Captive Port Cost Benefit Para

Embed Size (px)

Citation preview

  • 7/31/2019 Captive Port Cost Benefit Para

    1/2

    Cost benefit analysis

    The financial gain on account of the proposed strategic initiative of having captive Port

    facilities at different Ports including Bunkering facilities would be difficult to assess dueto lack of complete information and data. However to assess the impact of the

    proposed strategic initiative on a directional basis, the financial benefit to the

    Corporation on an order of magnitude basis has been analyzed for a typical Grass Root

    Refinery Case with reference to the proposed West Coast Refinery.

    The impact in financial terms for the same along with the assumptions made is

    summarized below. The workings are provided as Annexure A

    Grass Root Refinery Proposed West Coast

    The estimated cost of setting up the Captive Port facilities on an order of magnitudebasis has been derived from the capital cost of a similar venture by Ennore Port Ltd

    which was set up in 2006. As there are no direct incomes generated by these facilities,

    for the purpose of evaluating the investment, the charges presently being paid to the

    Port and other agencies directly and indirectly has been considered as savings in case

    of Captive Port facilities. Further, owning the jetties will also reduce the turnaround time

    of each vessel which has also been translated in financial terms to indicate further

    savings. However, a certain percentage out of the savings thus derived has been

    considered as revenues to be shared with the Port authorities and has been treated as

    cost to IOCL. Repairs and maintenance costs for the Port facilities have also been

    considered in the lines of Ennore Port Limited.

    On an average, the total savings as described above on account of this initiative in

    terms of absolute value to the Corporation after deducting the operating expenses but

    before tax outgo would be to the tune of Rs. 223 crores per annum. Translating the

    same on a per barrel basis the savings would approximately amount to Rs 17.20 per

    barrel of crude processed equivalent to USD 0.31 per barrel. To arrive at the above

    results the following assumptions have been made.

    (a) Initial Refinery capacity 15 million metric tons per annum with an increase in

    capacity by another 5 million tones after 7 years of operation.(b) 50% of the products have been considered for exports as well as coastal

    movement.

    (c) All crude will be imported and 75% will be through Very Large Crude Carriers

    (VLCC) and balance will be through normal ships.

    (d) The estimated cost of the Port Facilities would be around Rs. 700 crore and the

    period of construction is considered as 36 months.

  • 7/31/2019 Captive Port Cost Benefit Para

    2/2

    (e) The expenses related to Port Charges, Pilotage, Wharfage, Tug Hire and

    Berthing/Mooring charges are based on the actual outgo presently at Vadinar

    and Paradip.

    (f) The turnaround days for each ship/VLCC are also based on the average

    turnaround presently encountered at Vadinar and Paradip. For the purpose of

    calculating the savings the turnaround time has been reduced with a view that

    the operations would be optimal and faster because the facilities are for captive

    use. However, savings on account of faster turnaround has been considered vis-

    -vis the existing operations.

    (g) A 5% revenue sharing with the State authority has been considered based on the

    lines of Gujarat Maritime Board.