Calgary Symposium Plan 54

Embed Size (px)

Citation preview

  • 7/25/2019 Calgary Symposium Plan 54

    1/63

    .

    User Experience with Plan 54

    Seal Flush System2007

  • 7/25/2019 Calgary Symposium Plan 54

    2/63

    .

    Presenters:

    Michel Boutin: Machinery Engineer

    Shell Scotford Refinery

    Brad Hatton: Machinery Engineer

    Shell Scotford Refinery

  • 7/25/2019 Calgary Symposium Plan 54

    3/63

    Definition Plan 54

    Pressurized external barrier fluid system

    supplying clean fluid to the sealchamber. Circulation is by an externalpump or pressure source. Reservoirpressure is greater than processpressure being sealed.

    API 682

  • 7/25/2019 Calgary Symposium Plan 54

    4/63

    Plan 54

    Clean

    External

    Source ofPressurized

    Barrier Fluid

    A PI Plan 54

  • 7/25/2019 Calgary Symposium Plan 54

    5/63

    Overview - Scotford

    Barrier fluid system is common to many

    pumps in the unit. (12 Pumps with 15seals)

    Finished product (ULSD) is the barrierfluid.

    Control the barrier fluid pressure at 140

    kPag (20psig) above the stuffing boxpressure.

  • 7/25/2019 Calgary Symposium Plan 54

    6/63

    Overview (cont)

    System pressure is maintained by amain pressure control valve on the skid.

    Pressure control to each pump is by alocal control valve.

    Flow control is maintained by arestriction orifice.

    Cooling of barrier fluid is by an AirCooled Heat Exchanger

  • 7/25/2019 Calgary Symposium Plan 54

    7/63

    Skid Details

    The barrier fluid skid consists of:

    2 IMO screw pumps

    Air Cooled Heat Exchanger

    Duplex Filters System reservoir

  • 7/25/2019 Calgary Symposium Plan 54

    8/63

    Pump Details

    Each pump has a local Pressure

    Reducing Valve (PRV) to drop theheader pressure

    One PRV for each pair of pumps Local Flow Indications to each seal.

    Flow orifice located down stream ofeach seal

  • 7/25/2019 Calgary Symposium Plan 54

    9/63

    Process P &ID

  • 7/25/2019 Calgary Symposium Plan 54

    10/63

    Typical Pump P&ID

  • 7/25/2019 Calgary Symposium Plan 54

    11/63

    Operating History

    System was chemically cleaned and

    flushed during commissioning Used milk pads at each seal to check

    for cleanliness

    Found three failed seals upon start up

    Flow indicators showed high flows and

    one was leaking to grade

  • 7/25/2019 Calgary Symposium Plan 54

    12/63

    20V26CP2:LI20471.PNT

    V2026 Barrier Fluid Reservoir

    03/05/2006 12:00:00 AM 10/16/2006 12:00:00 AM224.96 days

    10

    20

    30

    40

    50

    60

    70

    80

    0

    100

    62.4870

    Reservoir Level History from Start-up

  • 7/25/2019 Calgary Symposium Plan 54

    13/63

    Set points

    Alarms were set on the flows to eachseal

    High Flow was set@ 90% of instrumentrange (2X Normal flow)

    Low Flow was set @ value from SealSupplier

    Low Pressure Alarm set at 70 kPag (10psig) above stuffing box pressure.

  • 7/25/2019 Calgary Symposium Plan 54

    14/63

    Set Points (cont)

    Differential Pressure across the filters

    High Temp Alarm (50C)

    High Pressure Alarm on Reservoir.

    High and Low Level Alarm on Reservoir

  • 7/25/2019 Calgary Symposium Plan 54

    15/63

    Troubleshooting

    Detecting small leaks on the inner sealis next to impossible. Trending on the

    flows helps but small leaks are notdetectable.

    Leaks on the secondary seal will showbarrier fluid on the pump

    Trouble shooting guide for Operations

    was generated

  • 7/25/2019 Calgary Symposium Plan 54

    16/63

    Troubleshooting (cont)

    Would need to systematically isolate the

    spare pumps and trend the reservoir levelover a few days.

    Since all seals leak in order to provide

    lubrication we may not have a leak at all

    Finished product (ULSD) is the barrier fluid

    we are not contaminating the system

  • 7/25/2019 Calgary Symposium Plan 54

    17/63

    Learnings From Start-up

    Flushing of the system took longer than

    expected even though it was chemicallycleaned and under an N2 blanket during

    construction.

