c4-205

Embed Size (px)

Citation preview

  • 8/12/2019 c4-205

    1/8

    [email protected]

    A SYSTEMATIC APPROACH TO ELECTROMAGNETIC COMPATIBILITY

    ANALYSIS AND DESIGN IN UTILITY SYSTEMS

    A. XMARD1 P. Y. VALENTINB. BRESSAC

    J. MAHSEREJIAN*A. COUTU**

    G. JOS

    Electricit de FranceR&D

    France

    RTEGestionnaire du Rseau

    de TransportdElectricit

    France

    *Hydro-Qubec IREQ**Hydro-Qubec

    TransnergieCanada

    CEA TechnologiesInc.

    Canada

    1 Introduction

    In France, the constant evolution of the transmission network and of the telecommunication andpipeline systems results in a significant number of 50 Hz coupling studies being performed every year;more than 70 studies are performed every year by RTE. Such studies are performed when a line isinstalled or modified (for example in case of increase of the short-circuit current), or when apotentially disturbed system is installed or modified (pipeline, telecommunication cable) or in somemore specific cases (live work, accident analysis). RTE has signed an agreement with France Telecom

    (phone utility) and SNCF (railway utility) to specify the way coupling studies are to be performed andto define rules for the financing of constructions required to limit disturbances. The internalspecifications of RTE propose some simple conservative methods to calculate disturbance on nearbysystems but its role is in most of the cases limited to detect if a detailed study is required. Theexperience of the last years has shown that the modeling of the disturbed system is very often a sourceof difficulty for design engineers. HQ has similar needs regarding the computation of fundamentalfrequency induced voltages, but in addition requires a tool to assess interference in telecom lines inorder to specify dc filters performance in HVDC transmission projects. This feature involves thecomputation of the coupling impedance at several harmonic frequencies of the audio range.The above considerations have convinced CEATI, EDF, HQ, ELIA and others that it was essential thatan advanced modeling tool be available for this purpose. It must provide a structured framework forinduced voltage calculation and include an accurate representation of telecommunication and gas

    pipeline equipment. It can be advantageously based on EMTP (Electromagnetic Transients Program)type software [1]. This paper presents the importance of a structured approach to the problem, gives areview on theoretical considerations and illustrates important issues through practical examples.

    2 General presentation of the proposed new software

    The proposed automatic computation technique will use the new EMTP [2] transient simulationenvironment as a computational engine and will use an accurate electrical representation oftelecommunication and gas pipeline equipments. This choice of a background software layer isparticularly appropriate because it offers accurate models of overhead lines and underground cablesbased on the line theory and can work in the frequency domain (frequency scan and steady-statesolutions).

    The purpose of the complete software will be to generate automatically from the electro-geometricalconfiguration under study, an EMTP representation, using the rules specified in [3] [4]. The software

    21, rue d'Artois, F-75008 Parishttp://www.cigre.org CIGR

    Session 2004C4-205

  • 8/12/2019 c4-205

    2/8

    2

    will include a database for the representation of the different types of equipments (towers, conductors,underground power cables, telecommunication cables, pipelines, fences).The user will have the possibility to input the geometries of the power lines and of the disturbedsystems using a digital table, the screen of a PC, or GPS coordinates.The next paragraph gives a general review of the theoretical principles applied in the software.

    3 Computation of interference

    3.1 Inductive and capacitive couplingA current circulating along an electrical system generates in its vicinity a magnetic field which is at theorigin of the inductive interference between the electrical system and a disturbed system situated in thesame area. In the case of a three-phase system the magnetic field takes into account the magnetic fieldgenerated by each conductor, including ground wires in the case of overhead lines and sheaths in thecase of underground cables.Capacitive coupling originates from the electrostatic field due to the charge along the electricalsystems. In practical terms capacitive coupling is of interest only for overhead lines.The method used to evaluate inductive and capacitive coupling between power lines and disturbed

    systems is based on two steps.- The first step consists in splitting the disturbing and disturbed systems into sections in such a waythat the coupling may be represented based on the line theory. If a section i of the disturbing linesegpower[i] is considered as coupled with a section of the disturbed line segdisturbed[j], then the system(segpower[i], segdisturbed[j]) is treated as a multi-conductor propagation line, supposing that the sectionsare parallel. The accuracy of this approach is related to the way the sections are determined and thecorrespondence between sections is established. IUT [4] has proposed a method which will bepresented below.- The second step consists in evaluating the induced voltages on the disturbed system.

