CC Pump Manual-Full (Original)

Embed Size (px)

DESCRIPTION

500mw bhel boiler

Citation preview

  • 5/26/2018 CC Pump Manual-Full (Original)

    1/109

    HAYWARD TYLER

    ENGINEERED PRODUCTS

    BHARAT HEAVY ELECTRICALS LTD

    (BHEL)

    Kahalgaon Power Station

    SERIAL NUMBERS

    EP/03/10757A,B,C,D,E & F

    EP/04/10794A,B & C

    3 X 500 MW BOILER CIRCULATING PUMPS

  • 5/26/2018 CC Pump Manual-Full (Original)

    2/109

    FOREWORD

    Each section contains an itemised Contents List.

    The major illustrations of the Pump and Motor are

    included at the rear of Section 7. Additional

    illustrations of particular features are incorporated

    in the text.

    This instruction manual provides comprehensive

    installation, operating and maintenance information

    of a Hayward Tyler Glandless, Wet Stator, Motor

    Pump Unit, referred to in the text as the circulator.

    The General Contents list shows that the manual is

    divided into eight main sections. Paragraph

    references are consecutive throughout each section,

    and are preceded by the appropriate section

    number. For example 5.1. designates:-

    Note! Where a customer boiler layout drawing is

    shown, this is used in good faith. However,

    Hayward Tyler can accept no responsibility for any

    errors or consequences that may result.

    Hayward Tyler Manuals are for guidance only and

    we reserve the right to update, revise and modify

    this manual in accordance with our continuous

    research and development programme.

    Section 5, Commissioning.

    5.1. Pre-Start Check List.

    Hayward Tyler Engineered Products Ltd.

    1 Kimpton RoadRevised manuals will not automatically be issued,

    however, should they be required, Hayward Tylermay be contacted and arrangements can be made.

    Luton

    BedfordshireENGLAND

    LU1 3LD

    Telephone: +44 (0) 1582 731144

    Email: [email protected]

    Fax: +44 (0) 1582 452198

    i

  • 5/26/2018 CC Pump Manual-Full (Original)

    3/109

    GENERAL CONTENTS

    BOILER CIRCULATING PUMP INSTRUCTION AND MAINTENANCE MANUAL

    SECTION 1 TECHNICAL DATA

    SECTION 2 STORAGE

    SECTION 3 DESCRIPTION

    SECTION 4 INSTALLATION

    SECTION 5 COMMISSIONING

    SECTION 6 OPERATION

    SECTION 7 MAINTENANCE

    SECTION 8 STUD TENSIONING

    ii

  • 5/26/2018 CC Pump Manual-Full (Original)

    4/109

    SECTION 1

    TECHNICAL DATA

    1. 0

    CONTENTS

    PARAGRAPH PAGE

    1.1 GENERAL 1.1

    1.2 CHARACTERISTICS 1.1

    1.3 MOTOR CHARACTERISTICS 1.2

    1.4 CLEARANCES AND SETTINGS 1.2

    1.5 HEAT EXCHANGER 1.3

    1.6 INSTRUMENTATION 1.3

    1.7 TORQUE LOADINGS 1.3

    1.8 WEIGHTS (APPROXIMATE) 1.3

    ILLUSTRATIONS

    FIGURE 1/1 MOTOR ASSEMBLY 1.4

    FIGURE 1/2 WINDING RESISTANCE DIAGRAM 1.5

    FIGURE 1/3 PUMP PERFORMANCE CURVE 1.6

    FIGURE 1/4 MOTOR PERFORMANCE CURVE 1.7

  • 5/26/2018 CC Pump Manual-Full (Original)

    5/109

    SECTION 1

    TECHNICAL DATA

    1. 1

    1.1 GENERAL

    Unit Serial Nos: EP/03/10757 A B C D E F & EP/04/10794 A B

    Customer Order No: 0130645 & 0140593

    Service: Boiler Water Circulating Pump with

    Motor below Pump.

    Number Supplied: 9

    Electrical: 3300V - 3 Phase - 50Hz

    1.2 CHARACTERISTICS

    Type: Single Suction - Double Discharge

    Size: (2 x 13) x 16 x 19H Volute

    Design Pressure: 214 kg/cm2

    Design Temperature: 370C

    Hydrostatic Test pressure: 321 kg/cm2

    Suction Pressure: 197.4 kg/cm2

    Specific Gravity at pump suction 0.542

    N.P.S.H. required: 15 m (3% head drop)

    Quantity Pumped: 3135 m3/hr

    Differential Head: 32.37 m

    Pump Efficiency: 83 % Cold 83 % Hot

    kW Absorbed: 333.1 Cold 180.5 Hot

    1.3 MOTOR CHARACTERISTICS

    Type: Wet Stator Squirrel Cage Induction

    Output: 360 kW

    Service Factor: 1.0

    Winding Insulation: XLP

    Motor Case Design Pressure 214 kg/cm2

    Motor Case Design Temperature 368oC

    Speed: 1450 RPM.

    Hot Duty Cold Test

    Motor Efficiency: 89.5 % 89.5 %

    kW Input: 201.7 372.2

    Power Factor: 74.0 82.5

    Overall Efficiency: 74.3 % 74.3 %

    Full Load Current: 85 amps

    Motor Starting Current: 410 amps

  • 5/26/2018 CC Pump Manual-Full (Original)

    6/109

    SECTION 1

    TECHNICAL DATA

    1. 2

    1.4 CLEARANCES & SETTINGS (mm)

    Initial Maximum

    Impeller Wear Ring Clearance : 1.46 1.58 2.03

    Journal Bearing Clearance : 0.20 - 0.38 0.55

    Reverse Thrust Wear Ring Clearance :

    0.42 - 0.52 0.76

    Rotor End Float: 0.50 - 0.80 1.50

    Impeller Setting (Dimension Z): 572.5 571.5 mm

    1.5 INSTRUMENTATION:

    Temperature Switches: Ashcroft Model T.461-T20-030-69C-XNH:

    20-950C with 6096 mm capillary. 15amp. 125 to 250 Volt AC.

    Alarm Setting 60C Trip Setting at 65C

    Thermometer:Ashcroft Model 600A-03-C41-B01-A1-L07-BS-

    XNG

    0-1200C CD1

    Pressure Gauge:Ashcroft Model 60-1379SSL-04L-XNH-XNG

    0-250 Kg/cm2 CD1.

    Flowmeter:KDG Mobrey Series 250 Rotameter

    Model 250-50-CX-M12-TO-S6-Z6

    Relay Mains supply: 220V 50/60 Hz

    Contact Cut Off Capacity: Max 250V/4A/500VA

    Thermocouples: Type K Dual Element Ungrounded

    1.6 TORQUE LOADINGS:- Refer to Figure 1/1, Schedule of Torque Loadings

    1.7 WEIGHTS (Approximate)

    Pump Case 3425 kg

    Motor Complete 6020 kg

    Heat Exchanger 410 kg

  • 5/26/2018 CC Pump Manual-Full (Original)

    7/109

    SECTION 1

    TECHNICAL DATA

    1. 3

    TOTAL 9855 kg

  • 5/26/2018 CC Pump Manual-Full (Original)

    8/109

    SECTION 1

    TECHNICAL DATA

    1. 4

    Figure 1/1 Motor Assembly

  • 5/26/2018 CC Pump Manual-Full (Original)

    9/109

  • 5/26/2018 CC Pump Manual-Full (Original)

    10/109

    SECTION 1

    TECHNICAL DATA

    1. 6

    Fi ure 1/3 Pum Performance Curve

  • 5/26/2018 CC Pump Manual-Full (Original)

    11/109

  • 5/26/2018 CC Pump Manual-Full (Original)

    12/109

    SECTION 2

    STORAGE

    CONTENTS

    PARAGRAPH PAGE

    2.1 ENVIRONMENT 2.2

    2.2 STORAGE - GENERAL 2.2

    2.3 INHIBITOR 2.2

    2.4 HEAT EXCHANGER 2.2

    2.5 EXTERIOR SURFACES 2.2

    2.6 STANDARD STORAGE CHECKS FOR STORAGE UP TO 3 YEARS 2.3

    2.7 STORAGE PERIODS GREATER THAN 3 YEARS 2.4

    2.8 PREPARATION FOR STORAGE AFTER USE 2.4

    2.9 INSPECTION RECORD CARDS 2.4

    ILLUSTRATIONS

    FIGURE 2/1 MOTOR STORAGE / TRANSIT DETAILS 2.1

    FIGURE 2/2 PUMP CASE STORAGE DETAILS 2.2

    FIGURE 2/3 INHIBITOR FILLING VALVE 2.3

    FIGURE 2/4 ROTATING THE ROTOR ASSEMBLY 2.5

    FIGURE 2/5 INSPECTION RECORD CARD 2.6

    FIGURE 2/6 CHECK LIST 2.7

    2.0

  • 5/26/2018 CC Pump Manual-Full (Original)

    13/109

    SECTION 2

    STORAGE

    Figure 2/1 Typical Motor Transit/Storage Details

    2.1

  • 5/26/2018 CC Pump Manual-Full (Original)

    14/109

    SECTION 2

    STORAGE

    2.1 ENVIRONMENT

    The storage area must have a hard standing

    floor that will be capable of supporting the

    weight of the units.

    2.2 STORAGE GENERAL

    2.2.1 Pump Case (Fig. 2/2)

    1) The pump case internal cast areas and all

    machined faces must be cleaned and a

    suitable removable solvent rust

    preventative, with a minimum effective

    life of 6 months, applied. Recommendedrust preventatives are, Jenolac J400 or

    Shell Ensis Fluid 264, or their

    equivalents.

    2) All pump case openings must be closed

    with covers. These covers to be secured

    to the weld preparations with steel

    banding and the pump case main flange

    with the existing studs and nuts supplied

    on the pump flange.

    2.2.2 Motors (Fig. 2/1)

    1) The motor and transit assembly must be

    stored in a vertical position standing on

    the motor cover end.

    NOTE:

    When the terminal box protrudes

    below the motor cover stand, rest the

    motor cover on balks of timber of

    sufficient height to keep the terminal

    box clear off the ground (Fig. 2/1)

    2) The motor apertures must be blanked off

    with flanges secured with studs, bolts andnuts (Fig. 2/1).

    3) The motor and transit assembly must be

    filled to the top of the transit canister with

    inhibitor of the appropriate concentration,

    through the filling connector located in

    the temporary transit flange, sealing off

    the motor heat exchanger bottom outlet.

