Upload
arline-logan
View
212
Download
0
Tags:
Embed Size (px)
Citation preview
Carl Vance
Combustion Air Pre-heater Design Review Presentation
ME 486
3/13/03
Carl VanceCarl Vance
Purina Boiler Efficiency TeamPurina Boiler Efficiency Team
Members and RolesMembers and Roles Ryan CookRyan Cook
Documenter and SecretaryDocumenter and Secretary
Kofi CobbinahKofi CobbinahTeam Leader and Website Team Leader and Website ManagerManager
Carl VanceCarl VanceCommunicator and HistorianCommunicator and Historian
Matt BishopMatt BishopFinancial Officer and MediatorFinancial Officer and Mediator
Carl VanceCarl Vance
SummarySummary
Client IntroductionClient Introduction
Project DescriptionProject Description
Our DesignOur Design
Mathematical ModelMathematical Model
ScheduleSchedule
BudgetBudget
ConclusionConclusion
Carl VanceCarl Vance
Our Client – NestléOur Client – Nestlé Purina Purina
Client contact is John CainClient contact is John Cain
Manager of Engineering at the Flagstaff Manager of Engineering at the Flagstaff Plant.Plant.
Purina as a company:Purina as a company:Flagstaff Plant opened in 1975Flagstaff Plant opened in 1975
Employs 180 peopleEmploys 180 people
Purina is now a division of Nestlé FoodsPurina is now a division of Nestlé Foods
Carl VanceCarl Vance
Purina Steam SystemPurina Steam System
The boiler produces approximately 500,000 The boiler produces approximately 500,000 lbm of steam per day. lbm of steam per day.
40%: cooking products.40%: cooking products.
50%: drying products.50%: drying products.
10%: miscellaneous areas: air and water 10%: miscellaneous areas: air and water heating systems.heating systems.
Steam production is 2/3 of the plant's total Steam production is 2/3 of the plant's total energy use.energy use.
Carl VanceCarl Vance
Project DescriptionProject Description
Problem DefinitionProblem Definition NestlNestlé Purina has requested a proposal for a é Purina has requested a proposal for a
combustion air pre-heater. The goal of the combustion air pre-heater. The goal of the project is to provide savings for the plant by project is to provide savings for the plant by reducing energy costs and improving reducing energy costs and improving efficiency in the steam system.efficiency in the steam system.
Justification for the project is cost reduction Justification for the project is cost reduction and fuel conservation through higher and fuel conservation through higher efficiency.efficiency.
Carl VanceCarl Vance
Project DescriptionProject Description
Client’s Needs Statement:Client’s Needs Statement:
Design of a combustion air preheater must Design of a combustion air preheater must be:be:
Efficient Efficient
Economically FeasibleEconomically Feasible
Minimize Modifications to Existing Minimize Modifications to Existing SystemsSystems
Carl VanceCarl Vance
Our Design PhilosophyOur Design Philosophy
Finish Design and Construction Under Finish Design and Construction Under Budget.Budget.
Satisfy the Client’s Requirements.Satisfy the Client’s Requirements.
Design for Safety.Design for Safety.
Act with Integrity.Act with Integrity.
Carl VanceCarl Vance
What is a Combustion Air What is a Combustion Air PreheaterPreheater
Device or system that heats the boiler Device or system that heats the boiler intake air.intake air.
Uses recaptured waste heat to that would Uses recaptured waste heat to that would normally leave the boiler to the normally leave the boiler to the atmosphere.atmosphere.
Ryan CookRyan Cook
Design ChoiceDesign Choice
Final Design Choice: Final Design Choice: Concentric Duct DesignConcentric Duct Design
Air enters into a duct that surrounds the Air enters into a duct that surrounds the stack.stack.
The stack transfers heat to the air by The stack transfers heat to the air by convection and radiation.convection and radiation.
The air enters into the boiler at a higher The air enters into the boiler at a higher temperature.temperature.
Ryan CookRyan Cook
Preheater Design BasicsPreheater Design Basics
Ryan CookRyan Cook
Design BenefitsDesign Benefits
Concentric Duct Design Will Provide:Concentric Duct Design Will Provide: Relatively Low Installation CostRelatively Low Installation Cost Low Material CostsLow Material Costs Low Impact on Existing SystemsLow Impact on Existing Systems High Payback on InvestmentHigh Payback on Investment Low Maintenance CostsLow Maintenance Costs
Ryan CookRyan Cook
Specifications to dateSpecifications to date
The stack height is 4.3 meters, which fixes The stack height is 4.3 meters, which fixes our duct height and will provide our our duct height and will provide our surface area for heat transfer.surface area for heat transfer.
Duct diameter will be 1.15 meters to Duct diameter will be 1.15 meters to optimize forced convection.optimize forced convection.
