12
Cable Rehabilitation Program By Lee Maurer Maintenance Planning SWEDE Conference April 26, 2011 - Bastrop, Tx (Second Responder Cable Treatment Program)

Cable Rehabilitation Program By Lee Maurer Maintenance Planning SWEDE Conference April 26, 2011 - Bastrop, Tx (Second Responder Cable Treatment Program)

Embed Size (px)

Citation preview

Cable Rehabilitation Program

By Lee MaurerMaintenance Planning

SWEDE ConferenceApril 26, 2011 - Bastrop, Tx

(Second Responder Cable Treatment Program)

2

27,000 Square Miles of Territory

3.2 Million Electric Service Points

3,000 Circuits

Miles of Underground Primary

17,218 Cable Miles – URD

4,641 Cable Miles – Feeder

21,859 Total Miles.

(Networks not included)

Miles of Overhead Primary

10,608 Mainline Primary

13,026 3ø Non-Mainline

5,006 2ø Lines

27,212 Single Phase Lines

55,852 Total Miles

Oncor System Overview

630 miles

390 miles

2LM- Maintenance Planning

3

Cable Components

Tinned Copper Concentric Neutral

Insulation Shield

XLPE or HMWPE

Insulation

Conventional Conductor Shield

Aluminum Conductor

LM- Maintenance Planning

Aluminum

Conductor

(Strand-filled)Jacket Bare Copper

Concentric Neutral

Insulation Shield

TRXLPE Insulation

Super Smooth Conductor Shield

Pre-1990 Since 1990

4

Previous specification cable Current specification cable

Primary Underground Cable (Network Excluded)

5

Primary Cable Faults

LM- Maintenance Planning

6

Cable Rehabilitation Program - Background

System wide maintenance plan (Second Responder) for extending the life of aging infrastructure

Pre-1993 PE cable issues

8,000 cable miles – Pre-1993 PE cable

– 7,000 cable miles – URD

– 1,000 cable miles – Feeder

Cable Manufacture 1980 - 1995

– General Cable, Hendrix, Pirelli (Now Prysmian), Southwire

Capital Rehabilitation method for aged cable

– 235 cable miles rehabilitated (By Utilx)

Cost effective alternative to replacement of cable

Additional 600 cable miles rehabilitated in other programs

LM- Maintenance Planning

7

Second Responder Process

When a cable faults, the troubleman (first responder) determines if the cable is loop fed and if the faulted cable can be switched out.

Padmount Transformer Pole Riser

Normal Open PointFault

Isolated Faulted Cable

LM- Maintenance Planning

8

Second Responder Process (cont’d)

If the cable can be switched and service restored to the customers, the location of the faulted cable is sent to Oncor Program Services.

Program Services will then schedule a Utilx cable repair/rehabilitation crew to the cable.

The crew will attempt to repair and inject the cable with rehabilitation fluid.

LM- Maintenance Planning

9

2nd Responder Process

4,291 sections of failed cables came through the process since 2008

– 65% were able to be injected successfully.

235 cable miles have been rehabilitated using 2nd responder process since 2008.

LM- Maintenance Planning

10

Business Comparison

Cable Repair - Splicing $ X

– O&M Cost

– Same old cable

Rehabilitation of Span $ 4X

– Capitalized Cost

– Added 20+ years of life

New Cable (Bore) $ 15X

– Capitalized Cost

– New 40+ year asset

LM- Maintenance Planning

11

Business Considerations that Prevent Rehabilitation

Cable installed in conduit (except preventative)

Corroded concentric neutral of 25% or less remaining

The faulted cable section must not have been de-energized more than six months.

There cannot be more that one joint per 100 feet of cable. (Business Case)

Other Technical Reasons

– Butyl rubber cable

– Cable with tape conductor shield

– Loss of insulation shield conductivity

– Insulation shield with no adhesion

LM- Maintenance Planning

12

Questions

Oncor Contacts

Lee MaurerSenior Manager

Maintenance Planning 817-215-6128

[email protected]

Mark Darilek Project Manager

Maintenance Planning 817-215-6809

[email protected]

Richie Harp Consulting Engineer

Distribution Standards817-215-6008

[email protected]

Fort Worth, TX

Mike Sulak Program Manager

Operations/Program Services817-215-6151

[email protected]