magneticcircuit.
Suitable alarm and trip devices should be fittedto protect the motor and arranged to provide: -
Motor Starting Current: See Technical Data,
Section 1.
1) An alarm - as an indication of motor
overheat conditions.
4.9.4 Earth Leakage Protection (Fig. 4/5)2) Motor trip (shut down) - if the temperaturerise continues above the alarm setting.
Ground detection relays are recommended,
sufficiently sensitive to sound an alarm if a pin-
hole or minor crack should develop in the stator
winding. This protection is arranged in either of
the ways shown in Scheme A, Scheme B or
Scheme C.
The normally advised settings for the protection
devices are: 57C for alarm and 60C for trip. In
practice, the alarm setting should be reduced to
5C above normal motor operating temperature.
If the neutral point of the supply transformer is
grounded, a current transformer (CT) is inserted
into the ground lead, and a relay connected
across the current transformer secondary, see
Scheme A.
4.9 MOTOR PROTECTION
The following protective devices must be
provided for the motor: -
4.9.1 Continuous Overload Protection
Experience indicates that in the event of a fine
crack in the stator winding, the resistance to
ground drops to between 20,000 and 30,000
ohms. The relay should not trip the motors but
initiate an alarm.
The overload trip setting should be 10% above
the maximum current requirements which could
occur with the pump running on cold water at
some other point than the specified duty,
assuming nominal specified supply voltage. If
voltage variation can occur, then the trip setting
should be increased to 15% above maximum
current value.
If the neutral point of the supply transformer is
not grounded, three potential transformers (PT)are connected to the motor leads, with the
secondaries connected in an open delta, closed
by the relay winding, see Scheme B. The relay
should not trip the motors but initiate an alarm.
NOTE
Overload relays are now typically calibrated
in motor full load current (FLC) where the
relay trips with a current 10% above the
FLC setting point. Hence the overload relay
of this type should have a setting point of the
cold duty current.
Scheme C shows a core balance earth leakage
relay system where a core balance current
transformer encloses supply lines L1, L2 & L3
supplying the motor.
Maximum current at nominal voltage: NOTE
It is important that no earth conductor is
allowed to be enclosed by the current
transformer. The earth leakage sensitivityand trip time can generally be selected to
prevent nuisance tripping. Typical setting
points are 300 mA and 1 second. This may
require adjustment depending on supply
conditions.
See Technical Data, Section 1.
4.9.2 Instantaneous Trip Setting
To allow for transients during the first cycles of
the starting period, the instantaneous trip should
be set at 12 times the motor full load current.
Full Load current: See Technical Data, Section
1.
4.9
5/26/2018 CC Pump Manual-Full (Original)
36/109
SECTION 4
INSTALLATION
4.10
Figure 4/5 Earth Leakage Protection Circuit Diagram
5/26/2018 CC Pump Manual-Full (Original)
37/109
SECTION 5
COMMISSIONING
CONTENTS
PARAGRAP
HPAGE
5.1 PRE-START CHECK LIST 5.1
5.2 INITIAL STARTING-COLD BOILER CONDITION 5.1
5.3 STOPPING 5.3
5. 0
5/26/2018 CC Pump Manual-Full (Original)
38/109
SECTION 5
COMMISSIONING
5.1 PRE-START CHECK When a boiler is started from cold, a minimumof two circulators must be operated. It is
normal practice to simultaneously warm the
standby circulators to permit immediate staring
when required.
The following pre-start checks must be
satisfied before starting the motor.
1) Ensure that the circulator is completely
vented. CAUTION:
1. Motors must not be energised if the
motor cavity temperature is below 2C.
2) Ensure that the low pressure cooling
water valves are open and the cooling
water flow rate agrees with that specified
in the heat exchanger manufacturer's
specification. All other valves must be
closed.
2. There should be at least ten-minute
intervals between two repetitive starts.
This must never be exceeded;
otherwise the motor winding
temperature will rise and could
damage the winding insulation.NOTE:
If the circulator is to be started on hot
standby, the pump delivery by-pass
valves must be open. Refer to the hot
standby procedure in Section 6.
3. The motor may be damaged if motor
temperature exceeds 65C.
1) Ensure that the motor has been vented asdetailed in Section 4, Para. 4.7.3) Ensure that the high pressure cold water
purge at 20C maximum temperature is
connected but isolated. 2) Ensure that a flow of approximately 2
litres/min., is entering into the motor
through the low pressure fill line.4) Using a 1000V megger, check that the
insulation resistance to ground of the
motor leads conforms to the Winding
Resistance curve shown in Section 1,
Fig. 1/2 when measured at the terminal
stems with the unit full of water below
approximately 20C, if possible, or at
normal local ambient temperature.
3) Ensure that the pre-start checklist, as
described in Para. 5.1, has been satisfied.
