14
GIS-based location suitability of decentralized, medium scale bioenergy developments to estimate transport CO 2 emissions and costs Thomas Kurka*, Chris Jefferies, David Blackwood University of Abertay Dundee, Bell Street, Scotland DD1 1HG, UK article info Article history: Received 29 August 2011 Received in revised form 30 July 2012 Accepted 6 August 2012 Available online xxx Keywords: Bioenergy CHP GIS Distributed generation (DG) Spatial modeling Site suitability modeling abstract This paper presents a transferable and adaptable GIS-based approach to identify suitable locations of medium scale CHP bioenergy plants. Location suitability of bioenergy plants is of particular importance in planning decentralized bioenergy generation, as both biomass feedstock supplies and heat demand have to be considered in location selection when heat and electricity want to be utilized. A generic GIS model was developed to identify most suitable locations of CHP bioenergy plants based on regional supply, demand and prox- imity. Furthermore, the paper provides a simple approach to allocate biomass feedstock supplies to bioenergy plants and to estimate transport costs and CO 2 emissions. The GIS- based approach was applied in a Scottish region (Tayside and Fife) to identify locations for 10 decentralized, medium scale bioenergy plants based on which regional biomass feedstock supplies were allocated and road transport-related CO 2 emissions and costs were estimated. The paper concludes that the approach can assist in developing and imple- menting a long-term sustainable and integrated strategy for decentralized bioenergy generation, which includes heat utilization in addition to electricity production and which can be further developed to take account of broadly diversified conventional and renewable energy generation in a region. ª 2012 Elsevier Ltd. All rights reserved. 1. Introduction Bioenergy, the energy obtained from biomass, is considered to have the potential to supply a significant portion of global primary energy over the next century. On a European scale biomass will potentially contribute 17.2% of the EU heating and cooling mix and 6.5% of electricity consumption in 2020 [1]. Currently, there is also a strong policy drive at the global, national and regional level to address the effects of energy- based Greenhouse Gas (GHG) emissions, particularly CO 2 emissions, as it relate to global warming and climate change [2]. In Scotland legislation has been established to ensure compliance with the Kyoto Protocol. For instance, the Climate Change (Scotland) Act 2009 (asp 12) ‘ensures that the net Scottish emissions account for the year 2050 is at least 80% lower than the baseline’ with an interim target of at least 42% lower than the baseline by 2020. While biomass transportation will add to CO 2 emissions, the Royal Commission on Envi- ronmental Pollution [3] believes that bioenergy emissions are almost completely offset. For this reason, a number of actions are currently being taken or planned to develop medium and large scale bioenergy plants within Scotland. Important initiatives and drivers include the Renewables Obligation (RO) 2002e2037; Feed in Tariffs (FITs) April 2010 to 2021 (þ20yrs); Renewable Heat Incentive: (started 2011), the UK Renewable Energy Strategy (2009); the Scottish Biomass Action Plan * Corresponding author. Tel.: þ44 01382 308545; fax: þ44 01382 308117. E-mail addresses: [email protected], [email protected] (T. Kurka). Available online at www.sciencedirect.com http://www.elsevier.com/locate/biombioe biomass and bioenergy xxx (2012) 1 e14 Please cite this article in press as: Kurka T, et al., GIS-based location suitability of decentralized, medium scale bioenergy developments to estimate transport CO 2 emissions and costs, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/ j.biombioe.2012.08.004 0961-9534/$ e see front matter ª 2012 Elsevier Ltd. All rights reserved. http://dx.doi.org/10.1016/j.biombioe.2012.08.004

CasoEstudio-ArticuloIngles2.pdf

  • Upload
    carlo

  • View
    212

  • Download
    0

Embed Size (px)

Citation preview

  • ww.sciencedirect.com

    b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 4Available online at whttp: / /www.elsevier .com/locate/biombioeGIS-based location suitability of decentralized, medium scalebioenergy developments to estimate transport CO2 emissionsand costsThomas Kurka*, Chris Jefferies, David Blackwood

    University of Abertay Dundee, Bell Street, Scotland DD1 1HG, UKa r t i c l e i n f o

    Article history:

    Received 29 August 2011

    Received in revised form

    30 July 2012

    Accepted 6 August 2012

    Available online xxx

    Keywords:

    Bioenergy

    CHP

    GIS

    Distributed generation (DG)

    Spatial modeling

    Site suitability modeling* Corresponding author. Tel.: 44 01382 3085E-mail addresses: [email protected]

    Please cite this article in press as: Kurkdevelopments to estimate transport COj.biombioe.2012.08.004

    0961-9534/$ e see front matter 2012 Elsevhttp://dx.doi.org/10.1016/j.biombioe.2012.08.a b s t r a c t

    This paper presents a transferable and adaptable GIS-based approach to identify suitable

    locations of medium scale CHP bioenergy plants. Location suitability of bioenergy plants is

    of particular importance in planning decentralized bioenergy generation, as both biomass

    feedstock supplies and heat demand have to be considered in location selection when heat

    and electricity want to be utilized. A generic GIS model was developed to identify most

    suitable locations of CHP bioenergy plants based on regional supply, demand and prox-

    imity. Furthermore, the paper provides a simple approach to allocate biomass feedstock

    supplies to bioenergy plants and to estimate transport costs and CO2 emissions. The GIS-

    based approach was applied in a Scottish region (Tayside and Fife) to identify locations

    for 10 decentralized, medium scale bioenergy plants based on which regional biomass

    feedstock supplies were allocated and road transport-related CO2 emissions and costs were

    estimated. The paper concludes that the approach can assist in developing and imple-

    menting a long-term sustainable and integrated strategy for decentralized bioenergy

    generation, which includes heat utilization in addition to electricity production and which

    can be further developed to take account of broadly diversified conventional and renewable

    energy generation in a region.

    2012 Elsevier Ltd. All rights reserved.1. Introduction Change (Scotland) Act 2009 (asp 12) ensures that the netBioenergy, the energy obtained from biomass, is considered to

    have the potential to supply a significant portion of global

    primary energy over the next century. On a European scale

    biomass will potentially contribute 17.2% of the EU heating

    and cooling mix and 6.5% of electricity consumption in 2020

    [1]. Currently, there is also a strong policy drive at the global,

    national and regional level to address the effects of energy-

    based Greenhouse Gas (GHG) emissions, particularly CO2emissions, as it relate to global warming and climate change

    [2]. In Scotland legislation has been established to ensure

    compliance with the Kyoto Protocol. For instance, the Climate45; fax: 44 01382 308117, [email protected] (T

    a T, et al., GIS-based lo

    2 emissions and cost

    ier Ltd. All rights reserved004Scottish emissions account for the year 2050 is at least 80%

    lower than the baseline with an interim target of at least 42%

    lower than the baseline by 2020.While biomass transportation

    will add to CO2 emissions, the Royal Commission on Envi-

    ronmental Pollution [3] believes that bioenergy emissions are

    almost completely offset. For this reason, a number of actions

    are currently being taken or planned to develop medium and

    large scale bioenergy plants within Scotland. Important

    initiatives and drivers include the Renewables Obligation (RO)

    2002e2037; Feed in Tariffs (FITs) April 2010 to 2021 (20yrs);Renewable Heat Incentive: (started 2011), the UK Renewable

    Energy Strategy (2009); the Scottish Biomass Action Plan.. Kurka).

    cation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    .

    mailto:[email protected]:[email protected]/science/journal/09619534http://www.elsevier.com/locate/biombioehttp://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 42(2007); the Scottish Low Carbon Economic Strategy (2010) and