    2.3 INHIBITOR

    Inhibitor is to be produced from a pre-mixed

    concentration of mono-propylene glycol anddistilled water in a 50/50 solution by volume.

    The mono-propylene glycol must contain

    corrosion inhibitors and meet BS6580 or

    equivalent. A tolerance of 5% on the normal

    glycol/water mix may be applied.

    The distilled water used must have a

    conductivity of less than 10 reciprocal

    megohms (microsiemens) per centimetre.

    Check the specific gravity of the inhibitor to

    ensure the correct concentration.

    The specific gravity of the mixture at 20C isas follows:-

    Mixture by%Volume Specific Gravity

    45% MPG /55% Water 1.036

    50% MPG /50% Water 1.038

    55% MPG /45% Water 1.040

    MPG = Mono-propylene Glycol

    2.4 HEAT EXCHANGERFigure 2/2 Pump Case Storage DetailsThe heat exchanger should be stored as

    instructed by the manufacturers.

    The heat exchanger interconnecting pipe work

    and the fill and drain assemblies must also be

    filled with the same inhibitor as the motor,

    blank flanges being used to seal both ends.

    2.5 EXTERIOR SURFACES

    All exterior surfaces of the motor must be

    maintained in a good painted condition.

    Scratched or damaged paintwork must berepainted.

    2.2

  • 5/26/2018 CC Pump Manual-Full (Original)

    15/109

    SECTION 2

    STORAGE

    CAUTION:

    To rotate the assembly in a clockwise

    direction may damage the impeller nut

    locking screw.

    2.6 STANDARD STORAGE CHECKS FOR

    STORAGE UP TO 3 YEARS

    A visual examination and inspection of the

    motor and transit assembly must be made at

    least every three months as follows:-

    b) If the shaft cannot be rotated or is

    very difficult to turn, the motor mustbe stripped down and inspected as

    outlined in Section 7.NOTE:

    When stored by the contractor, or by an

    agency, a record card should be kept of the

    intervals between inspections and the results

    of the following inspection checks recorded.

    8) Check the inhibitor level in the motor and

    transit assembly. The level of inhibitor

    must not fall below the level of the

    impeller. Top up if necessary.

    2.6.1 MOTOR9) Check the glycol/water concentration by

    measuring the specific gravity of the

    inhibitor. The inhibitor is considered

    acceptable if it conforms to the

    concentration and tolerance given in

    paragraph 2.3.

    1) The motor is stored vertically resting on

    the motor cover - not horizontally.

    2) The exterior paintwork is in good

    condition. Repaint where necessary.3) All flanges and joints are tightly secured

    and no leakage of the inhibitor has taken

    place.

    10) Replace the transit inspection cover

    when the inspection is satisfied.

    2.6.1.2 Topping up/Draining Inhibitor (Fig 2/3)4)

    1) Remove the access cover plug.a) All studs, bolts and nuts are present

    and in sound condition. 2) Attach a hose leading from a pumping

    device to the hose tube of the inhibitor

    filling valve.b) The phosphate, or any other plating,

    applied to these items has not

    deteriorated.3) Unscrew the filling valve screw by two

    turns. This action opens the valve to allow

    the pumped liquid to enter the motor.

    5) Measure and record the ambient

    temperature of the storage area.

    4) When the sufficient inhibitor has been

    pumped in, turn screw to close the valve.6) Check and record the insulation resistance

    of the stator windings as follows:

    a) Remove the terminal box cover. 5) Remove the hose from the inhibitor

    filling valve.b) Check the insulation resistance at the

    terminal stems using a l000V megger.

    Record the result.NOTE:

    If the motor is to be drained, allow the

    liquid to flow out of the valve hose tube.

    Ensure disposal of inhibitor is carried

    out in accordance with local

    regulations.

    IMPORTANT: -

    If any insulation resistance value falls below

    200 megohms at 20C this, and any previous

    readings, with dates, must be reported to

    Hayward Tyler for comment.

    c) Fit the terminal box cover.

    7)

    a) Remove the inspection cover from the

    top of the transit canister (Fig.2/1).

    Fit impeller wrench onto the impeller

    nut and rotate the rotating assembly

    seven complete revolutions in an anti-

    clockwise direction when viewed from

    the pump-end.

    Fi ure 2/3 Inhibitor Fillin Valve

    2.3

  • 5/26/2018 CC Pump Manual-Full (Original)

    16/109

    SECTION 2

    STORAGE

    2.6.1.3 Pump Case and Transit Assemblies

    2.8 PREPARATION FOR STORAGE

    AFTER USE.Inspect the pump assembly and check the

    following: -

    1) Remove the motor from the pump caseand drain the motor as described in

    Section 7.

    1) No extensive corrosion has occurred on

    the internal pump cast or machined areas.

    2) The protective coating is satisfactory.

    Re-apply if necessary. 2) Disassemble the motor cover and clean

    out any loose material, sediment etc.3) Visually examine the assembly for

    damage. 3) Disassemble the motor as described in

    Section 7.4) Check that the pump case protective

    flanges are correctly fitted and secure. 4) Check all fittings and clearances and

    general condition (Section 1). Fit spare

    parts as necessary.2.6.2 Stud Tensioning Equipment

    After use, the stud tensioning componentsmust be thoroughly cleaned, examined for

    damage and a rust preventative lubricant

    applied to all surfaces.

    5) Reassemble the motor as described inSection 7.

    6) Using special wrench provided on the

    impeller nut, check that the shaft rotates

    freely, approximately seven revolutions in

    an anti-clockwisedirection.

    The components must be then wrapped in

    suitable waterproofed material and stored in

    a clean, dry area.7) Check the insulation resistance of the

    winding. This should not be below 200

    megohms.2.7 STORAGE PERIODS GREATER

    THAN THREE YEARS8) Fit the transit canister to the main flange

    and stand the motor upright on the motor

    cover.

    Units that remain in store over three years

    require special consideration and HaywardTyler Limited should be consulted for

    specialist advice.9) Seal off all apertures with appropriate

    transit flanges and gaskets.

    Motor assemblies that are stripped must be

    reassembled using new gaskets, the details

    recorded on the storage record card stating that

    it has been stripped and listing any relevant

    findings.

    10) Fill the motor with a pre-mixed

    concentration of inhibitor, in accordance

    with paragraph 3, through the filling

    connection in the transit flange, sealing

    the motor heat exchanger bottom outlet.

    CAUTION: 11) Fit the transit canister inspection cover.Precautions must be taken prior to use that

    the unit is pressure tight. 12) Re-check the insulation resistance of the

    motor windings.

    13) Check that the storage conforms to Para

    2.2.

    2.9 INSPECTION RECORD CARD

    (Fig. 2/5 and Fig 2/6)

    A typical inspection record card and check list

    is given on the following pages.

    2.4

  • 5/26/2018 CC Pump Manual-Full (Original)

    17/109

    SECTION 2

    STORAGE

    Fi ure 2/4 Rotatin the Rotor Assembl

    2.5

  • 5/26/2018 CC Pump Manual-Full (Original)

    18/109

    SECTION 2

    STORAGE

    Fi ure 2/5 Ins ection Record Card

    2.6

  • 5/26/2018 CC Pump Manual-Full (Original)

    19/109

    SECTION 2

    STORAGE

    2.7

    Fi ure 2/6 Check List

  • 5/26/2018 CC Pump Manual-Full (Original)

    20/109

  • 5/26/2018 CC Pump Manual-Full (Original)

    21/109

    SECTION 3

    DESCRIPTION

    3.1 GENERAL 3.2 PUMP

    The Hayward Tyler Glandless Motor

    Circulator Pump is designed for recirculating

    boiler water through the boiler water systems

    of fossil fuel or liquid cooled nuclear reactorpower stations and similar applications.

    The pump comprises a single suction and

    double discharge branch casing, welded into

    the boiler system pipe work at the suction and

    discharge branches with the suction branchuppermost.

    The circulators consist of a single stage

    centrifugal pump and a wet stator induction

    motor, which are mounted within a common

    pressure vessel. The vessel consists of three

    main parts, a pump casing, motor housing and

    motor cover.

    Within the pump cavity rotates a key driven,

    mixed flow type impeller, mounted on the end

    of the extended motor shaft. 'Renewable wear

    rings are fitted to both the impeller and pump

    case. The impeller wear ring is the harder

    component to prevent galling

    The motor is suspended beneath the pump

    casing and is filled with cold boiler water at

    full system pressure. No seal exists between

    the pump and motor, but provision is made to

    thermally isolate the pump from the motor in

    the following respect: -

    3.3 MOTOR

    The motor is a squirrel cage, wet stator,

    induction motor, the stator wound with aspecial water tight insulated cable. The phase

    joints and lead connections are also moulded in

    an insulated material. The motor is joined to

    the pump casing by a pressure tight flange joint

    and a motor cover completes the pressure tight

    shell.

    1) Thermal Conduction. Because the pump

    temperature is so high, usually above 340C

    and the motor temperature is limited to

    about 55C, a simple restriction, in the form

    of a 'neck', is provided to minimise heat

    conduction. The motor shell contains all the moving parts,

    except for the impeller. Below the impeller is

    situated an integral heat baffle which reduces

    the heat flow, a combination of convection and

    conduction, down the unit. A baffle wear ring-

    cum-sleeve above the baffle forms a labyrinthwith the underside of the impeller to limit

    sediment penetration into the motor. Should

    foreign matter manage to pass the labyrinth

    device into the motor enclosure, a filter located

    at the base of the cover end bearing housing

    strains it out.

    2) Hot Water Diffusion. To minimise

    diffusion of boiler water, a narrow annulus

    surrounds the rotor shaft, between the hot

    and cold regions. A baffle ring restrictssolids entering the annulus.

    3) Motor Cooling. The motor cavity is

    maintained at a low temperature by a heat

    exchanger in a closed loop water circulation

    system, thus extracting the heat conducted

    from the pump.

    The motor design is such that for ease of

    maintenance, the stator shell, complete with the

    stator pack, the rotor shaft, the journal bearing

    housings and the thrust assembly, can be

    withdrawn from the motor case in sequence.

    Lifting lugs are supplied to secure hoists whenraising and lowering the motor.

    In addition, this water circulates through the

    stator and bearings, extracting the heat

    generated in the windings and providing

    bearing lubrication. An internal filter is

    incorporated in the circulating system.