4)
a) Release any air trapped below the
discharge valves by opening valves.
b) When air-free water is discharged to
atmosphere, close valves.5) Check that the correct voltage isconnected to the circulator.
5)6) Check that the electrical supply is
available at the point of control selected
and that the starting equipment is
functioning correctly.
a) Vent the pump by opening vent
valves.
b) When air-free water is discharged
from vent valve to atmosphere, close
valves.7) Test the operation of all instrumentation
and alarms.6) Make sure that the boiler is full and open
the discharge valves.8) Ensure that sufficient N.P.S.H. is
available for the pump to run without
cavitation. NOTE:
The by-pass valve should never befully closed. It is normally throttled to
provide a minimal flow between the
pump suction and discharge system
9) Start parallel operating boiler circulating
pumps with the stems of the discharge
valves withdrawn to prevent overheating
of the boiler water in the pump case.7) Switch on power to the starter.
5.2 INITIAL STARTING-COLD BOILER
CONDITION8) Press the starter button on the control
console and energise the motor for 5
seconds only.In systems where the circulators are arranged
in parallel, to avoid cavitation, sufficient
circulators must be operated to limit the
capacity per pump to a value where the
N.P.S.H. required is less than the amount of
N.P.S.H. available.
5. 1
5/26/2018 CC Pump Manual-Full (Original)
39/109
SECTION 5
COMMISSIONING
5. 2
CAUTION:
The motor runs up to full R.P.M. in
appropriately one second. If the
motor fails to start after five seconds,
press the stop button and do not
attempt to restart the circulator for 20minutes.
9) After ten minutes pause, run the
circulator for a further (2nd) five
seconds. During this run, check the
following:-
a) Motor Current (after ammeter has
come off initial surge of current)
b) Differential pressure - when the
check valves open, the differential
pressure should rise immediately to
approximately 3 bars.
NOTE:
If the differential pressure does not
rise, stop the motor immediately; it
may be an indication that the motor is
running in reverse. Reverse rotation
will result in approximately 30% less
head generated and about 10% more
power absorbed than specified.
10) After a further (3rd) ten-minute pause,
repeat operation (9).
11) After another (4th) ten-minute pause,
energise the motor and run for twentyminutes. During this running period,
carry out the following checks:-
a) Check the motor for vibration, using
a vibration detector, several times and
record reading for future comparison.
b) Check for rubbing or excess bearing
noise by holding a listening rod
against the pump and motor case.
c) Check the motor operating
temperature at regular intervals.
Initially it should rise several degrees
then stabilise. If necessary, adjust thesecondary cooling water flow after
checking that the strainers are not
obstructed.
d) Check, as the motor warms, that the
high pressure circulation pipe entering
the heat exchanger from the top of the
motor becomes warmer than the high
pressure circulation pipe from the
bottom of the heat exchanger to the
motor case. This indicates correct
functioning of the heat exchanger.
e) Check that motor current anddifferential pressure readings several
times and record the readings.
12) When the motor temperature has
stabilised: -
a) Adjust the high temperature alarm
setting to 10% above this point, or to
57C, whichever is the lower. Thetrip setting must never exceed 60C.
b) Make adjustment to other
instrumentation as necessary.
c) Check all flanges, glands and valves
for leaks.
d) As the boiler water temperature
increase, its specific gravity decreases
and the amount of N.P.S.H., available
increases. The temperature of the
high pressure water to the heat
exchanger may alter due to lower
losses in the motor, or because ofincreased heat flow from the pump.
NOTE:
It is normal procedure to commission
circulators separately, but if required,
before the last circulator is stopped,
the others may be energised and their
recordings taken after each one is
brought on-line.
5.3 STOPPING
1) Press the stop button on the control
console. The run-down time isapproximately 2.5 seconds.
2) Close the discharge valves.
3) Maintain the low pressure cooling water
supply to the heat exchanger.
NOTE 1:
If the circulator is to stand idle for
some considerable time with the boiler
cold, the low pressure cooling water to
the heat exchanger may be turned off,
especially on systems where the
cooling water runs to waste.
NOTE 2:
On hot boilers, and whenever the
circulator is run, the low pressure
cooling water to the heat exchanger
must always be on.
CAUTION:
If the circulator is to be idle for an
extended period, and be subjected to
freezing temperatures, make sure that
provision is made to protect the
motors from freezing (see Section2.2.2.)
5/26/2018 CC Pump Manual-Full (Original)
40/109
SECTION 6
OPERATION
CONTENTS
PARAGRAP
HPAGE
6.1 STARTING THE CIRCULATOR 6.1
6.2 SHUTTING DOWN THE CIRCULATOR 6.2
6.3 ROUTINE CHECKS AND OPERATIONAL CONDITIONS 6.3
6.4 FAULT FINDING 6.5
ILLUSTRATIONS
Figure 6/1 FAULT LIST CHART 6.6
6.0
5/26/2018 CC Pump Manual-Full (Original)
41/109
SECTION 6
OPERATION
Any of the following conditions may exist
when putting a circulator into service. Follow
the relevant procedures below and refer to 6.3
for routine checks and operational fault action.
