Capital Program Update 3-13-07. Maintenance Garage. On schedule - Final Completion is May 19, 2007 but the District needs to move in April because the Brown Daub lease expires Work Completed - PowerPoint PPT Presentation

Citation preview

  • Capital Program Update3-13-07

  • Maintenance GarageOn schedule - Final Completion is May 19, 2007 but the District needs to move in April because the Brown Daub lease expires Work Completed The building is 90% complete. Sitework is 90% complete. Generator has been set. District is installing shelvingWork in progress District move preparations, HVAC start-up, final code inspections

    Sheet1

    12/05 Construction Budget$4,040,000.00

    Alternate for extra garage bay$120,460.00

    Original Aggregate Contract$4,270,460.00

    Approved Change Orders$145,622.00

    Revised Aggregate Contract$4,416,082.00

    Total Contract Time365 days

    Contract Time Remaining68 days

    Sheet2

    Sheet3

  • High School Tech Ed ProjectDistrict moved equipment to Tech Ed over Christmas and received occupancy on 1/22/06. Many second floor punchlist items were addressed over the holidayWork CompletedConditional Occupancy obtained 1/22, elevator has been certified, shop equipment is installed and connected, shop tables are installedWork in Progress Final inspections, District is installing TV StudioTV Studio Electrical Change Order: $6,500.00

    Sheet1

    12/05 Construction Budget$3,563,000.00

    Original Aggregate Contract$3,246,160.00

    Approved Change Orders$69,248.00

    Revised Aggregate Contract$3,315,408.00

    Total Contract Time212 days

    Contract Time Remaining0 days

    Sheet2

    Sheet3

  • Property AcqusitionResolution by the Board on the Calandra property is required. CompleteA public hearing is required (December) to review the acquisition. CompleteBoard approves PlanCon C. CompleteThe District needs 2 updated appraisals CompletePDE approves PlanCon C Submitted and under reviewDetermine next steps

    New 7-8 Building

  • PLANCON Board votes on the resolution. CompletePDE reviews and checks the Act 34 documents. CompleteThe District advertises for the Act 34 Hearing for a minimum of 21 days before hearing CompleteAct 34 Hearing CompleteAct 34 waiting period is 30 days following the hearing CompleteBoard approves PlanCon D & E CompletePlanCon E teleconference CompleteBoard approval PlanCon F prior to bidding

    New 7-8 Building

  • Other ItemsIntersection agreement. Supervisors and District have passed resolutions. Agreement being drafted.Phase II Archeological investigation is complete. A report has been filed with the State. Awaiting approval & Phase III proposal. This work is a prerequisite for DEP project permit.Township Supervisor Preliminary Approval. Complete with conditions on intersection and Mitchell one-way.

    New 7-8 Building

  • New 7-8 BuildingDEI investigated design changes to reduce construction. Board directed final decision on pool, auditorium, etc in Feb. Architect adjusted floorplan for addl efficiencies.

    Design team performed final evaluation of bid document preparation and anticipated the schedule for receipt of the municipal and regulatory approvals required to bid the project. There are no guarantees.

    Anticipated bid documents release in first week of June. Recommend 6 week bid period.

    Need to coordinate Board action dates for end of July/early August.

    Bid documents will include alternate option for completion by original 8/09 completion date or 11/09.

  • Other Capital ProjectsBoard Room HVAC Replacement HVAC work is complete. Doors have been installed.Stadium synthetic field Bids 3/15. Approval recd Northampton Conservation District . April 1 Construction startCapital Plan Update Meetings have been completed, proposed summer projects identified, draft list will be submitted through Superintendent4-5-6 Building Conversion Meetings have been completed and scope identified.

  • Future Capital ProjectsHigh School Classroom Expansions (Not Board approved) A review of the budgeted scope and budget was completed. Options need to be exploredBridge between new MS and HS (Not Board approved) The pending DEP permit contains information related to this project.

  • THANK YOU!

  • Option 2 Site Plan Development Synthetic Turf Stadium New Track and Field 2 New Practice Fields 1 New Middle School Field