Upload
lamanh
View
218
Download
0
Embed Size (px)
Citation preview
REG 361 CONSTRUCTION METHODS
METHOD STATEMENT
Dr Naser GhaniPhD, P.Eng, MIEM, MASCE, [email protected]/naserROOM 104 E49
4
Construction Method StatementsConstruction Method Statements
Submission Method Statement
Background 3
Planning/CostingMethod Statement
Work Method Statement
Work /SafetyMethod Statement
Why do we need work method statements?
The purpose of a work method statement is:
• to outline a safe method of work for a specific job• to provide an induction document that workers must read and understand before starting a job• to meet legal requirements, that is, hazard identification and control• to program work, materials, time, staff, and to anticipate possible problems• to use as a tool in quality assurance.
The employer or subcontractor must detail how they will do the work. As an example, where a person is required to work in a trench greater than 1.5 metres deep, the work method statement may say:
To prevent collapse of the trench I/we will apply benching to all sides of the trench and at an angle of no steeper than 45 degrees to the horizontal. When I/we bench a trench, the vertical trench side, below the benched portion, will not exceed 1.5 metres in height. The benching will be checked at least daily to ensure its continued effectiveness.
The completed work method statement must be signed and dated by the employer or subcontractor and the builder before the work being detailed commences.
Why do we need work method statements?
The purpose of a work method statement is:
• to outline a safe method of work for a specific job• to provide an induction document that workers must read and understand before starting a job• to meet legal requirements, that is, hazard identification and control• to program work, materials, time, staff, and to anticipate possible problems• to use as a tool in quality assurance.
Work Method StatementWork Method Statement
Work Method StatementWork Method Statement
1. Introduction
2. Scope of Works/Objectives
3. References/Standards
4. Resource Planning
5. Material and Delivery
6. Coordination
7. Methodology
8. Quality and Safety
Work Method StatementWork Method Statement
Resource Planning
4.1 Material Planning4.2 Manpower Planning4.3 Machinery & Equipment Planning
Work Method StatementWork Method Statement
Material and Delivery
5.1 Material Handling5.2 Material Delivery Inspection: Checking Methodology
Work Method StatementWork Method Statement
Coordination
6.1 Coordination between Architecture works6.2 Coordination between C&S works6.3 Coordination between M&E works6.4 Coordination between other specialist works
Work Method StatementWork Method Statement
Methodology (example…)
7.1 Surface Preparation 7.2 Application of Water Proofing (PU Type)7.3 Post-Application of Water Proofing (PU Type)
Work Method StatementWork Method Statement
Quality and Safety
8.1 Inspection and testing 8.2 Relevant Construction Standard & References8.3 QC and Relevant Checklist
Examples
1) PDA Testing - Work method statement
2) Earthworks – Submission method statement
3) Pedestrian bridge – Submission Method Statement
REFERENCES:
1)Illingworth, J.R. (2005), Construction Method and Planning, SponPress 2005.
2) NSW Dept of Education and Training (1998). Guidelines for writing work method statement in plain english. NSW Government 1998.
3) Gue and Partners (2005). General Earthwork specifications.
4) Arup (2008). Construction method statement -Eveleigh heritage walk construction method statement . Arup-Cox consulting.
5) Fairhurst, W.A. and Partners (2008). Earthworks method statement.