Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Capital Projects UpdateNovember 12, 2019
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
SCIENCE REPLACEMENT BUILDING
• Scopeo 110,000 gsfo Chemistry, Physics,
GeoSience, Psychology, Science Education,Dean’s Suite
• Scheduleo Design – Summer 2017-Spring 2018o Demolition – May-July 2018o Construction Start – June 2018o Est. Construction Complete – July 2020
• Project Cost: $101,137,000
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
ECC LAB RENOVATIONS• Phase 3: Langdon 120
o Advanced Materials Labo Design – Summer/Fall 2018o Construction Start – March 2019o Construction Completed – July 2019o Project Cost: $643,433
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
• Phase 1: Plumas 114o HVAC Upgrades in the Material Removal
and Robotics Labo Design – Fall 2018o Construction Start – July 2019o Construction Complete – Nov 2019o Project Cost: $325,000
• Omron Lab: Plumas 112o Robotics Labo Design – Spring 2019o Construction Start – July 2019o Construction Complete – Nov 2019o Project Cost: $660,000
MAIN SWITCHGEAR AND ELECTRICAL SYSTEM UPGRADE
• Scopeo Construction of a new +/- 2,800 sf
concrete block building o Install new 12kV medium voltage
electrical distribution switchgearo Using savings from Meriam Library
Water Intrusion and Central Plant Modifications along with other funds
• Scheduleo Design – Summer 2018 through
September 2019o Construction Ph 1 (site work) –
June through Sept. 2019o Construction Ph 2 (building) – Oct.
2019 through Oct. 2020• Project Cost: $7.6 Million
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
PHYSICAL SCIENCE BUILDING RENOVATION
• Scopeo Abatement, selective demolition,
seismic upgrade and renovation for general use building (surge/flex space)
o Will include demo and relocation of fish lab and greenhouse storage
• Scheduleo Programming/Design – October
2019 through Spring 2020o Est. Construction Start –
Summer 2020o Est. Construction Complete –
Summer 2021
• Project Cost: $30 Million
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
BUTTE HALL RENOVATION
• Scopeo Renovation of entire building to
include abatement, reconfigure of space, transition 4th floor from IT to classrooms
• Scheduleo Est. Programming/Design – Winter
2019 through Spring 2021o Est. Construction Start –
Summer 2021o Est. Construction Complete –
Summer 2023• Project Cost: $89 Million
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
WAREHOUSE AND FACILITIES SERVICES YARD
• Scopeo Replacement of the (E)
FMS Admin. Building, Central Supply, Shipping and Receiving, Trades Shops, and upgrades to (E) Warehouse, site, and utilities.
• Scheduleo Design – TBDo Construction – TBD
• Project Cost: $9-18 Million
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
FUTURE PROJECTS
• Utilities Infrastructureo Next Academic Projecto Awaiting approval and
funding
• Glenn Hall Replacemento Awaiting funding/
fundraising in processo Feasibility Study in process
• MLIB lighting upgrades• Maintenance projects at
BCP
• Warner Street/Rule 20A PG&Eo In planning phaseo Est. Start – Summer 2020
• New Residence Hallo Housing Market Demand
Study complete
• Student Health Center• Solar panels on BMU,
WREC, PS2, Science
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
CAMPUS MASTER PLAN
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
• MP Consultant – SmithGroupo Website o Focus Group Sessionso Student Outreacho Community Outreacho Open House Meetings
• Scheduleo Launch – Spring 2018o Discover – Summer/Fall 2018o Prototype and Refine –Spring 2019o Implement – Summer/Fall 2019
• CEQA Consultant – Dudeko Environmental Impact Reporto Public Comment Period (45 days)o Traffic Studieso Project Level studies for first 5-7 yearso Historical Evaluations
• Scheduleo Initiation – Fall 2018o Public Scoping Meeting – Spring 2019o Public Mtg/Comment Period – Spring
2020o Final Report – Spring 2020
• Upcoming Meetingso Public Meeting
o Tentatively late January 2020
CURRENT CAMPUS MAP
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
TODAY
MASTER PLAN MAP
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O
2030
QUESTIONS?Thank you for coming!
C A L I F O R N I A S T A T E U N I V E R S I T Y , C H I C O