6) Ensuring the boiler is still full, energise
the second duty circulator on line and run
up to speed.
7) Perform the operational checks below.
Refer also to Para. 6.3.
6.1 STARTING THE CIRCULATOR a) Amperage.
b) Motor cavity temperature on alarm
thermometer.6.1.1 Boiler Cold - Circulator Cold and
Filled (Boiler Start-Up).c) Differential pressure.
1) Ensure that the pre-start checklist, 5.1 is
satisfied. d) Low pressure cooling flow and
temperature.2) Vent the motor as follows: -
e) Vibration.a) Release any air trapped below the
suction by opening the by-pass valves
and the filling valves.
f) Drum level.
g) Valve and gland leakage.
8) Energising other motors: When the
boiler differential pressure parametersrequire the other circulators to be
energised: -
b) When air-free water is discharged
through the vent valve, close ventvalve.
3) Vent the pump as follows: -a) Check that the differential
temperature, between the pump case
and boiler water in the downcomers,
is within 28C.
a) Open the vent valve.
b) When air-free water is discharged
from vent valve, close vent valve and
filling valves.b) Energise the other motors.
c) Open the stems of the discharge
valves.c) Close by-pass valves on the newly
energised pump(s).
CAUTION: d) Perform the operation checks on the
newly energised pump as detailed in
para.6.1.1 (7).
The pump must always be re-vented in
this manner prior to starting when thedrum pressure is below 3.5 kg/cm
2.
6.1.2 Boiler Hot - Circulator Hot and
Filled (Hot Standby)NOTE:The motor starting procedure following
is based on a normal boiler starting
procedure where usually two circulators
are initially operated with the remainder
brought-on line as required.
NOTE:
The low-pressure coolant to the heat
exchanger must be on.
1) Check the differential temperature
between the pump case and the boiler
water in the downcomers.4)
a) On circulators that will not be
energised, open the pump discharge
by-pass valves. This ensures that asthe boiler heats up, a flow passes
from the discharge legs to the pump
case and impeller etc.
CAUTION:
The differential temperature between thepump case and the boiler water in the
downcomers must not exceed 28C. Non-
adherence to this may cause thermal
shocks and damage to occur.b) Check the motor temperature on the
alarm thermometer; this should not
exceed 49C or be less than 5C.2) Energise the motor.
3) Close by-pass valves.5) Energise the first motor. The current will
drop from full starting current after a few
seconds to approximately the value
corresponding to the operating point on
the makers test curve.
4) Check circulator operation as detailed in
para.6.1.1 (7).
6.1
5/26/2018 CC Pump Manual-Full (Original)
42/109
SECTION 6
OPERATION
6.1.3 Installation on a Hot Boiler 6) Check the pump case temperature as thepump case is cooling to ensure that the
cooling rate does not exceed 120C per
hour. If necessary, correct the cooling rate
as follows:
NOTE:
Not recommended for safety reasons but
not possible on this installation since no
suction valves are fitted and hence pumps
cannot be isolated. a) Cooling rate too fast: - If the pumpcase cooling rate is too fast, slow the
cooling rate by partially opening the
by-pass valves as necessary.6.2 SHUTTING DOWN THE
CIRCULATOR b) Cooling rate too slow: - If the pumpcase cooling rate is too slow, increase
the rate by injecting a high pressure
purge as detailed in Para. 6.3.8.
CAUTION
Low pressure cooling water flow and motor
temperatures must always be within the
specified limits, whenever the circulator is
on hot standby.7) When the pump case has cooled to 45C
de-pressurise the circulator as follows: -
a) Ensure the pump discharge by-pass
valves and shut-off valve are closed.6.2.1 Boiler Hot - Circulator to go on Hot
Standbyb) Slowly depressurise the circulator by
closing the pump suction by-pass
valve and partially opening the pump
and suction leg vent valve.
1) Press the stop button on the control
console.
2) Ensure that the low-pressure cooling line
valves are open. c) Open the motor cavity pressure
gauge shut-off valves and check the
pressure on the motor cavity gauge.
When the pressure has stabilised,
close the pump suction leg vent valve.
3) Open by-pass valves to provide
circulation of high temperature boiler
water through the pump casing, suction
and discharge lines.d) Re-check that the pressure does not
increase. Should it increase, check the
following: -
6.2.2 Boiler Hot - Circulator to be Isolated
for Maintenance
i) Make sure that all valves between
the circulator and high-pressure
system are closed.
1) Press the stop button of the control
console to de-energise the motor.
2) Close the stems on the discharge valves.ii) De-pressurise the circulator
again, if necessary.3) Close the pump jumper line service
valves.8) On completion of depressurising, the
motor is ready for removal.4) Crack open the pump suction bypass
valves to prevent a vacuum forming in the
pump case during the circulator cooling
process.