    Scotlands Renewable Heat Action Plan (2009). As a result,

    a high number of medium and large scale biomass plants

    (electricity-only and Combined Heat and Power (CHP)) have

    been proposed across the country, but the future demand of

    proposed plants is significantly higher than current indige-

    nous supply. The long term availability of biomass and bio-

    energy supply is a barrier that Scotland and other EU Member

    States will experience in attempting to achieve 2020 targets

    and beyond. Thus, a major objective is to ensure that bio-

    energy resources and technologies can be mobilized and

    utilized in the most efficient and sustainable manner possible

    to guarantee the long term transition to bioenergy [4]. For

    instance, the employment of a CHP plant can increase its

    overall efficiency [5]. The Scottish Government considered

    this aspect in its policy position, which prioritizes biomass for

    renewable heat [6], whereas in addition the Wood Fuel Task

    Force recommended that CHP plants should be at an appro-

    priate scale to use the heat most effectively [4]. In terms of

    biomass feedstock sourcing, long distance transportation of

    biomass resources, such as from Canada to Europe, can

    reduce the economic attractiveness of the bioenergy devel-

    opment in the long-term [7]. Locating bioenergy plants close to

    the supply of biomass feedstock can offer a sustainable way

    for bioenergy production as transport distances decrease,

    which again results in significant transport CO2 emissions and

    costs reductions. In regard to installing CHP plants and heat

    utilization, close proximity to heat demand is equally essen-

    tial as heat for industrial processes or district heating cannot

    be transported over long distances without significant heat

    loss [8]. To address both necessities for proximity, Geograph-

    ical Information System (GIS)-based location suitability can

    assist. There have been studies in the past looking into GIS-

    based assessments to identify sites for renewable systems.

    For instance Baban and Parry [9] and Aydan, Kentel and

    Duzgun [10] developed approaches to assist in locating wind

    farms in the UK and Turkey respectively. In a number of

    studies GIS was used to identify biomass resource potential

    with some also analyzing associated economic costs

    [8,11e16]. Perpina et al. [17] provided a GIS-based method-

    ology for determining optimal locations for bioenergy plants

    with a network analysis to calculate transport costs.

    Conversely, Ma et al. [18] proposed a GIS-based model for

    land-suitability assessment to identify bioenergy locations

    with integrated environmental and social constraints, as well

    as economic factors weighted by employing the analytic

    hierarchy process (AHP) to establish their relative importance.

    The research presented incorporates and builds on

    elements of these previously conductedworks in the field. The

    paper focuses on sourcing regionally and in particular on CO2emissions and costs as a result of transporting biomass

    feedstock from suppliers to bioenergy plants by road. The

    objectives of the research are threefold: The first objective is to

    develop a generic GIS model to locate most suitable locations

    for decentralized, medium scale bioenergy systems based on

    supply, demand and proximity. The second objective is to

    provide a simple approach to allocate biomass feedstock

    supply to bioenergy plants and based on this estimate trans-

    port costs and CO2 emissions. Finally the third objective is to

    implement model, biomass feedstock allocation process andPlease cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.004transport CO2 emissions and costs estimation by conducting

    a case study for Tayside and Fife in Scotland.2. GIS model-based methodology to identifythe most sustainable locations for decentralizedmedium scale bioenergy developments

    Naturally, transport CO2 emissions and costs evaluations are

    most influenced by the locations of bioenergy plants relative

    to the sources of biomass feedstock. A GIS-based model was

    built to support decisions on the location of bioenergy plants.

    The model integrates key factors relating to biomass feed-

    stock supply and heat demand locations and quantities,

    existing bioenergy developments and distances to these sites.

    This required a methodology comprising the following stages:

    data collection and assumptions, GIS modeling and location suit-

    ability analysis and allocation of supplies to the medium scale bio-

    energy plants.

    2.1. Data collection and assumptions

    Data required for input into the GIS model depend on data

    source and availability and can be obtained by desktop studies

    or surveys (phone and/or a face-to-face interviews etc) with

    industry values adopted as benchmark figures in case no

    relevant information should be available. Table 1 illustrates

    the type of data, which could be collected.

    2.2. GIS modeling and location suitability analysis

    A GISmodel which integrates collected and assumed data can

    be built to identify most suitable locations for medium scale

    bioenergy CHP developments. This identification of potential

    site locations is a prerequisite to assess the two distance-

    dependent criteria transport CO2 emissions and costs for the

    decentralized development. First, all supply and heat demand

    data collected has to be categorized into appropriate biomass

    feedstock supply or heat demand types such as for instance

    sawmills or universities. This categorization can be based on

    the spreadsheet application Microsoft Excel. Each category

    spreadsheet is then imported separately to GIS andmapped in

    form of an individual layer. Data gathered about the existing

    medium and large scale bioenergy plants is imported to GIS in

    the samemanner. Also, point of reference and additional data

    like regional base maps are imported, i.e. each GIS layer

    contains the dataset of one spreadsheet.

    The second step of the methodology involves modeling

    with the ArcView 9.3 ModelBuilder to identify most suitable

    site locations in case study areas based on proximity, biomass

    feedstock supply and heat demand. ArcView 9.3 Mod-

    elBuilder is an application, which can be used to create, edit,

    and manage models. Models are workflows that string

    together sequences of spatial analysis tools, feeding the

    output of one tool into another tool as input. As could be seen

    below (Fig. 1), layers (circular elements), which contain data-

    sets and processes of tools (rectangular elements) from the

    ArcView 9.3 toolbox are connected to produce a new output.

    Based on these outputs other tools can be applied until the

    desired result is achieved.cation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • Table 1 e Example of input data for GIS model.

    Data group Role of datagroup

    Type of data (case study) Individual layers(case study)

    Type of datastructure

    (case study)

    Source of spatialdata (case study)

    Notes (case study)

    Major biomass feedstock

    suppliers

    Scoring layers Name, address, coordinates for coordinate

    reference system (British National Grid,

    OSGB 1936 (EPSG:27700), Scale Factor:

    0.99960127), feedstock type and quantity

    available for bioenergy sector and current

    destinations

    Wood waste

    re-processors

    Vector point Own data gathering

    and processing

    Logs/chips/pellets

    producers

    Vector point Own data gathering

    and processing

    Sawmills Vector point [23] Relevant data were

    extracted from the

    original spatial dataset

    and modifications and

    additions were made

    Major heat customers Scoring layers Name, address, coordinates for coordinate

    reference system (British National Grid,

    OSGB 1936 (EPSG:27700), Scale Factor:

    0.99960127), heat demand quantities

    Primary schools Vector point [23]

    Secondary schools Vector point [23]

    Colleges Vector point [23]

    Universities Vector point [23]

    Major hospitals Vector point [23]

    Malt distilleries Vector point [23]

    Grain distilleries Vector point [23]

    Industrial points Vector point [23]

    Bioenergy plants competing

    for biomass feedstock

    and/or heat customers

    Screening layers Name, address, coordinates for coordinate

    reference system (British National Grid,

    OSGB 1936 (EPSG:27700), Scale Factor:

    0.99960127), feedstock requirements

    (type and quantity), heat customers

    and quantities provided

    Existing bioenergy

    plants (medium-scale)

    Vector point Own data gathering

    and processing

    Existing bioenergy

    plants (large-scale)

    N/A Own data gathering

    and processing

    Large-scale plants did

    not exist, but were

    proposed in case study

    area

    Major regional roads Screening layers Coordinates for coordinate reference

    system (British National Grid, OSGB 1936

    (EPSG:27700), Scale Factor: 0.99960127)