    4) In emergency conditions, if low pressure

    coolant to the heat exchanger fails, or is

    inadequate to cope with heat flow from the

    pump case, a cold purge can be applied to

    the bottom of the motor to limit the

    temperature rise.

    NOTE:

    A high pressure cold purge is to be used

    only as an emergency. (para 6.3.8)

    3.1

  • 5/26/2018 CC Pump Manual-Full (Original)

    22/109

    SECTION 3

    DESCRIPTION

    Figure 3/1 Auxiliary Cooling Circuit

    3.2

  • 5/26/2018 CC Pump Manual-Full (Original)

    23/109

    SECTION 3

    DESCRIPTION

    3.3.1 Auxiliary Cooling Circuit (Fig. 3/1)

    3.3.3 Internal FilterThe motor is provided with its own auxiliary

    closed circuit, which besides cooling the motor

    lubricates the bearings. The water is

    continuously circulated through the bearings,

    motor windings and an external heat exchanger(cooler), by an auxiliary impeller at the thrust

    bearing end of the motor shaft.

    A stainless steel woven wire strainer, fitted at the

    base of the reverse thrust seat, filters the liquid in

    the motor before it is circulated through the

    bearings after passing through the heat exchanger

    (cooler).

    The filter should be cleaned at normal

    maintenance periods, removing any accumulation

    of foreign matter in the motor cover.

    When the motor is stationary, thermosyphon

    circulation takes place to remove conducted heat

    from the pump end of the motor.

    3.3.4 Main Flange Joints3.3.2 Bearings

    The pressure joints at the pump and motor cover

    flanges employ spiral edge wound gaskets,

    specially designed for very high pressure and

    temperature. The main pump/motor flange

    gasket is housed in stainless steel overlay,

    recessed into the joint face.

    The motor rotor shaft is supported by water

    lubricated tilting pad type radial and thrust

    bearings mounted on the stator shell, thus making

    the motor internals into a separate construction

    independent of the motor pressure vessel.

    3.3.2.1 Journal BearingsThe studs and nuts securing the flanges are made

    from special high tensile steel and, because

    torque tightening these nuts is inadequate, the

    studs are hydraulically stretched and the nuts

    tightened down by hand. When the hydraulic

    tension in the stud is released, the load is

    transferred to the nut giving the required

    tightness.

    The journal bearings of the circulator are

    the water lubricated Michell type located at

    the ends of the motor shaft, i.e. pump-end

    and cover-end. Each bearing comprises a

    hardened steel sleeve on the shaft running

    in six radially located tilting pads whose

    bearing surfaces are lined with a composite

    material. The bearing surfaces must never

    be allowed to operate in a dry condition.Stud tensioning equipment is supplied with each

    circulator order.

    3.3.2.2 Thrust Bearing 3.3.5 Terminal GlandA main thrust bearing is situated below the

    cover-end journal bearing and takes the full

    hydraulic thrust of the pump. This bearing,

    also of the Michell water lubricated type, is

    formed by a steel thrust disc, with a

    composite bearing surface, on the bottom of

    the rotor shaft running on stationary

    hardened steel tilting pads.

    The electrical supply to the motor is taken

    through special high pressure single lead cable

    terminal glands of the high temperature, safety

    type.

    The seal is effected by a terminal gland

    moulding, together with o-rings located between

    an insulating sleeve and an inner casing, and

    between the inner casing and the motor case.

    The addition of a cone-shaped collar within the

    terminal moulding, plus the design of the inner

    casing, prevents any possibility of a glandblowout at high temperatures. However, if the

    motor is subjected to sustained overheating, a

    slight leakage may occur into the terminal box.

    The thrust disc is also designed to operate

    as an auxiliary impeller to circulate the

    internal water content of the motor.

    3.3.2.3 Reverse Thrust Bearing

    The weight of the rotating assembly, as well

    as the down thrust imposed at start-up and

    shut-down, are taken by a reverse thrust

    bearing located on a reverse thrust housing

    which forms the bottom of the cover

    housing cylinder.

    The reverse thrust housing also includes a

    composites reverse thrust wear ring and is

    the mounting for the internal filter.

    3.3

  • 5/26/2018 CC Pump Manual-Full (Original)

    24/109

    SECTION 3

    DESCRIPTION

    Fi ure 3/2 Terminal Gland

    3.4

  • 5/26/2018 CC Pump Manual-Full (Original)

    25/109

    SECTION 3

    DESCRIPTION

    3.4 TERMINAL BOX

    Robust fabricated steel terminal boxes are

    provided on the side of the motor casing for

    connecting the power supply to the motor.

    Each phase supply cable for the motor enters a

    box at its base and should be sealed by a cable

    gland. Each phase notation is identified by a

    colour coding, Red, Yellow or Blue.

    Bursting discs are fitted to the wall of the

    terminal boxes to relieve excessive pressure

    build up within the box should a flash over

    occur at the terminals.

    Desiccators are fitted to absorb atmospheric

    moisture that may decrease the electrical

    resistance to ground. Each assembly is

    completely enclosed by a bolted on cover.

    3.5 HEAT EXCHANGER

    A heat exchanger (cooler) must be fitted to

    dissipate the heat generated by the motor and

    the heat transferred from the pump casing.

    High pressure outlet and inlet raised facings are

    situated at the bottom and top of the motor case

    respectively for connection to high pressure

    heat exchanger / motor case stub pipes.

    Interconnecting pipework must be short and

    direct with the heat exchanger mounted as high

    as possible to promote good thermosyphon

    circulation when the unit is on hot standby.

    3.6 ALARM SYSTEMS

    3.6.1 Thermometer

    The thermometer instrument is mounted adjacent

    to the motor, and gives visual indication of the

    motor temperature.

    3.6.2 Temperature Switches

    Two temperature switches, remotely mounted,

    are provided for actuating the alarm. When a

    pre-set temperature is reached, the alarm circuit

    is energised via one of the switches. Should the

    motor temperature continue to rise, the second

    switch is activated to de-energise the motor.

    3.6.3 Thermocouples

    A thermocouple is provided for measuring motor

    cavity temperature. Two thermocouples are also

    supplied with weld on pads for measuring the

    skin temperature of the pump case and suction

    manifold. These are to be installed on site by the

    user.

    3.6.4 Instrument Pockets

    Temperature switch, thermometer and

    thermocouple pockets are provided where

    required.

    3.6.5 Differential Pressure Transmitter with

    manifold

    These are to be connected to the process

    connections in the pump case by the user.

    (Customer supply)

    3.6.6 Pressure Gauge

    A pressure gauge is remotely mounted to the

    motor case.

    3.6.7 Flow Meter

    A flow meter is supplied to be fitted in the low

    pressure cooling water return line by the user.

    3.6.8 Ground Detection Relays

    The motor windings should be protected by

    ground detection relays, sufficiently sensitive to

    detect the development of a pinhole or minor

    crack in the stator winding insulation.

    3.5

  • 5/26/2018 CC Pump Manual-Full (Original)

    26/109

    SECTION 4

    INSTALLATION

    CONTENTS

    PARAGRAPH PAGE

    4.1 GENERAL 4.2

    4.2 PUMP CASE INSTALLATION 4.2

    4.3 PREPARATION FOR MOTOR INSTALLATION 4.2

    4.4 MOTOR INSTALLATION 4.4

    4.5 FITTING THE HEAT EXCHANGER 4.5

    4.6 FILLING THE CIRCULATOR WITH BOILER COLD 4.6

    4.7 HYDROTESTING BOILER WITH CIRCULATOR INSTALLED 4.6

    4.8 ELECTRICAL CONNECTIONS 4.8

    4.9 MOTOR PROTECTION 4.9

    ILLUSTRATIONS

    FIGURE 4/1 PUMP CASE INSTALLATION 4.1

    FIGURE 4/2 MOTOR INSTALLATION 4.3

    FIGURE 4/3 TERMINAL BOX 4.7

    FIGURE 4/4 BURSTING DISC ASSEMBLY 4.8

    FIGURE 4/5 EARTH LEAKAGE PROTECTION CIRCUIT DIAGRAM 4.10

    4.0

  • 5/26/2018 CC Pump Manual-Full (Original)

    27/109

    SECTION 4

    INSTALLATION

    Fi ure 4/1 Pum Case Installation

    4.1

  • 5/26/2018 CC Pump Manual-Full (Original)

    28/109

    SECTION 4

    INSTALLATION

    3) The cables, leading to the motor, should be

    flexible and looped immediately prior to

    entering the terminal boxes. The looping

    should be sufficient to accommodate unit

    movement caused by expansion and

    contraction of the boiler pipe work.

    4.1 GENERAL

    WARNING

    The Hayward Tyler boiler circulating pump is

    a precision piece of heavy machinery.

    It should only be installed under the

    supervision of a qualified professional engineer

    who should ensure that the staff directly

    concerned are adequately trained and have

    read and understood this manual.

    4.2 PUMP CASE INSTALLATION (FIG 4/1)

    1) Remove the pump case flange and branch

    covers and clean the pump branches.

    When installing the circulators the following

    conditions MUST be observed.2) Attach shackles and slings to the casing

    eyebolts. A plate on the pump case

    indicates the front of the pump.1) The system pipe work should be adequately

    supported to accept the weight of the

    circulator.3) Raise the case to meet the system pipe

    work, with the suction branch uppermost.

    2) When mounted, the pump should

    accommodate movement in the pipe work

    due to thermal expansion without imposingexcessive loads on the casing and branches.

    4) Ensure that the main motor/case flange is

    horizontal to within 1. Tack weld to thesystem pipe work and re-check the

    horizontal limits.

    3) Sufficient clearance should be allowed

    beneath the motor to permit lowering of the

    motor from the pump case for maintenance.

    (See Section 7 Fig. 7/35.). If removable

    floors or girders etc. are fitted after the

    motor is installed, ensure that the terminal

    boxes or low pressure cooling water supply

    lines will not foul them when the boiler is on

    load and the circulator moves downwards

    due to thermal expansion.

    5) Complete the weld to the procedure

    approved by the boiler manufacturer and test

    radiographically for flaws.

    6) On completion of a satisfactory

    radiographic test, fit any pressure

    differential transmitters using the stub pipes

    on the pump case branches.

