Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Carter Lawson, Jeri
From: Sent: To: Subject:
FYI
Donna Dones CBU
Dones, Donna Tuesday, September 23, 2014 8:17AM Carter Lawson, Jeri FW: Texas Public Information Request - Trinity Watershed Management
Trinity Watershed Management (214) 243-1164
From: Fernandez, Elizabeth Sent: Tuesday, September 23, 2014 7:56AM To: Dones, Donna; 1ippie, Kristina; Cottingham, Jennifer
Cc: Nguyen, Than Subject: FW: Texas Public Information Request- Trinity Watershed Management
Please address
From: Hal Barker [mailto:hbarker [email protected]]
Sent: Tuesday, September 23, 2014 6:10AM To: OpenRecords Cc: Fernandez, Elizabeth Subject: RE: Texas Public Information Request - Trinity Watershed Management
Correction in Open Records Request To Trinity Watershed Management.
In my September 22 2014 request below, I had identified Borrow Area D AKA Borrow Area 3.
This should be Borrow Area D AKA Borrow Area 4. For further clarification, this is also located on the Burrescia property
noted in maps south of Elam Road.
Please note this correction in my request.
Hal Barker 9191 Garland Road 1126
Dallas, TX 75218 Hbarker [email protected]
From: Hal Barker [mailto:hbarker [email protected]]
Sent: Monday, September 22, 2014 9:24AM To: 'OpenRecords' Cc: 'Fernandez, Elizabeth' Subject: Texas Public Information Request - Trinity Watershed Management
Greetings,
This is a request under the Texas Public Information Act.
Records relating to Trinity Watershed Management
Reference: Proposal Documents for Simpkins Remediation- Vegetative Support Layer PBSWM007, File NO. 428D-20, 251D-l. A Notice to all Bidders dated April 25, 2014. I have a 186 page set of records relating to this filing. I do not need an additional copy.
Clarification: Recently, I was told by officials ofthe Trinity Watershed Management that Borrow Area D, AKA Borrow Area 3, was originally designated for most if not all borrow soil needs for the Simpkins Remediation and additional facilities needs ( in conjunction with Borrow Area C south of Loop 12). The statements were that the City of Dallas determined that due to a stand of trees in Borrow Area D, and the desire to protect these trees, Borrow Area A was designated to provide soil needs for the Simpkins Remediation.
Request:
I request copies of all communications, including emails and communications reduced to writing, relating to the Borrow Area D, AKA Borrow Area 3, from the date January 1 2013 to date of this request.
This should include all communications between Trinity Watershed Management and the City Arborist relating to Borrow Area D.
If any contracts were let and signed for removal of soil from Borrow Area D, please provide a copy of the contract.
If you have any questions, please let me know. If this appears overly broad in scope, we can discuss narrowing the scope of this request.
Hal Barker 9191 Garland Road 1126 Dallas, TX 75218 Hbarker [email protected]
2
Nguyen, Than
From: Sent: To: Subject: Attachments:
Than,
Jim Barger <J [email protected]>
Thursday, November 07, 2013 12:11 PM
Nguyen, Than RE: Nearby Borrow Source for Golf Course
Trinity Forest - Elam Borrow Areas.pdf
Use this file . I think I was looking at your exhibit incorrectly. I believe your Lake A is theE & F areas in this file. Your lake
A (areas E & Fin the attached) is certainly viable but PK should look at all the utilities in this area.
Jim
From: Jim Barger Sent: Thursday, November 07, 2013 11 :53 AM To: 'Nguyen, Than' Subject: RE: Nearby Borrow Source for Golf Course
Than,
Here is where we are with the borrow area. Think we 're pretty close but would like to:
1. Maximize Lake A/B excavatron . 2. Stay away from the Horse Park, or any areas not adjacent to the landfills (to minimize haul distances)
3. Explore Lakes C, D and E, or some variant of them.
Thanks,
Jim
PS· Attached a complete vcard for me for your contacts.
From: Nguyen, Than [mailto:[email protected]] Sent: Tuesday, November 05, 2013 4:25PM To: Jim Barger Subject: FW: Nearby Borrow Source for Golf Course
We are getting close to finalizing the scope of work with Pacheco Koch on these ponds. Let me know 1f you agree w1 th
the new ponds as a borrow source.
Than
From: Nguyen, Than Sent: Friday, September 06, 2013 6:25 PM To: 'Jim Barger' Cc: 'Jim Barger' Subject: Nearby Borrow Source for Golf Course
Hi Jim,
Long time no hear. I know that the last t ime we met, we discussed the nearby offsite borrow source needed and how
the sand layer at the Burrescia property (5950 Elam Road) was needed for your project as a total of 450,000 cubic yards
of borrow material was needed north of Loop 12.
