CASE STUDY:CASE STUDY:Malabar Creek, NSW
Ecoflex EEcoflex E--Rosion SystemRosion SystemProject No: EAJ00094Project No: EAJ00094
EA-MAR-036Rev 01
© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 51820 Kalaroo Road, Redhead NSW 2290 Australia.
Page 2© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
TABLE OF CONTENTSTABLE OF CONTENTS
Lic No: EF-2003AELA Approved
TITLE PAGE#
Project Background…………………………………… 03
Project Specification & Design………………………... 04
Design Drawings…………………………………….
05-08
Engineers Certification………………………………... 09-12
Construction Photographs……………………………. 13-22
Company Information………………………………
23
Product
The recycled rubber technology employed by Ecoflex has been assessed by the Australian Environmental Labeling Association and has been awarded a Good Environmental Choice Licence by the Australian Ecolabel Program. The technology was assessed against the voluntary environmental labeling standard for
Recycled Rubber Products: AELA-Recycled Rubber 2003. Details: www.aela.org.au.
Page 3© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
PROJECT BACKGROUNDPROJECT BACKGROUNDThe client, North Moruya Industrial Estate, as a condition of the Development Consent issued by Eurobodalla Shire Council to client’s project manager JCL Development Solutions was required to rehabilitate a portion of Malabar Creek and riparian zone. This consent condition was imposed as a result of continuing degradation of the creek due to the previous unsuccessful attempts by the developer of the estate to control erosion, and after extensive coordination with DIPNR, now conservation and environment, and Eurobodalla Shire Council on extent of words required.
Cardno Willing were briefed and engaged by JCL to design a solution for rehabilitation works that would provide cost effective solution for the client, whilst ensuring that the completed structure would comply with all Council and DIPNR requirements.
These requirements for rehabilitation included works included consideration of:
• Aesthetics as a non engineered visually natural structure was mandated.
•A raft of environmental considerations for the protection and rehabilitation of natural flora and fauna.Performance of the structure up to the 1 in 100 year flood design flow rates.
Lifecycle cost of the structure from a maintenance perspective.
After coordination with Jim Olive of JCL, John Tilley from Cardno Willing considered that a design using the hoop strength of the Ecoflex units with a locally available dense granite to his specifications would fulfil all the interested parties requirements.
After extensive consideration by all the interested parties the project was approved to proceed.The Designer had particular regards to the unique properties of the Ecoflex Systems; namely:
Cost – The E.Bridge system is estimated to have reduced costs by around 20%.
Environmental – Low impact environmental considerations were a major factor in the selection of the E.Bridge System for this project.
Durability – The long term retention of the hoop strength of the Ecoflex units ensures a long life for the structure irrespective of vegetative cycles.
Sustainability – Ecoflex units were manufactured on site using locally obtained used truck tyres using a very low energy consumption process.
Page 4© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
PROJECT SPECIFICATION & DESIGNPROJECT SPECIFICATION & DESIGN
Project Name: Malabar Creek, Moruya NSW
Client:: Moruya Industrial Estate Pty Ltd
Project Administration: JCL Development Solutions
Ecoflex System: E-Rosion
Contractor:: Ecoflex Civil Constructions Pty Ltd
Project Purpose: Rehabilitation of Malabar Creek and Riparian Zone
Consulting Engineer: Cardno Willing (NSW) Pty Ltd
The design drawings are included in this case study for further information regarding this project.
The project involved construction of Ecoflex E-Rosion to the engineers design to create scour protection to the creek bed and erosion protection to the adjacent riparian zone.The final area was 2222 m2.
The construction of this Ecoflex E-Rosion area utilised approximately 100 Tonnes of used truck tyres all gained from the regional area. This is a contribution to greenhouse savings especially when compared to the environmental costs of virgin materials.
Key considerations included:• Environmental• Speed of Construction• Sustainability• Durability• Performance
Page 5© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
DESIGN DRAWINGSDESIGN DRAWINGS
Page 6© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
DESIGN DRAWINGSDESIGN DRAWINGS
Page 7© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
DESIGN DRAWINGSDESIGN DRAWINGS
Page 8© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
DESIGN DRAWINGSDESIGN DRAWINGS
Page 9© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
ENGINEER’S CERTIFICATIONENGINEER’S CERTIFICATION
Page 10© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
ENGINEER’S CERTIFICATIONENGINEER’S CERTIFICATION
Page 11© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
ENGINEER’S CERTIFICATIONENGINEER’S CERTIFICATION
Page 12© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
ENGINEER’S CERTIFICATIONENGINEER’S CERTIFICATION
Page 13© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
CONSTRUCTION PHOTOGRAPHSCONSTRUCTION PHOTOGRAPHS
Malabar Creek Prior to StartMalabar Creek Prior to Start
Page 14© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
CONSTRUCTION PHOTOGRAPHSCONSTRUCTION PHOTOGRAPHS
Malabar Creek Prior to StartMalabar Creek Prior to Start
Page 15© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
CONSTRUCTION PHOTOGRAPHSCONSTRUCTION PHOTOGRAPHS
Granite Infill Specified ( Circled Film Case)Granite Infill Specified ( Circled Film Case)
Page 16© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
CONSTRUCTION PHOTOGRAPHSCONSTRUCTION PHOTOGRAPHS
Pre Installation TestingPre Installation Testing
Page 17© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
CONSTRUCTION PHOTOGRAPHSCONSTRUCTION PHOTOGRAPHS
Construction PhaseConstruction Phase
Page 18© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
CONSTRUCTION PHOTOGRAPHSCONSTRUCTION PHOTOGRAPHS
Construction PhaseConstruction Phase
Page 19© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
CONSTRUCTION PHOTOGRAPHSCONSTRUCTION PHOTOGRAPHS
Top Soil PlacementTop Soil Placement
Page 20© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
CONSTRUCTION PHOTOGRAPHSCONSTRUCTION PHOTOGRAPHS
Top Soil Application CompletedTop Soil Application Completed
Page 21© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
CONSTRUCTION PHOTOGRAPHSCONSTRUCTION PHOTOGRAPHS
Storm Event Post ConstructionStorm Event Post Construction
Page 22© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
CONSTRUCTION PHOTOGRAPHSCONSTRUCTION PHOTOGRAPHS
During and After Storm Event
Page 23© Copyright 2006 ECOFLEX AUSTRALIA PTY LTD ABN 53 081 641 518
20 Kalaroo Road, Redhead NSW 2290, Australia.
CASE STUDY:Malabar Creek, Moruya NSW
Ecoflex E-Rosion System
EA-MAR-036 Rev 1
COMPANY INFORMATIONCOMPANY INFORMATION
HEAD OFFICE:Newcastle
20 Kalaroo RoadRedhead NSW 2290, Australia
Telephone: +61 2 4944 7711Facsimile: +61 2 4944 9911
E-mail: [email protected]: www.ecoflex.com.au
PATENTSInternational Patents cover the works and intellectual property shown in this document. All rights reserved. No part of the works and/or
intellectual property may be reproduced or utilised in any form or by means, without prior written consent of ECOFLEX AUSTRALIA PTY LTD.