Ryan CookRyan Cook
Proposed DesignProposed Design
Matt BishopMatt Bishop
Forced Convection ModelForced Convection Model
Vol Flow rate (cms)2.837 k = .0263 W/(m*K) kinematic visc. = 2E-05 T(K) surface= 399.7
T(K) air = 299.7
variableO.D. (D2) I.D. (D1) hydraulic diameter X section area (m^2) airspeed (m/s) Re Pr Nu h (W/(m^2 K)) Ts - Ta (K) q" stack S.A (m^2) Energy transfer (W)
1 0.9144 0.086 0.13 22.04 59334.82 0.707 131.87 40.52 100 4051.59 12.26 49672.471.05 0.136 0.21 13.56 57824.57 129.18 25.05 2505.43 30716.521.1 0.186 0.29 9.66 56389.29 126.61 17.94 1794.03 21994.86
1.15 0.236 0.38 7.43 55023.53 124.15 13.86 1385.85 16990.471.2 0.286 0.47 5.98 53722.37 121.79 11.22 1121.55 13750.16
1.25 0.336 0.57 4.97 52481.33 119.54 9.37 936.77 11484.811.3 0.386 0.67 4.23 51296.33 117.37 8.01 800.54 9814.63
1.35 0.436 0.77 3.66 50163.66 115.29 6.96 696.11 8534.251.4 0.486 0.88 3.21 49079.93 113.30 6.14 613.61 7522.92
1.45 0.536 0.99 2.85 48042.03 111.38 5.47 546.90 6704.991.5 0.586 1.11 2.55 47047.13 109.53 4.92 491.90 6030.69
Heat Exchanger ModelHeat Exchanger Model
Cp,c (J/kg*K) Cp,h (J/kg*K)1007 1030
Hot side data
hot air density (kg/m^3) stack cross section area (m^2) vhot (m/s) Re hot Pr NuD k (W/m*K) hi (W/m^2*K) ho (W/m^2*K)
0.6964 0.6566 9.8900 233140.0000 0.6840 388.9052 0.0407 17.3102 124.1500
variable result check
Th,o (K) Th,I (K) mdot h (kg/s) mdot c (kg/s) q (Watts) Tc,I (K) Tc,o (K) Delta Tlm (K) U (W/m^2*K) Area (heat transfer)
501.20 509.10 4.52 4.52 36779.24 305.40 313.48 195.71 15.19 12.37017571501.21 36732.68 313.47 195.72 12.35387882501.22 36686.13 313.46 195.73 12.3375836501.23 36639.57 313.45 195.74 12.32129008501.24 36593.02 313.44 195.75 12.30499823501.25 36546.46 313.43 195.76 12.28870807501.26 36499.90 313.42 195.77 12.2724196501.27 36453.35 313.41 195.78 12.2561328501.28 36406.79 313.40 195.79 12.23984769
Radiation ModelRadiation Model
variableD2 D1 ε1 ε2 σ (W/(m2*K4)) stack surface area (m^2) T1 T2 q (W)1 0.9144 0.87 0.15 5.67E-08 12.26 399.7 322 1622.06
1.05 1687.841.1 1752.44
1.15 1815.911.2 1878.26
1.25 1939.541.3 1999.75
1.35 2058.941.4 2117.13
Project Monetary SavingsProject Monetary Savings
Gallons per year saved Yearly monetary savings 5- year savings
5120.473467 2355.417795 11777.088975113.991855 2352.436253 11762.181275107.510243 2349.454712 11747.273565101.028631 2346.47317 11732.365855094.547019 2343.491629 11717.458145088.065407 2340.510087 11702.550445081.583795 2337.528546 11687.642735075.102183 2334.547004 11672.735025068.620571 2331.565463 11657.82731
Gallons per year saved Yearly monetary savings 5- year savings225.83 103.88 519.40234.98 108.09 540.46243.98 112.23 561.15252.81 116.29 581.47261.50 120.29 601.44270.03 124.21 621.06278.41 128.07 640.34286.65 131.86 659.29
Convection SavingsRadiationForced Convection
Kofi CobbinahKofi Cobbinah
Accomplishments to DateAccomplishments to Date
Proposal Document has been accepted by Proposal Document has been accepted by clientclient
Mathematical Analysis of the design has been Mathematical Analysis of the design has been accepted by the client.accepted by the client.
Kofi CobbinahKofi Cobbinah
Problems EncounteredProblems Encountered
CAD model is taking more time than CAD model is taking more time than estimated. estimated.
Kofi CobbinahKofi Cobbinah
Future Design TasksFuture Design Tasks
Final Design will include:Final Design will include: Finalizing Mathematical ModelsFinalizing Mathematical Models Finishing CAD Models Finishing CAD Models Design ResultsDesign Results Bill of MaterialsBill of Materials Construction MethodsConstruction Methods
Kofi CobbinahKofi Cobbinah
Project ScheduleProject Schedule
CAD Models ------------- March 24, 2003CAD Models ------------- March 24, 2003Final Design-------------- April 20, 2003Final Design-------------- April 20, 2003Capstone Presentation- April 25, 2003Capstone Presentation- April 25, 2003Final Report ------------- May 2, 2003Final Report ------------- May 2, 2003
Kofi CobbinahKofi Cobbinah
BudgetBudget
Printing CostPrinting Cost Proposal Document ----------------- $15Proposal Document ----------------- $15 Mathematical Models Document - $15Mathematical Models Document - $15 Total--------------------------------------- $30Total--------------------------------------- $30
Kofi CobbinahKofi Cobbinah
Team Time LogTeam Time Log
Team Time (Hours)
100
6
117.6
Team Meetings
Client Contact
Individual Work
Kofi CobbinahKofi Cobbinah
ConclusionConclusion
We are on schedule to finish all We are on schedule to finish all deliverables and have a completed design deliverables and have a completed design as planned.as planned.
We will provide the client with a design We will provide the client with a design that is both efficient and feasible to that is both efficient and feasible to implement.implement.
Kofi CobbinahKofi Cobbinah
Questions?Questions?