BWMS retro it installation and operation6 November 2020 • 09:00-09:45 GMT
Ballast WaterWebinar Week
Part of
4-6 November 2020
Sponsored by
Panellist documentsPage 2: John Loaiza, BioMarine ServicesPage 9:Tom Hazen, Hyde MarinePage 14: Shobhit Agarwal, Maersk Line
BioMarine Services Ltd
BioMarine Services Limited (Reg. No. 10424111) is a limited company registered in England and Wales. Registered Office. Unit 21, Building A, 1st Floor 99-109 Lavender Hill, Battersea Business Centre, London, England, SW11 5QL
WHO WE ARE
BioMarine Services Ltd is a specialist service provider for Marine
environmental services. We have an extensive experience in ballast water
sampling, Sampling for VGP and BWMS installation.
Our VisionTrusted partner in marine
environmental services
Project Management
BW Installation
Manufacturer
Engineering Company
Shipyard
Shipowner
Class
Service provider for
Commissioning testing
BWTS PROJECT MANAGEMENT
The principal affected for the delays is the Shipowner• Correct planning• Communications between the parties• Prefabricating Components• Crew training• Sampling for Commissioning testing• Interference with other systems
BACKLOG, DELAYS, COST OVERRUNS
BWTS Installation and Commissioning
IMO require sample and analysis during commissioning of BWMS on board shipsBMS is an approved service provider for conducting commissioning testing for BWMS. For more information https://www.biomarineservices.co.uk/commissioning-testingBMS offer engineering services for BWTS installation;3D scanningBWMS selection and feasibility studyDetail Engineering drawing and documentationCommissioning testing
BWMS Commissioning testing
Success criteria for commissioning testing:1. Sampling of BW dischargeWe conduct combine of detail and indicative analysis
2. Assessing self monitoring parametersObserve BWMS operation.analyse residual TRO, UVT
We provide complete report to flag/RO to satisfy IMO circular BWM.2/Circ 70, as may be amended and additional flag specific requirement, if any for the commissioning testing of BWMS.
This report and Class initial survey report is the two document needed to issue IBWMC certificate to the ship.
Service provider should be independent from the BWMS manufacturer or supplier
BMS Service portfolioBMS service portfolio include various sampling, consultancy and engineering services.BWMS and Biofouling product developmentPort BWMS feasibility studyIMO D-2 compliance samplingBWMP, BFMP developmentCrew training Biofouling prevention feasibility study – offshore, Fish farming, yacht and leisure industries.
Contact us:Hot Line: +44 (0) 7783849115T: + 44 (0) 2079244487Email : [email protected]
THANK YOU
Tom HazenSales Engineer
6-November-2020
Riviera Maritime – Ballast Water Webinar Week
BWMS Retrofit Installation and Operation
Full Project ExecutionEstimates indicate as many as 10,000 vessels per year are to be retrofit from 2021 – 2024– Only systems certified in accordance with the modified IMO Type Approval
guidelines can be installed, limiting equipment selection
Commonly held industry belief is that a minimum of 12 months should be allocated for BWTS project execution
System Selection Pre-Engineering Ship-Specific
Engineering Class Submittal Flag SubmittalProduction
Drawing Preparation
Equipment Production
Equipment Installation Commissioning
© Hyde Marine 2020 | Slide 3
Is the system correctly specified?
The devil is in the details• Specific vessel parameters have a significant impact on the
equipment configuration
How is it operated?Where does the crew conduct ballast operations from?
Factory-witnessed testing can identify flaws and enable corrections to be made before system arrives onsite.
© Hyde Marine 2020 | Slide 5
The more frequent communication between all parties (maker, engineering firm, installation contractor, operator) the more effective and successful a project execution will be.
Plan early and plan often
Classification: Internal
Retrofit and supervision of BWTS project-How to ensure quality is maintained
Riviera Maritime Ballast Water Webinar Week - 06th Nov 2020
ShobhitAgarwalProjectManager,Maersk
.
Classification: Internal
AGENDA
|2
Int roduct ionPlanningPreparat ionQualit yTimeline
Classification: Internal
AGENDA
|3
Int roduct ionPlanningPreparat ionQualit yTimeline
Planning
Class Approved Drawings
Shipyard Specification & Drawings
BWTS Equipment Readiness
Vessel Readiness
Supervision Planning
Shipyard/Installation Schedule – Location & Date
Successful Commissioning
Drawings
Specifications
Maker
Vessel
Shipyard
Logistic
Classification: Internal
AGENDA
|5
Int roduct ionPlanningPreparat ionQualit yTimeline
Preparation
Vessel Preparation (Ballast Tank, Ballast System, BWTS
Installation Area etc )
Shipyard Preparation ( Pre-fabrication of spools/foundation
, Pressure Tests etc)
Logistic Arrangement (Equipment delivery to yard,
Auxiliaries etc)
Service & Commissioning Engineers Arrangement
Liaison with laboratory for Ballast Water Sampling &
Analysis Preparation
Classification: Internal
AGENDA
|7
Int roduct ionPlanningPreparat ionQualit yTimeline
Quality
Standards/Specification to be shared with Engineering
Partner (Pipe Material/coating/cables/breaker etc)
Shipyard Specification to include all details (Web/hull
penetration etc )
Material Certificate
Welder’s Certificate
Pressure Test Certificates
Overboard Valves ( Certificates/ pressure testing etc)
Pressure Testing of Pre-fabricated spools
NDT testing
Classification: Internal
AGENDA
|9
Int roduct ionPlanningPreparat ionQualit yTimeline
Timeline
Readiness prior vessel arrival in Shipyard
Gantt Chart from Shipyard ( Total days, Docking days etc)
Docking Jobs
Commissioning Time
Training Time
BW Sample & Analysis Time ( Single/Two Pass system,
Holding time etc)
Classification: Internal
Thank you