Structure Name Structural Part Casting DateConcrete
Quantity (Cum)Remarks
Floculator Base (Road Side),+1.2Level
17-May-16 250
Floculator Middle wall (RiverSide),+1.2 Level
14-May-16 60
Floculator Slope wall (RiverSide),+1.2 Level
14-May-16 100
Floculator North wall (RoadSide),+1.2 Level
31-May-16 55
Receiving Well Base,+2.7 Level 20-May-16 15
Receiving Well Base,+3.35 Level 15-May-16 90
Rapid Sand Filter Base Casting,Zone-2 (Road side) 22-May-16 324
Back Wash Wast Tank Wall Casting +3.7 to +5.0 19-May-16 92
Wall Casting +1.4 to +3.5 (RiverSide)
10-May-16 65
Wall Casting +1.4 to +3.5 (RoadSide)
15-May-16 95
Levelling Concrete10 May 2016 to
10 June 201670
Base Casting20 May 2016 to
20 July 2016300
Floculator
Receiving Well
Casting Date for May' 16
CONSTRUCTION OF MODUNAGHAT WATER TREATMENT PLANT & PATENGABOOSTER PUMP STATION (CWSISP/W-1)
Dewatering Building