    Major regional roads Vector line [23] Relevant data were

    extracted from the

    original spatial dataset

    and modifications and

    additions were made

    Points of reference Illustrative purpose Coordinates for coordinate reference

    system (British National Grid, OSGB 1936

    (EPSG:27700), Scale Factor: 0.99960127)

    Base map of

    Scotland

    Vector polygon [23]

    Settlements

    in Scotland

    Vector polygon [23]

    bio

    mass

    and

    bio

    energy

    xxx

    (2012)1e14

    3

    Please

    citeth

    isarticle

    inpress

    as:

    Kurk

    aT,etal.,

    GIS-base

    dloca

    tion

    suita

    bility

    ofdece

    ntra

    lized,m

    edium

    scale

    bioenergy

    developm

    ents

    toestim

    ate

    transp

    ort

    CO

    2em

    issions

    and

    costs,

    Biom

    ass

    and

    Bioenergy

    (2012),

    http

    ://dx.doi.o

    rg/10.1

    016/

    j.biom

    bioe.20

    12.08.004

    http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • Sawmills

    Kernel Density

    Euclidean Distance

    Extraction

    Extraction

    Combination of model sub-strings

    Normalization

    Normalization

    Case studyarea

    1

    2

    43

    5

    Fig. 1 e Example of a scoring model string with steps marked.

    b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 44The model we built for this research comprised of two

    groups of layers, which we called screening layers and scoring

    layers. When combining these layers, a layer to whichwe refer

    to as location suitability layer can be produced. Based on this,

    most suitable locations can be identified and allocation of supplies

    to the medium scale bioenergy plants can be undertaken as

    a separate step.

    2.2.1. Scoring modelCombined layers of biomass feedstock suppliers and heat

    customers illustrate the suitability score of locations. The so-

    called scoring layers are used to identifymost suitable locations

    based on the distance to potential heat customers and

    biomass feedstock suppliers and the quantities of biomass

    feedstock supply and heat demand. The information for the

    GIS model strings consists of data gathered during the data

    collection process as described in 2.1. For each supplier or heat

    customer a model string with two parallel sub-strings is

    required to reflect distance on the one hand and demand or

    supply quantities on the other hand. The Euclidean Distance

    (ED) tool calculates straight-line distance, whereas the Kernel

    Density (KD) tool is applied to consider the quantities per

    individual site or building.

    TheKD tool (step 1 in Fig. 1) delivers density values basedon

    heat demand or supply quantities within defined search

    radiuses. These radiuses take into account that realistically

    demand for the generated heat and supply for the plants only

    takes place within a certain zone around plants. Conversely,

    the ED tool (step 2 in Fig. 1) also considers locations outside of

    these zones and delivers distance-based values for the

    remaining case study area. TheKDand the ED tools are applied

    for each of the scoring layers, which have to be combined to

    obtain the final suitability score of a location. Unlike the KD

    tool, which provides only values for locations within defined

    zones, the ED tool enables this combination of layers by

    delivering a value for every location in a case study area.

    After applying both, the ED and the KD for the two different

    sub-model strings, aGISpolygon representinga case studyarea

    extractsdata toproceedwith datawithin a case studyarea only

    (step 3 in Fig. 1). This step is optional and required only if the

    base maps used include areas exceeding a case study area.

    Normalization is required (step 4 in Fig. 1) in order tomake the

    resulting grids with different unit dimensions comparable and

    to aggregate them into a single scoring grid. For this purposePlease cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.004the Single Output Map Algebra function is applied with the

    same scale (range from zero to one) for all grids. A higher value

    for a cell (50 m 50 m) indicates a higher suitability score andthe closer a cell to the selected grid, the higher the value

    assigned. ED and KD values are normalized as follows:

    ED : Fnormij Fij Fij;max

    Fij;max1

    KD : Fnormij Fij

    Fij;max

    where Fnormij is the normalized distance for the ith cell in the jthfactor grid, Fij is the originally calculated distance for the ithcell in the jth factor grid, and Fij,max is the maximum distance

    for the jth factor grid.

    Following normalization, a Single Output Map Algebra step

    combines the two model sub-strings (step 5 in Fig. 1). At this

    stage, twice the weight is assigned to the ED grid, as the

    distances on a regional scale are assumed to be of more

    importance than the quantity densities within the defined KD

    search radiuses. This combination and weighting are under-

    taken through multiplication. The resulting grids are then

    aggregated to a single scoring grid showing the degree of

    suitability of every location in a case study area.

    2.2.2. Screening modelA sub-model towhichwe refer to as screeningmodel is built to

    exclude unsuitable areas from a case study region by applying

    Boolean logic. The first model sub-string is based on the

    regional major roads network. Depending on regional acces-

    sibility and economics of road transport, proximity to major

    roads can be of differing influencing importance to transport

    CO2 emissions and costs. To make allowance for this, an

    appropriate regional-depending buffer zone around major

    roads canbe incorporated into theGISmodel. Locationswithin

    this buffer zone are considered suitable and locations beyond

    the zone unsuitable. In an intermediate step the polygon

    resulting from buffering is converted into a raster allowing

    proceeding with a reclassification with the Boolean value one.

    Consequently, all areas beyond the buffer zone are assigned

    a value of zero indicating unsuitability. These three steps are

    repeated for the two remaining screening layers model sub-

    strings, for which it is assumed that new bioenergy plants

    cannot be built within an appropriate buffer zone aroundcation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 4 5existing bioenergy developments, which can be of different

    size in a case study area. The reason for this assumption is that

    demand for themajority of heat produced at locations in close

    proximity to existing plants, which also utilize generated heat,

    is expected to be limited. Therefore, buffer zones around the

    existing medium and large bioenergy plants can be incorpo-

    rated with different model sub-strings and buffer zones for

    each of the two types of scale. Contrary to the major roads

    model sub-string, the resulting binary grid that assigns each

    raster cell either a value of one or a value of zero and classifies

    them into suitable and unsuitable locations is reversed, as in

    this case the locations beyond the buffer zone are suitable and

    vice versa. A Single Output Map Algebra step combines the

    three resulting binary grids, followed by an extraction step to

    proceedwith datawithin a case study area only. The produced

    screening grid allows exclusion or cutting-out of unsuitable

    locations of the scoring grid as described below (2.2.3).

    2.2.3. Location suitability layerFinally, the screening grid with binary cell values and the

    scoring grid with cell values between zero and one for every

    location in a case study area are combined bymultiplication to

    create a location suitability layer. In principle, the Single Output

    Map Algebra tool cuts out unsuitable locations of the scoring

    map. The produced location suitability layer allows identifica-

    tion and illustration of most suitable locations for bioenergy

    plants in a case study area based on proximity, biomass

    feedstock supply and heat demand.

    2.2.4. Most suitable locations identification modelBased on the location suitability layer, the second part of the

    GIS modeling comprises of various model strings, which

    number depends on the quantity of bioenergy plants to be

    developed. The quantity and size of bioenergy plants can be

    determined by the actual amount of biomass feedstock,

    which can be sourced regionally in a case study area. Data

    about the actual amount of biomass feedstock should be

    available after the data collection process as described

    previously (2.1).

