    Apr i l 4 , 201 2

    d e si g n / co n st ru c t i o n so l u t i o n s

    CampbellAvenue ProjectUtility Replacement &

    Slope Stabilization

    Public Informational Meeting

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    2/43

    Goals for this Meeting

    Define the Project Challenges

    Utility Replacement Slope Stabilization

    Provide Overview of Project Schedule

    Summarize Work Done to Date

    Define Tasks and Schedule Moving Forward

    Provide Answers to Frequently Asked Questions

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    3/43

    Project Overview

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    4/43

    Utility Replacement

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    5/43

    RPhase ISew erRepa i rs

    Phase I ISew er Repa i rs

    Rem ova l o fB lockage ( Roo ts )

    15 Sanita

    ry Se

    wer

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    6/43

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    7/43

    Complications Caused by Voids Under the Roadway

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    8/43

    Complications Caused by Voids Under the Roadway

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    9/43

    Challenging Work Condit ions

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    10/43

    Challenging Work Condit ions

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    11/43

    Night Time Construction

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    12/43

    Damaged Waterline caused by Sewer Collapse

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    13/43

    Temporary Roadway Resurfacing

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    14/43

    Root Removal from Sewer by City Forces

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    15/43

    Preliminary Geotechnical Evaluation

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    16/43

    Con t r i bu to r yDra inag e Sour ce

    Erosion

    of Bank

    Seepage

    PerchedGroundwa te rTable

    Se t t l em en ta long Shou lde r

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    17/43

    Settlement Along the Roadway Shoulder

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    18/43

    Settlement Along the Roadway Shoulder

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    19/43

    Erosion of Slope

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    20/43

    Erosion of Slope

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    21/43

    Erosion of Slope

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    22/43

    State Wet land at the Bott om of the Slope

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    23/43

    Upland Cont ributory Drainage Course

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    24/43

    Steepness of the Slope

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    25/43

    Steepness of the Slope

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    26/43

    Steepness of the Slope

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    27/43

    Expanded Geotechnical Program

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    28/43

    Survey of Slope with Wetland Delineation

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    29/43

    Expanded Soils and Groundwater Program

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    30/43

    Laboratory Test ing

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    31/43

    Cross Section of the Slope

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    32/43

    Activities Moving Forward

    Final Evaluation and Coordination of Utilities

    Advancement of Slope RemediationAlternatives

    Development of Concepts for Thomas Pond

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    33/43

    Slope Stabilization

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    34/43

    Frequently Asked Questions

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    35/43

    Frequently Asked Questions

    Why was Campbell Avenue closed?

    An emergency declaration was issued onFebruary 23rd to close Campbell Avenue.This recommendation was made based onongoing issues with the utilities as well asconcerns relative to the stability of theslope. Without a full understanding of

    these issues, conditions potentially posed apublic safety threat.

    Q:

    A:

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    36/43

    Frequently Asked Questions

    What is the cause of these problems?

    The initial sewer collapse appears to be theresult of surcharging conditions, with high

    flows and velocities, experienced during theextreme weather in the Fall. The repair ofthe damaged utilities led to the discovery ofother factors which raised concerns relative

    to the overall stability of the slope.

    Q:

    A:

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    37/43

    Frequently Asked Questions

    What is causing delays in remediating theproblems?

    In order to better understand the existingconditions for both the utilities and theslope, expanded geotechnical and utility

    investigations needed to be progressed.The Engineer recommended that furtherrepairs to the infrastructure were placed onhold until the direction of the remediationmeasures was better understood.

    Q:

    A:

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    38/43

    Frequently Asked Questions

    What problems need to be addressed priorto the re-opening of the roadway?

    The solution needs to address issues withthe damage utilities as well as theconditions affecting the stability of the

    slope.

    Q:

    A:

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    39/43

    Frequently Asked Questions

    How much is this project going to cost?

    The extent of the remediation work has notbeen fully defined at this time. As such,cost implications are currently being

    evaluated and will be taken into accountwith other factors such as the constructionmethods and the Citys ability to reopenthe roadway. Upon completion of ongoingwork tasks, further details will be releasedto the public later this month.

    Q:

    A:

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    40/43

    Frequently Asked Questions

    Will FEMA assist with the funding of thisproject?

    The City is currently working together withFEMA on this project, as well as otherprojects resulting from Hurricane Irene and

    Tropical Storm Lee. A final determinationof FEMA funding for this project has notbeen made to date. Remediation of theutilities and slope will need to be completedby the City for Campbell Avenue regardlessof FEMAs decision on funding.

    Q:

    A:

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    41/43

    Frequently Asked Questions

    When will Campbell Avenue be re-openedto the general public?

    The City hopes to have the roadway re-opened by July, upon completion of theutility repairs. It is anticipated that themajority of the work required to stabilizethe slope will be completed from the baseof the slope. That said, temporary closuresand/or limitations to traffic may be

    necessary to complete specific itemsassociated with the slope remediationwork.

    Q:

    A:

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    42/43

    Additional Questions

  • 8/2/2019 Campbell Ave Rehabilitation Project Powerpoint Presentation

    43/43

    ContactMike Fraser

    Deputy Director of Public Information518.279.7131