    CAUSES OF

    CONTRACTORS FAILURES

    IN SAUDI ARABIA

    Thesis Written by : Adel Al-Barrak

    Presented By : Jalal Al-Khatam

    KING FAHD UNIVERSITY OF PETROLEUM AND

    MINERALS

    COLLEGE OF ENVIRONMENTAL DESIGN

    CEM-520 CONSTRUCTION CONTRACTING AND ADMINISTRAION

  • 8/12/2019 Causes of Contractors Failure in 4

    2/24

    OUTLINE

    INTRODUCTION

    LIMITATION OF THE STUDY

    OBJECTIVE OF THE STUDY

    METHODOLOGY

    STATISTICAL SAMPLING Sample Size

    Scoring

    CAUSES OF FAILURES

    STATISTICAL METHODS

    TEST OF HYPOTHESIS

    MAJOR FINDINGS

    CONCLUSIONS

    RECOMMENDATIONS

    MANAGERIAL CAUSES

    FINANCIAL CAUSES

    EXPANSION CAUSES

    ENVIRONMENTAL CAUSES

  • 8/12/2019 Causes of Contractors Failure in 4

    3/24

    INTRODUCTION

    The construction business has very high

    risk.

    These risks, which could lead to failure,

    come from the sensitivity of the business

    to economy cycles, and from high levels ofcompetition.

  • 8/12/2019 Causes of Contractors Failure in 4

    4/24

    INTRODUCTION Cont.

    Contractors failure could be defined as

    Ceases operation following assignments

    due to the inability to continue construction.

    Goes into bankruptcy due to failure of

    collecting money from customers.

    Voluntarily withdraws because of

    dissatisfaction with business or profit.

  • 8/12/2019 Causes of Contractors Failure in 4

    5/24

    LIMITATION OF THE STUDY

    This study is limited to building and highway contractors

    who are qualified and registered in the Ministry of

    Housing and Public Works as of 25th of Muharam,

    1413H.

    The contractors are from grades one to four in Saudi

    Arabia.

    The technical failures of project are not covered in this

    study. The study is restricted to construction phase only.

  • 8/12/2019 Causes of Contractors Failure in 4

    6/24

    OBJECTIVE OF THE STUDY

    To undertake a comprehensive analysis of the most

    important factors that cause business failure among

    contractors.

    To identify and analyze the most severe factors causing

    contractor's failure in Saudi Arabia.

    To test the hypothesis that different grades of

    contractors, generally agree on the severity of failure.

  • 8/12/2019 Causes of Contractors Failure in 4

    7/24

    METHODOLOGY

    Data Collected by reviewing related literatures, and

    gathering information through site visits, interviews, and

    discussions with different grade contractors.

    Data analysis and identification of the most relevant

    factors influencing causes of contractor failures.

    As a result, formation of the questionnaire which was

    distribution to the contractors.

    Data Collection

  • 8/12/2019 Causes of Contractors Failure in 4

    8/24

    STATISTICAL SAMPLING

    The contractors who had qualified and registered in

    the Ministry of Housing and Public Works year 1413 H

    had the chance to participate.

    The Ministry of Public Works classified contractors to

    fields and activities.

    In this study, two fields have been included (Buildings

    and Roads) only

    Sample Size

  • 8/12/2019 Causes of Contractors Failure in 4

    9/24

    STATISTICAL SAMPLING Cont.

    The Ministry of Public Workers classified each

    field to five grades for Saudi contractors and six

    grades for foreign contractors.

    The study includes Saudi and Foreign

    contractors for building and road activities.

    Sample Size

  • 8/12/2019 Causes of Contractors Failure in 4

    10/24

    STATISTICAL SAMPLING Cont.

    In this study, the population of the contracting

    firm has been divided into three strata:

    Group 1 (Grade one and two)

    Group 2 (Grade three)

    Group 3 (Grade four)

    Grade one and two are added together becausethe amount of volume of grade one is just little

    greater than grade two.

    Sample Size

  • 8/12/2019 Causes of Contractors Failure in 4

    11/24

    STATISTICAL SAMPLING Cont.

    The options given for each question are on a

    four-point scale. Each factor has a severity index

    and the severity index is controlled by equation:

    Severity Index (Is) = ai xi

    Where

    i = 1,2,3,4

    Scoring

    4

    i=1

  • 8/12/2019 Causes of Contractors Failure in 4

    12/24

    CAUSES OF FAILURES

    The Questionnaire includes (34) causes of

    contractors failure

    The 34 causes are divided into four groups

    Managerial Causes

    Financial Causes

    Expansion Causes

    Environmental Causes

  • 8/12/2019 Causes of Contractors Failure in 4

    13/24

    CAUSES OF FAILURES (MANAGERIAL)

