AttendeesName Job title
Richard Bull CIOAnastasia Birchwood CFO
Cape Rock LtdDate 24.12.2015
Consultant Mats Nyström
BT Monitor Assessment Report Cape Rock Ltd
Solutions area pages:A summary page for one or two solution areas. Each page consists of the following elements: - Current environment's key information - Development projects: - "What next": All development areas to do in green background - "Top Priority project": The most important of them with its schedule and phase.
IT Services mapThis page shows the IT operations' present and planned service production model.
RoadmapThe last pages summarise all development projects in a single, time lined view. This can help you create a more comprehensive view of all key projects with priorities and interaction.
This report is a summary of the answers, assessments, views and strategies that were recorded during the customer interview. Solution map- A summary of key solutions
Maturity analysis- One for key business solution (p.4) and one IT Infrastructure and services (p. 11)- A scorecard based on your assessments of each solution environment's maturity- Top development project within the solution included inside the box
Color codes of the report and their description
Poor Inadequate Intermediate Good Excellent
© 2015 Business Technology International2
Solution area Solution / Application /Support for business
Deployment /End of life span
Maturity assessment
Solution provider /Recommendation
ERP Customized solution / 3 2012 / 2016 2 MXG / 1
Financials iScala / 1 2004 / 2016 2 Epicor / 2
Procurement Visma / 2 2007 / 2016 2 Visma / 2
BI Cognos / 1 2008 / 2014 3 IBM / 2
HR Unit4 Business World / 4 2012 / 2017 3 Unit4 / 3
Payroll As a service / 3 2006 / - 3 Visma / 3
CRM MS Dynamics AX / 4 2006 / - 1 MXG / 2
Digital Service Customized solution / 2 2001 / 2017 2 Self / 3
Document management No solution / 1 2011 / - 2 /
Contractor Extranet Customized solution / 2 2011 / - Self /
# of business apps in total 100
Cape Rock LtdSolution Map
© 2015 Business Technology International3
24.12.2015 1. PAST 2. OUTDATED 3. NORM 4. MODERN 5. FUTURE
1. ERP New Global ERP Evaluation 2016-H1
2. FinancialsNew global Finance and Group Conslidation tools evaluation as part of ERP
2016-H1
3. ProcurementNew purchase to pay
solution as part of ERP 2016-H1
4. BI BI tool evaluation 2016-H2
5. HRM HRM & Payroll solution evaluation 2016-H2
6. Payroll HRM & Payroll solution evaluation 2016-H2
7. CRM Global CRM solution evaluation 2016-H2
8. Digital service Auction features for contractors 2016-H1
9. Document management
New global DM solution evaluation 2016-H1
Cape Rock Ltd
Maturity analysis of key solutions
© 2015 Business Technology International4
Cape Rock Ltd
ERP FinancialsEnvironment
Solution /Business support Life span Solution area
maturitySolution provider /Recommendation
Customized solution / 3 2012 - 2016 2 MXG /1
EnvironmentSolution /
Business support Life span Solution area maturity
Solution provider /Recommendation
iScala / 1 2004 - 2016 2 Epicor /2
What nextElectronic processes / Process
automationMobile workforce solutions (tablets
etc.)