We discussed this internally and found a solution for this needed dirt as this borrow source will consist of 3 ponds; 2
new ponds (1 northwest of the western end of Elam Road and 1 on the northern portion of the Burrescia property) and
an enhancement of an existing pond near the entrance into the Horse Park; see enclosed figure. Pacheco Koch revised
the hydraulic modeling for the approved fill permit.
Let me know if you agree with the 3 ponds as the sand borrow source is still there.
Than
This email was Anti Virus checked by Astaro Security Gateway. ttto://www . astaro . com
2
Nguyen, Than
From: Sent: To: Subject:
Than,
Jim Barger <[email protected] >
Thursday, June 06, 2013 10:04 AM
Nguyen, Than
RE: Borrow Area and Irrigation Pond Location
The darker blue area should take care of everything. May be less than thls ... JUSt depends upon how deep we can
go. This is less area disturbed than the fill permit plan .
The lighter area south is if more •s needed.
Jim
From: Nguyen, Than [mailto:[email protected]
Sent: Wednesday, June OS, 2013 11:35 AM
To: Jim Barger SUbject: Borrow Area and Irrigation Pond Location
Jim,
Do you have a sketch or conceptual layout for the Burrescia property to use as a borrow area/pond and the irrigation pond? If so, please provide so we have an idea of the layout. Thanks.
Than
This email was l\.nti Virus checked by Astaro Security Gateway. http://ww•,.,.astaro.com
2
Carter Lawson, Jeri
From: Sent: To: Subject: Attachments:
FYI
Fernandez, Elizabeth Thursday, September 18, 2014 10:53 AM Clark, Dorey FW: Tree Survey for Borrow Areas A, B, C, and D Combined Tree removal pdf; Simpkins Remediation- Vegetative Support Layer (PBSWM007}
Overview Map.pdf
--Original Message-From: Nguyen, Than Sent: Tuesday, September 16, 201 '1: 3:3~) PM
To: Fernandez, Elizabeth Cc: Standifer, Sarah; Cottingham, Jennifer
Subject: RE: Tree Survey for Borrow Areas A, B, C, and D
Liz,
The index cover page was old but has been updated; see enclosed. I inserted an aerial overlay
to help out for Borrow Area A. Below is the tree count and mitigation inches for each Borrow
Area:
Borrow Area A- 'i94 trees- 3511 inches (Selected due to the lower concentration of trees)
Borrow Area B- 172 trees- 2,329 inches (Large and heavily wooded and near abandoned
United Gas line easement). A lot smaller in size than Borrow Area A.
Borrow Area C- "1·.'34 trees - 5,562 inches (lrrigation Pond) Borrow Area D- 14· trees- 31 S
inches (Burrescia Property- small number of trees but they were all very large pecan trees)
Than
--Original Message-From: Fernandez, Elizabeth Serit: Tuesday, September 16, 2014 10:29 AM
To: Nguyen, Than Cc: Standifer, Sarah; Cottingham, Jennifer Su~ject: Re: Tree Survey for Borrow Areas A, B, C, and D
Than,
This is the old borrow A. vVhat is the new borrow A tree count?
> On Sep 1.5, 201 <~, at 2:00 PM, "Nguyen, Than" <[email protected]> wrote:
> >Sarah,
> > Enclosed is the finalized tree survey for Borrow Areas A, B, C (Irrigation Pond), and D
(Burrescia Property). We do not plan on using Borrow Area Band D. \Ve chose Borrow Area
A dues to the amount of tree in that area. We may slight modifications to BoHow Area A & C
in the construction phase as the enclosed file has the updated survey information.
> >Than > <Tree Survey for Borrow Areas A, B, C & D.pdf>
2
II ' ' '.
_) ) /
•• ..> "'\
'0.:(·--,,.·-·-··''-,, ...
'" C"'
\
..
'"\ ...
-~ ~-\ v '.
f. ~
~~ ] I ? l ,.,. .. .r l
~-.-~ . ·' 3 ·c
,; 1"
·,
" '
i (
~ r · --~ _ _:~-;;.--;;;;;-:_~--_ . I ~-1 ( .. r ·~-··...... -1 ) ~ --::·.: .. ~- l"'"'!!!..~~~r .:.;l~· .. h; i
~ ~'-~:=E:::i:...!.~ I I · :;:;.. --::!...:.!J.!_:_:.:.:::...:L __ ~ l
I ----~---'-·- --- - - · .. .!':~--= .·.::.~:.~:-· ·---·· ]·--'-~-! ~ ......... _..................................................... ~
~~·- ~~
\ ,/ ' ~ l.~-~~~---~------~/
l ! I
,//
~ • " ... o-.:
c:rr.: ...... L•uf · Oo 11(1
- t· ·-----! l
i· . ~ : ~~ f.i J 1·
~ t -· ·--- r--.. ... ' ., ·: ' ,) , . , . . II ' ! 0 Jt' ; I I ! !
