21
Capital and Strategic Planning Committee Item III - A May 10, 2018 FY2018 Third Quarter Capital Program Updates Page 4 of 44

Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

Capital and Strategic Planning Committee

Item III - A May 10, 2018

FY2018 Third Quarter Capital Program Updates

Page 4 of 44

Page 2: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

Washington Metropolitan Area Transit Authority

Board Action/Information Summary

Action Information MEAD Number: 201991

Resolution: Yes No

TITLE:

FY2018 Third Quarter Capital Program Update

PRESENTATION SUMMARY:

This presentation provides an overview of Metro’s performance in executing theFY2018 Capital Program from both a project delivery and benefits to customers’perspectives. The presentation highlights key investments that were delivered or progressedsignificantly during FY2018.

PURPOSE:

Management will update the Capital and Strategic Planning Committee on the status,delivery and success of the FY2018 Capital Program through the third quarter.

DESCRIPTION:

Key Highlights:

$810 million of capital investments were made through Q3. Full yearcapital investment is forecasted between $1.17 and 1.25 billion,compared to a budget of $1.25 billion.Capital investments are a major contributor to Metro customers ridingexperience. Customers are experiencing less rail offloads due to powerand equipment failures and an increase in bus on-time performance. Escalator and elevator availability have met or exceeded target.

Background and History:

Metro invested $810 million in its capital program through March, compared toa budget of $902 million. Full year capital investment is forecasted between$1.17 and $1.25 billion, compared to a budget of $1,250 million.

Discussion:

Programmatic investments in nine key focus areas represent 75% of capitalinvestment in FY2018.

Page 5 of 44

Page 3: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

Railcars Investment: Metro placed 520, 7000 series railcars into revenueservice by March 30th. Railcar series 1000 and 4000 were disposed and130, 5000 series railcars were removed from passenger service. Metro’s railcars investments contributed to increased reliability with trainstraveling 113,000 miles before an incident; and a nearly 37% decline incustomer offloads due to equipment failure.Rail Infrastructure – Power: Completed installation of 7,538 orangeboots on the entire mainline and 8,651 linear feet of cables off theground in the underground section. Metro installed six tie breakers, fourtraction power substations, and three uninterruptable power supply. Thecompletion of power projects contributed to a 46% reduction in trainoffloads due to power issues.Rail Infrastructure – Track and Structures Rehabilitation and Red LineWater Mitigation: Metro experienced a 48% reduction in speedrestrictions due to improved track. As of third quarter of FY2018, Metrois above or on target with its planned deliverables for structural concretepoured, deck joints, grout pads, fastners, and running rail. Metro addedRed Line Leak Mitigation to its FY2018 deliverables. Structural concretepoured and grout pads increased planned deliverable to addressdefects. Plannned deliverables for leak mitigation and drain rehabilitationare behind schedule due to reallocating resources to higher priorities. Cellular Phone and Radio System Upgrade: Customers benefited fromunderground cell phone service between Metro Center to PotomacAvenue, as well as Benning Road to Addison Road. Metro accelerateddelivery of 450 multi-band radios for MTPD officers. The new radios willimprove interoperability. Rail Station Lighting: Completed 55 of 61 mezzanine lightimprovements. Light levels improved at eight Blue/Orange LineStations. New light fixtures produced a 67% energy savings.Rail Station Improvement - Escalators Replacement: Metro replaced 23escalators. Escalator availability exceeded the 93% target.Rail Station Improvement - Elevator Replacement: Elevator availabilitymet the target of 97%. Metro rehabilitated 9 elevators.Bus Investment: Delivery of bus replacements are slightly behindschedule due to new regulation requirements. Other bus projects, suchas bus rehabilitations, energy storage system replacements andtransmission assemblies, are on or ahead of schedule.Bus - Andrews Bus Garage: Work continues on the installation ofmechanical, electrical, plumbing, interior finishes, and site securityfencing. The project is 82% complete with a projected service date ofJuly 2019.

FUNDING IMPACT:

Information item only - no funding impact.

TIMELINE:

Page 6 of 44

Page 4: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

Previous Actions February 2018 - FY2018 Second Quarter CapitalProgram Update

Anticipated actionsafter presentation

September 2018 - FY2018 Year-End Capital ProgramUpdate

RECOMMENDATION:

No action required -- information item only.