New EAI / Integration to other solutions New solution
New Systems/Services environment ERP User Interface development
Version Upgrade Internet-of-Things Reporting
What next
New solution Version upgrade Group consolidation
Integration to other solutions Automation & electronic processes Reporting
New systems/services environment Partial / total outsourcing or Insourcing
Top priority project Top priority project
Project New Global ERP Evaluation
Schedule 2016-H1 Phase Budgeted
Project New global Finance and Group Conslidation tools evaluation as part of ERP
Schedule 2016-H1 Phase Budgeted
© 2015 Business Technology International5
Cape Rock Ltd
Procurement Business IntelligenceEnvironment
Solution /Business support Life span Solution area
maturitySolution provider /Recommendation
Visma / 3 2007 - 2016 2 Visma /2
EnvironmentReporting solution /
Business support Life span Solution area maturity
Solution provider /Recommendation
Cognos / 1 2004 - 2016 3 IBM / 2
What next
New Purchase-to-Pay solution New systems/services environment
Partial / total outsourcing or Insourcing Invoice automation system
Version upgrade Integration to other solutions New procurement solution
Banking systems
What next
New solution New systems/services environment
Big data Master Data management Database optimization
Version upgrade Data Warehouse improvements Budgeting / forecasting
Reporting Business process definitions (visualisation)
Top priority project Top priority project
Project New purchase to pay solution as part of ERP
Schedule 2016-H1 Phase Budgeted
Project BI tool evaluation
Schedule 2016-H2 Phase Budgeted
© 2015 Business Technology International6
Cape Rock Ltd
HRM PayrollEnvironment
Solution /Business support Life span Solution area
maturitySolution provider /Recommendation
Unit4 Business World / 4 2012 - 2017 3 Unit4 /3
EnvironmentSolution /
Business support Life span Solution area maturity
Solution provider /Recommendation
As a service / 3 2006 - 3 Visma / 3
What next
New solution Version upgrade Recruitment
New systems/services environment Partial / total outsourcing or Insourcing
Workforce planning Data collection Travel management
Working time attendance Competence management Training management
What next
New solution New systems/services environment
Version upgrade Partial / total outsourcing or insourcing
Top priority project Top priority project
Project HRM & Payroll solution evaluation
Schedule 2016-H2 Phase Scheduled
Project HRM & Payroll solution evaluation
Schedule 2016-H2 Phase Scheduled
© 2015 Business Technology International7
Cape Rock Ltd
CRM Digital serviceEnvironment
Solution /Business support Life span Solution area
maturitySolution provider /Recommendation
MS Dynamics AX / 4 2006 - 1 MXG / 2
EnvironmentSolution /
Business support Life span Solution area maturity
Solution provider /Recommendation
Customized solution / 2 2001 - 2017 2 Self / 3
What next
New solution Version upgrade Sales management
New systems/services environment Comprehensive customer view
Contact / Call center Campaign mgmt. Electronic marketing
Activity reporting Business Portal
Social Media integration Global Customer Register
What next
New web store New systems/services Environment
Version upgrade New Extranet/Customer Portals
Security Service usage reporting & analysis
Integrations to other systems
Top priority project Top priority project
Project Global CRM solution evaluation
Schedule 2016-H2 Phase Scheduled
Project Auction features for contractors
Schedule 2016-H1 Phase Budgeted
© 2015 Business Technology International8
Cape Rock Ltd
Document Management (DM) MessagingEnvironment
DM Solution /Business support Life span Solution area
maturitySolution provider /Recommendation
No solution 2011 - 2 /
Environment
E-mail system Mobile Switchboard Messaging platform Solution area maturity
MS Exchange Mobile operator service MS Lync 3
What next
New solution Version upgrade Intranet
New systems/services environment Integration to other solutions
Archiving Content Management System Security
What nextNew voice messaging
solution Telephone exchange services
Email Integration between solutions