I ' • j
' ,: . .• I t . , ' : < •.: lllr.l ff:WffllP~ l•"··t.w
f
I I
' I
.,. ;
. /
... ......._ ------~_,.. _ __,..,__.....___
·,
;'
I.
- ·~
... /'' ---•; .
-?,.
I i ,,,. ..
·-......_
/ /--- - ~-..
- :r ol
.;
'.
·' <:!:! (~·:::!.;:::':i!!~,!-;; .. :·.i ' .•. i ·rr···-:-·-r;--:ri--~----
1 I r-..t ............... · · .
. : .. ••t ,.j'l ;• : . ::·i· I • • t . ' I - i t'j' . . .. ,;;, 0
.. I . ".1 .. ··-L~;· J~·: . ·'j -1- • ' •.•
F!ill~i~·· :(d'' ):L ·:,, ,:I I . . L' · r"' 1%!?·1!! · M·~!'· ·a ~ 1 :1 ••· • . ·-·---;..'i''• :" '-': ' '.jJltll , ... ,, ~ ·f···-r--~-----....... ·-·-· r.~tr:l:;l!t:Jr~:r::t::: 1 · l'l . .~r_ .J. :-.
. ''· . ... ' . ~ . ~:
• .l 0c.J
'' 'ti
,. ,. i• i ;·
I' l-~·:~ !' ._ ;
0 '- ,;, /:;. v s /
6 /
= J "/ , ...
• <! I.
,.,.,.., .... u-.. .._ . r.J• ·-·- ... l>'t ,..,..,,.._,., •noo• '?>~-~·Too:~.
~ ~ 0
•.
' rliliM'tlll' ~~iOiii>lo~ n~t'jrt~~~~~ ffi1HI] I al ~ I kl ~~ ~·~ m I 'IH ~ n·~ ,J,H [il~rH•ql . JJtf 'r.Jl~it1J1 }, .. 1 ~:1 t .. ~ 1, J.r~i·.~~·~i ~~ 114U .. ·~~ I ~~~ ~f ! ~~~,~~r I ,11!1 ,,~n~~~"~'~' I~ t~ ,, J~J~ 'il! ~ ~ , .I ~ I· , u • ~r ~~~ , ·' Mi ~ '~*~~~~ I, ~~~~~ , ~:~~~~~. ,
1 • 1+ -'-'-i-t+'- f .. I I I • , I .l 4·t .111 ol I .
I ' ' I'!:' ' I I ' I ! I I I I ' ' ., r H~rflrwmttt t . .ff · ~ ·; H h c r ~ ~ r'h ,. t1T! ·~ r ~~H ,., L 1111 !I~ li 11 ilm!illli! ~i Ill! lliii· IL !IIHtllli} !.U lJW] ·W m~~ ., m!IU I rriO~'IIil~r·· ili!il'i~'li'H hiiTi"Hi
n~ t; 'I! "I m lfiW ~~· ' ml ' 11'11!1'~ rrn ~1 . ~,, r .~ri~m~~ ,. ~r:: i "~ :~ l ·'(r:/ l .~ .~t.rJ·Fi ~~~ ~) .. - .t~it·' t'. ~ r r 1 ~~~,~~~~ '~1,,1: I 1 ·,~m~, · ., 'li\1111~ '1' )~I ,~ ~~~ 1!
1 ~~I !)~~mm~~~~ ~~lt ~ ~ ~~~ ~ U~1 ~i 1 j,! I n 111~~ :1 ~~ . .. , rr..lf1 l1f~ +w:·. r~tffi 1· dlr .. P':H~ ·tmf. ff. Ti f' :]~l[JJJIJ i · · H IJ 1,! 11ll II I I I . Ill IHUilllLJJJ ~ L:
I I: @ R Z . ~
_. ·-
I I. •, -.;t f • I~ l t If f • • • 0
• 0
• • t i : ~ •.• 0
i 'I
j t b :-:~r illdftsi~l
.... -· - ... .... .... -. . , "":: -
" ' r
~ ;
~ i?: «
!!'
"•"" t.....:' .. o\' ~""'I'"' ....... . • ., .. » '--' ..... .... G-.. 8·-· "~·-" ·' G,.. ,,, ~~t ~· ... '""'"' ·-· " .... . G ..... G··" Q .... ,.. ...... _
. ... ~. . . ~,. G G"G .. , "Q-. .... ,.,... G::::._
cr~ ;~,,,
o~
.• r;)
G" // "~C· r--~ ... Go¥ \ ... c ........ 10 //
1
a .. /
/ I - &," G.' 0 .-<", C" .. :. / "'.,_]""' ,·.. G... G· !( r·:.~·-
G·.. I I ,...\.IS', ;I (]--• ·~
0· ,, ..._,..,.