    3.1.1 Splitting into coupling sectionsThe coupling sections are determined in the zone of influence, corresponding to the zone in which thecoupling is significant. In most of the cases this area extends [4] to less than 3 km from the line forinductive coupling and to a few tenths of meters for capacitive coupling. The determination of thesections and the correspondence between the sections of the disturbing and disturbed systems leads toconsider 3 different cases (Figure 1): parallel, oblique and crossing. An oblique case may be

    approximated by a parallel case if some geographical condition is fulfilled: 12

    d13

    3 d

    1d2d

    1d

    2d

    Parallel Oblique Crossing

    Disturbed line

    Disturbing line

    1d2d

    1d

    2d

    Parallel Oblique Crossing

    Disturbed line

    Disturbing line

    Figure 1: Represented coupling cases between the disturbing and disturbed lines

    In the case of crossing, an equivalent parallel segment is used as a section of the disturbed line such asd1 < 10m, d2 < 10m [3][4].

  • 8/12/2019 c4-205

    3/8

    3

    3.1.2 Evaluation of the induced voltagesThis step corresponds to the application of line theory. The coupled segments segpower[i] of the powerline and segdisturbed[j] of the disturbed line are treated like a multi-conductor EMTP line. The multi-conductor overhead line includes directly the electrical representation of phase conductors and groundwires. In the case of an underground cable it includes the representation of phase conductors and

    sheaths. If the disturbed line is sheathed the sheath is included directly in the representation.This approach leads to the computation of impedance +Z = R sL and admittance +Y = G sC matricesused in the solution of wave equations:

    (x,s) (x,s)

    x

    =

    VZ I and

    (x,s) (x,s)

    x

    =

    IY V

    The primed variables are given per unit length, x is a position in the line and s stands for Laplacetransformation. The above equations are used for each segment of the disturbing and disturbed system,coupled or not, taking into account the boundary conditions.

    This calculation is readily available in EMTP frequency domain computations for solving togetherboth the disturbing and the disturbed system. The EMTP PI-Exact model (which is exact at everyselected frequency) can be used in order to avoid the approximations related to the application of themodal theory. The frequency domain approach is however unusable for taking into account nonlinearcomponents, such as surge-arresters or air-gaps which may be used to limit the level of inducedvoltage. If a study requires the modeling of such components then the time-domain solver must beused in conjunction with distributed parameter line and cable models that can correctly account for thefrequency dependency of parameters [5].

    3.1.3 Presence of screening conductorA metallic conductor present in the zone of influence and connected to ground can reduce significantlythe inductive influence of the disturbing system on the disturbed one. This conductor is coupled at thesame time to the disturbing and to the disturbed systems. It is possible to represent its effect by acoefficient which reduces the mutual inductance between the coupled segments of the disturbedsystem and the disturbing system.

    It is also possible to represent it as a separate electric system coupled both to the disturbing anddisturbed one. If the screening conductor is parallel to the disturbing one (the case of a ground wire) itcan be treated as a supplementary conductor of this one. A similar approach can be applied if it isparallel to the disturbed system. In other cases (non-parallel conditions, as in Figure 2) the followingapproach may be applied:

    At first the current circulating along the screening conductor is evaluated by applying themethods described in 3.1.1 and 3.1.2, then the effect of the screening conductor on thedisturbed system is represented by equivalent voltage sources, which are evaluated by:

    o splitting the disturbed system, considering that it is disturbed by the screeningconductor;

    o applying for each section i of the disturbed system influenced by section j of the

    screening conductor the formula i ij je M I= , where ijM is the mutual conductance

    between segments i and j and jI is the current circulating along the segment j .