    7) Fit the blanking off plate until the motor is

    installed.NOTE:

    Two long lift hoists should be used to

    raise the pump or motor, each hoist being

    capable of taking the full weight of the

    pump or motor

    4.3 PREPARATION FOR MOTOR

    INSTALLATION

    CAUTION:

    The motor should be stored, topped-up with

    inhibitor for as long as possible. If it is

    necessary to install the motor before boiler

    water is available, install in the inhibited

    condition to provide additional protection for

    the motor internal components. However,

    the inhibitor must then be drained

    immediately before mounting the heat

    exchanger.

    4) The pump should be positioned so that the

    N.P.S.H. available exceeds the N.P.S.H.

    specified in the Technical Data - Section 1).

    NOTE:

    When operating at temperature, sub

    cooling of the inlet water is normally

    present and this gives a considerableincrease in the N.P.S.H. available. The

    worst condition is normally operating

    cold. We do not recommend motor installation on

    a Hot Boiler.4.1.2 Installation Notes

    1) Hose down internally, the pump case, the

    valves and adjacent-piping, to ensure the

    removal of all loose debris.

    The following conditions must be observed

    when installing the circulator:

    1) Ensure that the main system is free from

    solids before mounting the circulators.2) Fully close the pump suction and discharge

    valves.2) Permanent insulation should be applied

    only to the pump case. No insulatingmaterial must be applied to the motor case

    or to the main flange studs and nuts, as this

    will cause the motor to overheat.

    4.2

  • 5/26/2018 CC Pump Manual-Full (Original)

    29/109

    SECTION 4

    INSTALLATION

    Fi ure 4/2 Motor Installation

    4.3

  • 5/26/2018 CC Pump Manual-Full (Original)

    30/109

  • 5/26/2018 CC Pump Manual-Full (Original)

    31/109

    SECTION 4

    INSTALLATION

    c) If, after fitting of the heat exchanger,

    running the motor is reasonably

    imminent, and sub-freezing

    temperatures are not envisaged, the

    motor and heat exchanger must be filled

    with treated boiler water or condensate

    within 3 hours of fitting.

    f) Check the gaps every 10 mm, or less,

    during the last 100 mm of the motor

    raising sequence to ensure that the motor

    does not 'cock' or rotate as it is raised.

    Adjust the gap as necessary.

    g) Continue raising the motor until an

    increase in the effort required on thehoists indicates that the gasket is in

    contact with the pump case face. At this

    stage, the gap between the flange faces

    should be approximately 2.5mm and

    should be equal all round the flange.

    4.5 FITTING THE HEAT EXCHANGER

    (CUSTOMER SUPPLY)

    1) Remove the blank flanges from the motor

    high pressure outlet to cooler and fill and

    drain connection.CAUTION:

    If the gap is unequal, the gasket may

    have come out of its recess. If the gap

    is unequal, lower the motor

    sufficiently to check the condition of

    the gasket. If the gasket is damaged -

    renew. Never use any substance onthe gasket to make it adhere to its

    recess.

    2) Ensure that the motor, the heat exchanger

    and the high pressure pipe work and high

    pressure purge lines, have been flushed free

    from all obstructions and foreign matter.

    3) Flush out the secondary cooling watersystem until clear water is discharged.

    4) Mount the heat exchanger onto the motor

    case brackets and proceed.h) Coat the stud threads with high

    temperature anti-seize compound or

    silicon grease and install the nuts by

    hand.

    a) Bring the heat exchanger parallel to the

    motor supporting the weight with the

    lifting tackle.NOTE:

    b) Clamp the heat exchanger to the motor

    by tightening up the securing bolts, nuts

    and washers.

    Do not coat the exposed extended

    diameter threads of the studs as these

    threads are for the tensioner

    application. c) Ensure the motor / heat exchanger

    interconnecting pipe work assembly is

    correct for the circulator.i) Tighten the nuts, using the hydraulic studtensioner in accordance with the

    instructions in Section 8. Remove the

    lifting tackle and removable lifting lugs.

    d) Offer up the interconnecting pipe work

    to the heat exchanger and motor flanges

    and complete all pipe welds and NDE in

    accordance with site approved

    procedures.

    j) Thoroughly flush out the fill and drain

    system piping, to the motor cover and

    when satisfied that the piping is clean,

    connect to the motor cover. 5) Install gauges and recorders for temperature

    and pressure. Connect the low pressure

    cooling systems to the heat exchanger.k) Install the heat exchanger: see Para. 4.5

    l) Install the appropriate thermocouples,

    the thermometer, pressure guage and

    temperature alarm switches.

    6) Fit temporary strainers to the low pressure

    cooling systems, and then check that

    circulation meets the heat exchangerspecification.

    m) Connect the power supply cables to the

    motor terminals, See 4.8.

    7) Close the shut off valve in the high pressure

    fill and purge line and blow down piping.n) Install the vibration pick up probes if

    permanent vibration monitoring is

    required.The motor and heat exchanger circuit must

    now be refilled with inhibitor (See 4.4, Para.

    13 (a) or (b) or with treated boiler water or

    condensate.

    13)

    a) If, after fitting the heat exchanger,

    running is not reasonably imminent, the

    motor and heat exchanger circuit must

    be refilled immediately with inhibitor.

    b) If, after fitting the heat exchanger, sub-

    freezing temperatures are envisaged themotor and heat exchanger circuit must

    be refilled immediately with inhibitor.

    4.5

  • 5/26/2018 CC Pump Manual-Full (Original)

    32/109

    SECTION 4

    INSTALLATION

    5) After connecting the supply, open the heat

    exchanger vent on the high pressure side, fill

    the motor from the bottom and vent air from

    the top, until clean air free water is

    discharged from the vents.

    4.6 FILLING THE CIRCULATOR WITH

    BOILER COLD

    Filling the circulator correctly is a prerequisite to

    ensure satisfactory operation. If air is present in

    the motor it could affect bearing lubrication and

    precipitate bearing failure.

    6) Close the vent on the high pressure side of

    the heat exchanger.

    7) Continue to fill the motor and vent any air

    via the vent connections in the boiler system

    pipe work.

    If air pockets are present in the stator this would

    affect dissipation of heat generated in the

    windings, creating hot spots and consequent

    degrading of the insulating material, and

    ultimately cause winding failure.8) Isolate the now filled circulator.

    9) Ensure that the terminal box is dry and with

    the unit full of water below 20C or at

    normal ambient temperature, using a 1,000

    Volt Megger, check winding resistance to

    ground at the terminals. The resistance

    should exceed 200 megohms.

    Due to the complexity of the passages in the

    motor through which water must flow to displace

    all air, it is necessary to fill the motor very slowly.

    If air pockets are present in the stator this would

    affect dissipation of heat generated in the

    windings, creating hot spots and consequentdegrading of the insulating material, and

    ultimately cause winding failure.

    IF NOT, CALL HAYWARD TYLER.

    DO NOT ATTEMPT TO RUN THE

    MOTOR.The maximum filling rate is 2 litres /min.

    The motor must NOT be filled via the pump

    casing, but only through the filling connector

    located at the motor cover.

    4.7 HYDROTESTING BOILER WITH

    CIRCULATOR INSTALLED

    Treated Water or Condensate Available: -1) Isolate the circulator from the boiler by

    closing appropriate discharge valves. Should the customer wish to hydrotest the

    circulator, the hydrostatic test pressure must not

    exceed the maximum specified in Section 1.2) Supply the low pressure side of the heat

    exchanger as follows: -

    Treated Water Not Available: -a) Open the supply valves in the low

    pressure cooling water system. If the boiler is to be hydrotested at an early state

    of construction, the pump casing can be pressure

    tested without the motor once the blank off plate

    is installed refer to para.4.2.

    b) Flush out the piping for the supply of

    low pressure treated boiler water, or

    condensate, for filling the motor, until

    clean air free water is discharged.4.7.1 Post Hydrostatic Test Procedure

    NOTE:1) Boiler circulators are not to be drained, but

    left filled to a level above the suction

    downcomer.

    The flushing must always be carried out

    before introducing any water through the

    lines to the motor and heat exchanger.

    2) Freezing can be avoided by filling with

    glycol in the concentration detailed inSection 2.

    3) If the low pressure supply contains an

    orifice, check that it is clean and that its flowrate is correct.

    4) Adjust the flow rate to approximately 2

    litres/min.

    4.6

  • 5/26/2018 CC Pump Manual-Full (Original)

    33/109

    SECTION 4

    INSTALLATION

    Fi ure 4/3 Terminal Box

    4.7

  • 5/26/2018 CC Pump Manual-Full (Original)

    34/109

    SECTION 4

    INSTALLATION

    4.8 ELECTRICAL CONNECTIONS

    4.8.1 Power Supply to Motor

    Refer to the terminal box arrangement shown in

    Fig. 4/3.

    WARNING:

    Disconnect the power supply and the starter

    before commencing any work.

    CAUTION:

    Ensure that the cable length will

    accommodate expansion and removal of the

    circulator.

    Ensure that the voltage connected to the

    circulator is the correct operating voltage as

    stamped on the motor nameplate situated on

    the bottom of the motor case.

    1) Remove the nuts and washers, and thenremove the terminal box cover using lifting

    gear, if necessary.

    2) Feed the cable through the conduit entry

    gland and connect to the terminals in the

    phase rotation RED, YELLOW, BLUE (U,

    V or W). When so connected the unit

    will operate in the designed direction, i.e.

    clockwise when viewed from above. All

    connecting cables and links are marked with

    appropriate phase colours.

    3) Earth the circulator adequately. Earthing

    studs are provided on the motor casingadjacent to the terminal box.

    4) Ensure that all electrical connections

    particularly at the terminal box entry gland

    are secure.

    5) Fit the bursting discs to the terminal box as

    follows: -

    NOTE:

    The bursting discs are supplied as loose

    items and are packed separately to

    prevent damage in transit. They are

    fitted to the terminal box on theinstallation of the motor.

    a) Dismantle the bursting disc assembly

    and discard the cardboard sheet fitted in

    lieu of the disc.

    b) Reassemble the bursting disc assembly

    with the bursting disc in place, as

    depicted in Fig. 4/4.

    6) Fit the desiccators, also supplied as loose

    equipment, as follows:-

    a) Check that the desiccator crystals are

    coloured blue.b) If pink, reactivate by placing the

    desiccator in a well ventilated oven

    where it should be maintained at a

    temperature of 110oC until the colour

    reverts to blue. The re-activating time is

    between 1 and 2 hours.

    c) Screw the desiccators into the terminal

    box covers taking precautions not to

    damage the desiccators.

    7) Fit and secure the terminal box covers using

    the nuts and washers previously removed.

