PRESENTATION TO SARF ZULULAND SUB- REGION UPDATE ON SANRAL PROJECTS 21 OCTOBER 2015 by Daniel Govender (AMSAICE) Project Manager in Training (ARE) Eastern Region

by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

Embed Size (px)

DESCRIPTION

CONTENTS SANRAL Projects N2 Project Update (current) N2 & R22 Project Update (future) Community Development Projects

Citation preview

Page 1: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

PRESENTATION TO SARF ZULULAND SUB-

REGIONUPDATE ON SANRAL PROJECTS

21 OCTOBER 2015

by Daniel Govender (AMSAICE)Project Manager in Training (ARE)Eastern Region

Page 2: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

CONTENTSSANRAL ProjectsN2 Project Update (current)N2 & R22 Project Update (future)Community Development Projects

Page 3: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

SANRAL PROJECTS Routine Road Maintenance (RRM) / Repairs Periodic Maintenance & Rehabilitation Capacity Upgrades Community Development Incident Management Traffic Control Toll Projects

Page 4: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

N2 PROJECT UPDATE Mtunzini to Empangeni

Page 5: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

MTUNZINI TOLL PLAZA TO EMPANGENI T-JUNCTION N2 Section 28 Km 42.7 To 29 Km 13.0 Scope

Upgrade to four lane dual carriagewayExtension of structures to

accommodate new cross-section Consulting Engineer: UWP Tender adjudication is ongoing

Page 6: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

N2 PROJECT UPDATE Mtunzini to Empangeni

Kwabhoboza Interchange

Page 7: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

KWABHOBOZA INTERCHANGE N2 Section 30 Km 5.6 Scope

New interchange Consulting Engineer: Mott Macdonald PDNA Construction start: June 2014 Construction duration: 25 months

Page 8: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

N2 PROJECT UPDATE Mtunzini to Empangeni

Kwabhoboza Interchange Eteza TCC

Page 9: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

ETEZA TRAFFIC CONTROL CENTRE N2 Section 29 Km 44 To Km 48 Scope

New interchange and TCCNew screener lanesDual carriageway for 4km

Consulting Engineer: WP Contractor: Raubex Construction Construction start: October 2014 Construction duration: 26 months

Page 10: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

ETEZA PROJECT SCOPE OF WORKS

Page 11: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

N2 PROJECT UPDATE Mtunzini to Empangeni

Kwabhoboza Interchange Eteza TCC Pongola Reseal

Page 12: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

RESEAL PONGOLA RIVER TO PONGOLA TOWN N2 Section 32 Resurfacing from Pongola

River to Pongola town Consulting Engineer: Gibb Contractor: KPMM Construction start: November 2014 Construction duration: 8 months Status: Project Complete

Page 13: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

N2 PROJECT UPDATE Mtunzini to Empangeni

Kwabhoboza Interchange Eteza TCC Pongola Reseal Phelandaba to

Mozambique

Page 14: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

2 RESEAL contracts on R22 Section 4 and 5 Phelandaba to Manguzi (8 months)

Consulting Engineer: Ingerope SA Contractor: Raubex Construction

Manguzi to Mozambique Border (7 months) Consulting Engineer: Nathoo Mbenyana and Associates Contractor: Raubex Construction

Both projects to be completed in 2015

Page 15: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

N2 & R22 PROJECT UPDATE

Empangeni to Kangela KwaMsane & Mkuze Crawler Lanes (N2/32) R22 Railway Line Manguzi Bypass

Page 16: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

FUTURE PROJECTS

N2 Section 29 Km 13 To 30 Km 14 Upgrade to dual carriageway from

Empangeni intersection to Kangela (design only)

KwaMsane Interchange N2 Section 30 km 2.5 (south of KwaBhoboza)

Mkuze Interchange

Page 17: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

FUTURE PROJECTS

N2 Section 32 Crawler lanes (due to go to tender for consulting engineers)

R22 Hluhluwe railway line crossing elimination (design has commenced)

Manguzi Bypass (design is complete)

Page 18: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

COMMUNITY DEVELOPMENT PROJECTS Umhlabuyalingana Pongola

Page 19: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

COMMUNITY DEVELOPMENT PROJECTS Umhlabuyalingana

R22 Road Safety & Public Transport Project Status: Contracts re-tendered due to termination

for both Contractors Pongola

Road Safety & Public Transport facilities on N2/32Consulting Engineer: UWP/TLS (JV) Contractor: Chapps ConstructionStatus: Contract Complete

Page 20: by Daniel Govender (AMSAICE) Project Manager in Training (ARE)

THANK YOU…