    MANAGERIAL CAUSES Lack of Experience in the

    Line of Work

    Replace Key Personnel

    Assigning Project Leader inthe Site

    Labor Productivity and

    Improvement

    Bad Decisions in Regulating

    Company Policy Use of Project Management

    Techniques

    Company Organization

    Procurement Practices

    Claims

    Internal Company

    Problems Recruitment from One

    Country

    Recruiting Multinational

    Owners Absence from

    the Company Using Computer

    Applications

    Frauds

    Neglect

  • 8/12/2019 Causes of Contractors Failure in 4

    14/24

    CAUSES OF FAILURES (FINANCIAL)

    FINANCIALCAUSES

    Low Margin Profit Due To Competition

    Cash Flow Management

    Bill and Collecting Effectively

    Poor Estimation Practices

    Evaluate Project Profit in One Fiscal Year

    Employee Benefits and Compensations

    Controlling Equipment Cost and Usage

  • 8/12/2019 Causes of Contractors Failure in 4

    15/24

    CAUSES OF FAILURES (EXPANSION)

    EXPANSIONCAUSES

    Expanding into New Geographic Locations

    Opening a Regional Office

    Increased Number of Projects

    Increased Size of Projects

    Change in the Type of Work

    Lack of Managerial Maturity

    Changes from private to Public or Vice Versa

  • 8/12/2019 Causes of Contractors Failure in 4

    16/24

    CAUSES OF FAILURES(ENVIRONMENTAL)

    ENVIRONMENTALCAUSES

    National Slump in the Economy

    Construction Industry Regulation in Saudi Arabia

    Owner Involvement in Construction Phase

  • 8/12/2019 Causes of Contractors Failure in 4

    17/24

    STATISTICAL METHODS

    Tabulation and cross tabulation

    Statistical techniques

    Correlation

    Ranking

  • 8/12/2019 Causes of Contractors Failure in 4

    18/24

    TEST OF HYPOTHESIS

    It is concluded from Test of Hypothesis

    that all parties agree on the severity rank

    of failures and these parties are reliable in

    their responses

  • 8/12/2019 Causes of Contractors Failure in 4

    19/24

    MAJOR FINDINGS

    The major causes of contractor failures are

    divided into four major areas

    27.78

    27.27

    21.1

    23.7 Managerial27.78 %

    Finance27.27 %

    Expansion21.10 %

    Environment23.70 %

  • 8/12/2019 Causes of Contractors Failure in 4

    20/24

    MAJOR FINDINGS Cont.

    Performance measures ranking

    Group one (Grade one and two contractors)

    Group two (Grade three contractors)

    Group three (Grade four contractors)

    All contractors (Group one, two, and three)

    http://a/PRESENTATION/Group%20one%20(Group%20one%20and%20two%20contractors).dochttp://a/PRESENTATION/Group%20two%20(Grade%20three%20contractors).dochttp://a/PRESENTATION/Group%20three%20(Grade%20four%20contractors).dochttp://a/PRESENTATION/All%20contractors%20(Group%20one,%20two,%20and%20three).dochttp://a/PRESENTATION/All%20contractors%20(Group%20one,%20two,%20and%20three).dochttp://a/PRESENTATION/Group%20three%20(Grade%20four%20contractors).dochttp://a/PRESENTATION/Group%20two%20(Grade%20three%20contractors).dochttp://a/PRESENTATION/Group%20one%20(Group%20one%20and%20two%20contractors).doc
  • 8/12/2019 Causes of Contractors Failure in 4

    21/24

    CONCLUSIONS

    Insufficient experience in the line of work is the main important cause of

    failure.

    Poor estimation practices are a major source of failure. The proper use of

    new methods for estimating cost would help to reduce failure.

    One of the major causes of failure is that there is no restriction on those

    entering the construction market; anyone could become a contractor.

    Delays in payment are one of the main cause of failures because they result

    in a financial problem to the contractor. This may cause cash flow problem

    to the contractor.

  • 8/12/2019 Causes of Contractors Failure in 4

    22/24

    CONCLUSIONS Cont.

    The study shows that the three Groups (group one, group two, and group

    three) generally agree in the rank of failure.

    Bad decisions in regulating company policy are a source of failure.

    Neglect is an important cause of failure. Neglect may add extra cost to the

    project which could cause a failure.

    Lack of managerial maturity as the company grows could cause a failure.

    This cause is more influential in grade three and four contractors because

    they manage small companies and are looking to become bigger.

  • 8/12/2019 Causes of Contractors Failure in 4

    23/24

    RECOMMENDATIONS

    It is recommended that a set of procedure be established to restrict

    the construction industry.

    Contractors should improve the practices for calculating the project

    cost.

    It is recommended that each contractor establish a program for

    motivating workers.

    Contractor development should be done with a long term planning.

    It is recommended that the number of payments increase so that

    each payment amount will be less.

  • 8/12/2019 Causes of Contractors Failure in 4

    24/24

    RECOMMENDATION FOR

    FUTURE RESEARCH

    The effect of the owner of a project on the failure in Saudi Contractors.

    The effect of government regulations on the construction industry.

    Construction company organization structures and their policies.

    Government policies that can be initiated in Saudi Arabia to help

    contractors stay in the business.

    The effect of the owner of a company on the failure.