Capacity Development for the Clean Development Mechanism in the PHILIPPINES. STATUS REPORT Asian Regional Workshop 16 th January 2003 Phuket, Thailand. Outline of the presentation. Project Implementers in the Philippines Formulation of the Draft Work Plan National Workshop - PowerPoint PPT Presentation
Citation preview
Capacity Development for the Clean Development Mechanism in the PHILIPPINES
STATUS REPORTAsian Regional Workshop
16th January 2003Phuket, Thailand
Outline of the presentation1. Project Implementers in the Philippines
2. Formulation of the Draft Work Plan
3. National Workshop
4. Revised Work Plan
5. Developments and Concerns
1. Focal Point AgencyGovernment agency formally responsible for
implementing the project in the Philippines
Inter-Agency Committee on Climate Change
(IACCC)
1. Focal Point AgencyInter-Agency Committee on Climate Change
(IACCC) Established 8th May 1991
Presidential Administrative Order No. 220
Coordinates the Philippines’ climate-change related activities
Prepares climate change policies and the Philippine positions at the UNFCCC negotiations
1. Focal Point AgencyInter-Agency Committee on Climate Change
(IACCC) Chair: Secretary, Department of Environment
and Natural Resources
Co-Chair: Secretary, Department of Science and Technology
Secretariat: Environmental Management Bureau, Department of Environment and Natural Resources
1. Focal Point AgencyMembers of the IACCC Department of Environment and Natural Resources Department of Science and Technology Philippine Atmospheric, Geophysical, Astronomical
Services Department of Foreign Affairs National Economic Development Authority Department of Energy Department of Transportation and Communications Department of Agriculture Philippine Network on Climate Change (NGO)
1. Assisting InstitutionInstitution responsible for the day to day
implementation of the project contracted by UCCEE to assist the IACCC in the Philippines
Climate Change Information Center(CCIC)
Manila ObservatoryAteneo de Manila University
2. Formulation of Draft Work PlanReviewed previous studies related to CDM in the
Philippines
1994 National GHG Inventory U.S. Country Studies Program
Asia Least Cost Greenhouse Gas Abatement Strategy (ALGAS) 1994-1998, GEF-UNDP-ADB
National Action Plan on Climate Change 1997, USAID
2. Formulation of Draft Work PlanReviewed previous studies related to CDM in the
Philippines
Philippine Climate Change Mitigation Program 1998-2001, DOE & IACCC
Study on Capacity Building on the CDM UNDP, 1999
Philippine Agenda 21 for Sustainable Development Philippine Council for Sustainable Development
2. Formulation of Draft Work PlanInterviewed relevant experts and resource persons
Developers of renewable energy projects
Financiers of renewable energy projects
Government officials Department of Environment and Natural Resources Department of Energy Department of Finance
Multilateral institution Asian Development Bank
2. Formulation of Draft Work PlanAttended seminars and conferences related to CDM
World Wildlife Fund forum on CDM
Executive briefing on CDM for senior officials of Development Bank of the Philippines
Climate Change Impacts in the Philippines
Climate Change and Sustainable Development
Orientation to CDM
2. Formulation of Draft Work PlanMade presentations and facilitated discussions in
seminars and conferences on CDM
Seminar on CDM for mid-level officials of the Development Bank of the Philippines
CDM: Transforming the Energy Economy of the Philippines
Consultation on Designated Operational Entities for CDM
2. Formulation of Draft Work Plan
The Draft Work Plan is a consolidation of elements gathered through research, data gathering, interviews, consultations, meetings, seminars and conferences.
The Draft Work Plan was the principal document for discussion and comment at a National Workshop.
3. National Workshop Conducted 9th—11th December 2002
Participants Private Sector (especially developers &
financiers of renewable energy projects) – majority of workshop participants
Government officials (especially members of IACCC)
Non-Governmental Organizations Academe Auditing firms and ISO certifiers
3. National Workshop Objectives
1. Present the proposed Work Plan
2. Discuss the comprehensiveness, suitability and feasibility of the Work Plan
3. Solicit comments, suggestions and revisions which will make the Work Plan more appropriate
4. Build consensus that the Work Plan be endorsed for funding and implementation
3. National Workshop Topics
Overview of the CDM
CDM National Authority
Capacity Development for CDM Project Developers
CDM Project Financing
Work Plan for Capacity Development for CDM in the Philippines
3. National Workshop Presentations by resource persons on
the prospects of CDM in the Philippines; the capacity needs of different CDM stakeholders in the
Philippines.
Plenary discussions on the prospects of CDM in the Philippines; the capacity needs of different CDM stakeholders in the
Philippines.
Plenary discussions on issues involved regarding the establishment of the CDM National Authority in the Philippines.
3. National Workshop
Small group discussions on details of the Draft Work Plan.
Plenary discussion on comments and suggested revisions of the Draft Work Plan.
4. Revised Work Plan The Draft Work Plan has been revised
taking into account the comments and suggestions made during the National Workshop.
The Revised Work Plan will be presented in detail during the afternoon session of Day 1 of the Regional Workshop.
4. Revised Work PlanFive Tasks
I. Conduct information campaign and awareness raising
II. Strengthen the capacity of policy-makers1. Generate the interest and support of senior policy-
makers
2. Develop the capacity of mid-level policy-makers
4. Revised Work PlanFive Tasks
III. Establish the institutional framework for the CDM
1. Establish the CDM National Authority
2. Develop the capacity of the CDM National Authority
4. Revised Work PlanFive Tasks
IV. Strengthen the capacity of private and public sector players
1. Develop the capacity of project developers
2. Develop the capacity of project financiers
3. Develop the capacity of NGOs, local communities, national research institutions and academe
4. Revised Work PlanFive Tasks
V. Create a pipeline of CDM Projects
1. Establish a CDM promotions office
2. Facilitate the development of CDM-Eligible Projects
5. Developments and Concerns Growing interest for CDM among developers of
renewable energy projects A few projects presently being developed as potential
CDM projects Philippines has not yet ratified the Kyoto Protocol Formation of CDM Task Force composed of
Department of Environment & Natural Resources Department of Energy Development Bank of the Philippines
Identification of key sectors and projects that should be targeted for CDM
Thank you! Ms. Jocelyn Goco
Inter-Agency Committee on Climate Change
[email protected] Tel +63 2 920-2251
Mr. Rey Guarin Development Bank of
the Philippines [email protected] Tel +63 2 893-1782 Fax +63 2 815-1611
Dr. Roberto Yap Climate Change
Information Center [email protected] Tel +63 2 426-6144; Fax +63 2 426-6070
Ms. Marina Mallare Climate Change
Information Center [email protected] Tel +63 2 426-6495 Fax +63 2 426-6141