Change to service model Enterprise social network
Customer service solutions
Top priority project Top priority project
Project New global DM solution evaluation
Schedule 2016-H1 Phase Scheduled
Project Evaluation of MS Skype for Business as global messaging solution
Schedule 2015-H2 Phase Budgeted
Messaging & Collaboration
© 2015 Business Technology International9
Cape Rock Ltd
Video Conferencing Digital SignageEnvironment
Video conferencing solution Solution provider Solution area
maturity
Cisco Decens 2
EnvironmentNumber of digital signs
(Now / In 2 years)Satisfaction with
Messaging & Collaboration
1 / 60 2
What next
Video utilization in web conferencing New video conferencing solution
Adding video conference rooms Integration between solutions
Conference room technology standardization Video conference equipment
Transform meeting rooms into brainstorm rooms Conference room management
Change to service model
What next
Solution for internal communication Adding targets / units in current system
Content management solution Replacing video projectors with digital signs
Interactive presentation devices Solution for marketing Change to service model
Video projectors
Top priority project Top priority project
Project New Video conferencing solution
Schedule 2016-H1 Phase Scheduled
Project Global Digital Signage solution evaluation
Schedule 2017 Phase Research
Messaging & Collaboration
© 2015 Business Technology International10
24.12.2015 1. PAST 2. OUTDATED 3. NORM 4. MODERN 5. FUTURE
1. Messaging & Collaboration
Evaluation of MS Skype for Business as global
messaging solution 2015-H2
2. PCs & Workstations PC Brand and PC supplier evaluation 2016-H1
3. Tablets & Mobile phones
Tablet/hybrid evaluation (hybrids to replace tablets)
and platform choices as part of new global ERP 201
4. Compute & StorageEvaluation of Hyper
converged systems 2016-H1
5. Corporate WANEvaluation of WAN
operators (tendering 2016-H1) 2015-H2
6. LAN & WLANEvaluation of LAN/WLAN
service providers (tendering 2016-H1) 2015-H2
7. PrintingGlobal Printing agreement
evaluation (including management) 2016-H1
8. IT Service Models Global IT Service Portfolio definitions 2015-H2
Cape Rock Ltd
Maturity analysis of infrastructure
© 2015 Business Technology International11
Cape Rock Ltd
PCs & WorkstationsEnvironment
Device type # of devices Primary brand / base (share)
Satisfaction with PCs environment
All brands & share /new
Preferred procurement model
Primary brand reasoning
Vendor /Recommendation
Notebooks 650 Dell (90%) Dell (90%) Buy Range of products DELL /2
Desktops 1400 Dell (90%) 3 Dell (90%) Buy Range of products DELL /2
Workstations 100 Dell (90%) Dell (90%) Buy Range of products DELL /2
Thin clients 200 Dell (100%) Dell (100%) Buy Quality DELL /2
Volume and TechnologiesNumber of PCs in total PCs annual volume Standard OS Standard Office
2350 750 Win 7 Office 2013
PCs renewing year (amount of units)
Desktop virtualization technology (VDI) PC Protection solution
Citrix F-Secure
What next
Additional OS platforms Windows 10 migration New power workstations
New PCs Security solution Applications virtualization
Desktop virtualization (VDI) Identity Access Management
Lifecycle procurement model
Top priority project
Project PC Brand and PC supplier evaluation
Schedule 2016-H1 Phase Scheduled
End User Computing
© 2015 Business Technology International12
Cape Rock Ltd
Tablets & Mobile phonesEnvironment
Device type # of devices Primary brand / base (share) Satisfaction All brands & share
/newPreferred procurement
modelPrimary brand
reasoningVendor /
Recommendation
Tablets 120 Microsoft (100%) 4 Microsoft (100%) Buy Platform Verkkokauppa.com /3
Mobile phones 2000 Nokia (35%) 3Nokia (30%),
Samsung (55%), Apple (15%)
Volume and preferred device typeAnnual volume
/tablets# of tablets in 2 years
Preferred device type (Hybrid/Tablet) Annual volume /phones
150 400 Hybrid 1000
Platform choicesApple 2
Google 4
Microsoft 4
1. Not recommended or allowed2. Can be used but is not supported3. Can be used but is not fully supported4. Fully supported platform5. Fully supported and recommended platform
What next