    Remaining water in the skid from the

    OEM was frozen and only after the

    system was started up did the ice thawreleasing small debris into the piping.

  • 7/25/2019 Calgary Symposium Plan 54

    18/63

    Learnings (cont)

    We did not flush through each seal and had

    to install a temporary jump-over to avoid

    flushing debris thru the seal. The reservoir does not have a weir or baffle

    plate. Suction to pumps is located on the

    bottom. Future projects should have it on the

    side or use a stand pipe inside.

    No Source of heat for the fluid. Relying on theheat generated by the seals.

  • 7/25/2019 Calgary Symposium Plan 54

    19/63

    Learnings (cont)

    The piping run to each pump has a lot

    of low points and high points. Shouldbe stream lined to push any vapour in

    the piping up and though the seals.

  • 7/25/2019 Calgary Symposium Plan 54

    20/63

    First Major Failure

    Operators have been making entries into the

    logs that this system has been operating

    poorly from Nov 21 Dec 5, 2006 during acold snap

    December 5th, 2006 after an extended cold

    snap, local ambient temperatures rose above

    0oC

    First indication of trouble was the loss ofsystem pressure the morning of Dec 5th.

  • 7/25/2019 Calgary Symposium Plan 54

    21/63

    First Major Failure (Cont)

    IMO pump started to cavitate

    Operators started the spare, believingthat the first pump failed.

    Filter differentials on the skid were

    erratic. Barrier Fluid usage as indicated by the

    level in the surge vessel had not beenthe same as it had been in the past.

  • 7/25/2019 Calgary Symposium Plan 54

    22/63

    First Major Failure (Cont)

    Fluid sample from the surge vessel was

    the first indication that there was a largeamount of water in the system.

    System contents was drained, and filled

    at the same time to purge the system of

    water.

    Second pump quickly showed signs offailed internals.

  • 7/25/2019 Calgary Symposium Plan 54

    23/63

    Reservoir Level Leading up to Failure

    20V26CP2:LI20471.PNT

    V2026 Barrier Fluid Reservoir

    10/01/2006 12:00:00 AM 12/10/2006 12:00:00 AM70.04 days

    10

    20

    30

    40

    50

    60

    70

    80

    0

    100

    61.8730

  • 7/25/2019 Calgary Symposium Plan 54

    24/63

    E2014 BARRIER COOLR TO HDR

    E2014 BARRIER COOLR TO HDR

    E2014 BARRIER COOLR TO HDR

    S2022A/B BARRIER FILTERS

    20E14CP2:PC20411.MEAS

    kPag

    20E14CP2:PC20411.OUT

    %

    20E14CP2:PC20411.SPT

    kPag

    20E14CP2:PDI20472.PNT

    kPa

    Supply to Pumps

    12/05/2006 12:00:00 AM 12/06/2006 12:00:00 AM24.00 hours

    500

    1000

    1500

    2000

    2500

    0

    3000

    0

    100

    0

    3000

    0

    100

    -0.1155

    31.6277

    0.0000

    31.6277

    System Pressure Failure Trend

  • 7/25/2019 Calgary Symposium Plan 54

    25/63

    System Pressure Failure Trend

    E2014 BARRIER COOLR TO HDR

    E2014 BARRIER COOLR TO HDR

    E2014 BARRIER COOLR TO HDR

    S2022A/B BARRIER FILTERS

    20E14CP2:PC20411.MEAS

    kPag

    20E14CP2:PC20411.OUT

    %

    20E14CP2:PC20411.SPT

    kPag

    20E14CP2:PDI20472.PNT

    kPa

    Supply to Pumps

    12/05/2006 8:00:00 AM 12/05/2006 10:00:00 AM2.00 hours

    500

    1000

    1500

    2000

    2500

    0

    3000

    0

    100

    0

    3000

    0

    100

    6.1878

    1408.6914

    0.0000

    1408.6914

  • 7/25/2019 Calgary Symposium Plan 54

    26/63

    First Major Failure (Cont)

    Process Unit was shutdown, to preserve

    critical equipment. Two teams were set up. One to repair

    and flush the system, the other to

    investigate the failure.

