c02a_fema349

Embed Size (px)

Citation preview

  • 7/29/2019 c02a_fema349

    1/9

    FEDERAL EMERGENCY MdANAGEVENT AGENCYFEDERAL EMERGENCY MANAGEMENT AGENCY

    g ll lIACTION PLAN

    FOR

    PERFORMANCE BASEDSEISMIC DESIGN

    1k

    Prepared for theFederal Emergency Management AgencyBy theEarthquake Engineering Research Institute

    _FEM~A-349IAorilFEMA-349!Anril 2000000

  • 7/29/2019 c02a_fema349

    2/9

    FORWARDOne of the primary goals of the Federal Emergency Management Agency (FEMA) is theprevention, or mitigation, of this country's losses from natural hazards. To achieve thisgoal, we as a nation need to ask what level of performance do we expect from ourbuildings during an event such as an earthquake. Inorder to answer this question, FEMAis exploring the possible development of "performance-based seismic design" criteria.Such criteria could be voluntarily used by this nation's engineers and designers to improvethe performance of critical classes of buildings that are currently only designed to a"lifesafety" level to avoid collapse, but would infact probably still suffer significant damagein a design event.FEMA contracted with the Earthquake Engineering Research Institute (EERI) (contractnumber EMW-92-K-3955, Task 13) to solicit the input of the nation's leading seismicprofessionals in developing an action plan that could be used to develop performance-based seismic design criteria. This project and the resulting action plan have gone a longway in identifying key issues that will need to be addressed in this process.This action plan builds upon a similar effort that FEMA funded in 1993 with the EarthquakeEngineering Research Center, now the Pacific Earthquake Engineering Research Center(PEER). The end product of that study was a similar plan, "Performance Based SeismicDesign of Buildings" (FEMA-283), published by FEMA in September 1996. The material inthat plan had an emphasis on the research that would be required, and has in fact beenused by PEER inthe last several years as the basis for their research work inthis arena.While this action plan does an excellent job of describing the requirements that would beneeded to successfully develop performance based seismic design criteria, FEMA doeshas some concerns, such as the proposed budget, which exceeds what FEMA is capableof devoting within the recomended time frame. FEMA is planning to identify some of thekey elements of the plan and to begin to address them through a series of projects underits Problem Focused Studies program. However, without additional specific funding forthis plan, it will be very difficult to accomplish the entire plan. To avoid further delay,FEMA has decided to publish this document as a "final draft for informational purposesonly. Publication of this document in no way obligates this or any other Federal agency toany portion of plan contained herein. The information and opinions contained inthisdocument are solely those of EERI and the project participants and do not necessarilyrepresent the views of FEMA.In closing, FEMA sincerely wishes to express its,gratitude to all who were involved in thisproject. The results of their hard work will play an important role as this country movesforward towards performance-based seismic design and reducing the losses suffered bythis nation's citizens after the next earthquake.Cover Art: Part of a presentation developed by Ronald 0. Hamburger, EE International

  • 7/29/2019 c02a_fema349

    3/9

    I ACTION PLAN

    FORPERFORMANCE BASED SEISMIC DESIGN

    Executive Summary

    PrepareFederalBy theEarthqu

  • 7/29/2019 c02a_fema349

    4/9

    Action Plan for Performance Based Seismic Design

    Table of Contents

    The Need for Changes in Current Seismic Design Practice ...................What is Performance Based Seismic Design? ....................................... v

    Products Necessary to ImplementPerformance Based Seismic Design ................................i

    Schedule and Budget ................... VIConclusion ....................................................................... EE..E...ixReferences ...........................................................................................

  • 7/29/2019 c02a_fema349

    5/9

    Action Plan for Performance B ased Seismic Design

    The Need for Changes inCurrent Seism ic Design-IR ecent decades have seen a dramaticrise in insured and uninsuredearthquake related losses. In the past tenyears estimated losses were twenty timeslarger than in the previous 30 yearscombined. F E MAs expenditures related toearthquake losses have become anincreasing percentage of its disasterassistance budget.' Predictions are thatfuture single earthquakes, which willinevitably occur, may result in losses of

    $50-100 billion each.'Losses are rising due to several factors.These include: a denser population ofbuildings being located in seismicallyactive regions. an aging building stock andthe increasing cost of business FEMA Disaster Assistanceinterruption. Nonstructural and contents 1988-1997damage are also large contributors to loss,especially in regions with high-technologymanufacturing and health-care industries.It is this increase in losses from all hazardsthat has led FEMA to support actions to re-duce future losses. One of these is P rojectImpact, an initiative to encourage loss re-duction activities through partnerships atthe local community level. One of the keycomponents of Project Impact is the com-munity's adoption and enforcement of anadequate building codeHistorically, building codes have required I * 4that buildings be built to a minimum level of I** I,OEarthquakessafety. Specifically, structures designed to mother I Ithe Uniform Building Code are expected to"resist a minor level of earthquake ...without damage,...a moderate level.. with