0'--.-. ... , ··8 ~ ""' wE) G ..
G--'Z::_:::::~-·
(iJF \\ I'
&}. ~ \G•u 'I ). ~
\ tlflt:_.. ..
:,• ---- . , ..... :- lo!
• I p ~
-~ G .. -
---I 0·
~~' - - .•. ~ ... : -.. -.... ,. - •.
'~
LEOE~D
OICIIIQI-··U'rlliFill ,... CMMt
ONJI'·~~
l- ..... i-·1 ~ 1'"1-:-..=:-1--1 ..=;:."::...
8
~ • .. '11 -
CliAI'tCS,C-.. .........
-- II ........... ~
I-'-~ i __i ~~~~ -!fl_
& -
"----~-TRI!I'! MITIGATION AREAO
SIMPKINS REMEDIATiON VEGETATIVE SUPPORT UYEli IMPROVEMENTS'
C/TYOF.lWl.LA~' ,~.,-
-1-I"'·J--1~-1 ~· I '" ~ I .. 1-;;,"1 ··-I I4:Z8DI 20
_"'",.... ... -... _~
Carter Lawson, Jeri
From: Clark, Dorey Sent: To:
Thursday, September 18, 2014 10:55 AM Fernandez, Elizabeth
Subject: RE: Tree Survey for Borrow Areas A, 8, C, and D
Includes non-protected in count.
Dorey Clark Sr Project Coordinator Trinity Watershed Management City of Dallas 2 H-.671.9583
--Original Message-From: Fernandez, Elizaheth Sent: Thursday, September IS, 201 <~ 10:53 AM To: Clark, Dorey Subject: FW: Tree Survey for Borrow Areas A, B, C, and D
FYI
--Original Message--From: Nguyen, Than Sent: Tuesday, September 16, 2014 3:39PM To: Fernandez, Elizabeth Cc: Standifer, Sarah; Cottingham, Jennifer Subject: RE: Tree Survey for Borrow Areas A, B, C, and D
Liz,
The index cover page was old but has been updated; see enclosed. I inserted an aerial overlay
to help out for Borrow Area A. Below is the tree count and mitigation inches tot· each Borrow
Area:
Borrow Area A- 294 trees- 3.51 1 inches (Selected due to the lower concentration of trees)
Borrow Area B - 172 trees - 2,329 inches (Large and heavily wooded and near abandoned
United Gas line easement). A lot smaller in size than Borrow Area A. Borrow Area C- 434 trees- 5,562 inches (Irrigation Pond) Borrow Area D- H trees- 31 S
inches (Burrescia Property- small number of trees but they were all very large pecan trees)
Than
--Original Message--
3 l
From: Fernandez, Elizabeth Sent: Tuesday, September 16,2014 10:2~1 AM To: Nguyen, Than Cc: Standifer, Sarah; Cottingham, Jennifer Su~ject: Re: Tree Survey for Borrow Areas A, B, C, and 0
Than,
This is the old borrow A. What is the new borrow A tree count?
>On Sep 15, 20 1+, at 2:00PM, "Nguyen, Than" <[email protected]> wrote: > >Sarah, > > Enclosed is the finalized tree survey tor Borrow Areas A, B, C (Irrigation Pond), and 0 (Burrescia Property). We do not plan on using Borrow Area Band D. vVe chose Borrow Area A dues to the amount of tree in that area. We may slight moJifications to Borrow Area A & C in the construction phase as the enclosed file has the updated survey information. > >Than > <Tree Survey for Borrow Areas A, B, C & D.pdf>
Carter Lawson, Jeri
From: Nguyen, Than Sent: Tuesday, June 17, 2014 4:58PM
dproctor@dcicontracting org Greg Sherman
To: Cc: Subject: RE: Simpkins Remediation- Rock Excavation, Other Issues
Simpkins Remediation -Addendum #1 - Letter Only.pdf Attachments:
David,
See my response in blue below:
Than
From: [email protected] [mailto:[email protected]]
Sent: Friday, June 13, 2014 10:02 AM
To: Nguyen, Than Cc: Diviney, Patrick; Greg Sherman Subject: Simpkins Remediation - Rock Excavation, Other Issues
Than, As requested per your previous e-mail, here is the additional cost for rock excavation:
Based on a reduced depth of 16', this equates to an additional cost for 12,200 cu. )'ds (ii) $16 pc1·
cu.p..l. = SJ 95,200.00 If this material can be placed in a single layer in the bottom of the base ofthc structural fill, 12" to
18" pieces, then run O\-'Cr with a sheepsfoot compactor, then the additional cost fo excaYatc would be
$8.00 per cu. yd. x 12,200 cu. yd~;. = S97,600.00
I have review the plans and spec book for this and feel that additional compensation for rock excavation is not
justified. As stated within B-11 (Unclassified Excavation, Bid Item 103 & Alternate Bid Item 1), "Technical
Specification B-14 (Geotechnical Information} will apply for this project also." Within 8-14, it talks about
limestone fill material as shown in the Boring logs and Plan sheets. The boring logs were shown in the spec book
and plan sheets near the cross section pages. The soil stratums were presented in the bid documents (plans and
specification book) and the volume accounted for in the cross sections and the bid quantity of 656,418 cubic
yards of material needed. This was not an unforeseen existing condition and your proposed cost is unreasonable
also.