    Being a new unit, the system had

    functional instrumentation

  • 7/25/2019 Calgary Symposium Plan 54

    27/63

    Major Findings from First Failure

    One seal that was not designed for the full

    Plan 54 system pressure

    Failed one seal before the major incident.Pump is in water service. Analysis showed it

    had a reverse pressure event.

    Failed another seal in water service. It had

    been suspected a procedural error in

    checking for leakage during the first event.

  • 7/25/2019 Calgary Symposium Plan 54

    28/63

    Major Findings

    No way to tell when there is water in thesystem.

    No easy way to drain water from thesystem.

    Circulation pump selection is acceptablefor a clean system, but did not take inaccount for off design conditions.

    EHT was not considered in the project

  • 7/25/2019 Calgary Symposium Plan 54

    29/63

    Pump Seal Failure in Water Service

  • 7/25/2019 Calgary Symposium Plan 54

    30/63

    Pump Seal Failure in Water Service

  • 7/25/2019 Calgary Symposium Plan 54

    31/63

    Proposed Post Failure Changes

    Installation of a water boot

    Installation of a conductivity detector forwater

    Proposed new pump to handle high

    levels of water

    Working to remove one water pump

    from the system (H2S Levels)

  • 7/25/2019 Calgary Symposium Plan 54

    32/63

    Implemented Post Failure Changes

    Developed Procedure to test individual

    pump seals for integrity before start-up.

    Complete spare pump now on the shelf.

    PM plan to replace pump and inspect.

    EHT being installed at low points.

  • 7/25/2019 Calgary Symposium Plan 54

    33/63

    Minor Failure in May 2007

    Circulation Pump pressure started to fall, and

    operators detected water in the system again. Immediately started to conduct an online

    flush of the system to save the second IMO

    pump.

    P-2005 (Sour Water from Driers) was

    suspected leaking water into the Barrier FluidSystem, as the water was clean.

  • 7/25/2019 Calgary Symposium Plan 54

    34/63

    Minor Failure in May 2007

    Removed seal from pump did not indicate afailure of the seal.

    Had the revelation that the barrier systempressure was too low for the P-2005s

    Pumps were rebuilt shortly after start-up, and

    after the initial barrier pressure survey. Stuffing box pressure was higher than the set

    pressure for the barrier fluid.

    Adjusted barrier pressure from 1250 kPa to1800 kPa.

  • 7/25/2019 Calgary Symposium Plan 54

    35/63

    P2005A/B BARRIER FLUID

    P2005A/B BARRIER FLUIDP2005A/B BARRIER FLUID

    P2005A BARRIER FLUID

    P2005B BARRIER FLUID

    20P05CP2:PC20551.MEAS

    20P05CP2:PC20551.OUT

    20P05CP2:PC20551.SPT

    20P05CP2:FI20549.PNT

    20P05CP2:FI20554.PNT

    P2005A/B Sour water

    05/14/2007 3:12:32.363 PM 05/21/2007 4:12:32.363 PM7.04 days

    500

    1000

    1500

    0

    2000

    0

    100

    0

    2000

    0.3

    0.6

    0.3

    0.6

    0.4921

    0.5514

    1800.0000

    31.4801

    1801.4902

  • 7/25/2019 Calgary Symposium Plan 54

    36/63

    Minor Failure in May 2007

    After the set pressure change, no major

    water excursions have occurred.

  • 7/25/2019 Calgary Symposium Plan 54

    37/63

    P-2008 Vacuum Pump Seals

    ANSI style seal, limited stuffing box

    size.

    Moved to a TiC/SiC seal face

    combination due to initial seal failuresduring start-up.

  • 7/25/2019 Calgary Symposium Plan 54

    38/63

    August 29 30, 2007 Operation

    Numerous Stop Starts on both pumps.

    Started another rapid loss of level in the

    surge drum, greater that what we haveseen in the past.

    Barrier fluid flow was not that muchhigher than what it was in the past.

    Decided to swing to P-2008A and

    isolate P-2008B

  • 7/25/2019 Calgary Symposium Plan 54

    39/63

    September 5, 2007 Operation

    Isolated P-2008B and the level in the

    surge drum stabilized.