    The last step consists in considering the direct effect of the disturbing system on the disturbedone by applying the methods of 3.1.1 and 3.1.2.

  • 8/12/2019 c4-205

    4/8

    4

    Screening conductor

    Disturbing system

    Disturbed system

    Screening conductor

    Disturbing system

    Disturbed system

    Figure 2: Splitting approach in the presence of a screening conductor

    3.1.4 Key technical issues allowing accurate calculationsAn extensive representation of the power systemFor a fault condition the induction on neighboring systems depends directly on the value of the faultcurrent. A precise determination of the fault current requires also an adequate representation of thepower system and especially of the interaction between the substations located at both ends of thepower line. In many practical cases the representation of the electrical network cannot be limited to a

    representation of the substations at both ends of the line by some independent Thevenin equivalents,evaluated using the short-circuit power at substation. It may be necessary to represent moreextensively the system. Another possibility could be to represent both ends by a generalized Theveninequivalent, which is an impedance matrix with of-diagonal terms accounting for the interactionbetween the substations through the rest of the network when the power line under consideration hasbeen removed.

    A precise representation of the return path of the fault currentIn the case of a fault the induction on nearby pipelines or telecommunication cables is stronglyinfluenced by the return path of the fault current. For instance if one considers a single-phase fault inthe cable of the configuration presented in Figure 3, the fault current circulating on the sheath willdecrease the induction effect of the current circulating on the phase conductor. If 2R is high and 1R is

    small, most of the fault current will return by the sheath and the induction will be limited. But if 1R is

    high and 2R is small, most of the fault current will return through the resistance 2R . This simple

    example illustrates the necessity to represent precisely not only the fault current but also the way thefault current returns, by making in particular an adequate representation of the connections andgroundings of the sheaths. The use of an EMTP type software rends possible such a modeling andallows to avoid too conservative simplifications as it will be illustrated in the example below.

    Underground Cableline

    +

    +

    +

    R1

    +

    R2

    Figure 3: Overhead line terminated by an underground cable with grounded sheath at both

    ends

    3.1.5 Application examplesExample 1: 50 Hz voltage induced on a telecommunication cable by an underground cable during afaultThe 225 kV system of this example is shown in Figure 4. It is made of a 700 m underground cableconnected to an 8 km single circuit overhead line equipped with 2 ground wires. The undergroundcable is a three-phase single-core system, bonded at substation A and equipped with a parallel earth

    continuity conductor which is connected at the earth electrode of the substation at one terminal andconnected to the earth electrode of the first tower at the other terminal. A telecommunication cable

  • 8/12/2019 c4-205

    5/8

    5

    whose sheath is earthed at one end, is parallel to the underground cable at a distance of 50 m. Thisstrictly parallel configuration has been chosen to allow an EMTP calculation without determination ofcoupling segments. The same method will be applied in the next examples.For a single-phase-to-ground fault on the overhead part of the line, the level of induction on thetelecommunication cable will depend not only on the fault current but also on the part of the faultcurrent circulating back to substation A by the earth conductor. This statement can be illustrated byconsidering 2 different configurations. In the first configuration phase-a is short-circuited at the firsttower following the underground cable. Calculation results are summarized in Table 1. All values arecrest values. It can be seen that the magnitude of the current circulating along the earth conductor issimilar to the current circulating on phase-a of the underground cable. The voltage at the end of thecable is limited to 109 V.

    Telecom line

    Tower 2Tower 1

    . . .

    . . .