    Fi ure 4/4 Burstin Disc Assembl

    4.8.2 Recommended Instrumentation

    It is recommended that the following be

    provided: -

    1) Pump suction and discharge pressure

    gauges.

    2) Continuous record of motor voltage.

    3) Continuous record of motor current.

    4) Ground leakage relay to warn of very low

    winding resistance in order to prevent

    winding insulation failure.

    5) Indication and record of downcomertemperature and pump case temperature.

    This is required to avoid thermal shocks

    when starting a pump on a hot boiler.

    4.8

  • 5/26/2018 CC Pump Manual-Full (Original)

    35/109

    SECTION 4

    INSTALLATION

    4.8.3 Alarm Circuits (Fig.4/5)

    4.9.3 Starting Period ProtectionWARNING:Lethal voltage is present in the alarm system

    when the motor is inoperative. To make the

    circulator safe - open the isolator.

    If the motor fails to start, trip out after a period

    of approximately 5 seconds. The starting

    current is based on a locked rotor test with an

    allowance made for saturation of the magneticcircuit.

    Suitable alarm and trip devices should be fittedto protect the motor and arranged to provide: -

    Motor Starting Current: See Technical Data,

    Section 1.

    1) An alarm - as an indication of motor

    overheat conditions.

    4.9.4 Earth Leakage Protection (Fig. 4/5)2) Motor trip (shut down) - if the temperaturerise continues above the alarm setting.

    Ground detection relays are recommended,

    sufficiently sensitive to sound an alarm if a pin-

    hole or minor crack should develop in the stator

    winding. This protection is arranged in either of

    the ways shown in Scheme A, Scheme B or

    Scheme C.

    The normally advised settings for the protection

    devices are: 57C for alarm and 60C for trip. In

    practice, the alarm setting should be reduced to

    5C above normal motor operating temperature.

    If the neutral point of the supply transformer is

    grounded, a current transformer (CT) is inserted

    into the ground lead, and a relay connected

    across the current transformer secondary, see

    Scheme A.

    4.9 MOTOR PROTECTION

    The following protective devices must be

    provided for the motor: -

    4.9.1 Continuous Overload Protection

    Experience indicates that in the event of a fine

    crack in the stator winding, the resistance to

    ground drops to between 20,000 and 30,000

    ohms. The relay should not trip the motors but

    initiate an alarm.

    The overload trip setting should be 10% above

    the maximum current requirements which could

    occur with the pump running on cold water at

    some other point than the specified duty,

    assuming nominal specified supply voltage. If

    voltage variation can occur, then the trip setting

    should be increased to 15% above maximum

    current value.

    If the neutral point of the supply transformer is

    not grounded, three potential transformers (PT)are connected to the motor leads, with the

    secondaries connected in an open delta, closed

    by the relay winding, see Scheme B. The relay

    should not trip the motors but initiate an alarm.

    NOTE

    Overload relays are now typically calibrated

    in motor full load current (FLC) where the

    relay trips with a current 10% above the

    FLC setting point. Hence the overload relay

    of this type should have a setting point of the

    cold duty current.

    Scheme C shows a core balance earth leakage

    relay system where a core balance current

    transformer encloses supply lines L1, L2 & L3

    supplying the motor.

    Maximum current at nominal voltage: NOTE

    It is important that no earth conductor is

    allowed to be enclosed by the current

    transformer. The earth leakage sensitivityand trip time can generally be selected to

    prevent nuisance tripping. Typical setting

    points are 300 mA and 1 second. This may

    require adjustment depending on supply

    conditions.

    See Technical Data, Section 1.

    4.9.2 Instantaneous Trip Setting

    To allow for transients during the first cycles of

    the starting period, the instantaneous trip should

    be set at 12 times the motor full load current.

    Full Load current: See Technical Data, Section

    1.

    4.9

  • 5/26/2018 CC Pump Manual-Full (Original)

    36/109

    SECTION 4

    INSTALLATION

    4.10

    Figure 4/5 Earth Leakage Protection Circuit Diagram

  • 5/26/2018 CC Pump Manual-Full (Original)

    37/109

    SECTION 5

    COMMISSIONING

    CONTENTS

    PARAGRAP

    HPAGE

    5.1 PRE-START CHECK LIST 5.1

    5.2 INITIAL STARTING-COLD BOILER CONDITION 5.1

    5.3 STOPPING 5.3

    5. 0

  • 5/26/2018 CC Pump Manual-Full (Original)

    38/109

    SECTION 5

    COMMISSIONING

    5.1 PRE-START CHECK When a boiler is started from cold, a minimumof two circulators must be operated. It is

    normal practice to simultaneously warm the

    standby circulators to permit immediate staring

    when required.

    The following pre-start checks must be

    satisfied before starting the motor.

    1) Ensure that the circulator is completely

    vented. CAUTION:

    1. Motors must not be energised if the

    motor cavity temperature is below 2C.

    2) Ensure that the low pressure cooling

    water valves are open and the cooling

    water flow rate agrees with that specified

    in the heat exchanger manufacturer's

    specification. All other valves must be

    closed.

    2. There should be at least ten-minute

    intervals between two repetitive starts.

    This must never be exceeded;

    otherwise the motor winding

    temperature will rise and could

    damage the winding insulation.NOTE:

    If the circulator is to be started on hot

    standby, the pump delivery by-pass

    valves must be open. Refer to the hot

    standby procedure in Section 6.

    3. The motor may be damaged if motor

    temperature exceeds 65C.

    1) Ensure that the motor has been vented asdetailed in Section 4, Para. 4.7.3) Ensure that the high pressure cold water

    purge at 20C maximum temperature is

    connected but isolated. 2) Ensure that a flow of approximately 2

    litres/min., is entering into the motor

    through the low pressure fill line.4) Using a 1000V megger, check that the

    insulation resistance to ground of the

    motor leads conforms to the Winding

    Resistance curve shown in Section 1,

    Fig. 1/2 when measured at the terminal

    stems with the unit full of water below

    approximately 20C, if possible, or at

    normal local ambient temperature.

    3) Ensure that the pre-start checklist, as

    described in Para. 5.1, has been satisfied.

    4)

    a) Release any air trapped below the

    discharge valves by opening valves.

    b) When air-free water is discharged to

    atmosphere, close valves.5) Check that the correct voltage isconnected to the circulator.

    5)6) Check that the electrical supply is

    available at the point of control selected

    and that the starting equipment is

    functioning correctly.

    a) Vent the pump by opening vent

    valves.

    b) When air-free water is discharged

    from vent valve to atmosphere, close

    valves.7) Test the operation of all instrumentation

    and alarms.6) Make sure that the boiler is full and open

    the discharge valves.8) Ensure that sufficient N.P.S.H. is

    available for the pump to run without

    cavitation. NOTE:

    The by-pass valve should never befully closed. It is normally throttled to

    provide a minimal flow between the

    pump suction and discharge system

    9) Start parallel operating boiler circulating

    pumps with the stems of the discharge

    valves withdrawn to prevent overheating

    of the boiler water in the pump case.7) Switch on power to the starter.

    5.2 INITIAL STARTING-COLD BOILER

    CONDITION8) Press the starter button on the control

    console and energise the motor for 5

    seconds only.In systems where the circulators are arranged

    in parallel, to avoid cavitation, sufficient

    circulators must be operated to limit the

    capacity per pump to a value where the

    N.P.S.H. required is less than the amount of

    N.P.S.H. available.

    5. 1

  • 5/26/2018 CC Pump Manual-Full (Original)

    39/109

    SECTION 5

    COMMISSIONING

    5. 2

    CAUTION:

    The motor runs up to full R.P.M. in

    appropriately one second. If the

    motor fails to start after five seconds,

    press the stop button and do not

    attempt to restart the circulator for 20minutes.

    9) After ten minutes pause, run the

    circulator for a further (2nd) five

    seconds. During this run, check the

    following:-

    a) Motor Current (after ammeter has

    come off initial surge of current)

    b) Differential pressure - when the

    check valves open, the differential

    pressure should rise immediately to

    approximately 3 bars.

    NOTE:

    If the differential pressure does not

    rise, stop the motor immediately; it

    may be an indication that the motor is

    running in reverse. Reverse rotation

    will result in approximately 30% less

    head generated and about 10% more

    power absorbed than specified.

    10) After a further (3rd) ten-minute pause,

    repeat operation (9).

    11) After another (4th) ten-minute pause,

    energise the motor and run for twentyminutes. During this running period,

    carry out the following checks:-

    a) Check the motor for vibration, using

    a vibration detector, several times and

    record reading for future comparison.

    b) Check for rubbing or excess bearing

    noise by holding a listening rod

    against the pump and motor case.

    c) Check the motor operating

    temperature at regular intervals.

    Initially it should rise several degrees

    then stabilise. If necessary, adjust thesecondary cooling water flow after

    checking that the strainers are not

    obstructed.

    d) Check, as the motor warms, that the

    high pressure circulation pipe entering

    the heat exchanger from the top of the

    motor becomes warmer than the high

    pressure circulation pipe from the

    bottom of the heat exchanger to the

    motor case. This indicates correct

    functioning of the heat exchanger.

    e) Check that motor current anddifferential pressure readings several

    times and record the readings.

    12) When the motor temperature has

    stabilised: -

    a) Adjust the high temperature alarm

    setting to 10% above this point, or to

    57C, whichever is the lower. Thetrip setting must never exceed 60C.

    b) Make adjustment to other

    instrumentation as necessary.

    c) Check all flanges, glands and valves

    for leaks.

    d) As the boiler water temperature

    increase, its specific gravity decreases

    and the amount of N.P.S.H., available

    increases. The temperature of the

    high pressure water to the heat

    exchanger may alter due to lower

    losses in the motor, or because ofincreased heat flow from the pump.

    NOTE:

    It is normal procedure to commission

    circulators separately, but if required,

    before the last circulator is stopped,

    the others may be energised and their

    recordings taken after each one is

    brought on-line.

    5.3 STOPPING

    1) Press the stop button on the control

    console. The run-down time isapproximately 2.5 seconds.

    2) Close the discharge valves.

    3) Maintain the low pressure cooling water

    supply to the heat exchanger.

    NOTE 1:

    If the circulator is to stand idle for

    some considerable time with the boiler

    cold, the low pressure cooling water to

    the heat exchanger may be turned off,

    especially on systems where the

    cooling water runs to waste.

    NOTE 2:

    On hot boilers, and whenever the

    circulator is run, the low pressure

    cooling water to the heat exchanger

    must always be on.