    Maintained operation of P-2008A

  • 7/25/2019 Calgary Symposium Plan 54

    40/63

    V2026 BARRIER FLUID DRuM

    20V26CP2:LI20471.PNT

    %

    V2026 Barrier Fluid Reservoir

    08/28/2007 11:40:57.985 AM 09/11/2007 12:40:57.985 PM14.04 days

    20

    30

    40

    50

    60

    70

    80

    0

    100

    84.4665

  • 7/25/2019 Calgary Symposium Plan 54

    41/63

    P2008A BARRIER FLUID

    P2008A BARRIER FLUID

    P2008A BARRIER FLUIDP2008B BARRIER FLUID

    P2008A BARRIER FLUID

    P2008A LIQ RINGRUN STAT

    P2008B LIQ RINGRUN STAT

    20P08CP2:PC20561.MEAS

    kPag

    20P08CP2:PC20561.OUT

    %

    20P08CP2:PC20561.SPT

    kPag

    20P08CP2:FI20559.PNT

    Am3/h

    20P08CP2:FI20564.PNT

    Am3/h

    20P08CP2:XI20734.CIN

    20P08CP2:XI20735.CIN

    P2008A/B Vacuum

    08/28/2007 11:44:26.677 AM 09/11/2007 12:44:26.677 PM14.04 days

    200

    400

    600

    800

    1000

    0

    1200

    0

    100

    0

    1200

    0.2

    0.5

    0.2

    0.5

    0

    2

    0

    2

    0

    1

    -0.0004

    -0.0002

    232.0000

    68.2035

    238.2031

  • 7/25/2019 Calgary Symposium Plan 54

    42/63

    20V26CP2:LI20471.PNT

    V2026 Barrier Fluid Reservoir

    08/07/2007 12:00:00 AM 11/05/2007 12:00:00 AM90.04 days

    10

    20

    30

    40

    50

    60

    70

    80

    0

    100

    65.7390

    Present Operation of the Reservoir Level

  • 7/25/2019 Calgary Symposium Plan 54

    43/63

    Present Water Status in the System.

    We are still building water in the system

    The rate of water build up is very slow.

    The water is not sour, which indicates

    possibly three sources of water.

  • 7/25/2019 Calgary Symposium Plan 54

    44/63

    October 11th Sample

  • 7/25/2019 Calgary Symposium Plan 54

    45/63

    October 29th Sample

  • 7/25/2019 Calgary Symposium Plan 54

    46/63

    Barrier Fluid Skid

  • 7/25/2019 Calgary Symposium Plan 54

    47/63

  • 7/25/2019 Calgary Symposium Plan 54

    48/63

    Local Pump Control

  • 7/25/2019 Calgary Symposium Plan 54

    49/63

    Local Pump Control

  • 7/25/2019 Calgary Symposium Plan 54

    50/63

    Barrier Fluid Skid

    EHT/T W f Wi t

  • 7/25/2019 Calgary Symposium Plan 54

    51/63

    EHT/Temp Wrap for Winter

    EHT @ P 2014A

  • 7/25/2019 Calgary Symposium Plan 54

    52/63

    EHT @ P-2014A

    Fl I di ti S t

  • 7/25/2019 Calgary Symposium Plan 54

    53/63

    Flow Indication Setup

    O ifi L ti

  • 7/25/2019 Calgary Symposium Plan 54

    54/63

    Orifice Location

    Pi i @ P 2005

  • 7/25/2019 Calgary Symposium Plan 54

    55/63

    Piping @ P-2005

    C t l St ti @ P 2008

  • 7/25/2019 Calgary Symposium Plan 54

    56/63

    Control Station @ P-2008

    Fl I di ti @ P 2008

  • 7/25/2019 Calgary Symposium Plan 54

    57/63

    Flow Indication @ P-2008

    Outlet Piping @ P 2008

  • 7/25/2019 Calgary Symposium Plan 54

    58/63

    Outlet Piping @ P-2008

    Outlet Piping from V 2021

  • 7/25/2019 Calgary Symposium Plan 54

    59/63

    Outlet Piping from V-2021

    Temperature Bypass on Skid

  • 7/25/2019 Calgary Symposium Plan 54

    60/63

    Temperature Bypass on Skid

    IMO Pump Orientation

  • 7/25/2019 Calgary Symposium Plan 54

    61/63

    IMO Pump Orientation

    System Pressure Control Station

  • 7/25/2019 Calgary Symposium Plan 54

    62/63

    System Pressure Control Station

  • 7/25/2019 Calgary Symposium Plan 54

    63/63

    .

    End of Presentation