CAUTION
The low pressure cooling water must
be maintained until the motor has been
separated from a hot pump case.5) Maintain the low pressure cooling
system to the heat exchanger, via the lowpressure flowrator valves in the cooling
pipes open until the motor has been
separated from the pump.
6.2.3 Boiler Cold
1) Press the button on the control console.
2) Leave open the low pressure cooling
water line valves.CAUTION:
Keep a close watch on the motor cavity
temperature, should the temperature
increase, apply a high-pressure purge as
described in para. 6.3.8.
3) Pump discharge valves may be left open.
6.2
5/26/2018 CC Pump Manual-Full (Original)
43/109
SECTION 6
OPERATION
3) If temperature increase continues and
exceeds the 60C - trip setting - and the
cause cannot be detected or the condition
corrected, refer to the relevant shutdown
procedure in Para. 6.2. If necessary, blowdown the boiler system or apply a high-
pressure purge to the motor. See 6.3.8.
6.3 ROUTINE CHECKS AND
OPERATION CONDITIONS
(Also see fault list chart)
6.3.1 Supply Current
1) Check the motor running current each
shift. The current should be constant and
comply with that specified in section 1. a) After cooling and draining, removeand disassemble the motor andexamine for worn bearings, blocked
internal strainer, motor passages,
auxiliary impeller and fouled cooling
surfaces. In addition, leaks in the heat
exchanger.
NOTE:
High amperage readings or fluctuating
motor currents indicate wear or partial
seizure at the bearing or wear ring
surfaces. This condition can cause
vibration necessitating motor removal
strip and re-installation.4) Should the alarm sound whilst the
circulator is on stand-by, start the
circulator to accelerate internal highpressure cooling water flow. Check
possible causes for temperature increase
as above. The circulator should be tripped
if the temperature exceeds 60C and the
shutdown / purge procedure 6.2 carried
out.
6.3.2 Motor Temperature
1) During normal operation, the motor
temperature should be checked at weekly
intervals. The thermometer is originally
set to initiate an alarm if the motor cavity
temperature reaches 57C and to de-
energise the motor if the temperature
reaches 60C. If desired, the
aforementioned alarm temperature
settings may be lowered, on the
temperature alarm thermometer, to suit
normal operation but only after the boiler
and circulator has been operated longenough to stabilise.
6.3.3 High Temperature Alarm and Trip
Settings
At weekly intervals check that the motor
high temperature alarm setting does not
exceed 57C or 5C above normal operating
Temperature (whichever is the lower) andthat the trip setting does not exceed 60C.
Re-set if necessary.2) Immediately investigate the following
possible causes for high temperature
alarm sounding: - 6.3.4 Pump Head and Quantity1) Check the total head generated by each
pump at weekly intervals.CAUTION
Do not stop the motor.
2) Correct possible causes of decrease in
head and quantity as follows: -a) Check the low pressure cooling water
supply for adequate flow, temperature
vapour locks and leakage in piping
(see 6.3.7.).a) The gate valve in the circulating
pump suction line and the check valve
in the circulating pump discharge
lines are not fully open. Check and
adjust the setting as necessary.
b) Check the circulator for leaks fromthe motor casing, high pressure fill
and drain cooling water connections,
particularly the motor fill and purge
line shut-off valves and the motor
drain valves.
b) Discharge through the pump and
suction leg vent or the pump casing
and suction leg drain valves. Ensure
both are closed.c) Check that the cooling water strainers
are not obstructed. c) Low N.P.S.H., available due to
reduced water level in the steam
drum, changes in system pipework or
system blockage. Check and adjust
the number of circulators operating to
suit until the fault can be corrected.
d) Check for indication of bearing
damage (noise, vibration).
6.3
5/26/2018 CC Pump Manual-Full (Original)
44/109
SECTION 6
OPERATION
d) Vent the pipe system to remove
vapour locks.
f) Electrically induced vibration also a
factor, i.e. Rotor bar breakage etc.e) Power supply and reverse rotation
checks are given in 5.5.1 (5) and 5.2
(9).
NOTE:
When (e) is the cause, the motor must be
removed, as detailed in section 7.2,
before repairs can be undertaken.f) Worn wear rings and a blocked ordamaged impeller can be corrected
only after removing the motor
assembly from the pump case.
Clearances are specified in section 1.
6.3.7 Low Pressure Cooling Water Supply
Failure.
If the cooling water to the heat exchanger is
lost while the circulator is at operating
temperature, the motor must be de-energised
within five minutes and the suction and
delivery valves closed as soon as possible.
6.3.5 Insulation Condition
Before initially energising the motor and
thereafter at monthly intervals, check the
following: -CAUTION
1) The insulation resistance to ground of the
motor leads.Damage to the windings may occur if:
a) the motor remains in operation after 5
minutes from the loss of cooling water.a) With the unit filled with water below20C or at normal local ambient
temperature, the resistance measured
at the terminal links, using a 1000V
megger, must exceed 200 megohms.
