Upload
dhanuaqua
View
217
Download
0
Embed Size (px)
Citation preview
7/25/2019 Calgary Symposium Plan 54
1/63
.
User Experience with Plan 54
Seal Flush System2007
7/25/2019 Calgary Symposium Plan 54
2/63
.
Presenters:
Michel Boutin: Machinery Engineer
Shell Scotford Refinery
Brad Hatton: Machinery Engineer
Shell Scotford Refinery
7/25/2019 Calgary Symposium Plan 54
3/63
Definition Plan 54
Pressurized external barrier fluid system
supplying clean fluid to the sealchamber. Circulation is by an externalpump or pressure source. Reservoirpressure is greater than processpressure being sealed.
API 682
7/25/2019 Calgary Symposium Plan 54
4/63
Plan 54
Clean
External
Source ofPressurized
Barrier Fluid
A PI Plan 54
7/25/2019 Calgary Symposium Plan 54
5/63
Overview - Scotford
Barrier fluid system is common to many
pumps in the unit. (12 Pumps with 15seals)
Finished product (ULSD) is the barrierfluid.
Control the barrier fluid pressure at 140
kPag (20psig) above the stuffing boxpressure.
7/25/2019 Calgary Symposium Plan 54
6/63
Overview (cont)
System pressure is maintained by amain pressure control valve on the skid.
Pressure control to each pump is by alocal control valve.
Flow control is maintained by arestriction orifice.
Cooling of barrier fluid is by an AirCooled Heat Exchanger
7/25/2019 Calgary Symposium Plan 54
7/63
Skid Details
The barrier fluid skid consists of:
2 IMO screw pumps
Air Cooled Heat Exchanger
Duplex Filters System reservoir
7/25/2019 Calgary Symposium Plan 54
8/63
Pump Details
Each pump has a local Pressure
Reducing Valve (PRV) to drop theheader pressure
One PRV for each pair of pumps Local Flow Indications to each seal.
Flow orifice located down stream ofeach seal
7/25/2019 Calgary Symposium Plan 54
9/63
Process P &ID
7/25/2019 Calgary Symposium Plan 54
10/63
Typical Pump P&ID
7/25/2019 Calgary Symposium Plan 54
11/63
Operating History
System was chemically cleaned and
flushed during commissioning Used milk pads at each seal to check
for cleanliness
Found three failed seals upon start up
Flow indicators showed high flows and
one was leaking to grade
7/25/2019 Calgary Symposium Plan 54
12/63
20V26CP2:LI20471.PNT
V2026 Barrier Fluid Reservoir
03/05/2006 12:00:00 AM 10/16/2006 12:00:00 AM224.96 days
10
20
30
40
50
60
70
80
0
100
62.4870
Reservoir Level History from Start-up
7/25/2019 Calgary Symposium Plan 54
13/63
Set points
Alarms were set on the flows to eachseal
High Flow was set@ 90% of instrumentrange (2X Normal flow)
Low Flow was set @ value from SealSupplier
Low Pressure Alarm set at 70 kPag (10psig) above stuffing box pressure.
7/25/2019 Calgary Symposium Plan 54
14/63
Set Points (cont)
Differential Pressure across the filters
High Temp Alarm (50C)
High Pressure Alarm on Reservoir.
High and Low Level Alarm on Reservoir
7/25/2019 Calgary Symposium Plan 54
15/63
Troubleshooting
Detecting small leaks on the inner sealis next to impossible. Trending on the
flows helps but small leaks are notdetectable.
Leaks on the secondary seal will showbarrier fluid on the pump
Trouble shooting guide for Operations
was generated
7/25/2019 Calgary Symposium Plan 54
16/63
Troubleshooting (cont)
Would need to systematically isolate the
spare pumps and trend the reservoir levelover a few days.
