Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Copyright Kenya Bankers Association, 2015
Case Study:
Three cases to demonstrate the risk to business viability from unmanaged E&S impacts
2
Three cases to demonstrate how unmanaged E&S impacts can generate business risk
Introduction
The present case study considers three projects
highlighting where community health and safety
issues present a significant business risk - for both
clients and banks providing loans.
The case considers a fertilizer plant, a chemical
plant dealing with highly inflammable substances,
and a production unit for activated carbon from
coconut shells.
Each of the three banks approached for
financing had an Environmental and Social Risk
Management System (ESMS) in place, as well as
a policy requiring clients with high E&S risk profiles
to adhere to the IFC Performance Standards (see
box on p.11).
All three cases clearly show that there is a strong
business case for banks to assess and manage
E&S risks, particularly community health and
safety risks.
While the first bank was able to avoid large losses
by properly formulating conditions prior to
disbursing the loan to its client, the third incurred
them, as it had not properly assessed the risks. In
the second case the bank successfully engaged
its client in mitigation.
All the cases are based on actual facts, and
names have been changed for reasons of
confidentiality.
Cutting the wrong corners
The company concerned is a medium sized
fertilizer manufacturer in sub-Saharan Africa. It is
located two kilometres from a national park and
4
already considered to be “environmentally
stressed” due to pollution levels.
The company has applied for a long-term loan of
around $10m. The bank categorized its activities
as a high-risk project and engaged an external
consultant to assist with the E&S due diligence.
Findings of the E&S due diligence
The E&S due diligence revealed weaknesses in
E&S management commitment and capacity
(IFC Performance Standard 1), pollution control
(PS 3), community health and safety impact
management (PS 4) and management of
impacts on the nearby national park (PS 6).
In particular, it noted that remediation actions
had not been implemented to control and
manage pollution, or to avoid significant failure
of the effluent holding ponds. These leakage risks
had been known for at least six months and the
local authorities had specifically requested the
company to address them. Specialists hired by
the company had proposed a series of mitigation
measures, a budget, responsibilities and a time
frame.
However, because of financial and time
constraints, and limited expertise, the
recommended actions were not implemented
before the loan request was made. During the
due diligence, the company management
appeared to underestimate the potential risks
associated with leakage from the pond.
Accordingly, and in order to remedy risks for both
the client and the bank, the following condition
precedent was formulated: “Client to successfully
implement all necessary activities to reduce
leakage risk”.
The E&S due
diligence found out
that the
remediation actions
as suggested with
regard to the
leakage risks were
not implemented
even though the
suggested timing
had expired.
5
What happened next?
Shortly after the bank agreed to the facility in
accordance with the preconditions, heavy rain
resulted in the release of significant volumes of
polluted effluent into the neighboring river after
the holding ponds had failed.
Wildlife and livestock were affected, with deaths
occurring along a 15km stretch of the river, and
tourism activities had to be suspended.
The local environmental authorities closed the
facilities for several weeks until the root causes
were identified and clean-up measures identified
and implemented.
Fortunately, the first loan disbursement was on
hold pending the implementation of the
condition precedents when the river pollution
incident happened. At the time of writing it is still
unclear whether or not the company will survive.
What do we learn from this case?
1. The characteristics of the receiving environment have a bearing on the
consequences of an impact. In this case, the location on an
environmentally stressed watercourse upstream from a National Park
increased the sensitivity of the environment, and so the client should
have taken more precautions.
2. The bank’s E&S system correctly identified the need for stringent
conditions regarding the repair of the leaks and saved it from potential
losses.
3. Paying attention to the E&S clauses and applying them in the loan
agreement are critical first steps in ensuring improved management of
E&S impacts..
First disbursement was on hold when the river pollution
incident happened.
6
Beyond our direct control, so it is
not our business?
The second case relates to a greenfield chemical
plant in East Africa involving highly inflammable
substances. The request was for a multimillion-
dollar long term loan from a Kenyan bank. The
project sponsors are considered to be very
professional and have a good track record in the
industry. The market potential looks good, the
technology used is state of the art, all E&S related
licenses have been obtained, construction is
almost completed, and first trial runs have started.