    The first step for each model string is to identify the

    location with the highest suitability score by applying the

    Single Output Map Algebra tool. After extraction to proceed

    with the identified location only, the produced raster is con-

    verted into a point to illustrate the location in the map. To

    allow continuation of the process and to identify the suitable

    location with the next highest score, the identified location

    has to be excluded or cut-out of themap. In consistencewith

    the screening model string for existing bioenergy plants, the

    same distance for buffering has to be applied. An interme-

    diate step converts the generated polygon into a raster. This

    allows reclassification and results in a binary grid, which

    again classifies suitable and unsuitable locations in the

    remaining case study area. Combination of this produced grid

    with the previous location suitability layer ensures that both

    the original scoring and screening grids are considered. In

    other words, the new identified location is cut out of the

    previous location suitability layer to create the next one. In

    descending order, the same process continues until all most

    suitable locations for the medium scale bioenergy plants are

    identified.Please cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.0042.3. Allocation of supplies to the medium scale bioenergyplants

    The identification of the most suitable locations for bioenergy

    plants in a case study area and gathered data about suppliers

    as illustrated in 2.1 allows available supplies of biomass

    feedstock to be allocated following the proximity principle.

    Starting with the plant location with the highest suitability

    score, the ED tool can be applied for this location to facilitate

    the identification of the closest suppliers. Then, the quantities

    of biomass feedstock from the closest supplier are allocated to

    this plant followed by the supplies from the second closest

    supplier and so on. This sequence continues until the biomass

    feedstock required for the operation of this plant is satisfied.

    In this process a spreadsheet can be of assistance to keep the

    overview and also to calculate the transport CO2 emissions

    and costs per supply. The same supply allocation process is

    repeated for the plant location with the second highest suit-

    ability score and then in descending order for the remaining

    suitable locations until all the plants feedstock demands are

    satisfied. This allocation process provides the values for the

    overall transport CO2 emissions and costs calculation.

    2.4. Calculation of transport CO2 emissions and costs

    Distances and benchmark figures for the carbon intensity and

    costs of different modes of transporting biomass feedstock

    have to be taken into account in determining CO2 emissions

    and costs associated with the transportation of biomass

    feedstock to the bioenergy plants. Benchmark figures for both

    transport CO2 emissionsand costs are available from literature

    and other relevant information sources. Based on these figures

    and the allocation of supplies process described in Section 2.3,

    the total transport CO2 emissions and costs can be calculated.3. Practical application of the methodologyin Tayside and Fife/Scotland

    The methodology described in Section 2 was applied in a case

    study area comprising of Tayside (including Angus, Perth and

    KinrossandDundee) andFife inScotland to locatemost suitable

    locations for decentralized, medium scale bioenergy plants.

    3.1. Scenario description

    Wood pellets with a water mass fraction of 8% and waste

    wood re-processed to industrial softwood chips with a water

    mass fraction of 20% were selected as biomass feedstock for

    the case study area. These materials have a relatively high

    Lower Heating Values (LHVs), which are typically about

    17.5 GJ t1 and 15.2 GJ t1, respectively [19] and were assumedto be regionally sourced from the case study area. In terms of

    bioenergy conversion technologies, the direct combustion

    technology was assumed to be installed at the decentralized

    sites. This technology is known to produce a high net effi-

    ciency for energy generation with approximately 80e90%

    boiler efficiency for industrial Combined Heat and Power

    (CHP) systems fired with biomass [20]. One of the case studies

    in a report about the situation of biomass CHP technologies incation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • Scoring Layers

    Screening Layers

    Location Suitability

    Layers

    Fig. 2 e Case study GIS model.

    Table 2 e Kernel density search radiuses for scoringlayers in case study area.

    Layer KD search radiuses

    Primary schools 3000 m

    Secondary schools 5000 m

    Colleges 10,000 m

    Universities 10,000 m

    Major hospitals 10,000 m

    Malt distilleries 10,000 m

    Grain distilleries 10,000 m

    Industrial sites 10,000 m

    Sawmills 25,000 m

    Logs, pellets and chips producers 50,000 m

    Wood waste re-processors 50,000 m

    b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 46Finland, Denmark and Sweden evaluated a CHP plant in

    Kuhmo/Finland with 4.9 MW electrical, and 12.9 MW of

    thermal output for district heating [21]. Typical sized CHP

    plants firing biomass feedstock in Finland have an electrical

    output ranging from 1 to 5 MW [21]. The biomass resource

    used for the Kuhmo plant is made up of industrial wood

    residues and forest chips, which are sourced regionally from

    nearby sawmills and wood waste re-processors. The plant is

    operating with fluidized bed combustion boiler technology

    with a total efficiency of 88%. For the case study reported in

    this paper it was assumed that the same kind of installations

    will be built in Tayside and Fife each with a biomass feedstock

    demand of 65 kt y1. In this area district heating and CHP areunderused, with utilization of waste heat from industrial and

    electricity generating processes a fairly new concept. Biomass

    feedstock availability for bioenergy generation is expected to

    be scarce in this area, if all proposed developments will be

    built in the future. Additionally, as in many other regions, in

    the case study area typically large proportions are already

    dedicated to alternative markets.

    3.2. Data collection and assumptions

    The case study data required for input into the GIS model

    was obtained by desktop studies and phone/email or face-

    to-face interviews, while industry values were sourced and

    adopted as benchmark figures for transport CO2 emissions

    and costs. Heat demand data was centered on the current

    heat consumption of large industrial, commercial or insti-

    tutional buildings, which included universities, colleges,

    schools (primary and secondary), grain and malt distilleries,

    industrial point sites and major hospitals within the study

    area. Data about significant biomass suppliers were

    centered on the current quantity of woody biomass obtain-

    able from wood waste re-processors, logs/chips/pellets

    producers and sawmills within the study area and beyond.

    These types of buildings and suppliers were chosen in the

    case study area because in a previous study [22] they have

    proven to be the main consumers of heat and suppliers of

    biomass resources, respectively. The Heat Map of Scotland

    [22] provided data already available in GIS shape file format

    [23], which was exported to Microsoft Excel for modifica-

    tions and additions to complete the data required as

    described in 2.1.

    Some assumptions had to be made for both heat demand

    and biomass feedstock supply. For the universities and colleges

    within Tayside and Fife, it was assumed that the data about the

    energyconsumedwas foroneof themaincampusesand thatall

    students were full time equivalent. The energy demand was

    calculatedper student basedon thenumberof students in2008/

    2009 [24]. The benchmark figure adopted for the total energy

    consumption per Scottish university/college student (FTE) was

    6264 KWh y1 [25]. This general benchmark figure was chosendue a lack of information with regard to the total heat

    consumption per individual university/college. For the same

    reason, a general benchmark figure for schools for the total heat

    consumed per pupil (2583 KWh)was adopted [26]. For grain and

    malt distilleries, energy demand was based on the assumption

    that the energy demandper liter of alcohol produced is equal to

    the energy demand per liter of whisky produced. ThePlease cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.004benchmark figure (9.36 MWh m3 of alcohol) was provided byone of the malt distilleries interviewed. Since data on the floor

    area of each hospital in Scotlandwas not available, the number

    of beds in the identifiedmajor hospitals was used as ameasure

    of their size. Based on this assumption, a benchmark figure

    (25,740 KWh) for heat demand per hospital bed was used to

    calculate the heat demand of major hospitals [26].

    Assumptions were also made to estimate the biomass

    feedstock supply from wood waste re-processors sawmills

    and logs/chips/pellets producers. For some groups of

    suppliers, it was necessary to estimate the number of

    employees, because the amount of biomass feedstock

    supplies was calculated based on this number. Relevant datacation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • Fig. 3 e Example of a kernel density grid map e sawmills in the case study area.

    Fig. 4 e Example of an Euclidean distance grid map e sawmills in the case study area.