Page 7 of 44

Page 5: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY1

FY2018 Third QuarterCapital Program Update

Capital and Strategic Planning Committee05/10/2018

Page 8 of 44

Page 6: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY2

PurposeProvide FY2018 Third Quarter Capital Program update and highlight

customer benefits of key capital projects

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITYPage 9 of 44

Page 7: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY3 WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITYPage 10 of 44

Page 8: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY4

Railcars Investments

Project DescriptionAcquire 748 new 7000

series railcars by summer 2019

Annual program of railcar preventive maintenance, rehabilitation, safety and reliability improvements

Benefits to CustomersRailcars, on average,

travelled more than 113,000 miles before an incident occurred that delayed passenger travel

Customer offloads due to equipment have declined nearly 37%

100% eight-car trains on Green and Yellow Lines to meet peak ridership demand

FY18 Accomplishments160 new cars placed in

service in FY2018, for a total of 520 in service as of March 31st

Disposed 1000 and 4000 series railcars, oldest and least reliable vehicles

Removed 130 5000 series cars from passenger service23 24 25 23 17 14

2013 2014 2015 2016 2017 2018

Average Fleet Age

Page 11 of 44

Page 9: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY5

Rail Infrastructure – Power

Project DescriptionAnnual ongoing rehabilitation improvements critical to the safe and reliable electrical system performance, and ability to provide additional capacity for 8-car trains

Benefits to Customers46% reduction in train

offloads due to power issues

100% eight-car trains on Green and Yellow Lines

FY18 Accomplishments Installed 6 Tie Breaker

Stations Installed 4 Traction Power

Substations Installed 3

Uninterruptable Power Supply and accelerated system-wide installation

Completed 7,538 Orange Boots on the mainline

Completed 8,651 lf of cables off the ground (underground)

Page 12 of 44

Page 10: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY6

Rail Infrastructure – Track and Structures Rehabilitation / Red Line Water Mitigation

Project Description Annual program to rehabilitate

track and structures by replacing deteriorated components

Pilot grouting solution near Medical Center to mitigate water infiltration in the tunnels without disturbance, removal, relocation, or replacement of any of the existing utilities, infrastructure or track components

FY18 Accomplishments

Components Planned Actual to Date Forecast Status

Structural Concrete Poured (sf) 1,200 1,797 2,000

Deck Joints 600 508 600

Grout Pad Rehabilitation (lf) 8,200 7,696 13,000

Leak Mitigation (ea) 2,750 1,050 1,700 *Drain Rehabilitation (lf) 70,000 19,054 38,000 *Fasteners (ea) 23,500 17,797 23,500

Running Rail (mi) 13.0 8.7 13.0

Red Line (around MedicalCenter) Leak Mitigation (ft) 0 14,270 14,270

Benefits to Customers48% reduction in speed restrictions due to improved track

* Resources were reallocated to higher priority actions and less work required in Medical Center TunnelPage 13 of 44

Page 11: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY7

Cellular Phone / Radio System Upgrade

Project DescriptionReplace existing

comprehensive radio communication system with a new 700 MHz radio system, with interoperable capabilities with other jurisdictions by FY2020

Improves customer access and reliability to cellular service in underground tunnel system

Benefits to CustomersUnderground cell phone

service provided from Metro Center to Potomac Avenue and Benning Road to Addison Road

Cell phone service will be available from Addison Road to Largo Town Center and College Park to Gallery Place later this year

FY18 Accomplishments 13% of overall project

complete through March and project is on schedule

Complete factory acceptance test of all fixed network equipment for the 700MHz radio system (May 2018)

Accelerated delivery of 450 multi-band radios for MTPD officers to improve interoperability

Installed 140,000 linear feet of snake tray and more than 548,000 linear feet of cable

Page 14 of 44

Page 12: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY8

Rail Station Lighting Investments

Light levels improved at eight Blue/Orange Line Stations, including 700% increase at Foggy Bottom and Farragut West

New light fixtures produced a 67% energy savings

New bulbs require replacement 50% to 80% less frequently

Project Description FY18 Accomplishments

Light levels improved at eight Blue/Orange Line Stations, including 700% increase at Foggy Bottom and Farragut West

New light fixtures produced a 67% energy savings New bulbs require replacement 50% to 80% less frequently

Improve illumination, safety, and security in all Metrorail stations by installing new lighting systems that also require less energy, decrease maintenance, and improve system reliability

Awarded three-year contract to replace platform and track bed lights at all 48 underground stations

55 of 61 mezzanine lightings completed. Remaining six mezzanine lighting to be completed by June 30th as planned

Foggy Bottom Passageway Pre-Installation = 1.5 fc

Foggy Bottom Passageway Post-Installation = 10.9 fc

Benefits to Customers

Page 15 of 44

Page 13: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY9

Rail Station Improvement – Escalator Replacement

Project DescriptionRepair, rehabilitate or replace Metro’s 618 escalators

Benefits to CustomersEscalators availability exceeded its target of 93%

FY18 AccomplishmentsReplaced 23 escalators

as of March 31st, with another 5 planned by year end

Judiciary Square escalator completed one month early allowing the acceleration of two Southern Avenue escalators by a month

Page 16 of 44

Page 14: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY10

Rail Station Improvement – Elevator Rehabilitation

Project DescriptionRepair or rehabilitate Metro’s 278 elevators

Benefits to CustomersElevators availability met its target of 97%

FY18 AccomplishmentsRehabilitated 9 elevators as of March 31st, with another 5 planned by year endPentagonFranconia Springfield (2)Judiciary SquareNew CarrolltonWoodley ParkKing Street (2)West Falls Church

Service and Inspection

Page 17 of 44

Page 15: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY11

Bus Investments

Project Description Replace on average 100

buses per year to maintain average fleet age of 7.5 years

Annual program to rehabilitate another 100 buses annually to improve reliability and extend the useful life.