Or
b) if the cooling water is not
restored before the motor
temperature rises above 60C.
NOTE:CAUTIONThe insulation resistance of the stator
winding varies with temperature and
must always be measured cold 20C or at
normal local ambient temperature.
Do not attempt to operate the motor by
overriding the temperature controller trip
mechanism and restore the low pressure
cooling water as quickly as possible.
Damage to the windings may occur if the
cooling water is not restored before themotor temperature rises above 60C.
2) Ensure that the interior of the terminal
box is dry, especially the insulation
projecting over the gland stems.
6.3.6 Vibration NOTE:Before re-starting a circulator after an
emergency shutdown, low pressure cooling
water must be supplied to the pump to
reduce the motor temperature to at least
38C.
Check the circulators for excessive noise or
vibration, which can be either hydraulic or
mechanical in origin.
Vibration should be monitored and recorded
daily. If a permanent vibration transducer is
not installed, check at weekly intervals
using temporary pick-ups. If the reading
increases, check for the following causes: -
6.3.8 High Pressure Purge Supply To
Motor.
On some boiler installations the motor fill
and drain connection may be connected to ahigh pressure cold purge system which can
be used for emergency motor cooling and to
protect the motor during boiler cleaning.
During normal operation this purge supply
must be isolated with a double isolation
valve fitted to the motor, as any leakage or
reverse flow from this point can result in
motor overheating, winding and / or bearing
damage. (Reverse flow totalling no more
than 2 3 litres is sufficient to cause
damage).
a) Cavitation due to low N.P.S.H., asdescribed in 6.3.4.
b) Unequal settings of the discharge
valves. Check and re-set in the fully
open position.
c) Incorrect directional rotation as
described in section 5.2, para. 9.
d) Excessive pipe strain on the pump
casing due to expansion or inadequate
support of pipes. Eliminate any strain
by providing adequate support.
e) Damaged or unbalanced rotor or
impeller, worn bearings, excessiveend float or incorrect impeller setting.
6.4
5/26/2018 CC Pump Manual-Full (Original)
45/109
SECTION 6
OPERATION
NOTE:If the boiler is laid-up under a nitrogen
blanket, take necessary precautions to
prevent damage to the motor through
gaseous water. Any pump start-up, when
the boiler is in this condition, must be
undertaken and initial start and the full filland vent procedure, as detailed in section
4.7, must be followed.
Continuous purging of the motor during
operation is recommended only during
boiling-out and acid cleaning. A purge rate
of 3.8 litres / min., is normally sufficient to
prevent the ingress of harmful fluids andsolids into the motor.
1) Flush down the fill and purge system to
ensure the line is clean.6.3.10 Boiler Cleaning
2) Check that the low pressure cooling
water supply valves are open.During any boiling-out or acid cleaning
operation of the boiler, the de-energised
circulators must be isolated completely prior
to introducing any chemicals to the boiler.
The circulators must be continuously purged
with clean cool water at a pressure of
approximately 7 bar, in excess of the existing
drum pressure to eliminate infiltration ofcontaminated water into the bearing and
motor components.
3) Introduce high pressure purge through
the filling valves. Check that the purge
temperature does not exceed 49C and
that the purge pressure is above the boiler
pressure.
6.3.9 Extended Shut-Down
When the circulator remains shutdown for
an extended period: -CAUTION
Severe damage can be caused if acid is
allowed to enter the motor. If
contamination from acid cleaning is
suspected, motor must be purged
immediately with clean water and
inspected for damage.
1) Check regularly that it remains full of
water.
2) Run the circulator for a minimum of ten
minutes every two months.
CAUTION
If the motor is to be subjected to extreme
low temperature, the motor must be
prevented from freezing, see section 2.2. (5)6.4 FAULT FINDING
Refer to the fault list chart that follows.