    Please cite this article in press as: Kurka T, et al., GIS-based location suitability of decentralized, medium scale bioenergydevelopments to estimate transport CO2 emissions and costs, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 48about logs/chips/pellets producers in Tayside and Fife and

    50 km beyond its regional borders were collected. Depending

    on the level of this data assumptions about the number of

    employees had to bemade and the average biomass feedstock

    output per employee was calculated based on data from

    conducted surveys. The available supplies per site were esti-

    mated using both figures. Gathered data about total outputs of

    sawmills helped to calculate an average amount available for

    the bioenergy sector from sawmills. The database included all

    sawmills within the Tayside and Fife region and within

    a 25 km radius beyond the regions borders. Data about the

    available amounts of biomass feedstock from major wood

    waste re-processors were obtained from a survey conducted

    in the case study area and 50 km beyond. The reason for

    a wider radius for this type of suppliers was the larger quan-

    tities of biomass feedstock produced at these sites and

    affected by that, the more advantageous economics for

    transportation assumed. Finally, additional data about exist-

    ing plants and the network of major roads in the case study

    area was gathered by a desktop study.

    3.3. GIS modeling and location suitability analysis

    In total, eight heat demand layers, including primary and

    secondary schools, colleges,universities,majorhospitals,malt

    and grain distilleries and industrial points; and three biomass

    feedstock suppliers layers, including sawmills, logs/chips/Fig. 5 e Example of a scoring grid layer m

    Please cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.004pellets producers and wood waste re-processors, were map-

    ped.Additionally, data aboutmajor regional roadsandexisting

    plants, basemaps of the region and Scotland, as well as points

    of referencesuchascitiesweremapped for spatial analysisand

    illustrative purposes. Modeling allowed the identification of

    the most suitable decentralized bioenergy plants locations.

    Fig. 2 shows a simplified illustration of the developed GIS

    model. It shows 11 scoring layers (top left), 3 screening layers

    (bottom left) and the model strings to identify the 10 most

    suitable plant locations in the case study area (right).

    3.3.1. Scoring modelThe scoring model for the case study was built following the

    processes described in Section 2.2.1. The search radiuses for

    the KD tool were defined for the scoring layers in the case

    study as illustrated in Table 2.

    Depending on the type of layer, the KD population field for

    each layer was either heat/energy demand or biomass feed-

    stock quantity.

    Following the steps outlined (Section 2.2.1) the model was

    built to undertake intermediate steps (KD (Fig. 3), ED (Fig. 4)

    and scoring grid layers (Fig. 5)) for each layer, before the latter

    were combined into a final scoring grid layer map (Fig. 6).

    3.3.2. Screening modelThe screeningmodel for the case studywas built following the

    processes described in Section 2.2.2. There were no existingap e sawmills in the case study area.

    cation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • Fig. 6 e Example of a final scoring grid layer map e all scoring layers in the case study area.

    b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 4 9large scale plants in Tayside and Fife when data was gathered.

    Therefore the associated model sub-string was not necessary

    and only the binary grids taking account of the regional major

    road networks and existing medium scale plants were

    combined to form the screening grid layers map (Fig. 7).

    3.3.3. Location suitability layerAgain, following the methodology described above (Section

    2.2.3), the location suitability layer (Fig. 8) indicating most

    suitable locations for medium scale bioenergy plants in the

    case study area based on proximity, biomass feedstock supply

    and heat demand was produced.

    3.3.4. Most suitable locations identification modelThe location suitability layer served as a basis for identifying

    the 10 most suitable locations in the case study area. As out-

    lined above (Section 3.1) biomass feedstock demand for one of

    the plantswas assumed to amount 65 kt y1. The total amountof biomass feedstock from suppliers available for the bio-

    energy industry in the case study area, estimated as part of

    Section 3.2, amounted 632,788 t y1. In accordance with thisregional and import-independent sourcing of biomass feed-

    stock, the input demand of 10 plants could almost bemet. The

    most suitable locations of these plants in the case study area

    were identified and mapped following the methodology

    described in Section 2.2.4 (Fig. 9).Please cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.0043.4. Allocation of supplies to the medium scale bioenergyplants

    In accordance with the steps described in Section 2.3, the

    supplies were allocated to the 10 plants. The suppliers closest

    to the plants were identified by using the ED tool. A spread-

    sheet facilitated the allocation process and based on the

    distances measured between suppliers and plants, transport

    costs and CO2 emissions were calculated for each plant indi-

    vidually and in total for the case study. Table 3 illustrates an

    example of this process for one plant.

    3.5. Calculation of transport CO2 emissions and costs

    In a report produced for the Department for Environment

    Food and Rural Affairs (Defra) and the Department of Energy

    and Climate Change (DECC) [27], outlining the guidelines to

    GHG emissions conversion factors for company reporting, the

    carbon intensities of different modes of transporting biomass

    resources were presented. According to this report the carbon

    dioxide intensity for road transportation of biomass is

    86 g t1 km1. As only road transport was considered asa mode of transporting biomass feedstock, this figure served

    as a benchmark value used for the evaluation of CO2 emis-

    sions within the context of the case study. Based on this

    benchmark value and the allocation of supplies process, thecation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • Fig. 7 e Example of a screening grid layers map e all screening layers in the case study area.

    b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 410transport CO2 emissions for the case study amounted

    3525 t y1. Similarly, the road transport costs were calculated:E4tech [28] in a report to DECC, evaluated biomass prices in

    the heat and electricity sectors in the UK. In this report it was

    stated that the average UK road transport costs for wood chips

    with a water mass fraction of 25% are 0.55 V t1 km1

    (currency conversion from GBP at a rate of 1.2 V per GBP, 27

    Jun 2012). This benchmark figure was used for the case study

    to represent biomass and again combined with the results of

    the allocation of supplies process made up the total transport

    costs, which amount 22,625,485 V y1.4. Results and discussion

    By implementing the GIS modeling as outlined in Section 3,

    areas were determined where biomass feedstock availability

    and heat demand are highest, and based on this most suitable

    locations for 10 medium scale CHP bioenergy plants were

    identified in the case study area (Fig. 9). Not surprisingly, the

    locations of the bioenergy developmentswere identified in the

    two biggest cities of the area. The first reason for this is that

    the assessed buildings with the highest heat demand can be

    found there and secondly, the majority of the case studys

    large biomass feedstock suppliers also tend to be based inPlease cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.004those two cities. The 10 bioenergy plants could produce

    49MWelectrical, and 129MWof thermal output. Based on this

    suitability of plant locations the transport CO2 emissions and

    costs were calculated, which amount 3525 t y1 and22,625,485 V y1, respectively.

    With a net electricity and heat use efficiency of 88%, the 10

    mediumscale developments can provide an efficient supply of

    bioenergy and as a result increase the overall energy and

    carbon savings compared to, for example less efficient

    electricity-only plants of similar or larger size. Large scale CHP

    plants as an alternative to the decentralized medium scale

    bioenergy plants also have the capability to utilize and deliver

    all generated heat to potential userswith the aim of improving

    the plants efficiency. However, this would mean large

    concentrated heat generation, for which it can be more diffi-

    cult to find heat end-users. In this case a large amount of heat

    concentrated at one specific location is required to be

    matched with equally concentrated end-user demand in

    vicinity to the same location if maximum efficiency is desired.

    In the case study for example, it is unlikely that for such

    a relatively high amount of heat equally much demand would

    exist in close proximity to a large scale development.

    However, close proximity to heat customers is desired,

    because transporting of heat between heat source and end-

    user is associated with high infrastructure cost. Thecation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • Fig. 8 e Example of a suitability layer map e case study area.

    b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 4 11spatially diversified medium scale plants are more likely to

    match demand for parts or ideally all of the smaller amounts

    of heat produced at each individual site. The GIS model in

    particular addresses this aspect, as it considers both biomass

    feedstock supply and heat demand to identify the most suit-

    able locations for the medium scale developments. This again

    considerably increases the likelihood of matching heat supply

    of plants with end-user demand entirely.