Additionally, at the pre-constructionlpartnering meeting today, Greg Sherman and Jim Barger (Oncor) had a
discussion and we w~:re asked to put some costs together for the following items:
I) Pond B -COD would like to eliminate and move that quantity, if needed, to Pond A (east) ..... Aud .'50.50
per cu. yd to the Fill Area #2 lJUntcd unit price of S2.25 per cu. yd ..... 81 ,315 CY x SO.SO = $40,457.00
additional cost Per Addendum Ill, Note 119 says 'The primary borrow sources (in order of priority} are Borrow
Areas A, C, 8, ond D. Barrow Area D will only be used is the City decides to not use Borrow Area 8 or additional
soils are needed. The calculated amount of borrow dirt needed is 625,160 cubic yards as this amount can be
obtained from Borrow Areas A and C together. The City will decide on the borrow areas used for this project as
the grading plans for the borrow areas may change". Note #16 says 'The bid quantities for Bid Items 103
{Unclassified Excavation), 1341 (Transport Dirt to Fill Area 1}, 1342 (Transport Dirt to Fill Area 2}, 1343 (Transport
Dirt to Fill Area 3}, and 1344 (Transport Dirt to Fill Area 4} will not be renegotiated based on overages or
underage of these bid items." This additional cost is unjustified.
If any contracts were let and signed for removal of soil from Borrow Area D, please provide a copy of the contract.
If you have any questions, please let me know. If this appears overly broad in scope, we can discuss narrowing the scope
of this request.
Hal Barker 9191 Garland Road 1126
Dallas, TX 75218 Hbarker [email protected]
6
2) Pond C a) Haul limestone to structural fill area .... add $2.25 per cu. yd. to the fill area #2 quoted unit
price of $2.25 prr cu. yd ...... I 2,200 cu. yds. x S2.25 = $27,450.00 additional cost This is
already paid for in Bid Items 1341, 1342, 1343, and 1344. The Bid Item 1346 is to include survey
staking, compaction, and geotechnical testing. Per Addendum Ill, Note 1115 says "For Bid Alternate 3
(Bid Item 1346- Process/Compact Fill at Structural Fill Locations), payment far this item will include
survey staking, compaction, and geotechnical testing as this will be considered incidental to the bid
item. Additional fill allowance shall be not be stockpiled and bidders are to assume an average haul
distance to the center of each fiJI zone for this additional fill material. All additional fill material shall
be spread by others."
b) Haul approx. I 6,000 cu. yd. of sand from Pond "C" to Fill Area #2 ... . add $2.75 per cu. yd.
= S4.:f,OOO.OO additional cost Per Addendum #1, Note #5 says '7here are 4 identified soil stratums in the
borrow areas; clay, silty clay, limestone, and high quality sands. Landscapes Unlimited would like for soils from
these stratums to be placed in specific areas within the fill areas as they will be spreading of the fill. Due to the
size of the borrow areas and soil stratum depths, the amount of dirt from each stratum of each borrow source
will be substantial sa this will not delay the Contractor's construction schedule. The Contractor will not be
responsible for determining these soil stratums or the associated depths as Landscapes Unlimited will inform the
Contractor on the depth and placement of this material in regions within the fill areas. However, Landscapes
Unlimited requests that the Contractor use best efforts to inform Landscapes Unlimited when contractor observes
a significant change in soil type, stratum, or encounters ground water during eKcavations." If the intended area
for this sand is in another zone not planned, that Fill Zone price will apply.