Since all seals leak in order to provide
lubrication we may not have a leak at all
Finished product (ULSD) is the barrier fluid
we are not contaminating the system
7/25/2019 Calgary Symposium Plan 54
17/63
Learnings From Start-up
Flushing of the system took longer than
expected even though it was chemicallycleaned and under an N2 blanket during
construction.
Remaining water in the skid from the
OEM was frozen and only after the
system was started up did the ice thawreleasing small debris into the piping.
7/25/2019 Calgary Symposium Plan 54
18/63
Learnings (cont)
We did not flush through each seal and had
to install a temporary jump-over to avoid
flushing debris thru the seal. The reservoir does not have a weir or baffle
plate. Suction to pumps is located on the
bottom. Future projects should have it on the
side or use a stand pipe inside.
No Source of heat for the fluid. Relying on theheat generated by the seals.
7/25/2019 Calgary Symposium Plan 54
19/63
Learnings (cont)
The piping run to each pump has a lot
of low points and high points. Shouldbe stream lined to push any vapour in
the piping up and though the seals.
7/25/2019 Calgary Symposium Plan 54
20/63
First Major Failure
Operators have been making entries into the
logs that this system has been operating
poorly from Nov 21 Dec 5, 2006 during acold snap
December 5th, 2006 after an extended cold
snap, local ambient temperatures rose above
0oC
First indication of trouble was the loss ofsystem pressure the morning of Dec 5th.
7/25/2019 Calgary Symposium Plan 54
21/63
First Major Failure (Cont)
IMO pump started to cavitate
Operators started the spare, believingthat the first pump failed.
Filter differentials on the skid were
erratic. Barrier Fluid usage as indicated by the
level in the surge vessel had not beenthe same as it had been in the past.
7/25/2019 Calgary Symposium Plan 54
22/63
First Major Failure (Cont)
Fluid sample from the surge vessel was
the first indication that there was a largeamount of water in the system.
System contents was drained, and filled
at the same time to purge the system of
water.
Second pump quickly showed signs offailed internals.
7/25/2019 Calgary Symposium Plan 54
23/63
Reservoir Level Leading up to Failure
20V26CP2:LI20471.PNT
V2026 Barrier Fluid Reservoir
10/01/2006 12:00:00 AM 12/10/2006 12:00:00 AM70.04 days
10
20
30
40
50
60
70
80
0
100
61.8730
7/25/2019 Calgary Symposium Plan 54
24/63
E2014 BARRIER COOLR TO HDR
E2014 BARRIER COOLR TO HDR
E2014 BARRIER COOLR TO HDR
S2022A/B BARRIER FILTERS
20E14CP2:PC20411.MEAS
kPag
20E14CP2:PC20411.OUT
%
20E14CP2:PC20411.SPT
kPag
20E14CP2:PDI20472.PNT
kPa
Supply to Pumps
12/05/2006 12:00:00 AM 12/06/2006 12:00:00 AM24.00 hours
500
1000
1500
2000
2500
0
3000
0
100
0
3000
0
100
-0.1155
31.6277
0.0000
31.6277
System Pressure Failure Trend
7/25/2019 Calgary Symposium Plan 54
25/63
System Pressure Failure Trend
E2014 BARRIER COOLR TO HDR
E2014 BARRIER COOLR TO HDR
E2014 BARRIER COOLR TO HDR
S2022A/B BARRIER FILTERS
20E14CP2:PC20411.MEAS
kPag
20E14CP2:PC20411.OUT
%
20E14CP2:PC20411.SPT
kPag
20E14CP2:PDI20472.PNT
kPa
Supply to Pumps
12/05/2006 8:00:00 AM 12/05/2006 10:00:00 AM2.00 hours
500
1000
1500
2000
2500
0
3000
0
100
0
3000
0
100
6.1878
1408.6914
0.0000
1408.6914
7/25/2019 Calgary Symposium Plan 54
26/63
First Major Failure (Cont)
Process Unit was shutdown, to preserve
critical equipment. Two teams were set up. One to repair
and flush the system, the other to
investigate the failure.