  • 7/29/2019 c02a_fema349

    6/9

    Action Plan for Performance Based Seismic Designsome nonstructural damage, [and] a majorlevel of earthquake.. without collapse."3Deaths in recent California earthquakeshave been few, showing that the intent ofthe code has been met. However, there isa major misperception on the part of manyowners, insurers, lending institutions andgovernment agencies about the expectedperformance of a code conformingbuilding. This has led to losses that wereunexpected and in many cases financiallyruinous. Building stakeholders--those witha financial or social interest in the builtenvironment--who expect that theirbuildings are "earthquake proof" becausethey meet the code, have often been verydisappointed. It must be said, too, thatnone of these recent events has been ofan intensity that would typically beconsidered catastrophic. Catastrophictemblors with a magnitude similar to the1812 New Madrid or 1906 San Franciscoearthquakes will now likely result in lossesseveral times larger than anythingpreviously experienced if they occur in adensely populated area.Many building owners are unaware of thetradeoffs they face when using the currentstate of design practice. Interestingly,people make similar tradeoffs with moreeveryday choices. For example, thenumber of highway fatalities could bedramatically reduced if everyone drovetanks. Yet most people are unwilling orcannot afford to do so, and instead acceptthe increased risk of driving a car.Consciously or not, car buyers performcost-benefit analyses when weighing therisk of an accident against a car's cost. Acareful consumer may decide to spendmore to buy a safer car or he may opt tospend the same amount of money, butresearch much more closely the safetyrecords of similarly priced cars. Thisconsumer is reducing risk either byincreasing his investment or by reducinghis uncertainty.

    Current codes clearly serve an essentialand effective role in protecting buildingoccupants. The design basis of the code isintended to provide a basic level of safetyand a relatively economical means bywhich to construct buildings. However,using current code methods to design andbuild to a higher level of performance mayadd significantly to a project's cost.Stakeholders, however, have becomepainfully aware of the financial and socialconsequences of earthquakes and aredemanding that practical and cost-effectivemeans be developed to address the issuesof damage control and loss reduction.

    The community of designprofessionals needs to be able torespond to this demand with thedevelopment of design andevaluation methodologies thatlook at a broad range of buildingperformance and constructiontechniques.Current codes represent an evolution ofprescriptive rules that have changed everythree years as more is learned aboutbuilding behavior. The expectedperformance of new code designedbuildings is poorly understood, andprobably inconsistent among buildingtypes. It is currently difficult for rationaladvanced design techniques andinnovative systems to be fit into the codeframework. It is also difficult to applybuilding codes for new buildings toevaluation and retrofit of existing buildings.Special guidelines have been developedfor these purposes, potentially creating adouble standard.Performance Based Seismic Design(PBSD) is a methodology that provides ameans to more reliably predict seismic riskinall buildings in terms more useful tobuilding users. It permits owners to:

    ii

  • 7/29/2019 c02a_fema349

    7/9

    Action Plan for Performance Based Seismic Design

    > Make an efficient use of their designand construction budgets, resulting inmore reliable performance for themoney spent.> Consider spending more money toachieve quantifiably higherperformance than provided for in thecode, thereby reducing risk andpotential losses.PBSD will benefit nearly all building users.The PBSD methodology will be used bycode writers to develop building codes thatmore accurately and consistently reflectthe minimum standards desired by thecommunity. A performance based designoption in the code will facilitate design ofbuildings to higher standards and will allowrapid implementation of innovativetechnology. When performance levels aretied to probable losses in a reliabilityframework, the building design processcan be tied into owner's long-term capitalplanning strategies, as well as numericallife cycle cost models.PBSD is not limited to the design of newbuildings. With it, existing facilities can beevaluated and/or retrofitted to reliableperformance objectives. Sharing thecommon framework of PBSD, existingbuildings and new buildings can becompared equitably. It is expected that arating system will develop to replace thecurrently used ProbableMaximum Loss(PML) system. Such a system is highlydesirable to owners, tenants, insurers,lenders, an d others involved with buildingfinancial transactions. Despite itsinconsistency and lack of transparency, thePML system is widely used and a poorrating often creates the financial incentiveneeded for retrofit decisions.PBSD will provide a common base fordesign of new buildings, evaluation of