3) Structural fill a) East parking lor will not be filled to Q l 00. This lot will be filled to a .5% grade from
existing to the south. How much is this reduced? See revised structural fill area email sent earlier today
b) Emergency access road till eliminated. How much is this reduced? See revised
structural fill area email sent earlier today c) "Bump-out" area at clubhouse pad eliminated. How much is this n~duccd? See
revised structural fill area email sent earlier today
4) Stratum Excavation. What docs this mean? See 2 B) above
5) Fill area 4 may be deleted and the quantity moved to area 3. Add $0.50 per cu.yd. to the <JUOtcd unit
price of S1.90 per cu. yd. for fill area 3. 58,217 cu . yds. x 0.51) =) 29,108.50 additional cost. I am
unaware of this. Please provide more details
6) Need to polhole gas line ASAP. We will discuss and get Dig Tt.·ss ... Scott talking to Om·or 06-12-
14 Please pothole the DWU line also per Addendum 111, Note 1118 says "On the plans, there is an existing DWU
wastewater easement along Elam Road and a United Gas easement in Borrow Area B. The Contractor shall
pothole and verify the existence of any existing utility line in both areas as payment will be made through Bid
Item 1652 (Locate Underground Utility Not Under Paving) for each of the 2 lines. Field verification is needed to
determine if existing lines are still present or ever installed."
7) Various sand material hauled to various fill areas (small quantities) ... additional $200.00 per
load Explained above as this does not apply
Please let us know on lhcsc items as soon as possible.
Thank you,
David Proctor, Vice President DCI Contracting, Inc.
2
2045 E. Hwy 380, Suite I 00 Decatur, TX 76234 Ph. (940)626-0022 Fax (940)626--0047 Cell (940)453-2472 e-mail : dproctor@dcicontractint.!..org
3
CITY OF DALLAS
April 25, 2014
TO: All PLANHOLDERS OF CITY OF DALLAS
SIMPKINS REMEDIATION- VEGETATIVE SUPPORT LAYER (PBSWM007)
CONTRACT NO. PBSWM007
ADDENDUM NO. 1
Attached is Addendum No. 1 to the subject contract. Please incorporate this addendum into your
bidding documents.
Steve Parker, P.E., CFM Program Manager Floodplain Management Trinity Watershed Management
Simpkins Remediation- Vegetative Support Layer (PBSWM007)- Addendum #1
ADDENDUM NO. 1 FOR
CONTRACT NO. PBSWM007
SIMPKINS REMEDIATION - VEGETATIVE SUPPORT LAYER (PBSWM007)
NOTICE TO ALL BIDDERS April 25, 2014
The following constitutes Addendum No. 1 to the Plans, Special Provisions, and Proposal for this
referenced project. This item is provided as clarification and general information, and is hereby
included as part of the specifications for the subject project:
1. Due to the proposed city council approval date of May 14, 2014 for this construction
contract and the City of Dallas's intent to issue a Notice to Proceed (NTP) date within
2 weeks of such approval, the Contractor shall submit normal Business Inclusion and
Development (BID) forms associated with a city council agenda item as part of their
bid package.
Attached are the forms to be completed as they can be downloaded at:
http://www.dallascitvhall.com/business development/business inclusion forms.htrnl.
Also attached are possible MWBE subcontractors to be considered based on the
scope of work for this project. For any questions about the forms, please contact Lisa
Brough at [email protected] & (214) 670-3335. If the Contractor does
not meet or exceed the BID goal of 25% for this project, the Contractor will need to
complete the attached MWBE Documentation Form.
2. The bid closing date will remain unchanged, Thursday, May 1, 2014.
3. The structural fill area near the main entrance for South Loop Landfill within Fill Area 2 on
Plan Sheet 13 will require removal of trees not currently identified on the plans as a
tree survey for this area will be done but has not been completed at the time of this
addendum issuance. The winning bidder will be given the completed tree survey in
this area.
No tree mitigation for this area will be needed by the Contractor. Payment for this bid
item includes tree removal (including stumps and root ball) and offsite disposal unless
arrangements are made for on site disposal as no additional payment will be made. All
structural fill areas shall be cleared and grubbed in accordance with the structural fill
requirements for site preparation.
The trees to be removed as part of this project are primarily identified within the
borrow areas only, with the exception of those areas identified above. The City of
Dallas (City) will begin construction on the 151 related project (remediation project -
Simpkins Remediation [PBSWM007]} within the next few weeks. All trees on the
landfill footprint for Elam and South Loop Landfills will be removed as part of that
project. There may be some additional trees to be removed in the identified fill areas
Page 2 of7
Simpkins Remediation- Vegetative Support Layer (PBSWM007) -Addendum #1
not on the landfill footprint. No payment will be made for additional trees to be
removed for construction access, staging purposes, or not shown on the plans.
As clarification for Bid Items 639A (Remove Trees 6 - 12 inches diameter), 639B
(Remove Trees 13 -24 inches diameter). and 639C (Remove Trees over 24 inches
diameter), payment for these bid items includes tree removal (including stumps and
root ball).
4. The calculated quantity for Bid Item 101 (Clearing and Grubbing) is estimated at 32.8
acres with a bid quantity of 35 acres as this is estimated for the borrow areas only.
There may be some additional areas to clear and grub in the fill areas.