Being a new unit, the system had
functional instrumentation
7/25/2019 Calgary Symposium Plan 54
27/63
Major Findings from First Failure
One seal that was not designed for the full
Plan 54 system pressure
Failed one seal before the major incident.Pump is in water service. Analysis showed it
had a reverse pressure event.
Failed another seal in water service. It had
been suspected a procedural error in
checking for leakage during the first event.
7/25/2019 Calgary Symposium Plan 54
28/63
Major Findings
No way to tell when there is water in thesystem.
No easy way to drain water from thesystem.
Circulation pump selection is acceptablefor a clean system, but did not take inaccount for off design conditions.
EHT was not considered in the project
7/25/2019 Calgary Symposium Plan 54
29/63
Pump Seal Failure in Water Service
7/25/2019 Calgary Symposium Plan 54
30/63
Pump Seal Failure in Water Service
7/25/2019 Calgary Symposium Plan 54
31/63
Proposed Post Failure Changes
Installation of a water boot
Installation of a conductivity detector forwater
Proposed new pump to handle high
levels of water
Working to remove one water pump
from the system (H2S Levels)
7/25/2019 Calgary Symposium Plan 54
32/63
Implemented Post Failure Changes
Developed Procedure to test individual
pump seals for integrity before start-up.
Complete spare pump now on the shelf.
PM plan to replace pump and inspect.
EHT being installed at low points.
7/25/2019 Calgary Symposium Plan 54
33/63
Minor Failure in May 2007
Circulation Pump pressure started to fall, and
operators detected water in the system again. Immediately started to conduct an online
flush of the system to save the second IMO
pump.
P-2005 (Sour Water from Driers) was
suspected leaking water into the Barrier FluidSystem, as the water was clean.
7/25/2019 Calgary Symposium Plan 54
34/63
Minor Failure in May 2007
Removed seal from pump did not indicate afailure of the seal.
Had the revelation that the barrier systempressure was too low for the P-2005s
Pumps were rebuilt shortly after start-up, and
after the initial barrier pressure survey. Stuffing box pressure was higher than the set
pressure for the barrier fluid.
Adjusted barrier pressure from 1250 kPa to1800 kPa.
7/25/2019 Calgary Symposium Plan 54
35/63
P2005A/B BARRIER FLUID
P2005A/B BARRIER FLUIDP2005A/B BARRIER FLUID
P2005A BARRIER FLUID
P2005B BARRIER FLUID
20P05CP2:PC20551.MEAS
20P05CP2:PC20551.OUT
20P05CP2:PC20551.SPT
20P05CP2:FI20549.PNT
20P05CP2:FI20554.PNT
P2005A/B Sour water
05/14/2007 3:12:32.363 PM 05/21/2007 4:12:32.363 PM7.04 days
500
1000
1500
0
2000
0
100
0
2000
0.3
0.6
0.3
0.6
0.4921
0.5514
1800.0000
31.4801
1801.4902
7/25/2019 Calgary Symposium Plan 54
36/63
Minor Failure in May 2007
After the set pressure change, no major
water excursions have occurred.
7/25/2019 Calgary Symposium Plan 54
37/63
P-2008 Vacuum Pump Seals
ANSI style seal, limited stuffing box
size.
Moved to a TiC/SiC seal face
combination due to initial seal failuresduring start-up.
7/25/2019 Calgary Symposium Plan 54
38/63
August 29 30, 2007 Operation
Numerous Stop Starts on both pumps.
Started another rapid loss of level in the
surge drum, greater that what we haveseen in the past.
Barrier fluid flow was not that muchhigher than what it was in the past.
Decided to swing to P-2008A and
isolate P-2008B
7/25/2019 Calgary Symposium Plan 54
39/63
September 5, 2007 Operation
Isolated P-2008B and the level in the
surge drum stabilized.
