Calibration Order Scenario: PM – QM Integration
Calibration Equipment
General task List (IA06)
QM Data – Inspection points setup in the Header as shown above
MIC assigned for the Operation as displayed.
Now create a Maintenance plan – For the Calibration Equipment (IP01)
Assign the General task list for the Plan (We can also Equipment task lists as well)
Scheduling overview: (IP24)
Now lets simulate Calibration orders for future dates for running IP30.
As I ran the simulation for 400 days – I had got the above order generated.
Lets view the scheduling overview…IP24
See orders generated till March 2018.
Lets release the order and do next steps.
IW32
Order is in created status and I see no inspection lot generated.
Release the order now..
Save.
Open the order again. An inspection lot should be generated. (PM-QM Integration)
Lets view the inspection lot…
Inspection lot got generated for the order against the Equipment.
Now We need to do Result Recording and Usage Decision against the Inspection lot.
PM – QM Integration:
There are ways to do the RR & UD:
QE51N
Result Recording…
Enter your results against each MIC
We see the lot status as Results confirmed.
Now lets do the UD:
Click Save
Click OK
Prompts to Order confirmation screen.
Enter work hours and save.
Lets go the order and see the status.
Order got CNF Confirmed.
See the Inspection Lot status:
RR & UD has been made.
CASE II : Negative Scenario Test (when my results are out of limits)
Lets take order with inspection lot – 140000000356
Lets do RR & UD
I had recorded failure results here. As we see above
Am selecting – Reject – Out of Tolerance
No do the UD
Save the order.
If you wanna rework on the Order – As we see PCNF.
We can add an another step to install an new Equipment in our operation
Now you can TECO this order.
Note: (order would not be copied to Inspection lot as we the results have failed)