5. There are 4 identified soil stratums in the borrow areas; clay, silty clay, limestone, and
high quality sands. Landscapes Unlimited would like for soils from these stratums to
be placed in specific areas within the fill areas as they will be spreading of the fill . Due
to the size of the borrow areas and soil stratum depths, the amount of dirt from each
stratum of each borrow source will be substantial so this will not delay the Contractor's
construction schedule. The Contractor will not be responsible for determining these
soil stratums or the associated depths as Landscapes Unlimited will inform the
Contractor on the depth and placement of this material in regions within the fill areas.
However, Landscapes Unlimited requests that the Contractor use best efforts to inform
Landscapes Unlimited when contractor observes a significant change in soil type,
stratum, or encounters ground water during excavations.
6. The estimated amount of dirt to be processed by the Contractor is 5,000 cubic yards a
day as the intent is to place the dirt in front of the earthwork equipment for Landscapes
Unlimited to grade. If the Contractor processes more than 5,000 cubic yards a day (or
more than Landscapes Unlimited can handle), an agreed upon stockpile location will
be given within the fill areas to not slow operations by the Contractor.
7. For Alternate Bid 2 (Bid Item 1345A- Clay Cap for Borrow Areas A, B. and/or D), the
Contractor shall install an 18-inch clay liner using native clay material having a
minimum plasticity index of 25 and compact to 92%-98% at or above optimum
moisture content to all areas under normal water surface elevations. Seal all
permeable areas to restrict seepage from the ponds as no separate payment will be
made.
The City will procure a local geotechnical firm for this testing. The Contractor shall pay
for any retesting fees not meeting these requirements. Payment for Bid Item 1345A
will include unclassified excavation. transport to the fill area, and compaction.
Payment will be based on a ground survey before and after by a Texas Registered
Professional Land Surveyor (RPLS) and a summary report as this will be paid by the
Contractor. Import material can be used and will be paid through delivery tickets.
8. As clarification for General Note #44 on Page 2 of the plans, a trench burn pit will not be
allowed on the landfill footprint due to safety concerns. However, a trench bum pit will
Page 3 of 7
Simpkins Remediation -Vegetative Support Layer (PBSWM007) -Addendum #1
be allowed at a minimum distance of 500 feet away from the landfill footprint as the
Contractor will obtain approval from the Texas Commission on Environmental Quality
and Dallas Fire Rescue. The trench burn location must be approved by the Engineer
as a trench burn pit may be allowed near Borrow Areas A. No payment will be made
for removal of additional trees to accommodate this trench burn. The Contractor shall
verify if the trench burn pit is located within the landfill permit.
9. The primary borrow sources (in order of priority) are Borrow Areas A, C, B, and D.
Borrow Area D will only be used is the City decides to not use Borrow Area B or
additional soils are needed. The calculated amount of borrow dirt needed is 625,160
cubic yards as this amount can be obtained from Borrow Areas A and C together. The
City will decide on the borrow areas used for this project as the grading plans for the
borrow areas may change.
10. As clarification for Bid Item 222A (Dewatering for Borrow Area D) -Alternate Bid 1, this
bid item will also apply during the installation of the clay cap until it is completed. No
additional payment will be made for dewatering associated with Alternate Bid 2.
11.As clarification for the cubic yards and bank yards notes shown on the fill area plan
sheets, those 2 numbers reflect the range of dirt volumes that could be brought to that
fill area as the final layout has not been finalized to date. The grading plans are for
information purposes only as Landscapes Unlimited will perform the spreading of the
fill material.
12. This is a closed landfill project as the 40-hour safety trained in accordance with 29 CFR
1910.120 is not required but recommended. Borrow areas are not located within the
landfill footprint.
13. This project will start subsequent to the start of the 1st City project mentioned above but
shall run concurrent with such project. It is recommended that the Contractor follows
the same sequencing as the 151 City project.
14.1f there are exposed waste as a result of the Contractor's recent construction activities,
the Contractor shall place at least 2 feet of clay material on top of this area and inform
the Engineer as this will be considered incidental with no separate payment.
15. For Bid Alternate 3 (Bid Item 1346 - Process/Compact Fill at Structural Fill Locations),
payment for this item will include survey staking, compaction, and geotechnical testing
as this will be considered incidental to the bid item. Additional fill allowance shall be
not be stockpiled and bidders are to assume an average haul distance to the center of
each fill zone for this additional fill material. All additional fill material shall be spread
by others.
16. The bid quantities for Bid Items 103 (Unclassified Excavation), 1341 (Transport Dirt to Fill
Area 1 ), 1342 (Transport Dirt to Fill Area 2) , 1343 (Transport Dirt to Fill Area 3), and
Page 4 of7
Simpkins Remediation- Vegetative Support Layer (PBSWM007) -Addendum #1
1344 (Transport Dirt to Fill Area 4) will not be renegotiated based on overages or
underage of these bid items.