    When the methodology was applied in the case study area

    two or more cells did not have the same suitability score. In

    case this should occur, the cells with the same scores should

    be equally considered as plant locations. The allocation of

    biomass feedstock is only affected by this if the locations in

    question are in close proximity to each other and thus

    compete for the same supplies. Then, an equal and fair supply

    distribution has to be considered with allocating biomass

    feedstock from the various suppliers in turns for example. In

    this connection the likelihood of a supplier being exactly the

    same distance away from two or more locations with the

    same suitability score is relatively low.

    For GISmodeling it has to be considered that amending the

    radiuses in the screening model (buffer zones around existing

    bioenergy plants considering heat demand) and the scoring

    model (KD radiuses for maximum distances of suppliers and

    heat demand) can change the results and therefore should be

    appropriate and realistic for a case study area.Please cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.004For further work in regard to GIS modeling, it could be

    considered to convert biomass feedstock supply data into

    energy units. This would mean that the same unit can be

    used for supply and demand, which would reduce the

    number of normalization steps required and result in

    a simplification of the GIS model. Additionally, an electricity

    grid layer could also be added to the GIS model to take grid

    connectivity into account. Furthermore, the application of

    GIS extensions, such as the ArcGIS Network Analyst and the

    ArcGIS 3D Analyst could be considered. The latter extension

    can assist in improved illustration of GIS layers and spatial

    analysis results to stakeholders. The ArcGIS Network Analy-

    st can improve the identification of most suitable locations,

    as well as the calculation of transport costs and CO2 emis-

    sions resulting from the allocation of supplies process,

    because it allows calculating distances based on road trans-

    port routes, rather than on straight-line distances to plants.

    Modeling based on straight-line distances has to be kept

    however due to the model strings for heat customers and the

    presumed straight-line distribution of heat to neighboring

    premises.

    Another issue to take into account is the type of biomass

    feedstock used. In the case study, general benchmark figures

    for both CO2 emissions and costs due to biomass trans-

    portationwere applied. However, the type of biomass can vary

    and influence both costs and emissions indirectly, as thecation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • Fig. 9 e Example of a final suitability map e 10 most suitable plant locations in the case study area.

    b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 412combustion of a biomass type with a higher LHV requires

    lower quantities of biomass feedstock to generate the same

    amount of energy. Less biomass feedstock requirements

    reduce logistical needs, which again lead to reduced transport

    CO2 emissions and costs. The GIS model can be extended byTable 3 e Example for supplies allocation and calculationof transport costs and CO2 emissions for a bioenergyplant in the case study area.

    Supplier Suppliedamount(t y1)

    Transportdistance(km)

    Transportcosts(V y1)

    CO2 emissions(kg y1)

    Supplier 1 11,088 1.88 11,525.04 1795.57

    Supplier 2 25,000 2.59 35,742.00 5568.5

    Supplier 3 2112 9.99 11,655.91 1815.96

    Supplier 4 374 11.09 2288.89 356.6

    Supplier 5 20,000 12.73 140,550.24 21,897.32

    Supplier 6 1500 14.9 12,337.20 1922.1

    Supplier 7 374 17.27 3564.53 555.34

    Supplier 8 125 18.84 1299.68 202.49

    Supplier 9 187.5 20.64 2136.24 332.82

    Supplier 10 355 21.01 4116.92 641.4

    Supplier 11 3168 22.03 38,528.15 6002.57

    Supplier 12 717.5 21.65 8574.70 1335.91

    Total 65,000 272,319.50 42,426.58

    Please cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.004a weighting step to incorporate these differences in supply

    materials and LHVs. Furthermore, the application of more

    case-specific benchmark figures and consultations with

    regional market actors and stakeholders about actual

    amounts of biomass feedstock supply and heat demand can

    contribute to increased accuracy of the GIS model results.

    Data gathering could also include the residential sector for

    district heating considerations. Furthermore, procedures

    could be established, which allow incorporation of planned

    supply and demand developments and a continuous updating

    of input data rather than working with point-in-time snap-

    shot data.

    An aspect to reflect on is the availability of supplies. In the

    case study it was assumed that available amounts for the

    bioenergy sector from the different suppliers can theoretically

    be allocated to the identified plants entirely. In reality

    however, proportions of these amounts can already be dedi-

    cated to other existing bioenergy plants or competitive

    markets such as the wood panel industry in the region. Hence

    these amounts have to be subtracted from the total quantity

    of regional supplies. This aspect was not considered in this

    research, because it was assumed that installation of a rela-

    tively high number of medium sized plants will significantly

    change existing markets, logistics and sourcing of biomass,

    which would eventually lead to a new structure of supplies

    distribution altogether in the case study area. A number ofcation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 4 13new bioenergy plants of various sizes are currently proposed

    there. However, it can be argued that building of large scale,

    low efficient electricity-only biomass plants among them can

    be questionedwhen keeping the scarcity of biomass feedstock

    in mind. These developments would highly rely on imports.

    From a GIS-modeling perspective even if imports are desired,

    they can be incorporated in the presented approach by

    widening the KD radiuses of the scoring model and by

    including suppliers further away from the case study area.

    Alternatively, in a regional and import-independent sourcing

    scenario more or less available biomass feedstock supply

    could simply result in a reduced or increased number of bio-

    energy plants. To compensate for limited resources for

    biomass-fueled installations, bioenergy can also be generated

    by alternative technologies such as anaerobic digestion. This

    diversification of bioenergy technologies approach would

    require a policy change and a more ambitious commitment

    toward energy self-sufficiency in the case study area.

    The presented work can also build the basis for future

    research in regard to comprehensive sustainability assess-

    ments and sustainable energy generation strategies. Gener-

    ally, the criteria used to evaluate the sustainability of

    bioenergy developments are divided into: technical,

    economical, environmental and social [29]. In terms of further

    GIS modeling work some environmental criteria could be

    taken account of in the screening model. As suggested by

    Fiorese and Guariso [8] andMa et al. [18] unsuitable areas such

    as protected areas, wetlands and lakes or streams, where

    bioenergy plants cannot be built, can be excluded through

    additional screening layers.

    For strategic decision-making toward bioenergy develop-

    ment participatorymulti-criteria decisionmaking approaches

    involving regional key stakeholders can be employed, as they

    are known to address the complexities of a broad range of

    stakeholders perspectives, goals and objectives [29]. By

    following these approaches decision-making toward

    a sustainable bioenergy generation strategy can be signifi-

    cantly improved in Tayside and Fife and in similar regions.5. Conclusion

    This study provides a transferable and adaptable approach

    for identifying suitable locations for medium scale CHP bio-

    energy plants, for allocating biomass feedstock and for esti-

    mating transport CO2 emissions and costs. Location

    suitability of bioenergy plants is of particular importance as

    both biomass feedstock supplies and heat demand have to be

    considered in location selection when heat and electricity are

    utilized. The generic GIS-based model developed to identify

    most suitable locations based on supply, demand and prox-

    imity facilitates planning of decentralized bioenergy genera-

    tion. The approach was applied to identify locations for 10

    decentralized, medium scale bioenergy plants spatially

    diversified throughout a Scottish region (Tayside and Fife)

    based on which regional biomass feedstock supplies were

    allocated and road transport-related CO2 emissions and costs

    were estimated. The results indicate where biomass feed-

    stock is available and heat demand is highest in the case

    study area. Furthermore, it also shows where most suitablePlease cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.004locations likely are to develop future bioenergy systems in

    this case study area, in which bioenergy development is still

    at an early phase due to insufficient political commitment,

    funding and technological expertise at both the production

    and operation stages of biomass processing and at the bio-

    energy plants. The presented work can assist in developing

    and implementing a long-term sustainable and integrated

    strategy for decentralized bioenergy generation, which

    includes heat utilization in addition to electricity production

    and which can be further developed to take account of the

    broadly diversified conventional and renewable energy

    generation in Scotland and in other regions.r e f e r e n c e s

    [1] European Renewable Energy Council. Mapping renewableenergy pathways towards. 2020-EU Roadmap [Internet].Brussels: European Renewable Energy Council (EREC) [cited2012 Jun 28]. 104 pp. Available from:, http://www.erec.org/media/publications/eu-roadmap.html; 2011 Mar.