    CAUTION:

    If the circulator is to be idle for an

    extended period, and be subjected to

    freezing temperatures, make sure that

    provision is made to protect the

    motors from freezing (see Section2.2.2.)

  • 5/26/2018 CC Pump Manual-Full (Original)

    40/109

    SECTION 6

    OPERATION

    CONTENTS

    PARAGRAP

    HPAGE

    6.1 STARTING THE CIRCULATOR 6.1

    6.2 SHUTTING DOWN THE CIRCULATOR 6.2

    6.3 ROUTINE CHECKS AND OPERATIONAL CONDITIONS 6.3

    6.4 FAULT FINDING 6.5

    ILLUSTRATIONS

    Figure 6/1 FAULT LIST CHART 6.6

    6.0

  • 5/26/2018 CC Pump Manual-Full (Original)

    41/109

    SECTION 6

    OPERATION

    Any of the following conditions may exist

    when putting a circulator into service. Follow

    the relevant procedures below and refer to 6.3

    for routine checks and operational fault action.

    6) Ensuring the boiler is still full, energise

    the second duty circulator on line and run

    up to speed.

    7) Perform the operational checks below.

    Refer also to Para. 6.3.

    6.1 STARTING THE CIRCULATOR a) Amperage.

    b) Motor cavity temperature on alarm

    thermometer.6.1.1 Boiler Cold - Circulator Cold and

    Filled (Boiler Start-Up).c) Differential pressure.

    1) Ensure that the pre-start checklist, 5.1 is

    satisfied. d) Low pressure cooling flow and

    temperature.2) Vent the motor as follows: -

    e) Vibration.a) Release any air trapped below the

    suction by opening the by-pass valves

    and the filling valves.

    f) Drum level.

    g) Valve and gland leakage.

    8) Energising other motors: When the

    boiler differential pressure parametersrequire the other circulators to be

    energised: -

    b) When air-free water is discharged

    through the vent valve, close ventvalve.

    3) Vent the pump as follows: -a) Check that the differential

    temperature, between the pump case

    and boiler water in the downcomers,

    is within 28C.

    a) Open the vent valve.

    b) When air-free water is discharged

    from vent valve, close vent valve and

    filling valves.b) Energise the other motors.

    c) Open the stems of the discharge

    valves.c) Close by-pass valves on the newly

    energised pump(s).

    CAUTION: d) Perform the operation checks on the

    newly energised pump as detailed in

    para.6.1.1 (7).

    The pump must always be re-vented in

    this manner prior to starting when thedrum pressure is below 3.5 kg/cm

    2.

    6.1.2 Boiler Hot - Circulator Hot and

    Filled (Hot Standby)NOTE:The motor starting procedure following

    is based on a normal boiler starting

    procedure where usually two circulators

    are initially operated with the remainder

    brought-on line as required.

    NOTE:

    The low-pressure coolant to the heat

    exchanger must be on.

    1) Check the differential temperature

    between the pump case and the boiler

    water in the downcomers.4)

    a) On circulators that will not be

    energised, open the pump discharge

    by-pass valves. This ensures that asthe boiler heats up, a flow passes

    from the discharge legs to the pump

    case and impeller etc.

    CAUTION:

    The differential temperature between thepump case and the boiler water in the

    downcomers must not exceed 28C. Non-

    adherence to this may cause thermal

    shocks and damage to occur.b) Check the motor temperature on the

    alarm thermometer; this should not

    exceed 49C or be less than 5C.2) Energise the motor.

    3) Close by-pass valves.5) Energise the first motor. The current will

    drop from full starting current after a few

    seconds to approximately the value

    corresponding to the operating point on

    the makers test curve.

    4) Check circulator operation as detailed in

    para.6.1.1 (7).

    6.1

  • 5/26/2018 CC Pump Manual-Full (Original)

    42/109

    SECTION 6

    OPERATION

    6.1.3 Installation on a Hot Boiler 6) Check the pump case temperature as thepump case is cooling to ensure that the

    cooling rate does not exceed 120C per

    hour. If necessary, correct the cooling rate

    as follows:

    NOTE:

    Not recommended for safety reasons but

    not possible on this installation since no

    suction valves are fitted and hence pumps

    cannot be isolated. a) Cooling rate too fast: - If the pumpcase cooling rate is too fast, slow the

    cooling rate by partially opening the

    by-pass valves as necessary.6.2 SHUTTING DOWN THE

    CIRCULATOR b) Cooling rate too slow: - If the pumpcase cooling rate is too slow, increase

    the rate by injecting a high pressure

    purge as detailed in Para. 6.3.8.

    CAUTION

    Low pressure cooling water flow and motor

    temperatures must always be within the

    specified limits, whenever the circulator is

    on hot standby.7) When the pump case has cooled to 45C

    de-pressurise the circulator as follows: -

    a) Ensure the pump discharge by-pass

    valves and shut-off valve are closed.6.2.1 Boiler Hot - Circulator to go on Hot

    Standbyb) Slowly depressurise the circulator by

    closing the pump suction by-pass

    valve and partially opening the pump

    and suction leg vent valve.

    1) Press the stop button on the control

    console.

    2) Ensure that the low-pressure cooling line

    valves are open. c) Open the motor cavity pressure

    gauge shut-off valves and check the

    pressure on the motor cavity gauge.

    When the pressure has stabilised,

    close the pump suction leg vent valve.

    3) Open by-pass valves to provide

    circulation of high temperature boiler

    water through the pump casing, suction

    and discharge lines.d) Re-check that the pressure does not

    increase. Should it increase, check the

    following: -

    6.2.2 Boiler Hot - Circulator to be Isolated

    for Maintenance

    i) Make sure that all valves between

    the circulator and high-pressure

    system are closed.

    1) Press the stop button of the control

    console to de-energise the motor.

    2) Close the stems on the discharge valves.ii) De-pressurise the circulator

    again, if necessary.3) Close the pump jumper line service

    valves.8) On completion of depressurising, the

    motor is ready for removal.4) Crack open the pump suction bypass

    valves to prevent a vacuum forming in the

    pump case during the circulator cooling

    process.

    CAUTION

    The low pressure cooling water must

    be maintained until the motor has been

    separated from a hot pump case.5) Maintain the low pressure cooling

    system to the heat exchanger, via the lowpressure flowrator valves in the cooling

    pipes open until the motor has been

    separated from the pump.

    6.2.3 Boiler Cold

    1) Press the button on the control console.

    2) Leave open the low pressure cooling

    water line valves.CAUTION:

    Keep a close watch on the motor cavity

    temperature, should the temperature

    increase, apply a high-pressure purge as

    described in para. 6.3.8.

    3) Pump discharge valves may be left open.

    6.2

  • 5/26/2018 CC Pump Manual-Full (Original)

    43/109

    SECTION 6

    OPERATION

    3) If temperature increase continues and

    exceeds the 60C - trip setting - and the

    cause cannot be detected or the condition

    corrected, refer to the relevant shutdown

    procedure in Para. 6.2. If necessary, blowdown the boiler system or apply a high-

    pressure purge to the motor. See 6.3.8.

    6.3 ROUTINE CHECKS AND

    OPERATION CONDITIONS

    (Also see fault list chart)

    6.3.1 Supply Current

    1) Check the motor running current each

    shift. The current should be constant and

    comply with that specified in section 1. a) After cooling and draining, removeand disassemble the motor andexamine for worn bearings, blocked

    internal strainer, motor passages,

    auxiliary impeller and fouled cooling

    surfaces. In addition, leaks in the heat

    exchanger.

    NOTE:

    High amperage readings or fluctuating

    motor currents indicate wear or partial

    seizure at the bearing or wear ring

    surfaces. This condition can cause

    vibration necessitating motor removal

    strip and re-installation.4) Should the alarm sound whilst the

    circulator is on stand-by, start the

    circulator to accelerate internal highpressure cooling water flow. Check

    possible causes for temperature increase

    as above. The circulator should be tripped

    if the temperature exceeds 60C and the

    shutdown / purge procedure 6.2 carried

    out.

    6.3.2 Motor Temperature

    1) During normal operation, the motor

    temperature should be checked at weekly

    intervals. The thermometer is originally

    set to initiate an alarm if the motor cavity

    temperature reaches 57C and to de-

    energise the motor if the temperature

    reaches 60C. If desired, the

    aforementioned alarm temperature

    settings may be lowered, on the

    temperature alarm thermometer, to suit

    normal operation but only after the boiler

    and circulator has been operated longenough to stabilise.

    6.3.3 High Temperature Alarm and Trip

    Settings

    At weekly intervals check that the motor

    high temperature alarm setting does not

    exceed 57C or 5C above normal operating

    Temperature (whichever is the lower) andthat the trip setting does not exceed 60C.

    Re-set if necessary.2) Immediately investigate the following

    possible causes for high temperature

    alarm sounding: - 6.3.4 Pump Head and Quantity1) Check the total head generated by each

    pump at weekly intervals.CAUTION

    Do not stop the motor.

    2) Correct possible causes of decrease in

    head and quantity as follows: -a) Check the low pressure cooling water

    supply for adequate flow, temperature

    vapour locks and leakage in piping

    (see 6.3.7.).a) The gate valve in the circulating

    pump suction line and the check valve

    in the circulating pump discharge

    lines are not fully open. Check and

    adjust the setting as necessary.

    b) Check the circulator for leaks fromthe motor casing, high pressure fill

    and drain cooling water connections,

    particularly the motor fill and purge

    line shut-off valves and the motor

    drain valves.

    b) Discharge through the pump and

    suction leg vent or the pump casing

    and suction leg drain valves. Ensure

    both are closed.c) Check that the cooling water strainers

    are not obstructed. c) Low N.P.S.H., available due to

    reduced water level in the steam

    drum, changes in system pipework or

    system blockage. Check and adjust

    the number of circulators operating to

    suit until the fault can be corrected.

    d) Check for indication of bearing

    damage (noise, vibration).

    6.3

  • 5/26/2018 CC Pump Manual-Full (Original)

    44/109

    SECTION 6

    OPERATION

    d) Vent the pipe system to remove

    vapour locks.

    f) Electrically induced vibration also a

    factor, i.e. Rotor bar breakage etc.e) Power supply and reverse rotation

    checks are given in 5.5.1 (5) and 5.2

    (9).

