CLIENT: SAKURA FERROALLOYS PROJECT: SAKURA HCFeMn AND SiMn SMELTER COMPLEX DOCUMENT: ENQUIRY SECTION C7: PROGRAM ENQUIRY NO.: MM001-5001 PIPING SUPPLY AND INSTALL Printed on: 18 June 2014 Page 1 of 2 S:\Engineering\MC363 Sakura\CONTRACTS\MM\MM001-5001 Piping\Enquiry\SECTION C\C7 PROGRAM\C7 Program.docx SECTION C7: PROGRAM 1. SCHEDULE The following are the latest scheduled dates on the Project. The Supplier must accept the scheduled completion dates or state in this Contract, other dates for the performance of the work. Earlier dates are preferred. No dates filled into the “Supplier’s guaranteed schedule” columns will imply automatic acceptance of the “Proposed by Purchaser” dates. Day duration as indicated below, shall be expressed as calendar days and not working days. See Attached Programme. Supplier to provide his acceptance of the program dates. Activity Proposed Schedule Supplier’s Guaranteed Schedule Start Completion Duration Start Completion Enquiry Adjudication Order placement, Contract finalisation Effective date of Contract Submission of Bond within 10 days from Contract start (if applicable) Submission of program and required information documents within 14 days from effective date of Contract/Purchase order Submission of engineering documents incl. joint review (drawings, analyses, lists) Proof of Malaysian DOSH approval submitted to Purchaser Site Establishment All equipment manufacturing (Engineer to specify)

C7 Program

Embed Size (px)

DESCRIPTION

C7 Program

Citation preview

Page 1: C7 Program

CLIENT: SAKURA FERROALLOYS

PROJECT: SAKURA – HCFeMn AND SiMn SMELTER COMPLEX

DOCUMENT: ENQUIRY – SECTION C7: PROGRAM

ENQUIRY NO.: MM001-5001 PIPING SUPPLY AND INSTALL

Printed on: 18 June 2014 Page 1 of 2 S:\Engineering\MC363 Sakura\CONTRACTS\MM\MM001-5001 Piping\Enquiry\SECTION C\C7 PROGRAM\C7 Program.docx

SECTION C7: PROGRAM

1. SCHEDULE

The following are the latest scheduled dates on the Project. The Supplier must accept the

scheduled completion dates or state in this Contract, other dates for the performance of the

work. Earlier dates are preferred.

No dates filled into the “Supplier’s guaranteed schedule” columns will imply automatic

acceptance of the “Proposed by Purchaser” dates.

Day duration as indicated below, shall be expressed as calendar days and not working days.

See Attached Programme. Supplier to provide his acceptance of the program dates.

Activity Proposed Schedule

Supplier’s Guaranteed Schedule

Start Completion Duration Start Completion

Enquiry

Adjudication

Order placement, Contract finalisation

Effective date of Contract

Submission of Bond within 10 days from Contract start (if applicable)

Submission of program and required information documents within 14 days from effective date of Contract/Purchase order

Submission of engineering documents incl. joint review (drawings, analyses, lists)

Proof of Malaysian DOSH approval submitted to Purchaser

Site Establishment

All equipment manufacturing (Engineer to specify)

Page 2: C7 Program

CLIENT: SAKURA FERROALLOYS

PROJECT: SAKURA – HCFeMn AND SiMn SMELTER COMPLEX

DOCUMENT: ENQUIRY – SECTION C7: PROGRAM

ENQUIRY NO.: MM001-5001 PIPING SUPPLY AND INSTALL

Printed on: 18 June 2014 Page 2 of 2 S:\Engineering\MC363 Sakura\CONTRACTS\MM\MM001-5001 Piping\Enquiry\SECTION C\C7 PROGRAM\C7 Program.docx

Activity Proposed Schedule

Supplier’s Guaranteed Schedule

Start Completion Duration Start Completion

Testing of electrical / mechanical equipment at Suppliers Works

Disassembly & packaging

Ex works collection

Delivery to Port FOB (if applicable)

Full delivery to site of piping and fittings as per BOQ