    existing buildings, and prediction of futuredamages. This will enable the results ofregional loss estimates to be directlyinterpreted in terms of building code an dretrofit strategies. PSD will thus supportand encourage efficient mitigation on bothan individual and a regional scale, resultingin safer and economically strongercommunities.The availability and use of PBSD will alsoallow building owners and a local community to determine the performance level ofbuildings within their jurisdiction. This isespecially true for structures that are critical to the continued function and livabilityof a community. For this reason, PBSDcan play a significant role in meeting theintent and goals of FEMVIA's Project Impactinitiative to reduce future losses.This Action Planpresents a rational an dcost effective approach by which buildingstakeholders: owners, financial institutions,engineers, architects, contractors,researchers, the public and governingagencies, will be able to move to aperformance based design and evaluationsystem.The Plan recognizes that there is a strongdemand from stakeholder groups for morereliable, quantifiable and practical meansto control building damage. It alsorecognizes that there is not a focusedunderstanding among these groups as tohow these goals can be obtained. ThisPlan describes how performance basedseismic design guidelines can bedeveloped and used to achieve thesegoals. Itwill be a vehicle to bring togetherthe diverse sets of demands from withinthe stakeholder groups and distill them intocohesive and practical guidelines. Itengages each of the groups in thedevelopment these guidelines, by whichfuture building design will become moreefficient and reliable.

    iii

  • 7/29/2019 c02a_fema349

    8/9

    Action Plan for Perfo rmance Based Seismic Design

    What i s PerformanceBased Seismic Design(PBSD)?

    T based seismic design ishe basic concept of performanceto provideengineers with the capability to designbuildings that have a predictable andreliable performance in earthquake^^Further, it permits owners and otherstakeholders to quantify financially orotherwise the expected risks to theirbuildings and to select a level ofperformance that meets their needs whilemaintaining a basic level of safety.PBSD employs the concept of performanceobjectives. A performance objective is thespecification of an acceptable level ofdamage to a building if it experiences anearthquake of a given ~everity.~hiscreates a sliding scale whereby a buildingcan be designed to perform in a mannerthat meets the owners economic andsafety goals. A single performanceobjective that requires buildings remainoperational even in the largest events, willresult in extraordinarily high costs.Conversely, a design where life safety isthe only consideration may not adequatelyprotect the economic interests of buildingstakeholders.A key to knowing how a building willperform in a given earthquake is having theability to estimate the damage it will sustainand the consequences of that damage.Current codes do notevaluate a buildingsperformance after the onset of damage.Instead, they obtain compliance with aminimum safety standard by specifying adesign which historically has protected life

    safety in earthquakes. In some cases, thecode may actually be unconservative. if abuildings irregularities are very substantial,or if a higher performance level such asdamage control is the desired.

  • 7/29/2019 c02a_fema349

    9/9

    Action Plan for Perform ance Based Seismic DesignP BS D differs from current codes in that itfocuses on a building's individuaipedormance. I t provides a road map thatpermits design professionals, owners andother stakeholders to learn more about abuilding's performance in differentearthquakes, and implement a design thatoptimizes design and construction costswith respect to life-cycle performance. Inits broadest sense, P BS D creates globalplanning opportunities for reducingeconomic and social losses to wholecommunities, regions and states.To implement PBS D several issues mustbe resolved. P BS D will change the waystakeholders look at the built environment.It will require a comprehensive effort tobring the various interested parties to aconsensus. Six challenges to adoptionexist. They are:i ncreasing the current knowledge baseof building behavior. This fundamentalissue will require that broader and moreaccurate information be developed andcollected on structural andnonstructural performance.i aising awareness amongstakeholders about how PBS D canaddress many of the problems theyalready perceive with current designpractice.i Developing PBS D to be compatible thestakeholders' economic interests.i Communicating the complex conceptsand information in a way that ISunderstandabie to all stakeholders.i Reducing uncertainty about how PBS D

    will effect stakeholders, in terms of costand possible changes in liabilityexposures.i Implementing incremental changes inthe current standards, to create acontinuum of design improvementrather than a perceived radical change.This Action Plan identifies the specifictasks required to develop a cohesive set ofproducts and guidelines that will meetthese challenges. These products will be

    more than just technical documents. TheP lan calls for going beyond earlier andmore purely analytical performance basedefforts by creating education andimplementation programs to bring allstakeholders on boardThis Plan is to be used by the teamsdeveloping the guidelines. It will provide amechanism to ensure that the goals ofPBSD are being tracked. Itencouragescreativity while capturing the requiredelements of a successful program. Foreach of the products, a proposed budgetand schedule are presented. A priority isassigned to individual tasks so that theprogram can be tailored to an overallfunding level.

    A Successful Useof

    er, were unac

    ethodologybThe re$

    ner'sminimum eq ufdingrepresenteda

    1 to thenextmostneedy facilities. .", . _ A