    NOTE:

    When (e) is the cause, the motor must be

    removed, as detailed in section 7.2,

    before repairs can be undertaken.f) Worn wear rings and a blocked ordamaged impeller can be corrected

    only after removing the motor

    assembly from the pump case.

    Clearances are specified in section 1.

    6.3.7 Low Pressure Cooling Water Supply

    Failure.

    If the cooling water to the heat exchanger is

    lost while the circulator is at operating

    temperature, the motor must be de-energised

    within five minutes and the suction and

    delivery valves closed as soon as possible.

    6.3.5 Insulation Condition

    Before initially energising the motor and

    thereafter at monthly intervals, check the

    following: -CAUTION

    1) The insulation resistance to ground of the

    motor leads.Damage to the windings may occur if:

    a) the motor remains in operation after 5

    minutes from the loss of cooling water.a) With the unit filled with water below20C or at normal local ambient

    temperature, the resistance measured

    at the terminal links, using a 1000V

    megger, must exceed 200 megohms.

    Or

    b) if the cooling water is not

    restored before the motor

    temperature rises above 60C.

    NOTE:CAUTIONThe insulation resistance of the stator

    winding varies with temperature and

    must always be measured cold 20C or at

    normal local ambient temperature.

    Do not attempt to operate the motor by

    overriding the temperature controller trip

    mechanism and restore the low pressure

    cooling water as quickly as possible.

    Damage to the windings may occur if the

    cooling water is not restored before themotor temperature rises above 60C.

    2) Ensure that the interior of the terminal

    box is dry, especially the insulation

    projecting over the gland stems.

    6.3.6 Vibration NOTE:Before re-starting a circulator after an

    emergency shutdown, low pressure cooling

    water must be supplied to the pump to

    reduce the motor temperature to at least

    38C.

    Check the circulators for excessive noise or

    vibration, which can be either hydraulic or

    mechanical in origin.

    Vibration should be monitored and recorded

    daily. If a permanent vibration transducer is

    not installed, check at weekly intervals

    using temporary pick-ups. If the reading

    increases, check for the following causes: -

    6.3.8 High Pressure Purge Supply To

    Motor.

    On some boiler installations the motor fill

    and drain connection may be connected to ahigh pressure cold purge system which can

    be used for emergency motor cooling and to

    protect the motor during boiler cleaning.

    During normal operation this purge supply

    must be isolated with a double isolation

    valve fitted to the motor, as any leakage or

    reverse flow from this point can result in

    motor overheating, winding and / or bearing

    damage. (Reverse flow totalling no more

    than 2 3 litres is sufficient to cause

    damage).

    a) Cavitation due to low N.P.S.H., asdescribed in 6.3.4.

    b) Unequal settings of the discharge

    valves. Check and re-set in the fully

    open position.

    c) Incorrect directional rotation as

    described in section 5.2, para. 9.

    d) Excessive pipe strain on the pump

    casing due to expansion or inadequate

    support of pipes. Eliminate any strain

    by providing adequate support.

    e) Damaged or unbalanced rotor or

    impeller, worn bearings, excessiveend float or incorrect impeller setting.

    6.4

  • 5/26/2018 CC Pump Manual-Full (Original)

    45/109

    SECTION 6

    OPERATION

    NOTE:If the boiler is laid-up under a nitrogen

    blanket, take necessary precautions to

    prevent damage to the motor through

    gaseous water. Any pump start-up, when

    the boiler is in this condition, must be

    undertaken and initial start and the full filland vent procedure, as detailed in section

    4.7, must be followed.

    Continuous purging of the motor during

    operation is recommended only during

    boiling-out and acid cleaning. A purge rate

    of 3.8 litres / min., is normally sufficient to

    prevent the ingress of harmful fluids andsolids into the motor.

    1) Flush down the fill and purge system to

    ensure the line is clean.6.3.10 Boiler Cleaning

    2) Check that the low pressure cooling

    water supply valves are open.During any boiling-out or acid cleaning

    operation of the boiler, the de-energised

    circulators must be isolated completely prior

    to introducing any chemicals to the boiler.

    The circulators must be continuously purged

    with clean cool water at a pressure of

    approximately 7 bar, in excess of the existing

    drum pressure to eliminate infiltration ofcontaminated water into the bearing and

    motor components.

    3) Introduce high pressure purge through

    the filling valves. Check that the purge

    temperature does not exceed 49C and

    that the purge pressure is above the boiler

    pressure.

    6.3.9 Extended Shut-Down

    When the circulator remains shutdown for

    an extended period: -CAUTION

    Severe damage can be caused if acid is

    allowed to enter the motor. If

    contamination from acid cleaning is

    suspected, motor must be purged

    immediately with clean water and

    inspected for damage.

    1) Check regularly that it remains full of

    water.

    2) Run the circulator for a minimum of ten

    minutes every two months.

    CAUTION

    If the motor is to be subjected to extreme

    low temperature, the motor must be

    prevented from freezing, see section 2.2. (5)6.4 FAULT FINDING

    Refer to the fault list chart that follows.

    6.5

  • 5/26/2018 CC Pump Manual-Full (Original)

    46/109

    SECTION 6

    OPERATION

    Fi ure 6/1 Fault List Chart

    6.6

  • 5/26/2018 CC Pump Manual-Full (Original)

    47/109

    SECTION 7

    MAINTENANCE

    7.0

    CONTENTS

    PARAGRAPH

    PAGE

    7.1 INTERNAL INSPECTION 7.3

    7.2 MOTOR REMOVAL 7.3

    7.3 DISASSEMBLY 7.4

    7.4 INSPECTION OF COMPONENTS 7.16

    7.5 ASSEMBLY NOTES 7.27

    7.6 ASSEMBLY 7.29

    7.7 RE-INSTALLATION OF MOTOR 7.42

    PARTS LIST GENERAL 7.43

    ILLUSTRATIONS

    FIGURE 7/1 MOTOR REMOVAL 7.2

    FIGURE 7/2 MAIN IMPELLER REMOVAL 7.5

    FIGURE 7/3 TERMINAL BOX 7.6

    FIGURE 7/4 UP - ENDING THE MOTOR 7.7

    FIGURE 7/5 TYPICAL WORKING PLATFORM 7.8

    FIGURE 7/6 MOTOR COVER AND FILTER REMOVAL 7.9

    FIGURE 7/7 THRUST BEARING 7.10

    FIGURE 7/8 COVER END JOURNAL BEARING ASSEMBLY - REMOVAL 7.11

    FIGURE 7/9 ROTOR ASSEMBLY - REMOVAL 7.12

    FIGURE 7/10 TERMINAL GLAND REMOVAL 7.13

    FIGURE 7/11 STATOR ASSEMBLY - REMOVAL 7.14

    FIGURE 7/12 JOURNAL BEARING TILTING PADS - REMOVAL 7.15

    FIGURE 7/13 JOURNAL BEARING CLEARANCE 7.16

  • 5/26/2018 CC Pump Manual-Full (Original)

    48/109

    SECTION 7

    MAINTENANCE

    7.1

    FIGURE 7/14 JOURNAL BEARING SLEEVE - REMOVAL 7.17

    FIGURE 7/15 THRUST BEARING CLEARANCE 7.18

    FIGURE 7/16 IMPELLER AND CASE WEAR RING 7.19

    FIGURE 7/17 DETAILS OF TAPING HOOK 7.22

    FIGURE 7/18 DETAILS OF TAPING NEEDLE 7.22

    FIGURE 7/19 OUTER COIL TAPING 7.23

    FIGURE 7/20 INNER COIL TAPING 7.24

    FIGURE 7/21 TYPICAL KNOT SEALING 7.26

    FIGURE 7/22 ASSEMBLY OF FLANGE STUDS 7.27

    FIGURE 7/23 WIRE LOCKING 7.28

    FIGURE 7/24 JOURNAL BEARING - ASSEMBLY 7.29

    FIGURE 7/25 STATOR ASSEMBLY 7.30

    FIGURE 7/26 JOURNAL SLEEVE 7.31

    FIGURE 7/27 TERMINAL GLAND ASSEMBLY 7.32

    FIGURE 7/28A COVER END BEARING ASSEMBLY 7.33

    FIGURE 7/28B COVER END BEARING ASSEMBLY 7.33

    FIGURE 7/28C COVER END BEARING ASSEMBLY 7.34

    FIGURE 7/29 END FLOAT CHECK 7.35

    FIGURE 7/30 MOTOR COVER AND FILTER ASSEMBLY 7.37

    FIGURE 7/31 TERMINAL BOX 7.38

    FIGURE 7/32 TERMINAL LINK INSULATION 7.39

    FIGURE 7/33 BURSTING DISC DETAILS 7.40

    FIGURE 7/34 IMPELLER SETTING 7.41

    FIGURE 7/35 GENERAL ARRANGEMENT 7.47

    FIGURE 7/36 SECTIONAL ARRANGEMENT 7.48

    FIGURE 7/37 TERMINAL BOX ARRANGEMENT 7.49

    FIGURE 7/38 TOOL KIT LIST 7.50

  • 5/26/2018 CC Pump Manual-Full (Original)

    49/109

    SECTION 7

    MAINTENANCE

    7.2

    Fi ure 7/1 Motor Removal

  • 5/26/2018 CC Pump Manual-Full (Original)

    50/109

    SECTION 7

    MAINTENANCE

    7.3

    NOTE 1:

    Some of the illustrations shown are typical

    only and not necessarily specific to the

    circulator described, i.e. motor proportions

    and number of studs etc., but indicate

    generally the basis of the unit breakdown.

    NOTE 2:

    For items not annotated on the drawingswithin the text refer to the Main Sectional

    Arrangement at the rear of the Section.

    NOTE 3:

    A tool kit is supplied with each circulator

    contract, containing specialised tools

    necessary for the disassembly and assembly of

    the motor.

    7.1 INTERNAL INSPECTION

    Internal inspection of the circulator should becarried out to the recommendation of the station

    maintenance authority.

    Partial inspection of the internal filter and thrustbearing is possible in-situ after removal of themotor cover.

    WARNING:

    Inspection must only be carried out with the

    circulator isolated from the electrical supply,

    depressurised and the motor cover removed

    as in Section 7.3.4.

    A full inspection requires the motor assembly tobe removed as described below.

    7.2 MOTOR REMOVAL (FIG. 7/1)

    WARNING:

    Before removing the motor, the circulator

    must be completely isolated from the system,

    depressurised and cooled as described below.

    7.2.1 Motor Removal

    1) Isolate the electrical supply; disconnect allinstrument cables from the motor identifyingthe connections and leads.

