Upload
jthiru74
View
3
Download
0
Embed Size (px)
DESCRIPTION
C7 Program
Citation preview
CLIENT: SAKURA FERROALLOYS
PROJECT: SAKURA – HCFeMn AND SiMn SMELTER COMPLEX
DOCUMENT: ENQUIRY – SECTION C7: PROGRAM
ENQUIRY NO.: MM001-5001 PIPING SUPPLY AND INSTALL
Printed on: 18 June 2014 Page 1 of 2 S:\Engineering\MC363 Sakura\CONTRACTS\MM\MM001-5001 Piping\Enquiry\SECTION C\C7 PROGRAM\C7 Program.docx
SECTION C7: PROGRAM
1. SCHEDULE
The following are the latest scheduled dates on the Project. The Supplier must accept the
scheduled completion dates or state in this Contract, other dates for the performance of the
work. Earlier dates are preferred.
No dates filled into the “Supplier’s guaranteed schedule” columns will imply automatic
acceptance of the “Proposed by Purchaser” dates.
Day duration as indicated below, shall be expressed as calendar days and not working days.
See Attached Programme. Supplier to provide his acceptance of the program dates.
Activity Proposed Schedule
Supplier’s Guaranteed Schedule
Start Completion Duration Start Completion
Enquiry
Adjudication
Order placement, Contract finalisation
Effective date of Contract
Submission of Bond within 10 days from Contract start (if applicable)
Submission of program and required information documents within 14 days from effective date of Contract/Purchase order
Submission of engineering documents incl. joint review (drawings, analyses, lists)
Proof of Malaysian DOSH approval submitted to Purchaser
Site Establishment
All equipment manufacturing (Engineer to specify)
CLIENT: SAKURA FERROALLOYS
PROJECT: SAKURA – HCFeMn AND SiMn SMELTER COMPLEX
DOCUMENT: ENQUIRY – SECTION C7: PROGRAM
ENQUIRY NO.: MM001-5001 PIPING SUPPLY AND INSTALL
Printed on: 18 June 2014 Page 2 of 2 S:\Engineering\MC363 Sakura\CONTRACTS\MM\MM001-5001 Piping\Enquiry\SECTION C\C7 PROGRAM\C7 Program.docx
Activity Proposed Schedule
Supplier’s Guaranteed Schedule
Start Completion Duration Start Completion
Testing of electrical / mechanical equipment at Suppliers Works
Disassembly & packaging
Ex works collection
Delivery to Port FOB (if applicable)
Full delivery to site of piping and fittings as per BOQ