    . . .Substation A

    Substation B

    earth conductor

    ground wires

    Transmission line, 8kmUnderground cable, 700m

    1

    2

    3

    +1

    2

    3

    RL

    Thevenin

    +

    +

    +

    +

    + +

    +

    VM

    +

    +

    +

    +

    +

    +

    +

    1

    2

    3

    +1

    2

    3

    RL

    Thevenin

    + +

    a

    b

    c

    Figure 4: Representation of a 225 kV system: underground cable followed by a single circuit line

    with 2 ground wires

    Table1: single-phase fault occurring at the first tower following the cable Total fault current 43 kAContribution of substation A to the fault current 27 kACurrent circulating in the earth conductor 27 kACurrent circulating in the faulty tower 825 ATotal current circulating along the ground wire between towers 1 and 2 15 kAVoltage at the end of the telecommunication cable 109 V

    In the second configuration a single-phase-to-ground fault occurred at the 7th tower following theunderground cable. Table 2 summarizes the computations. It appears that part of the contribution fromsubstation A to the fault current circulates through the earth electrodes of the towers and does notreturn by the earth conductor. Therefore even with a smaller short-circuit current circulating in phase-afrom substation A, the voltage at the end of the disturbed system is significantly higher.

    Table2: single-phase fault occurring at the 7th tower following the cable Total fault current 39 kA

    Contribution of substation A to the fault current 21.5 kACurrent circulating in the earth conductor 18 kACurrent circulating in the faulty tower 1.1 kATotal current circulating along the ground wire between tower 1 and 2 15 kAVoltage at the end of the telecommunication cable 290 V

    This simple study illustrates the importance of a proper representation of the fault current path in orderto obtain a more realistic evaluation of the induction on the disturbed system.

    Example 2: Influence of the homopolar current component on inductive couplingWhen calculating inductive coupling in normal operating condition it is of major importance toaccount precisely for the effect of the homopolar component of the current as it is illustrated in thefollowing example. A 255 kV single circuit line (flat configuration) without ground wires is shown in

  • 8/12/2019 c4-205

    6/8

    6

    Figure 5. At mid-span, the distance of phase conductors to ground is equal to 20 m. The span length is400 m.

    25 m

    5.5 m5.5 m

    Figure 5: Configuration of phase conductors at tower of a 225 kV line

    The line is a 30 km long antenna. The induction on a 400 m long cable, parallel to the line andgrounded at one end is studied. The height of the cable is 1 m, its distance to the line is 40 m. Thepositive sequence current is equal to 520 A. The crest value of the 50 Hz induced voltage at the end ofthe cable is calculated when the line is transposed (the positions of phase conductors are changed each10 km) and when it is not transposed, in order to evaluate the effect of the absence of transposition ofthe line on the level of induced voltage.It is found that the absence of transposition of the phase conductors leads to an increase of 10% in theinduced voltage (9.4 V/km instead of 8.5 V/km). This example shows the importance of representingexactly the current circulating in the phase conductors and not to limit the representation to thepositive sequence.

    Example 3: Influence of the coating of pipelinesPipelines are tubes of steel, aluminum or cast-iron with a diameter ranging from 50 to 1100 mm. Theyare usually coated with polypropylene, polyethylene, hydrocarbon, epoxy or plicoflex.

    It is important to take into account the nature of the coating when calculating induced voltage becauseits influence on the loss factor may affect significantly the level of fundamental frequency inducedvoltage as it is illustrated in the example below.The studied configuration is similar to the one presented in Figure 5, but with a 400 m long steelpipeline buried at a depth of 1 m, replacing the telecommunication line.The influence of the nature of the coating will be illustrated by calculating the 50 Hz voltage at the endof the pipeline in the case of a single-phase-to-ground fault for a bituminous coating and then for apolyethylene coating. The loss factor of the coating is first determined and then the frequency domainsimulation option [2] of EMTP is used.The capacitance of the pipeline to the surrounding ground and the shunt conductance can be calculatedby:

    0 r

    c

    DC

    d

    = and

    c c

    DG

    d

    =

    with D being the diameter (1 m) of the pipeline, cd is the width of coating (1 mm), r is the relative

    permittivity (5) and c is the resistivity of the coating. The loss factor is given by:

    Gtan( )

    C =

    The results presented in Table 3, indicate a significant reduction of the induced voltage at the end ofthe pipeline, originating from the higher losses in a bituminous coating compared to polyethylenecoating.

