Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

Embed Size (px)

Citation preview

Page 1: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

Carstairs S&C Sustainability Renewals & Enhancement

Sean Malone Network Rail

Page 2: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

2

1.0 Carstairs Overview

East Jn

South Jn

North Jn

Station ECA2

WCM1

WCM1

To Edinburgh

To Glasgow

To Carlisle

Page 3: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

3

2.0 Carstairs – Need for Change

Currently a 1970s installation by British Rail. High level of operational redundancy built into the layout. This redundancy, with a number of surplus crossovers, has lead to high supplementary maintenance costs.

Shift in focus from aspired flexibility to “fit for purpose” & “value for money”, a once in a generation opportunity has been identified to tie in with Motherwell North Signalling Renewals Project (MNSR) and deliver an enhanced/rationalised junction.

Page 4: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

4

2.1 Drivers for Renewal/Enhancements

Cumulative Tonnage (age x tonnage) – Service Life.

Maintenance Issues – Poor timber bearer/sleepers, Very poor joints with high rail wear, old ballast & poor track geometry.

Technical Non-Compliances - Facing BV switches, S&C on curves, including transitions & tight toe-to-toe distances between S&C.

The RAM Track Scotland team concluded that some form of interventions additional to regular maintenance are required to keep Carstairs operating throughout the next 5-year Control Period (2014-19).

These are in the form of Medium Refurbishment in CP4 and Heavy Refurbishment & entire Base Case Renewals in CP5.

Additionally, Enhancement Options have been developed and illustrated in this presentation.

Page 5: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

5

3.0 Carstairs South Jn

• Remodel of 322, 323 & 319 Turnouts• Remodel/Relocation of 324 Crossover (~200 yards South)• Abandonment of 316 & 318 Crossovers and Abandonment of 321 Turnout• 1825 yds of Associated Plain Line • Line Speed Increase Throughout

Page 6: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

6

• Full Renewal of 315A & 314 Points• Remodel of 313 A&B Points / Remodel of CSP Branch Line• Abandonment of 315B Crossover• Abandonment of ECA1 Up Main Line• 1550 yds of Associated Plain Line • Line Speed Increase throughout with Larger S&C & Rationalisation

3.1 Carstairs East Jn

Page 7: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

7

Abandonment of 305 Turnout Extension of Down Loop Abandonment of 303, 304, 306B, 307, 309 & 311 Crossovers Renewal of 306A CrossoverRemodel/Relocate of 302 Crossover & 312 Turnout Renewal of Up Loop Yard TurnoutsModify Carstairs Platform 2 – Remodel of Down Plat Line, New Up MainCSP By-Pass Line to allow North/East Traffic whilst Plat 1 is occupiedLSI due to Remodel of CSP Curve & Reduced S&C

3.2 Carstairs Station

Page 8: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

8

3.3 Carstairs North Jn

• Renewal of 4A GF Turnout• Remodel/Relocation of 301 Turnout off Transition onto Straight• New Facing 299 Turnout (Ravenstruther)• Additional Crossover – 300 A/B on Main Line& New T/O for Extended Down Loop• 1145 yds of Associated Plain Line• Line Speed Increase Throughout

Page 9: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

9

Production of development Particular Requirement Specification (PRS) documents

PRS includes:

Existing Site Information – Infrastructure on site, age, location & condition (Geogis, OMNIInspector HD, Sectional Appendix, meetings with engineers from key disciplines etc)

P-way Issues - drivers for the proposed jobs

Track Proposals - their impact on the network & other disciplines

Layout Diagrams - depicting proposed layouts

The PRS documents formed a vital part in bringing the various schemes and ideas together and are used to define the options available. All key stakeholders were kept up to date with the progress of the PRS’ and these documents formally show the decision making process with these options.

4.0 My Role & What I Have Influenced

Page 10: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

10

5.0 Summary

The multi-disciplinary, in-house approach taken at Carstairs using the PRS documentation process has provided an opportunity to scope a large-scale project efficiently.

With continuous and structured channels of communication between stakeholders ensuring all requirements are considered, the delivered junction should provide an appropriate and cost effective solution, fit for another generation.

Page 11: Carstairs S&C Sustainability Renewals & Enhancement Sean Malone Network Rail

Thank you for your time