    [2] United Nations Framework Convention on Climate Change(UNFCCC). Report of the Conference of the Parties serving asthe meeting of the Parties to the Kyoto Protocol on its fifthsession, held in Copenhagen from 7 to 19 December 2009.Addendum. Part Two: action taken by the conference of theparties serving as the meeting of the parties to the Kyotoprotocol at its fifth session [Internet]. Geneva: United NationsOffice; 2010 Mar 30 [Version: FCCC/KP/CMP/2009/21/Add.1,cited 2010 Sep 7]. 34 pp. Available from: http://unfccc.int/documentation/documents/advanced_search/items/6911.php?priref600005733.

    [3] Royal Commission on Environmental Pollution. Biomass asa renewable energy source [Internet]. London: RoyalCommission on Environmental Pollution [cited 2012 Jun 28].94 pp. Available from: http://www.biomassenergycentre.org.uk/portal/page?_dadportal&_pageid74,15256&_schemaPORTAL; 2004.

    [4] Wood Fuel Task Force 2. The supply of wood for renewableenergy production in Scotland e an update report by thewood fuel task force to Scottish Ministers [Internet].Edinburgh: Forestry Commission Scotland [cited 2012 Jun 28].32 pp. Available from: http://www.forestry.gov.uk/forestry/INFD-7APFXA; 2011 Mar.

    [5] Hinnells M. Combined heat and power in industry andbuildings. Energy Policy 2008;36(12):4522e6.

    [6] The Scottish Government. Draft electricity generation policystatement 2010 e Scotland e a low carbon society.Edinburgh: The Scottish Government; 2010.

    [7] Bradley D, Diesenreiter F, Wild M, Tromborg E. World biofuelmaritime shipping study for IEA Task 40 [Internet]. BioenergyTask 40: Sustainable International Bioenergy Trade. Utrecht:IEA [cited 2012 Jun 28]. 38 pp. Available from:, http://www.bioenergytrade.org/reports/archive/reports-2007-2009.html;2009 Jul 1.

    [8] Fiorese G, Guariso GA. GIS-based approach to evaluatebiomass potential from energy crops at regional scale.Environ Modell Softw 2010;25(6):702e11.

    [9] Baban SMJ, Parry T. Developing and applying a GIS-assistedapproach to locating wind farms in the UK. Renew Energy2001;24(1):59e71.

    [10] Aydin NY, Kentel E, Duzgun S. GIS-based environmentalassessment of wind energy systems for spatial planning:a case study from Western Turkey. Renew Sust Energy Rev2010;14(1):364e73.cation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://www.erec.org/media/publications/eu-roadmap.htmlhttp://www.erec.org/media/publications/eu-roadmap.htmlhttp://unfccc.int/documentation/documents/advanced_search/items/6911.php%3Fpriref%3D600005733http://unfccc.int/documentation/documents/advanced_search/items/6911.php%3Fpriref%3D600005733http://unfccc.int/documentation/documents/advanced_search/items/6911.php%3Fpriref%3D600005733http://unfccc.int/documentation/documents/advanced_search/items/6911.php%3Fpriref%3D600005733http://www.biomassenergycentre.org.uk/portal/page%3F_dad%3Dportal%26_pageid%3D74%2C15256%26_schema%3DPORTALhttp://www.biomassenergycentre.org.uk/portal/page%3F_dad%3Dportal%26_pageid%3D74%2C15256%26_schema%3DPORTALhttp://www.biomassenergycentre.org.uk/portal/page%3F_dad%3Dportal%26_pageid%3D74%2C15256%26_schema%3DPORTALhttp://www.biomassenergycentre.org.uk/portal/page%3F_dad%3Dportal%26_pageid%3D74%2C15256%26_schema%3DPORTALhttp://www.biomassenergycentre.org.uk/portal/page%3F_dad%3Dportal%26_pageid%3D74%2C15256%26_schema%3DPORTALhttp://www.biomassenergycentre.org.uk/portal/page%3F_dad%3Dportal%26_pageid%3D74%2C15256%26_schema%3DPORTALhttp://www.forestry.gov.uk/forestry/INFD-7APFXAhttp://www.forestry.gov.uk/forestry/INFD-7APFXAhttp://www.bioenergytrade.org/reports/archive/reports-2007-2009.htmlhttp://www.bioenergytrade.org/reports/archive/reports-2007-2009.htmlhttp://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

  • b i om a s s a n d b i o e n e r g y x x x ( 2 0 1 2 ) 1e1 414[11] Blaschke T, Biberacher M, Gadocha S, Schardinger I, Prinz T.Integrated energy spatial planning: spatializing policydecision support. In: Hrebcek J, Hradec J, Pelikan E,Mirovsky O, Pillmann W, Holoubek I, et al., editors.Proceedings of the European conference towardseEnvironment. Opportunities of SEIS and SISE: integratingenvironmental knowledge in Europe. Prague/Brno, CzechRepublic: Masaryk University; 2009 Mar 25e27. p. 284e92.

    [12] Voivontas D, Assimacopoulos D, Koukios EG. Assessment ofbiomass potential for power production: a GIS based method.Biomass Bioenergy 2001;20(2):101e12.

    [13] Graham RL, Liu W, Downing M, Noon CE, Daly M, Moore A.The effect of location and facility demand on the marginalcost of delivered wood chips from energy crops: a case studyof the state of Tennessee. Biomass Bioenergy 1997;13(3):117e23.

    [14] Noon CE, Daly MJ. GIS-based biomass resource assessmentwith BRAVO. Biomass Bioenergy 1996;10(2e3):101e9.

    [15] Dagnall S,Hill J, PeggD.Resourcemappingandanalysis of farmlivestock manures e assessing the opportunities for biomass-to-energy schemes. Bioresour Technol 2000;71(3):225e34.

    [16] Singh J, Panesar BS, Sharma SK. Energy potential throughagricultural biomass using geographical information systemea case study of Punjab. Biomass Bioenergy 2008;32(4):301e7.

    [17] Perpina C, Alfonso D, Perez-Navarro A, Penalvo E, Vargas C,Cardenas R. Methodology based on geographic informationsystems for biomass logistics and transport optimisation.Renew Energy 2009;34(3):555e65.

    [18] Ma J, Scott NR, DeGloria SD, Lembo AJ. Siting analysis offarm-based centralized anaerobic digester systems fordistributed generation using GIS. Biomass Bioenergy 2005;28(6):591e600.

    [19] European biomass industry association, about biomass[Internet]. Brussels: European Biomass Industry Association.Biomass characteristics [cited 2012 Jun 28]; [about 4 screens].Available from: http://www.eubia.org/115.0.html; 2007.

    [20] Ertesvag IS. Exergetic comparison of efficiency indicators forcombined heat and power (CHP). Energy 2007;32(11):2038e50.