6.5
5/26/2018 CC Pump Manual-Full (Original)
46/109
SECTION 6
OPERATION
Fi ure 6/1 Fault List Chart
6.6
5/26/2018 CC Pump Manual-Full (Original)
47/109
SECTION 7
MAINTENANCE
7.0
CONTENTS
PARAGRAPH
PAGE
7.1 INTERNAL INSPECTION 7.3
7.2 MOTOR REMOVAL 7.3
7.3 DISASSEMBLY 7.4
7.4 INSPECTION OF COMPONENTS 7.16
7.5 ASSEMBLY NOTES 7.27
7.6 ASSEMBLY 7.29
7.7 RE-INSTALLATION OF MOTOR 7.42
PARTS LIST GENERAL 7.43
ILLUSTRATIONS
FIGURE 7/1 MOTOR REMOVAL 7.2
FIGURE 7/2 MAIN IMPELLER REMOVAL 7.5
FIGURE 7/3 TERMINAL BOX 7.6
FIGURE 7/4 UP - ENDING THE MOTOR 7.7
FIGURE 7/5 TYPICAL WORKING PLATFORM 7.8
FIGURE 7/6 MOTOR COVER AND FILTER REMOVAL 7.9
FIGURE 7/7 THRUST BEARING 7.10
FIGURE 7/8 COVER END JOURNAL BEARING ASSEMBLY - REMOVAL 7.11
FIGURE 7/9 ROTOR ASSEMBLY - REMOVAL 7.12
FIGURE 7/10 TERMINAL GLAND REMOVAL 7.13
FIGURE 7/11 STATOR ASSEMBLY - REMOVAL 7.14
FIGURE 7/12 JOURNAL BEARING TILTING PADS - REMOVAL 7.15
FIGURE 7/13 JOURNAL BEARING CLEARANCE 7.16
5/26/2018 CC Pump Manual-Full (Original)
48/109
SECTION 7
MAINTENANCE
7.1
FIGURE 7/14 JOURNAL BEARING SLEEVE - REMOVAL 7.17
FIGURE 7/15 THRUST BEARING CLEARANCE 7.18
FIGURE 7/16 IMPELLER AND CASE WEAR RING 7.19
FIGURE 7/17 DETAILS OF TAPING HOOK 7.22
FIGURE 7/18 DETAILS OF TAPING NEEDLE 7.22
FIGURE 7/19 OUTER COIL TAPING 7.23
FIGURE 7/20 INNER COIL TAPING 7.24
FIGURE 7/21 TYPICAL KNOT SEALING 7.26
FIGURE 7/22 ASSEMBLY OF FLANGE STUDS 7.27
FIGURE 7/23 WIRE LOCKING 7.28
FIGURE 7/24 JOURNAL BEARING - ASSEMBLY 7.29
FIGURE 7/25 STATOR ASSEMBLY 7.30
FIGURE 7/26 JOURNAL SLEEVE 7.31
FIGURE 7/27 TERMINAL GLAND ASSEMBLY 7.32
FIGURE 7/28A COVER END BEARING ASSEMBLY 7.33
FIGURE 7/28B COVER END BEARING ASSEMBLY 7.33
FIGURE 7/28C COVER END BEARING ASSEMBLY 7.34
FIGURE 7/29 END FLOAT CHECK 7.35
FIGURE 7/30 MOTOR COVER AND FILTER ASSEMBLY 7.37
FIGURE 7/31 TERMINAL BOX 7.38
FIGURE 7/32 TERMINAL LINK INSULATION 7.39
FIGURE 7/33 BURSTING DISC DETAILS 7.40
FIGURE 7/34 IMPELLER SETTING 7.41
FIGURE 7/35 GENERAL ARRANGEMENT 7.47
FIGURE 7/36 SECTIONAL ARRANGEMENT 7.48
FIGURE 7/37 TERMINAL BOX ARRANGEMENT 7.49
FIGURE 7/38 TOOL KIT LIST 7.50
5/26/2018 CC Pump Manual-Full (Original)
49/109
SECTION 7
MAINTENANCE
7.2
Fi ure 7/1 Motor Removal
5/26/2018 CC Pump Manual-Full (Original)
50/109
SECTION 7
MAINTENANCE
7.3
NOTE 1:
Some of the illustrations shown are typical
only and not necessarily specific to the
circulator described, i.e. motor proportions
and number of studs etc., but indicate
generally the basis of the unit breakdown.
NOTE 2:
For items not annotated on the drawingswithin the text refer to the Main Sectional
Arrangement at the rear of the Section.
NOTE 3:
A tool kit is supplied with each circulator
contract, containing specialised tools
necessary for the disassembly and assembly of
the motor.
7.1 INTERNAL INSPECTION
Internal inspection of the circulator should becarried out to the recommendation of the station
maintenance authority.
Partial inspection of the internal filter and thrustbearing is possible in-situ after removal of themotor cover.
WARNING:
Inspection must only be carried out with the
circulator isolated from the electrical supply,
depressurised and the motor cover removed
as in Section 7.3.4.
A full inspection requires the motor assembly tobe removed as described below.
7.2 MOTOR REMOVAL (FIG. 7/1)
WARNING:
Before removing the motor, the circulator
must be completely isolated from the system,
depressurised and cooled as described below.
7.2.1 Motor Removal
1) Isolate the electrical supply; disconnect allinstrument cables from the motor identifyingthe connections and leads.
2) Remove the terminal box covers anddisconnect the external power supply cables
from the terminal box as described in 7.3.4,identifying each lead for reassembly.