Pilot / PoC Platform choices Application evaluations
Application development New devices Security solution
Lifecycle procurement model (DaaS) for mobile phones
Lifecycle procurement model (DaaS) for tablets
Business application deployment Mobile Phone environment harmonization
Top priority project
Project Tablet/hybrid evaluation (hybrids to replace tablets) and platform choices as part of new global ERP
Schedule 2016-H1 Phase Budgeted
End User Computing
© 2015 Business Technology International13
Servers StorageOwn Data Centers
Service provider # of servers (physical / virtual)
Primary server brand /installed base Server brands /purchases
Self 90 / 350 HP (80) TBD (100%)
Satisfaction /environment
HW Vendor /recommendation Virtualization solution Protection solution
2 Atea / 3 VMware F-Secure
Own Data Centers
# of solutions Virtualization solution Primary storage brand /base
Storage brands /purchases
6 Citrix HP TBD (100%)
Backup system / Storage size (TB)
Satisfaction /environment
HW Vendor /recommendation Agreement renewal
HP Dataprotector / 180 TB 2 Atea / 2
Hosted, own hardware
Service provider # of servers (physical / virtual)
Primary server brand /installed base Server brands /purchases
India Telecom 5 / 20 Fujitsu (100) TBD (100%)
Satisfaction /environment
HW Vendor /recommendation Virtualization solution Protection solution
2 India Telecom / 1 Citrix MS Endpoint Protection
Hosted, own hardware
# of solutions Virtualization solution Primary storage brand /base
Storage brands /purchases
1 Citrix HP Fujitsu (100%), TBD (100%)
Backup system / Storage size (TB)
Satisfaction /environment
HW Vendor /recommendation Agreement renewal
Symantec / 15 TB 2 Fujitsu / 2 2017
Server Capacity Services
Service name # of virtual servers Satisfaction /environment
Tieto 45 1
Solutions provider /recommendation Virtualization solution Protection solution
Tieto / 2
Storage Capacity Services
Service name Storage size (TB) Satisfaction /environment
MS Azure StorSimple 10 TB 1
Solutions provider /recommendation Agreement renewal
Tieto / 1 2016
Server capacity as a serviceShare now (%) Estimate share in 2 years (%)
20% 40%
Storage capacity as a serviceShare now (%) Estimate share in 2 years (%)
20% 50%
Cape Rock LtdSystems
© 2015 Business Technology International14
Data Center / Compute & StorageWhat next /Data Center
DC infrastructure development plan Outsourcing
Security solution New data center Data center replication
Systems convergence
What next /Compute & Storage
Server acquirements (HW) Server virtualization
Storage virtualization New backup Archiving
Storage acquirements (HW) Storage performance optimization
In-memory Databases
Top priority project
Project Evaluation of Hyper converged systems
Schedule 2016-H1 Phase Budgeted
Capacity ServicesWhat next
Service model change towards XaaS Hybrid environment
Servers as a service (IaaS/PaaS) Storage as a service (IaaS/PaaS)
Database as a Service (DBaaS) Backup as a service
Big Data requirements
Top priority project
Project New server capacity services evaluation to support Big Data
Schedule 2016-H2 Phase Scheduled
Cape Rock LtdSystems - Development projects
© 2015 Business Technology International15
Cape Rock Ltd
WAN LAN & WLAN Mobile NetworkEnvironment
Internet operator /Recommendation
Firewall implementation model (Service provider)
Open Systems (UK) /1
As a service (Open Systems (UK))
EnvironmentCentral switches
/purchasesEdge switches
/purchasesWLAN devices
/purchases
Cisco (100%) HP (100%) Aruba (100%)
Network virtualization HW Vendor Satisfaction /LAN
environment
Not in use Elisa 2
EnvironmentMobile operator /Recommendation Number of SIMs
TeliaSonera /4 450
What nextOperator change / service tendering Capacity increase
Connecting offices Securing availability
Distributed Denial of Service mitigation Network acceleration
Security
What next
Comprehensive development plan LAN/WLAN as a service
Fault tolerance development Capacity increase
DC network virtualization New DC network switches
Access management Net management solution
Maintenance services Network traffic analyzer
Application acceleration
Application performance mgmt.