    2) Remove the terminal box covers anddisconnect the external power supply cables

    from the terminal box as described in 7.3.4,identifying each lead for reassembly.

    3) If hoses are not fitted in the low pressurecooling system, adjacent to the heatexchanger, with sufficient slack to allow themotor to be separated from the pump case, fittemporary hoses as follows:-

    a) Close the low pressure cooling watershut-off valves.

    b) Immediately secure temporary coolingwater hoses to the inlet and outletconnections of the heat exchanger tomaintain a low pressure cooling waterflow within the heat exchanger.

    c) Maintain cooling water until the motor isseparated from the pump.

    CAUTION:The low pressure cooling water flow, and

    motor temperature must be maintained

    within the specified limits, whenever the

    motor is in contact with the pump case.

    4) Check the pressure gauges to ensure that thecirculator is depressurised.

    5) Make sure that the discharge valves, thesuction valve, the by-pass valves and theshut-off valves are closed to isolate thecirculator from the boiler and fill system.

    6) Drain the pump casing.

    WARNING:Never drain the pump casing through the

    motor fill & drain line as this could cause

    contamination of the motor.

    7) Fit the removable lifting lugs to the weldedbrackets on the motor case.

    8) Set up two chain hoists and rigging, ofsufficient capacity for each to take the fullweight of the motor, and connect to thelifting lugs.

    WARNING:

    Normally two hoists are used for removing

    the motor and because the load can shiftfrom one hoist to the other during the

    removal, each hoist must be capable of

    taking the full weight of the motor.

    9) Take the initial strain of the motor.

    CAUTION:

    The motor must be removed from the

    pump casing without a break in the

    sequence (9) and (11).

    10) Loosen the pump/motor flange stud nuts inaccordance with the hydraulic studtensioning instructions - section 8.

    CAUTIONAlways double check that the motor and

    pump case are cooled and depressurized

    before loosening the studs nuts.

    11) Disconnect the fill and drain line upstreamof shut-off valve if there is not sufficient playin the line to permit motor removal.

  • 5/26/2018 CC Pump Manual-Full (Original)

    51/109

    SECTION 7

    MAINTENANCE

    7.4

    12) Remove the flange stud nuts and lower themotor clear of the pump casing, keeping theflange faces parallel until the impeller isclear of the pump casing.

    13) When the impeller is clear of the pump case,check the motor cavity temperature. Whenthe temperature falls below 54

    oC remove all

    instruments and store safely.14) Lower the motor to the floor.

    15) Drain the motor via the drain valve andremove the valve and pipework

    16) Remove the heat exchanger from the motor,in accordance with site procedures, asdescribed in 7.2.1.

    CAUTION:

    To prevent damage never stand or turn

    the motor on either the drain valves or

    terminal box.

    17) Lower the motor to the horizontal positionto give access to the terminal box, removethe lifting tackle and cover all joint faces andopenings with clean rags.

    18) If necessary, transport the motor to aworking area where adequate facilities areavailable for disassembly, inspection andmaintenance.

    7.2.1 Heat Exchanger Removal

    NOTE:

    As the heat exchanger is welded to the motor

    case via the interconnecting pipework,

    removal of the heat exchanger is at the

    discretion of, and the procedure will bedetermined by, the senior station engineer.

    Check the heat exchanger during the firstmotor maintenance removal for build up ofsediment in the shell base; this will provide aguide to any future attention that may berequired.

    7.3 DISASSEMBLYCAUTION:

    Lifting tackle must not be attached to the

    protruding rotor shaft nor must the shaft be

    subject to any shock loads.The motor must be adequately supported

    before and during any disassembly.

    7.3.1 Case Wear Ring

    1) The case wear ring can be left in place,bolted inside the pump case.

    2) To remove the wear ring, remove the sixscrews securing the wear ring inside thepump casing. Carefully lower the wear ringfrom its location within the casing.

    Lower to ground level, and store in a safeplace for inspection.

    7.3.2 Impeller (Fig. 7/2)

    1) Unlock the punch marks and remove theimpeller cap screw.

    2) Remove the LEFT-HAND threaded impellernut using the special spanner and tommy barprovided in the tool kit.NOTE:

    Do not use any leverage in the water

    passages of the impeller to oppose force

    exerted on the special spanner; the weight

    of the rotor will oppose rotation if the

    tommy-bar is given a few heavy blowswith a lead faced hammer.

    If the nut shows any tendency to seize onthe shaft, do not continue to exert force,

    but drill and split the nut to remove.

    3) Fit the puller, provided in the tool kit, to thetapped holes in the top of the impeller boss,using the applicable studs and nuts in the toolkit. Withdraw the impeller from the motorshaft.

    4) Withdraw the impeller washer and removethe impeller key.

    5) Immediately refit a serviceable impeller nutto permanently protect the shaft threads.

    7.3.3 Baffle Wear Ring

    Examine the baffle wear ring. If damaged,remove the socket headed cap screws and lockwashers. Remove the wear ring for a fullerinspection or renewal

    7.3.4 Terminal Boxes (Fig. 7/3)

    1) Remove the nuts and washers from the studsand remove the terminal box cover.

    2) Remove the nuts and washers from theterminal studs.

    3) Identify the motor supply cable links for

    reconnection.

    4) Carefully cut the insulation from around thecable connections and links.

    CAUTION:

    Do not damage the link insulation.

    5) Remove the washers and the nuts from theterminal stem as the link is removed.

  • 5/26/2018 CC Pump Manual-Full (Original)

    52/109

    SECTION 7

    MAINTENANCE

    7.5

    6) Remove the nuts and washers from theterminal box support studs. Using liftingtackle, lift off the terminal boxes and removethe gaskets.

    NOTE:

    A small metal cover should be fabricated

    and placed over the terminal stems to

    protect them during motor repair.

    Fi ure 7/2 Im eller Removal

  • 5/26/2018 CC Pump Manual-Full (Original)

    53/109

    SECTION 7

    MAINTENANCE

    7.6

    Fi ure 7/3 Terminal Box

  • 5/26/2018 CC Pump Manual-Full (Original)

    54/109

    SECTION 7

    MAINTENANCE

    7.7

    Fi ure 7/4 U -Endin the Motor

  • 5/26/2018 CC Pump Manual-Full (Original)

    55/109

    SECTION 7

    MAINTENANCE

    7.8

    7.3.5 Motor Cover and Filter (Fig. 7/6)

    1) Using two cranes and lifting tackle attach onewith shackles to the motor cover and theother via a sling around the motor flangeneck. Lift and up-end the unit as depictedFig. 7/4 until the motor is vertical, with themotor cover uppermost. Lower the motorpump flange on to a suitable building stand;a typical building stand is shownin Fig. 7/5.Support the rotor shaft beneath the standusing a screw or hydraulic jack. Care must betaken to avoid damaging the shaft or flangefaces. If a pit is not available, erect a suitableworking platform, similar to that depicted inFig. 7/5.CAUTION:

    Firmly support the impeller end of therotor shaft on a suitable wooden block

    when placing the motor on the stand and

    jack so that when the thrust nut is

    removed during a subsequent operation,

    the rotor will be adequately supported.

    2) Mark the cover relative to the motor case toensure correct alignment on reassembly.

    3) Using the stud tensioning equipment (Section8), release the tension of the motor cover nutsand remove the nuts.

    4) Attach the lifting tackle and carefully remove

    the motor cover from the motor case.5) Remove the flexitallic spiral wound gasket

    and before discarding, inspect the gasket forany unusual markings or depressions thatindicate a seat dressing is required.

    6) Remove the filter by removing the hexagon-headed screws and lock washers.

    Figure 7/5 Typical Working Platform

  • 5/26/2018 CC Pump Manual-Full (Original)

    56/109

    SECTION 7

    MAINTENANCE

    7.9

    Fi ure 7/6 Motor Cover and Filter Removal

  • 5/26/2018 CC Pump Manual-Full (Original)

    57/109

  • 5/26/2018 CC Pump Manual-Full (Original)

    58/109

    SECTION 7

    MAINTENANCE

    7.11

    7.3.7 Cover End Journal Bearing

    Assembly (Fig. 7/8)

    1)

    a) Remove the locking wire and the stator

    lock ring hexagon headed screws.b) Push down the stator lock ring sufficiently

    to permit split ring to be prised out of itsgroove.

    c) Remove the split ring from its casinggroove, using screwdrivers as levers.

    d) Withdraw the stator lock ring, usingscrews as lifters, from the motor case.

    2) Match-mark the cover end bearing housingand the motor case to ensure that they are re-fitted in their original radial location.

    3) Remove the bearing housing securing screws

    and lock washers.4) Attach eyebolts and lifting tackle to the cover

    end bearing housing and lift the housing,complete with the journal bearing assembly,to just above the motor casing.

    5) Lower the bearing housing and remove anddiscard the `O` ring.

    6) Place the housing in a clean and safe placefor subsequent disassembly.

    Fi ure 7/8 Cover End Journal Bearin Assembl - Removal

  • 5/26/2018 CC Pump Manual-Full (Original)

    59/109

    SECTION 7

    MAINTENANCE

    7.12

    7.3.8 Motor Shaft (Fig. 7/9)

    1) Fit an eyebolt, supplied in the tool kit, andlifting tackle to the rotor shaft as indicated.With an exact vertical lift, slowly lift therotor out of the stator, taking particular carenot to damage the cable ends whilst doing so.

    2) Lower the rotor into the horizontal positionand position it carefully on to wooden 'V'blocks at floor level. Fit suitable protection,i.e. clean rags, over the journal sleeves. Refitthe thrust nut to protect the threads.

    7.3.9 Terminal Gland Removal (Fig. 7/10)

    1) To facilitate re-assembly, identify eachterminal stem body and its respectiveposition.

    CAUTION

    Make sure that the gland moulding doesnot turn with the gland nut by holding the

    moulding stationary using a clamp

    connector and the connecting link.

    2) Remove the nuts and link from the terminalblock. Unscrew the gland nut and tap theconnector lightly until the gland assemblycan be carefully drawn out of the motor case.

    3) Remove the gland nuts from two of the stemsand placed on the third stem.

    4) Replace the clamp connector over this stemand undo the cable gland nut. This actionwill draw the gland assembly from the motorcase.

    5) Remove the inner casing & the C shapedsupport ring. The two belleville washers andback up sleeve remain on the cable.

    NOTE:

    The terminal gland stems are