3) If hoses are not fitted in the low pressurecooling system, adjacent to the heatexchanger, with sufficient slack to allow themotor to be separated from the pump case, fittemporary hoses as follows:-
a) Close the low pressure cooling watershut-off valves.
b) Immediately secure temporary coolingwater hoses to the inlet and outletconnections of the heat exchanger tomaintain a low pressure cooling waterflow within the heat exchanger.
c) Maintain cooling water until the motor isseparated from the pump.
CAUTION:The low pressure cooling water flow, and
motor temperature must be maintained
within the specified limits, whenever the
motor is in contact with the pump case.
4) Check the pressure gauges to ensure that thecirculator is depressurised.
5) Make sure that the discharge valves, thesuction valve, the by-pass valves and theshut-off valves are closed to isolate thecirculator from the boiler and fill system.
6) Drain the pump casing.
WARNING:Never drain the pump casing through the
motor fill & drain line as this could cause
contamination of the motor.
7) Fit the removable lifting lugs to the weldedbrackets on the motor case.
8) Set up two chain hoists and rigging, ofsufficient capacity for each to take the fullweight of the motor, and connect to thelifting lugs.
WARNING:
Normally two hoists are used for removing
the motor and because the load can shiftfrom one hoist to the other during the
removal, each hoist must be capable of
taking the full weight of the motor.
9) Take the initial strain of the motor.
CAUTION:
The motor must be removed from the
pump casing without a break in the
sequence (9) and (11).
10) Loosen the pump/motor flange stud nuts inaccordance with the hydraulic studtensioning instructions - section 8.
CAUTIONAlways double check that the motor and
pump case are cooled and depressurized
before loosening the studs nuts.
11) Disconnect the fill and drain line upstreamof shut-off valve if there is not sufficient playin the line to permit motor removal.
5/26/2018 CC Pump Manual-Full (Original)
51/109
SECTION 7
MAINTENANCE
7.4
12) Remove the flange stud nuts and lower themotor clear of the pump casing, keeping theflange faces parallel until the impeller isclear of the pump casing.
13) When the impeller is clear of the pump case,check the motor cavity temperature. Whenthe temperature falls below 54
oC remove all
instruments and store safely.14) Lower the motor to the floor.
15) Drain the motor via the drain valve andremove the valve and pipework
16) Remove the heat exchanger from the motor,in accordance with site procedures, asdescribed in 7.2.1.
CAUTION:
To prevent damage never stand or turn
the motor on either the drain valves or
terminal box.
17) Lower the motor to the horizontal positionto give access to the terminal box, removethe lifting tackle and cover all joint faces andopenings with clean rags.
18) If necessary, transport the motor to aworking area where adequate facilities areavailable for disassembly, inspection andmaintenance.
7.2.1 Heat Exchanger Removal
NOTE:
As the heat exchanger is welded to the motor
case via the interconnecting pipework,
removal of the heat exchanger is at the
discretion of, and the procedure will bedetermined by, the senior station engineer.
Check the heat exchanger during the firstmotor maintenance removal for build up ofsediment in the shell base; this will provide aguide to any future attention that may berequired.
7.3 DISASSEMBLYCAUTION:
Lifting tackle must not be attached to the
protruding rotor shaft nor must the shaft be
subject to any shock loads.The motor must be adequately supported
before and during any disassembly.
7.3.1 Case Wear Ring
1) The case wear ring can be left in place,bolted inside the pump case.
2) To remove the wear ring, remove the sixscrews securing the wear ring inside thepump casing. Carefully lower the wear ringfrom its location within the casing.
Lower to ground level, and store in a safeplace for inspection.
7.3.2 Impeller (Fig. 7/2)
1) Unlock the punch marks and remove theimpeller cap screw.
2) Remove the LEFT-HAND threaded impellernut using the special spanner and tommy barprovided in the tool kit.NOTE:
Do not use any leverage in the water
passages of the impeller to oppose force
exerted on the special spanner; the weight
of the rotor will oppose rotation if the
tommy-bar is given a few heavy blowswith a lead faced hammer.
If the nut shows any tendency to seize onthe shaft, do not continue to exert force,
but drill and split the nut to remove.
3) Fit the puller, provided in the tool kit, to thetapped holes in the top of the impeller boss,using the applicable studs and nuts in the toolkit. Withdraw the impeller from the motorshaft.
4) Withdraw the impeller washer and removethe impeller key.
5) Immediately refit a serviceable impeller nutto permanently protect the shaft threads.
7.3.3 Baffle Wear Ring
Examine the baffle wear ring. If damaged,remove the socket headed cap screws and lockwashers. Remove the wear ring for a fullerinspection or renewal
7.3.4 Terminal Boxes (Fig. 7/3)
1) Remove the nuts and washers from the studsand remove the terminal box cover.
2) Remove the nuts and washers from theterminal studs.
3) Identify the motor supply cable links for
reconnection.
4) Carefully cut the insulation from around thecable connections and links.
CAUTION:
Do not damage the link insulation.
5) Remove the washers and the nuts from theterminal stem as the link is removed.
