CAPITAL IMPROVEMENT PROJECT UPDATE

City Commission Meeting

April 23, 2018

T. Michael Stavres, Assistant City Manager

Winter Haven Tennis Center Project Commencement August 2017

Project Completion May 2018

Construction Cost $2,712,047

Winter Haven Tennis Center

Lake Maude Park Project Commencement February 2018

Project Completion September 2018

Construction Cost $4,410,441

Lake Maude Park

Master Lift Station Project Commencement January 2017

Project Completion June 2018

Construction Cost $3,091,881

Master Lift Station

South Central Park Improvement Project Project Commencement September 2017

Project Completion September 2018

Construction Cost $4,444,444

South Central Park Improvement Project

7th Street Improvement Project Project Commencement June 2018

Project Completion June 2019

Construction Cost $2,635,999

7th Street Improvement Project

Taxiway E & F Expansion Project Project Commencement June 2017

Project Completion April 2018

Construction Cost $4,108,281