6
CE 616: Earth Retaining Structures M.Tech Geotechnical Engineering. A case study on geotechnical design Dr. Ramakrishna Bag [email protected] Dept. of Civil Engineering National Institute of Technology, Rourkela

Case Study

Embed Size (px)

DESCRIPTION

PROPOSED HIGHWAY CONSTRUCTIONDesign 1km stretch of a highway in a rural area, encompassing a crossing with an existing rural road on a flat low lying flood plain.Design aspects should consider the following: A minimum gradient of 1:300 is required to meet surface water runoff requirements. The 10 year return period flood level is 52 m. Earth retaining embankments are to be constructed to a gradient of 1:2 due to limited land availability. A minimum clearance is required between road level and the underneath of a bridge. The clearance for each group should be

Citation preview

  • CE 616: Earth Retaining Structures

    M.Tech Geotechnical Engineering.

    A case study on geotechnical design

    Dr. Ramakrishna Bag

    [email protected]

    Dept. of Civil Engineering

    National Institute of Technology, Rourkela

    mailto:[email protected]

  • PROPOSED HIGHWAY CONSTRUCTION

    Design 1km stretch of a highway in a rural area, encompassing a

    crossing with an existing rural road on a flat low lying flood plain.

    Design aspects should consider the following:

    A minimum gradient of 1:300 is required to meet surface water

    runoff requirements.

    The 10 year return period flood level is 52 m.

    Earth retaining embankments are to be constructed to a gradient

    of 1:2 due to limited land availability.

    A minimum clearance is required between road level and the

    underneath of a bridge. The clearance for each group should be

    as given in the Table:

    Group no. Minimum clearance (m)

    1 4.5

    2 5.0

    3 5.5

    4 6.0

    Width of existing rural road is 5m and width of highway is 20m.

    Existing rural road and highway should not meet at the same

    level. There may be a separate connecting road between

    highway and rural road.

    There should not any sharing of calculations between different

    groups.

  • Every individual must submit their report latest by 17th April,

    2015; 17:00 hours through moodle.

    Only calculations will be shared amongst group members.

    Copying from other will lead to penalty for both students.

    The report must include Summary, Introduction, Design

    solution, Conclusion and Appendix. Except Appendix every

    individual must write on their own.

    Appendices will be group submission containing settlement,

    bearing capacity and slope stability calculation.

    The group members will be as follows

    BAISHNU BHUSAN BEHERA

    Gr 1 VIKAS KUMAR

    ABHISHEK KUMAR

    SHWETA YOGIRAJ MAHAJAN

    PIYUSH PARIK

    Gr 2 AHSAN RABBANI KARNATI CHAKRAPAN

    PADMAJA SWAIN

    ANOOP KUMAR TIWARI

    Gr 3 BANAVATH RAMESH

    RANAJEET MOHANTY

    TARINI JAHNAVI

    JYOTIRMAYEE MALLICK

    Gr 4 RAMANA REDDY KATIPELLY

    DUMMU SINDHUJA

    SHUBHAM RAJPUT

  • Site Plan

    Distance between Point A and B is 1000 m.

    Point A G.L. = 49.6 m

    Point B G.L. = 50.5 m

    Point C G.L. = 49.5 m

    Point D G.L. = 50.2 m

    Proposed highway

    Existing rural Road

  • Soil profile of borehole @ C/L of motorway as follows:

    Vane shear test results

    0

    4

    8

    12

    16

    20

    0 5 10 15 20

    Dep

    th b

    elo

    w G

    .L (

    m)

    Shear strength (kPa)

    150 mm Top soil

    Very soft Clay of high

    plasticity to soft brown clay

    of high plasticity at depth

    Brownish mud stone

    0.15 m

    0

    18 m

    20 m

  • Properties of the soil and backfill material as follows:

    Assume saturated soil

    Properties Clay Fill material

    Unit weight (kN/ m3) 18 (sat) 20

    LL (%) 58 --

    PL (%) 28 --

    PI (%) 30 --

    Friction angle, () 23o 35o

    Effective cohesion, C (kN/m2) 2 20

    Undrained shear strength,

    Cu (kN/m2)

    Look at vane

    shear test results

    73

    The ultimate bearing capacity of the foundation soil (saturated clay) can

    be calculated from, qu = 7.5 Cu, where Cu is the undrained shear strength

    of soil.

    Parameters for calculating total settlement and time required for

    settlement

    Consider 70% time dependent consolidation settlement will take place

    during the construction period; mv = 0.004 m2/kN, cv = 1.8 m

    2/yr.