5/26/2018 CC Pump Manual-Full (Original)
52/109
SECTION 7
MAINTENANCE
7.5
6) Remove the nuts and washers from theterminal box support studs. Using liftingtackle, lift off the terminal boxes and removethe gaskets.
NOTE:
A small metal cover should be fabricated
and placed over the terminal stems to
protect them during motor repair.
Fi ure 7/2 Im eller Removal
5/26/2018 CC Pump Manual-Full (Original)
53/109
SECTION 7
MAINTENANCE
7.6
Fi ure 7/3 Terminal Box
5/26/2018 CC Pump Manual-Full (Original)
54/109
SECTION 7
MAINTENANCE
7.7
Fi ure 7/4 U -Endin the Motor
5/26/2018 CC Pump Manual-Full (Original)
55/109
SECTION 7
MAINTENANCE
7.8
7.3.5 Motor Cover and Filter (Fig. 7/6)
1) Using two cranes and lifting tackle attach onewith shackles to the motor cover and theother via a sling around the motor flangeneck. Lift and up-end the unit as depictedFig. 7/4 until the motor is vertical, with themotor cover uppermost. Lower the motorpump flange on to a suitable building stand;a typical building stand is shownin Fig. 7/5.Support the rotor shaft beneath the standusing a screw or hydraulic jack. Care must betaken to avoid damaging the shaft or flangefaces. If a pit is not available, erect a suitableworking platform, similar to that depicted inFig. 7/5.CAUTION:
Firmly support the impeller end of therotor shaft on a suitable wooden block
when placing the motor on the stand and
jack so that when the thrust nut is
removed during a subsequent operation,
the rotor will be adequately supported.
2) Mark the cover relative to the motor case toensure correct alignment on reassembly.
3) Using the stud tensioning equipment (Section8), release the tension of the motor cover nutsand remove the nuts.
4) Attach the lifting tackle and carefully remove
the motor cover from the motor case.5) Remove the flexitallic spiral wound gasket
and before discarding, inspect the gasket forany unusual markings or depressions thatindicate a seat dressing is required.
6) Remove the filter by removing the hexagon-headed screws and lock washers.
Figure 7/5 Typical Working Platform
5/26/2018 CC Pump Manual-Full (Original)
56/109
SECTION 7
MAINTENANCE
7.9
Fi ure 7/6 Motor Cover and Filter Removal
5/26/2018 CC Pump Manual-Full (Original)
57/109
5/26/2018 CC Pump Manual-Full (Original)
58/109
SECTION 7
MAINTENANCE
7.11
7.3.7 Cover End Journal Bearing
Assembly (Fig. 7/8)
1)
a) Remove the locking wire and the stator
lock ring hexagon headed screws.b) Push down the stator lock ring sufficiently
to permit split ring to be prised out of itsgroove.
c) Remove the split ring from its casinggroove, using screwdrivers as levers.
d) Withdraw the stator lock ring, usingscrews as lifters, from the motor case.
2) Match-mark the cover end bearing housingand the motor case to ensure that they are re-fitted in their original radial location.
3) Remove the bearing housing securing screws
and lock washers.4) Attach eyebolts and lifting tackle to the cover
end bearing housing and lift the housing,complete with the journal bearing assembly,to just above the motor casing.
5) Lower the bearing housing and remove anddiscard the `O` ring.
6) Place the housing in a clean and safe placefor subsequent disassembly.
Fi ure 7/8 Cover End Journal Bearin Assembl - Removal
5/26/2018 CC Pump Manual-Full (Original)
59/109
SECTION 7
MAINTENANCE
7.12
7.3.8 Motor Shaft (Fig. 7/9)
1) Fit an eyebolt, supplied in the tool kit, andlifting tackle to the rotor shaft as indicated.With an exact vertical lift, slowly lift therotor out of the stator, taking particular carenot to damage the cable ends whilst doing so.
2) Lower the rotor into the horizontal positionand position it carefully on to wooden 'V'blocks at floor level. Fit suitable protection,i.e. clean rags, over the journal sleeves. Refitthe thrust nut to protect the threads.
7.3.9 Terminal Gland Removal (Fig. 7/10)
1) To facilitate re-assembly, identify eachterminal stem body and its respectiveposition.
CAUTION
Make sure that the gland moulding doesnot turn with the gland nut by holding the
moulding stationary using a clamp
connector and the connecting link.
2) Remove the nuts and link from the terminalblock. Unscrew the gland nut and tap theconnector lightly until the gland assemblycan be carefully drawn out of the motor case.
3) Remove the gland nuts from two of the stemsand placed on the third stem.
4) Replace the clamp connector over this stemand undo the cable gland nut. This actionwill draw the gland assembly from the motorcase.
5) Remove the inner casing & the C shapedsupport ring. The two belleville washers andback up sleeve remain on the cable.
NOTE:
The terminal gland stems are