As part of a belated E&S due diligence, the
investment officer of the bank categorised the
project as “high risk”, triggering the need to
establish whether it was in line with the IFC
Performance Standards. Of particular concern
were the risks to worker and community health
and safety, so an external expert was hired to
undertake a site visit and review the
Environmental and Social Impact Assessment
(ESIA) that had been prepared by the client and
approved by the authorities.
The study was found to address most of the
requirements of the IFC Performance Standards,
but there were a number of issues that had not
been adequately considered by the ESIA:
1. Inadequacy of emergency preparedness
and response plans and the absence of
any engagement with neighbouring
entities or communities;
2. The potentially fatal risks associated with
inadequate emergency services, poor
road infrastructure and a congested
industrial neighborhood;
3. The presence of informal vendors
immediately outside the company walls,
some of whom were preparing food and
beverages on open fires close to the
petroleum intake.
The eight
Performance
Standards have
become the
benchmark standards
for FI’s E&S risk
management.
7
The mitigation measures proposed included:
1. The development of a joint emergency response plan in consultation
with neighbouring companies and vendors;
2. Movement of the vendors to a vacant space 50 metres away from the
company boundary;
3. Improvements to the road infrastructure to ensure a quicker response
time of emergency services.
Although the company may not incur any major costs directly, management
must be committed to ensuring that the measures are implemented,
especially as some of them are the responsibility of third parties, such as the
local authority. Without these measures the safety of the public and other
businesses are put at risk.
What do we learn from this case?
1. Be aware when projects with inherently high community health and
safety risks are located in a congested environment. Always ask
whether the location is appropriate, regardless of approvals from
authorities. Are you exposing the bank unnecessarily?
2. Look beyond the factors that are directly within your client’s control.
What impact might your client’s activities have on areas outside their
direct control, such as the road infrastructure? Understand these risks,
establish whether the client has any influence over their management
and identify strategies and the associated costs.
8
Activated Carbon
Company from a bird’s
perspective (Source:
Google Earth)
Community kicks up some dust
The third case features a medium size company
that manufactures activated carbon from
coconut shells. Activated carbon is considered to
have several environmental benefits, as it is used
in filters to trap pollutants and is made from
organic waste.
While the product has benefits, its production
generates heavy dust pollution if it is not
managed properly by applying dust abatement
measures throughout the production chain, and
covering the stock to protecting it from the wind.
In order to expand production by developing a
further two hectares, the company requested a
long term loan of $7m. As part of its E&S risk
assessment the bank categorized the project as
medium risk and asked the client to respond to a
standard E&S questionnaire. No E&S specialist
was engaged.
The bank was under some pressure to close the
deal quickly and did not send a representative to
the site before approving and signing the facility
agreement. A clause was included in the
agreement requiring the company to comply
with all relevant local E&S legislation and norms
but at no point was it requested to submit
documentation to demonstrate compliance.
9
What could have gone wrong?
Shortly after the loan agreement was signed, the bank learned from a
newspaper report that the company had been closed down by the local
authority. The trigger for the closure was a community protest that had
blocked the factory and turned violent. The community was protesting
against the high levels of dust pollution and was concerned that the factory
expansion would worsen the situation.
It subsequently became clear to the bank that the factory had been
exceeding national emissions levels by a significant amount for some time,
but the local authorities had only issued occasional warnings and taken no
other action. None of this information had been shared with the bank when
the due diligence was undertaken and at no point after signing the loan
agreement did the bank follow it up. Had the bank taken the time to visit the
site and also to consult the employees and surrounding communities it would
not only have seen the high levels of dust but also have heard how the dust
was affecting residents and fuelling their concerns about an expansion.
For reputational reasons, the bank decided to withdraw from the project,
incurring heavy financial losses.
The company just about survived, but needed to install dust abatement
equipment and E&S management systems and invest heavily in corporate
social responsibility activities and community engagement to begin the
process of rebuilding local trust. Had the issue of dust emissions been
addressed earlier, the reputational and financial losses could have been
prevented.
What have we learned?
1. Do not rely on the client to conduct your due diligence, and visit the
site as often as possible, ideally with the help of a specialist. Continue
visiting the site even after disbursements have been made.
2. Talk to other stakeholders during the site visits, especially those directly
affected such as neighboring communities. This can be more revealing
than studying reports.
3. Start to consider E&S issues as early in the process as possible to avoid
cutting corners with the E&S due diligence.
