5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation Approach Key sites in former BP portfolio in South Wales Management of BP Legacy “Suitable for use” not definable at present Boundary protection Mass reduction => MNA can occur Perception Management Interaction of site specific factors on: Coed Darcy Baglan Transit

Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

1

Case Study

Remediation in Neath Port TalbotSt Modwen Developments

Richard Mitchener

Mike Poland

Remediation Approach

Key sites in former BP portfolio in South Wales

● Management of BP Legacy

– “Suitable for use” not definable at present

– Boundary protection

– Mass reduction => MNA can occur

•Perception Management

•Interaction of site specific factors on:

Coed Darcy

Baglan

Transit

Page 2: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

2

•Former Llandarcy Oil Refinery

•Junction 43 M4

•420 hectares

•Coed D’Arcy Business Park

•West and south – Crymlyn Bog

Coed Darcy

Page 3: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

3

Llandarcy Transformation…

Page 4: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

4

Environmental Risk Management

Historical land-use that has resulted in the release of contamination to the ground and groundwater.

The principal contaminants:

● Petroleum hydrocarbons

● Chlorinated Solvents

● Metals and Asbestos

● Varied spatial distribution

Page 5: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

5

Conceptual Model

Page 6: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

6

Page 7: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

7

Page 8: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

8

Tip Restoration

Page 9: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

9

RAP St Modwen

Development RemediationSt Modwen

Preventative MeasuresHousing Developer

StatutoryDirectional

Boundaries & Hot spotsNon Prosecution

RBSLNew RBSL

Development monitor

Vapour BarriersPassive Venting

Monitor

7-8Years

Final Housein 2026?

Remediation Process/Management

Catchment

Management

Page 10: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

10

Crymlyn Bog Lagoon

Page 11: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

11

Page 12: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

12

Page 13: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

13

25

Transit

26

Transit - Masterplan

Page 14: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

14

27

Transit - Remediation

Dune Complex to Chemical Works

KenfigNNR/SAC/SSSI

CrymlynBurrows SSSI

The site

Page 15: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

15

Dune Complex to Chemical Works

Site developed progressively from 1960s

Sand dunes levelled

Slag form nearby steel/ironworks imported

Maximum extent/operation in late 70s, wind down and demolition in 80s and 90s

Last facility removed in 2005

Today

Transit Site & CrymlynBurrows

GE Power Station Baglan

Energy ParkIntertissue

Sandifields

Ragwormfarm

Page 16: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

16

Sources?

Ground Investigation

Page 17: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

17

Geology

Hydrogeology

Page 18: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

18

Microbial Studies

How do you demonstrate MNA?

Aim: to get definitive proof that

● The right microbes are there

– Cultures, gene counts using qPCR

● The microbes are doing what they are supposed to

– Baited traps using C-13-labeled contaminant

● C-13 ends up mineralised and in the biomass.

● Benzene and phenol both used.

Risk Assessment – Human health

Key issues:

● Who uses the beach?

● How much do they use it?

● How do they come into contact with contamination?

Get real data!

● CCTV recording of beach

● Dog walkers main users, duration can be estimated

● Loads of monitoring to understand exposure

– Contaminated water close to low tide

Seepage zone

Page 19: Case Study Remediation in Neath Port Talbot · 2017. 7. 18. · 5/26/2011 1 Case Study Remediation in Neath Port Talbot St Modwen Developments Richard Mitchener Mike Poland Remediation

5/26/2011

19

Risk Assessment – Controlled Waters

Styrene areas key remediation objective

● Aquifer properties well known

– Site testing, CSIRO model

– MNA occurrence being demonstrated

– Infiltration high – flushing

● Declining source appropriate?

– But check equations carefully

– Decline of soil source or just assume that one pore volume of contamination

The Future