17. The Engineer (Than Nguyen), or an approved assignee, will sign all offsite waste
manifests.
18. On the plans, there is an existing DWU wastewater easement along Elam Road and a
United Gas easement in Borrow Area B. The Contractor shall pothole and verify the
existence of any existing utility line in both areas as payment will be made through Bid
Item 1652 (Locate Underground Utility Not Under Paving) for each of the 2 lines. Field
verification is needed to determine if existing lines are still present or ever installed.
All bidders shall be required to add the following sentence to the inside of the front cover sheet of
the special Provisions and Proposal with signatures:
--------------~--~~--~~--~~~------------------ acknowledges (Give Legal Name of Organization)
Receipt of Addendum No.1, and has taken due cognizance of the said addendum in all its forms
in the preparation and submission of this bid .
Page 5 of 7
S1mpkins Remed1ahon -Vegetative Support Layer (PBSWM007) -Addendum #1
BID ITEMS AND QUANTITIES
REVISE THE FOLLOWING BID ITEM & QUANTITIES:
1. As clarification for Bid Alternate 1, Bid Items 1 03A (Unclassified Excavation for Borrow
Area~ and 222A (Dewatering and Debris Removal for Borrow Area~ has been changed
to Bid Items 1 03A (Unclassified Excavation for Borrow Area Q) and 222A (Dewatering and
Debris Removal for Borrow Area Q). Borrow Area 4 is referred to as Borrow Area D on
the plans.
2. The bid quantity for Alternate Bid 1 (Bid Item 1 03A- Unclassified Excavation for Borrow
Areas D) has been changed from 92,610 cubic yards to 120,000 cubic yards.
3. The bid quantity for Alternate Bid 2 (Bid Item 1345A - Clay Cap for Borrow Areas A, B,
and/or D) has been changed from 34,000 cubic yards to 47,000 cubic yards.
4. Alternate Bid 4 includes 3 new bid items; Bid Items 640A (Remove Trees 6- 12 inches
diameter), 640B (Remove Trees 13 -24 inches diameter}, and 640C (Remove Trees over
24 inches diameter} with bid quantities of 525, 110, and 20 respectively.
5. For Bid Alternate 5, additional dirt may be needed and includes 5 new bid items; so
new bid items 1 03B (Unclassified Excavation for Contingency}, 1341 A (Transport Dirt
to Fill Area 1}, 1342A (Transport Dirt to Fill Area 2}, 1343A (Transport Dirt to Fill Area
3}, and 1344A (Transport Dirt to Fill Area 4} with bid quantities of 68562, 1000, 65564,
1018, and 1000 cubic yards respectively.
PROPOSAL
Enclosed are Revised Bid Proposal Sheets 1 through 9 as they will replace the Original Bid
Proposal Sheets 1 through 7. The attached bid proposal sheet shall apply in the preparation of
bids for this project and will replace the corresponding page of the bid proposal included in the
bid book.
PLAN SHEETS
Plan Sheet 4 has been updated with new surveying information. In addition, Plan Sheet T-0 has
been revised with updated tree removal information. See attached Sheet 4 and T-O as both
pages will replace the original Plan Sheet 4 and T-0.
DELETE THE FOLLOWING PLAN SHEETS:
1. Original Plan Sheet 4 2. Original Plan Sheet T-O
Page 6 of?
Simpkins Remediation -Vegetative Support layer (PBSWM007) -Addendum #1
ADD THE FOLLOWING PLAN SHEETS:
1. Revised Plan Sheet 4 2. Revised Plan Sheet T -0
Page 7 of?
Carter Lawson, Jeri
From: Sent: To: Subject:
Thanks.
Nguyen, Than Thursday, September 18, 2014 4 57 PM Lou Nance RE: Borrow Source B and D Size
From: Lou Nance [mailto:[email protected] Sent: Thursday, September 18, 2014 4:31PM To: Nguyen, Than Cc: ChrisM. Jones Subject: RE: Borrow Source B and D Size
Than: Borrow Area B: 4 2 acres, 13' deep Borrow Area D: 3.8 acres, 1 0' deep
Thanks, Lou Nance Senior Project Coordinator
Pacheco Koch 8350 N Cenlrol Expwy, Suite 1000. Dallas. TX 75206-1612
T: 972 235.3031 • F: 972.235.9544 • M: 214.926.6263
TBPE Firm No. F-469 • TBPLS Firm No. 10008000
.l lm~
From: Nguyen, Than [mailto:[email protected]]
Sent: Thursday, September 18, 2014 3:50PM To: Lou Nance Subject: Borrow Source B and 0 Size
Lou,
What is the acreage size of Borrow Area Band D please? Depths also please.
Than