4. Would you and your family like to live next to the project you are
financing? If not, you can probably count on community activism.
10
Lessons Learned from all Cases
1. E&S Management Systems in FIs pay: The integration of an E&S risk
assessment into the credit analysis processes can prevent significant
financial losses in the loan portfolio. Unfortunately, experiences show
that banks need to have incurred financial losses due to unmanaged
E&S risks at least once, before they start implementing such a system.
2. E&S risk enquiry must go beyond boundary walls: Understanding the full
scope of a client’s activities, area of influence and potential impacts is
fundamental. High risks can be associated with impacts on a
surrounding community, in the supply chain or an associated activity
that is located apart from the primary operation.
3. Don’t be shy with clients: Engaging with the client on E&S issues does
not damage the relationship between you. On the contrary, as shown
by the chemical industry case study the E&S conversation can be
much appreciated. A bank’s fear over losing business when addressing
E&S risks is rarely justified.
4. Don’t rely on permits only for due diligence: Relying on the clearance
and monitoring of environmental authorities (permits, acceptance of
EIA studies, etc.) may not always be sufficient. There are many
investment projects in which E&S risks have turned into business risks,
and they need to be treated as such, regardless of whether an
authority has passed an approval.
5. When in doubt, involve specialists…: E&S risks are not always obvious
and some can only be identified by experts. For financial institutions, it
is of prime importance to gauge whether a particular project could
have high E&S risks elements, and if so, where the right expert can be
found.
6. …and open your own eyes: Some E&S risks, including those to
neighboring communities, are often obvious and can be identified by
a non-expert. Never underestimate the importance of site visits and
taking the time to see as much as possible for yourself.
7. Be alert to inadequate management commitment and capacity: The
risk of a costly disaster is generally higher when a client’s activities have
inherently high E&S risks and when their track record indicates a lack of
commitment and capacity to act appropriately. This risk is heightened
when the bank is under pressure to close the deal rather than ensure
that the client takes appropriate mitigation measures.
IFC Performance Standard
The IFC Performance Standards (PS) define banks clients’ responsibilities for
managing their environmental and social risks. Together, they establish
standards that the client is to meet throughout the life of an investment.
IFC Performance Standard 1: Assessment and Management of E&S Risks
and Impacts
IFC Performance Standard 2: Labor and Working Conditions
IFC Performance Standard 3: Resource Efficiency and Pollution Prevention
IFC Performance Standard 4: Community Health, Safety, and Security
IFC Performance Standard 5: Land Acquisition and Involuntary Resettlement
IFC Performance Standard 6: Biodiversity Conservation and Sustainable
Management of Living Natural Resources
IFC Performance Standard 7: Indigenous Peoples
IFC Performance Standard 8: Cultural Heritage
IFC PS have become the benchmark standards for a bank’s E&S risk
management.
An estimated 80% of total project finance debt in emerging market economies
is already based on IFC PS.
Adherence to IFC PS and framework is international good banking practice
and significantly reduces risks.
12
Bhopal: A
disastrous accident
banks would not
want to be
involved in, and
case to learn from.
Union carbide pesticide plant in
Bhopal
One of the most disastrous industrial accidents of all
times: Bhopal
It occurred on the night of 2–3 December 1984 at
the Union Carbide India Limited (UCIL) pesticide
plant in Bhopal. Over 500,000 people were exposed
to methyl isocyanate and other chemicals.
The toxic substance made its way in and around the
shanty towns located near the plant. Estimates vary
on the death toll. The official immediate death toll
was 2,259. An investigation into the root causes of
the accident revealed that:
1. Gas tanks were filled beyond recommended
levels.
2. Equipment was poorly maintained.
3. There was a failure of several safety systems
(due to poor maintenance).
4. Some Safety systems were switched off (to
save money).
5. Little manpower was used (to save money).
6. No stainless steel used for crucial equipment
parts (to save money).
The problem was made worse by the mushrooming
of slums in the vicinity of the plant, non-existent
emergency response plans, and shortcomings in
health care and socio-economic rehabilitation.
By 2007, more than 1 million cases were filed out of
which some 570 thousand were awarded. The total
financial impact to the firm was in excess of $240m,
not including decontamination and environmental
rehabilitation costs.