    Table 3: 50 Hz induced voltage at the end of a pipeline for two types of coating

    Coating c tan( ) 50 Hz voltage

    bituminous 0.2*106 0.36*103 160 Vpolyethylene 1.*108 0.71 290 V

  • 8/12/2019 c4-205

    7/8

    7

    3.2 Resistive coupling3.2.1 PrinciplesThe ground is not usually used as an active conductor in transmission systems except in some specialconfigurations of DC lines. However some faults (due to pollution, lightning) may cause short-

    circuit currents to flow through the grounding electrode of a tower during a period of time. Thisgrounding electrode is constituted of buried metallic elements and presents some resistance related tothe shape, number and position of these elements. The flow of current in the earth electrode leads to anincrease of voltage in the soil, whose value depends on the nature of the soil and which may posesafety problems (touch and step voltages).Neighboring metallic structures buried in the area of the earth electrode are submitted to its voltageand may become damaged by it (puncture of sheath or insulation). They can also in some cases absorbthe fault current and transmit it to areas far away from the point where it has been injected into theground.

    3.2.2 Splitting of the disturbed systemThe goal of the splitting is to breakdown the disturbed system in the region of influence into sections

    along which the earth potential may be considered as of constant value (the difference is less than 5%compared to the accurate value). If one considers the earthing of a tower, at a distance d greater thanthree times the equivalent radius of the electrode [3], the potential rise may be approximated by:

    V I2 d

    =

    where is the soil resistivity and I is the fault current circulating in the electrode.

    The method consists in defining a series of circles iC centered on the current point injection, with

    radius iR calculated by:

    eqi

    RR

    1 0.05i=

    with i 20<

    The sections of the disturbed system are determined by finding its intersection with the series ofcircles. If the disturbed system is situated in the region of influence of several points of injection offault current (tower where the fault is located, neighboring towers if the line is equipped with groundwires, groundings of cable sheaths) the sections are determined by applying the same approach to allof them and by superposing the splitting results.If the disturbed system is very close to an earth electrode, the above equation is no longer valid and amore accurate method needs to be used [4].

    4 Conclusions

    The sharing of right-of-way between transmission networks and pipeline and telecommunicationsystems demands that the electric utilities perform fundamental frequency coupling studies more and

    more frequently. As it has been shown in this paper these studies require: A precise evaluation of the currents circulating in the conducting parts of the disturbing

    system in the zone of influence; An accurate modeling of the influence of the disturbing system on the disturbed ones taking

    into account precisely the geometry of the configuration; A detailed modeling of the potentially disturbed systems.

    A programmed method also allows determining the fault conditions resulting into the most severestresses of induced coupling. In addition, different grounding configurations can be analyzed tominimize stresses.

    This paper has proposed a structured framework for the computation of induced voltages based onEMTP type software layer. The choice of EMTP as a computational environment allows fulfilling theabove stringent requirements.

  • 8/12/2019 c4-205

    8/8

    8

    AcknowledgementsThe authors acknowledge contributions and support to this work from FT (France Tlcom) and GDF(Gaz de France)

    5 Bibliography

    [1] J. Mahseredjian, L. Dub, L. Grin-Lajoie, New advances in the Simulation of Transients withEMTP: Computation and Visualization Techniques, Electrimacs, August 19th, 2002, Plenarysession paper.

    [2] J. Mahseredjian, L. Dub and S. Dennetire: EMTP-RV documentation on simulation options,2003, IREQ-Report

    [3] CIGRE 36.02 CIGRE brochure 95 - Guide on the influence of high voltage AC power systemson metallic pipelines 1995

    [4] IUT Directives concernant la protection des lignes de telecommunication contre les effetsprjudiciables des lignes lectriques et des chemins de fer lectrifis Volume 2 1999

    [5] Morched A., Gustavsen B. and Tartibi M.: A universal model for accurate calculation ofelectromagnetic transients on overhead lines and underground cables. Power Delivery, IEEETransactions, Volume: 14, Issue: 3 , July 1999, pp. 1032 -1038