Maintained operation of P-2008A
7/25/2019 Calgary Symposium Plan 54
40/63
V2026 BARRIER FLUID DRuM
20V26CP2:LI20471.PNT
%
V2026 Barrier Fluid Reservoir
08/28/2007 11:40:57.985 AM 09/11/2007 12:40:57.985 PM14.04 days
20
30
40
50
60
70
80
0
100
84.4665
7/25/2019 Calgary Symposium Plan 54
41/63
P2008A BARRIER FLUID
P2008A BARRIER FLUID
P2008A BARRIER FLUIDP2008B BARRIER FLUID
P2008A BARRIER FLUID
P2008A LIQ RINGRUN STAT
P2008B LIQ RINGRUN STAT
20P08CP2:PC20561.MEAS
kPag
20P08CP2:PC20561.OUT
%
20P08CP2:PC20561.SPT
kPag
20P08CP2:FI20559.PNT
Am3/h
20P08CP2:FI20564.PNT
Am3/h
20P08CP2:XI20734.CIN
20P08CP2:XI20735.CIN
P2008A/B Vacuum
08/28/2007 11:44:26.677 AM 09/11/2007 12:44:26.677 PM14.04 days
200
400
600
800
1000
0
1200
0
100
0
1200
0.2
0.5
0.2
0.5
0
2
0
2
0
1
-0.0004
-0.0002
232.0000
68.2035
238.2031
7/25/2019 Calgary Symposium Plan 54
42/63
20V26CP2:LI20471.PNT
V2026 Barrier Fluid Reservoir
08/07/2007 12:00:00 AM 11/05/2007 12:00:00 AM90.04 days
10
20
30
40
50
60
70
80
0
100
65.7390
Present Operation of the Reservoir Level
7/25/2019 Calgary Symposium Plan 54
43/63
Present Water Status in the System.
We are still building water in the system
The rate of water build up is very slow.
The water is not sour, which indicates
possibly three sources of water.
7/25/2019 Calgary Symposium Plan 54
44/63
October 11th Sample
7/25/2019 Calgary Symposium Plan 54
45/63
October 29th Sample
7/25/2019 Calgary Symposium Plan 54
46/63
Barrier Fluid Skid
7/25/2019 Calgary Symposium Plan 54
47/63
7/25/2019 Calgary Symposium Plan 54
48/63
Local Pump Control
7/25/2019 Calgary Symposium Plan 54
49/63
Local Pump Control
7/25/2019 Calgary Symposium Plan 54
50/63
Barrier Fluid Skid
EHT/T W f Wi t
7/25/2019 Calgary Symposium Plan 54
51/63
EHT/Temp Wrap for Winter
EHT @ P 2014A
7/25/2019 Calgary Symposium Plan 54
52/63
EHT @ P-2014A
Fl I di ti S t
7/25/2019 Calgary Symposium Plan 54
53/63
Flow Indication Setup
O ifi L ti
7/25/2019 Calgary Symposium Plan 54
54/63
Orifice Location
Pi i @ P 2005
7/25/2019 Calgary Symposium Plan 54
55/63
Piping @ P-2005
C t l St ti @ P 2008
7/25/2019 Calgary Symposium Plan 54
56/63
Control Station @ P-2008
Fl I di ti @ P 2008
7/25/2019 Calgary Symposium Plan 54
57/63
Flow Indication @ P-2008
Outlet Piping @ P 2008
7/25/2019 Calgary Symposium Plan 54
58/63
Outlet Piping @ P-2008
Outlet Piping from V 2021
7/25/2019 Calgary Symposium Plan 54
59/63
Outlet Piping from V-2021
Temperature Bypass on Skid
7/25/2019 Calgary Symposium Plan 54
60/63
Temperature Bypass on Skid
IMO Pump Orientation
7/25/2019 Calgary Symposium Plan 54
61/63
IMO Pump Orientation
System Pressure Control Station
7/25/2019 Calgary Symposium Plan 54
62/63
System Pressure Control Station
7/25/2019 Calgary Symposium Plan 54
63/63
.
End of Presentation