Upload
narupatil
View
215
Download
0
Embed Size (px)
Citation preview
8/7/2019 cba_toolkit
1/3
DEPIT Project Cost-Benefit Analysis
Tangible Changes
P Division/Office:Division of X Project: Project X
Program(s) Title:Program Y Project Sponsor: Jane Doe
Tangible Changes in Program Operations resulting from Project Implementation
Program Operational Cost Elements FY FY FY FY FY
Changes in Program Operational Costs (Negative Values = Decr 2010-11 2011-12 2012-13 2013-14 2014-15 TOTAL
$ $ $ $ $ $
$ $ $ $ $ $
0.00 0.00 0.00 0.00 0.00 0.00
$ $ $ $ $ $
0.00 0.00 0.00 0.00 0.00 0.00
$ $ $ $ $ $
0.00 0.00 0.00 0.00 0.00 0.00
$ $ $ $ $ $
$ $ $ $ $ $
C-1. Contractor Services $ $ $ $ $ $
C-2. Maintenance & Support Services $ $ $ $ $ $
C-3. Network / Hosting Services $ $ $ $ $ $
C-4. Data Communications Services $ $ $ $ $ $
C-5. Other Specify $ $ $ $ $ $
$ $ $ $ $ $
D-1. Hardware $ $ $ $ $ $
$ $ $ $ $ $
D-3. Other Specify $ $ $ $ $ $
$ $ $ $ $ $
E-1. Training $ $ $ $ $ $
E-2. Travel $ $ $ $ $ $
E-3. Other Specify $ $ $ $ $ $
$ $ $ $ $ $
F. Revenues / External Contribution / Fiscal Offsets $ $ $ $ $ $
F-1. Revenues Specify $ $ $ $ $ $
F-2. Federal ParticSpecify $ $ $ $ $ $
F-3. Grants Specify $ $ $ $ $ $
$ $ $ $ $ $
Cumulative Change $ $ $ $ $
Character of Program Cost Change Estimate
Choose Type
Detailed/Rigorous
Not to Exceed
Order of Magnitude
A. Personnel -- Operational Costs
A-1.a. State FTEs (Salaries & Benefits)
A-1.b. State FTEs (# FTEs)
A-2.a. OPS FTEs (Salaries)
A-2.b. OPS FTEs (# FTEs)
A-3.a. Staff Augmentation (Contract Cost)
A-3.b. Staff Augmentation (# of Contract FTEs)
B. Plant & Facility -- Operational Costs
C. External Service Provider -- Operational Costs
D. Data Processing -- Operational Costs
D-2. Software
E. Others -- Operational Costs
Subtotal of Operational Costs ( Rows A through E)
Total Changes in Program Operational Costs (Sum of
Negative Values indicate decreased Costs (i.e., Tangible Benefits). Positive values indicate increased operational costs outside of thosespecified in the ProjectCosts spreadsheet. FY Totals are carried forward to the InvesmentSummary sheet for investment summarycalculations
Level of Uncertainty - Enter % (+/-)
8/7/2019 cba_toolkit
2/3
DEPIT Project Cost-Benefit Analysis
DEP Division/Office:Division of X Division of X Project: Project X
Program(s) Title:Program Y Program Y Project Sponsor: Jane Doe
Project Cost Elements Project Cost Table Character of Project Costs
(Project Planning,Development & Implementation FY FY FY FY FY TOTAL Choose Type
No Operational Costs) 2010-11 2011-12 2012-13 2013-14 2014-15 Detailed/Rigorous
$ $ $ $ $ $ Not to Exceed
$ $ $ $ $ $ Order of Magnitude
$ $ $ $ $ $
Consultant Services $ $ $ $ $ $
Hardware $ $ $ $ $ $Software $ $ $ $ $ $
Network Infrastructure $ $ $ $ $ $
Training $ $ $ $ $ $
Travel $ $ $ $ $ $
Other Specify $ $ $ $ $ $
Total Project Costs (*) $ $ $ $ $ $
Cumulative Project Costs $ $ $ $ $
Total Project Costs are carried forward to the InvestmentSummary form
Level of Uncerta
State FTEs (Salaries & Benefits)
OPS FTEs (Salaries)
Staff Augmentation (Contract Cost)
8/7/2019 cba_toolkit
3/3
DEPIT Project Cost-Benefit Analysis
53420290
InvestmentSummary_3Version 1.1 (4/20/09)
Page 3 of 3
Project Investment Summary 0
Agency: Division of X Project: Project X
m(s) Title:Program Y Project Sponsor: Jane Doe
Investment Summary
FY FY FY FY FY
TOTAL2010-11 2011-12 2012-13 2013-14 2014-15
Cost of Capital (as published by St 5.35% 5.38% 5.38% 5.38% 5.38%
Cost Benefit Analysis
I $ $ $ $ $ $
II $ $ $ $ $ $
Return on Investment Analysis
III $ $ $ $ $ $
IV Payback Period (years) NO PAYBAC Payback Period is the time required to recover the investment cos
V Breakeven Fiscal Year NO PAYBAC Fiscal Year during which the project's investment costs are recoveVI Net Present Value (NPV) $ NPV is the present-day value of the project's benefits less costs ov
VII Internal Rate of Return (IRR NO IRR IRR is the project's rate of return.
Proposed Funding Sources for Project Costs by Fiscal Year
Prospective Source(s) of Project Funding
Investment Summary FY FY FY FY FY TOTAL2010-11 2011-12 2012-13 2013-14 2014-15
VIII General Revenue $ $ $ $ $ $
IX Trust FunSpecify $ $ $ $ $ $
X Federal MSpecify $ $ $ $ $ $
XII Grants Specify $ $ $ $ $ $
XII Other Specify $ $ $ $ $ $
Project Funding Totals $ $ $ $ $ $
Net Sav ngs Resu t ng romthe Project(TangibleChangesForm)
Total Project Cost (ProjectCosts Fo
Return on Investment (Row I min