FY18 Accomplishments

Components Planned Actual to Date Forecast Status

Bus Replacement 100 17 87 *Buses Rehabilitated 100 75 100

Energy Storage SystemsReplaced 100 88 100

Engine Assemblies Rebuilt 100 74 100

Transmission Assemblies Rebuilt 120 134 150

Benefits to Customers Bus on-time performance

improved across all days of the week and all service periods

New buses are 100% low floor, improving accessibility and ease of boarding

6.8 7.5 8.1 7.6 7.1 7.7

2013 2014 2015 2016 2017 2018

Average Fleet Age

* Delivery of new buses delayed due to mandated environmental testing of enginesPage 18 of 44

Page 16: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY12

Bus – Andrews Bus Garage

Project DescriptionReplace Southern Avenue Bus Garage with a 175 bus capacity garage and major overhaul maintenance facility by FY2020

Benefits to CustomersIncrease maintenance capacity by ten additional bus bays to ensure that repairs are made in a timely manner

FY18 AccomplishmentsApproximately 82%

complete with a projected service date of July 2019

Continue to install fueling system, mechanical electrical plumbing (MEP), site paving, interior finishes, and acoustical ceilings, and site security fencing

Page 19 of 44

Page 17: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY13

Appendix

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITYPage 20 of 44

Page 18: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY14

Station Out-of-Service Date Return-to Service Date

1 U Street (2 Units) 4/3/2017 9/1/20172 Cleveland Park 6/5/2017 9/14/20173 Smithsonian 6/15/2017 9/21/20174 Naylor Road 5/30/2017 10/4/20175 Eastern Market 6/14/2017 10/23/20176 Friendship Heights 4/25/2017 11/9/20177 Medical Center 4/24/2017 11/15/20178 Stadium-Armory (2 Units) 5/15/2017 11/18/20179 NoMa- Gallaudet U 8/7/2017 11/20/201710 NoMa- Gallaudet U 9/11/2017 12/29/201711 Smithsonian 9/21/2017 1/19/201812 Suitland 10/2/2017 1/22/201813 Suitland 10/4/2017 1/31/2018

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITYPage 21 of 44

Page 19: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY15

Station Out-of-Service Date Return-to Service Date

14 Naylor Road 10/04/17 02/27/1815 Eastern Market 10/23/17 03/02/1816 Cleveland Park 10/23/17 03/12/1817 NoMa- Gallaudet U 11/20/17 03/16/1818 Judiciary Square (2 Units) 11/13/17 04/02/1819 NoMa- Gallaudet U 01/03/18 04/13/1820 Friendship Heights 11/14/17 05/04/1821 Suitland 01/31/18 05/18/1822 Suitland 01/22/18 05/25/1823 Congress Heights 12/04/17 05/28/1824 Courthouse 01/16/18 06/11/1825 Medical Center 11/20/17 06/11/18

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITYPage 22 of 44

Page 20: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY16

Station Out-of-Service Date

Return-to Service Date

1 Pentagon 03/24/17 07/14/172 Franconia Springfield (Unit J03X05) 05/23/17 09/27/173 Franconia Springfield (Unit J03X06) 05/10/17 09/27/174 Judiciary Square 07/07/17 10/21/175 New Carrollton 06/22/17 11/02/176 Woodley Park 07/25/17 11/09/177 King Street (Unit C13N01) 10/18/17 01/02/188 King Street (Unit C13N02) 01/02/18 03/02/18

9West Falls Church Service &Inspection 01/16/18 04/30/18

10 West Falls Church Facility MNT 10/25/18 5/11/1811 Gallery Place 11/08/17 05/19/1812 Prince George’s Plaza (2) 03/05/18 05/28/18

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITYPage 23 of 44

Page 21: Capital and Strategic Planning Committee Item III - A May ... · Discussion: Programmatic investments in nine key focus areas represent 75% of capital ... Metro rehabilitated 9 elevators

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY17

Pre-Foot CandleReadings

Post-Foot CandleReadings with

Tile

FootCandle

Increase

Foot Candle Increase

1 McPherson (East) 7.6 14.8 2.0x2 McPherson (West) 7.1 13.2 2.0x3 Arlington Cemetery 6.5 10.6 2.0x4 Crystal City (Passageway) 3.7 16.5 4.0x5 Foggy Bottom (Passageway) 1.5 10.9 7.0x

6 Foggy Bottom (Under Mezzanine) 2.1 11.4 3.5x

7 Smithsonian (South) 7.1 11.7 1.6x8 Farragut West (West) 1.7 12.3 7.0x9 Farragut West (East) 1.8 09.9 5.5x

10 Pentagon (Lower Level) 2.1 14.5 7.0x11 Pentagon (Passageway) 3.3 13.4 4.0x12 L'Enfant Plaza (7th & MD) 6.1 13.6 2.3x

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY

Page 24 of 44