What nextOperator change / service tendering Capacity increase
Cost optimization Security / management
New solution areas
Top priority project Top priority project Top priority project
Evaluation of WAN operators (tendering 2016-H1)
Schedule 2015-H2 Phase Budgeted
Evaluation of LAN/WLAN service providers (tendering 2016-H1)
Schedule 2015-H2 Phase Budgeted
Nordic Countries' Mobile Operator evaluation (tendering 2016-H1)
Schedule 2015-H2 Phase Budgeted
Data Communications & Networks
© 2015 Business Technology International16
Cape Rock Ltd
Printing devices
Device type Number of devices
Primary brand /base (share) Satisfaction All brands & share / new
purchases Vendor / recommendation Primary brand reasoning
A3 Multifunction 60 Canon (50%) 4 Canon /3 Price
A4 Workgroup 220 HP (70%) 5 HP (100%) Atea /3 Price
Personal 200 HP (%)
Acquired as a ServiceDevice type Devices Supplies Maintenance
A3 Multifunction No Yes Yes
A4 Workgroup No No Yes
Personal No No No
# of printers (total amount) Service agreement life span
480 2016
What nextOptimizing the # of
devices 3D printing Change into service model
Management solution Tendering (devices) Tendering (supplies)
Mobile printing Modernizing the device base
Follow me printing
Top priority project
Project Global Printing agreement evaluation (including management)
Schedule 2016-H1 Phase Scheduled
Printing
© 2015 Business Technology International17
Cape Rock Ltd
IT Services Map
Service areaService model
(Self / Outsourced)
Time for change Management solution Satis-
factionService provider
(external) /Recommendation
Workstation services Self 2016 MS System Center 3 / -
Service desk Self 2015 OTRS 3 / -
Mobile device management Outsourced 2016 Airwatch 3 Elisa / 2
Systems management Outsourced 2016 As a service 1 Tieto / 2
LAN management Self 2016 Cisco 2 / -
ITSM Self No solution 2 / -
Other informationIT employees (Own +
Others') Maturity / Model Maturity / Technology
60 + 5 = 65 2 2
What next
Workstation management Service desk Mobile device management
Systems management LAN/WLAN management ITSM solution
Asset mgmt Service portfolio Service order & delivery automation
Self service models Outsourcing of service operations Service provider evaluations
Cyber security Business Continuity & Disaster Recovery
Top priority project
Project Global IT Service Portfolio definitions
Schedule 2015-H2 Phase Budgeted
IT Service Models
© 2015 Business Technology International18
Roadmap of solutions development projects
Cape Rock Ltd
2015 201624.12.2015 1-6 7-12 1-6 7-12
ERP New Global ERP Evaluation
FinancialsNew global Finance and Group Conslidation tools evaluation as
part of ERP
HRM HRM & Payroll solution evaluation
Payroll HRM & Payroll solution evaluation
CRM Global CRM solution evaluation
Business intelligence BI tool evaluation
Digital Service Auction features for contractors
Procurement New purchase to pay solution as part of ERP
Document management New global DM solution evaluation
Color codes=phase of project Research Scheduled Budgeted Under way
© 2015 Business Technology International19
Roadmap of development projects Cape Rock Ltd
2015 201624.12.2015 1-6 7-12 1-6 7-12
IT managementConsolidation and rolling out of
global IT services (Harmonization, standardization, SLAs)
MessagingEvaluation of MS Skype for
Business as global messaging solution
Video conferencing New Video conferencing solution
Digital signage
PCs & workstations PC Brand and PC supplier evaluation
Business mobilityTablet/hybrid evaluation (hybrids to
replace tablets) and platform choices as part of new global ERP
Systems Evaluation of Hyper converged systems
Capacity services New server capacity services evaluation to support Big Data
WAN Evaluation of WAN operators (tendering 2016-H1)
LAN & WLAN Evaluation of LAN/WLAN service providers (tendering 2016-H1)
Mobile network Nordic Countries' Mobile Operator evaluation (tendering 2016-H1)
Printing Global Printing agreement evaluation (including management)
IT service models Global IT Service Portfolio definitions
Color codes=phase of project Research Scheduled Budgeted Under way
© 2015 Business Technology International20