    [21] Kirjavainen M, Sipila K, Savola T, Salomon M, Alakangas E.Small-scale biomass CHP technologies e situation in Finland,Denmark and Sweden. Espoo: VTT Processes and FinishDistrict Heating Association; 2004. Report No.: OPET Report12. Contract No.: NNE5/2002/52. Sponsored by the EuropeanCommission (Directorate-General for Energy and Transport).

    [22] AEA Technology plc. Scottish heat mapping project ecompanion report to EST [Internet]. Edinburgh: The ScottishPlease cite this article in press as: Kurka T, et al., GIS-based lodevelopments to estimate transport CO2 emissions and costj.biombioe.2012.08.004Government [cited 2012 Jun 27]. 27 pp. Available from: http://www.scotland.gov.uk/About/Information/FOI/Disclosures/2007/10/AEAHeatMap2007/FREDSHeatRep; 2008 May 15.

    [23] AEA Technology plc. Heat map of Scotland e GIS map file[Internet]. Edinburgh: The Scottish Government [cited 2012Jun 28]. Available from: http://www.scotland.gov.uk/About/Information/FOI/Disclosures/2007/10/AEAHeatMap2007/HeatMapGIS; 2008 Jan 24.

    [24] The Scottish Government, Education Analytical Services.Statistics publication notice: lifelong learning series estudents in higher education at Scottish institutions 2008e09[Internet]. Glasgow: The Scottish Government [cited 2011 Feb2]. 64 pp. Available from: http://www.scotland.gov.uk/Publications/2010/03/18144043/41; 2010 Mar 17.

    [25] IPD (Investment Property Databank) Ltd. Performance inhigher education estates e EMS annual report 2009 to Headsof HEFCE-funded higher education institutions, Heads ofSFC-funded higher education institutions, Heads of HEFCW-funded higher education institutions, Heads of universitiesin Northern Ireland [Internet]. Bristol: Higher EducationFunding Council for England (HEFCE) [cited 2012 Jun 29]. 44pp. Available from: http://www.hefce.ac.uk/pubs/year/2010/201004/; 2010 Apr.

    [26] Wiltshire R. The UK potential for community heatingwith combined heat and power. Watford: BuildingResearch Establishment Ltd, Energy Division; 2006. ReportNo.: 211-533. Sponsored by the Carbon Trust.

    [27] AEA Technology plc. The 2011 guidelines to Defra/DECCsGreenhouse Gas (GHG) conversion factors for companyreporting: methodology paper for emission factors[Internet]. London: Department of Energy and ClimateChange (DECC) and the Department for Environment Foodand Rural Affairs (Defra) [Version: 1.2, Updated: 2011 Aug19; cited 2012 Jun 28]. 102 pp. Available from: http://www.defra.gov.uk/publications/2011/09/01/ghg-conversion-factors-reporting/.

    [28] E4tech (UK) Ltd. Biomass prices in the heat and electricitysectors in the UK for the Department of Energy and ClimateChange [Internet]. London: Department of Energy andClimate Change (DECC) [cited 2009 Sep 2]. 33 pp. Availablefrom: http://www.decc.gov.uk/publications/AdvancedSearch.aspx?term&tags&urn10D/546&fromDate&toDateα 2010 Jan 31.

    [29] Wang J-J, Jing Y-Y, Zhang C-F, Zhao J-H. Review on multi-criteria decision analysis aid in sustainable energy decision-making. Renew Sust Energy Rev 2009;13(9):2263e78.cation suitability of decentralized, medium scale bioenergys, Biomass and Bioenergy (2012), http://dx.doi.org/10.1016/

    http://www.eubia.org/115.0.htmlhttp://www.scotland.gov.uk/About/Information/FOI/Disclosures/2007/10/AEAHeatMap2007/FREDSHeatRephttp://www.scotland.gov.uk/About/Information/FOI/Disclosures/2007/10/AEAHeatMap2007/FREDSHeatRephttp://www.scotland.gov.uk/About/Information/FOI/Disclosures/2007/10/AEAHeatMap2007/FREDSHeatRephttp://www.scotland.gov.uk/About/Information/FOI/Disclosures/2007/10/AEAHeatMap2007/HeatMapGIShttp://www.scotland.gov.uk/About/Information/FOI/Disclosures/2007/10/AEAHeatMap2007/HeatMapGIShttp://www.scotland.gov.uk/About/Information/FOI/Disclosures/2007/10/AEAHeatMap2007/HeatMapGIShttp://www.scotland.gov.uk/Publications/2010/03/18144043/41http://www.scotland.gov.uk/Publications/2010/03/18144043/41http://www.hefce.ac.uk/pubs/year/2010/201004/http://www.hefce.ac.uk/pubs/year/2010/201004/http://www.defra.gov.uk/publications/2011/09/01/ghg-conversion-factors-reporting/http://www.defra.gov.uk/publications/2011/09/01/ghg-conversion-factors-reporting/http://www.defra.gov.uk/publications/2011/09/01/ghg-conversion-factors-reporting/http://www.decc.gov.uk/publications/AdvancedSearch.aspx%3Fterm%3D%26tags%3D%26urn%3D10D/546%26fromDate%3D%26toDate%3D%26alpha%3Dhttp://www.decc.gov.uk/publications/AdvancedSearch.aspx%3Fterm%3D%26tags%3D%26urn%3D10D/546%26fromDate%3D%26toDate%3D%26alpha%3Dhttp://www.decc.gov.uk/publications/AdvancedSearch.aspx%3Fterm%3D%26tags%3D%26urn%3D10D/546%26fromDate%3D%26toDate%3D%26alpha%3Dhttp://www.decc.gov.uk/publications/AdvancedSearch.aspx%3Fterm%3D%26tags%3D%26urn%3D10D/546%26fromDate%3D%26toDate%3D%26alpha%3Dhttp://www.decc.gov.uk/publications/AdvancedSearch.aspx%3Fterm%3D%26tags%3D%26urn%3D10D/546%26fromDate%3D%26toDate%3D%26alpha%3Dhttp://www.decc.gov.uk/publications/AdvancedSearch.aspx%3Fterm%3D%26tags%3D%26urn%3D10D/546%26fromDate%3D%26toDate%3D%26alpha%3Dhttp://www.decc.gov.uk/publications/AdvancedSearch.aspx%3Fterm%3D%26tags%3D%26urn%3D10D/546%26fromDate%3D%26toDate%3D%26alpha%3Dhttp://www.decc.gov.uk/publications/AdvancedSearch.aspx%3Fterm%3D%26tags%3D%26urn%3D10D/546%26fromDate%3D%26toDate%3D%26alpha%3Dhttp://dx.doi.org/10.1016/j.biombioe.2012.08.004http://dx.doi.org/10.1016/j.biombioe.2012.08.004

    GIS-based location suitability of decentralized, medium scale bioenergy developments to estimate transport CO2 emissions an ...1. Introduction2. GIS model-based methodology to identify the most sustainable locations for decentralized medium scale bioenergy developments2.1. Data collection and assumptions2.2. GIS modeling and location suitability analysis2.2.1. Scoring model2.2.2. Screening model2.2.3. Location suitability layer2.2.4. Most suitable locations identification model

    2.3. Allocation of supplies to the medium scale bioenergy plants2.4. Calculation of transport CO2 emissions and costs

    3. Practical application of the methodology in Tayside and Fife/Scotland3.1. Scenario description3.2. Data collection and assumptions3.3. GIS modeling and location suitability analysis3.3.1. Scoring model3.3.2. Screening model3.3.3. Location suitability layer3.3.4. Most suitable locations identification model

    3.4. Allocation of supplies to the medium scale bioenergy plants3.5. Calculation of transport CO2 emissions and costs

    4. Results and discussion5. ConclusionReferences