62
27.1.11 1 Page Bundle Pipeline Systems & Shell FRAM Development Iain Watson & Peter Walker March 21 st , 2012

Bundle Pipeline Systems & Shell FRAM Development Iain ... uk lunch and learn 2012.pdf · Bundle Pipeline Systems & Shell FRAM Development Iain Watson & Peter Walker ... Control Depth

Embed Size (px)

Citation preview

27.1.11 1Page

Bundle Pipeline Systems

& Shell FRAM Development

Iain Watson & Peter Walker

March 21st, 2012

Bundle Technologies

Advantages of Bundle Systems

Shell Fram Bundle FEED

Agenda

27.1.11 2Page 2Page 27.1.11

Shell Fram Bundle FEED

Bundle Technologies

Advantages of Bundle Systems

Agenda

27.1.11 3Page 3Page 27.1.11

Advantages of Bundle Systems

Shell Fram FEED

What is a Bundle / Towed Pipeline Solution?

• A Pipeline Bundle is a carrier pipe within which any combination ofindividual pipelines and umbilical components is carried.

• The individual components terminate in “Towheads” within whichmanifolding may take place.

• A Towed Pipeline Solution provides a low stress installation methodwhere-by a pipeline bundle is towed and installed using the ControlledDepth Tow Method.

27.1.11 4Page

Subsea 7 Installed Bundles

Åsgard

Heidrun

NorwayNorway

Osprey

Cormorant

Frigg East

Murchison

GullfaksBruce

Keith

• 65 bundles in 33 years

• Up to 7.6km length

• Up to 28.7km in series

• Up to 320m water depth

• Shallowest 42m

27.1.11 5Page

Claymore

PiperSaltire Thelma

Cyrus, FarragonScapa

Alba

Gannet

Embla

DanDenmarkDenmark

WickWick

ScotlandScotland

Buckland

Keith

LeadonSkene

• Longest tow 1000 km

• Up to 49.5” carrier

• Up to 545 te towhead

• Heaviest bundle 9154 te

• Up to 3 PiP flowlines

• U-value <0.7 W/m2K

• 3 Ongoing Projects

Bundle Components

• Flowlines

• Insulation

• Sleeve Pipe

• Control/Chemical Tubes

• Power, Signal, & Data Highway cables

27.1.11 6Page

• Power, Signal, & Data Highway cables

• Main Spacer

• Centraliser – Pipe-in-Pipe Spacer

• Bulkheads

• Ballast Chains

• Anodes

What exactly is a “Pipeline Bundle?”

27.1.11 7Page

Typical Bundle Layout

BP Machar

27.1.11 8Page

BP Andrew

Kerr McGee Leadon

Materials

Flowline Materials

• Carbon steel - X52, X65, X70 with SS or

Alloy Liners

• Corrosion Resistant Alloys - 13% 22% & 25%

Cr Steels

27.1.11 9Page

• Plastic (HDPE) Liners for Water Injection Lines

Controls

• Hard Pipe Hydraulic and Chemical Systems -

316 SS, 25% Cr Duplex to Carbon Steel

• Electrical & Fibre Optic Control Systems

The Long Trek West

27.1.11 10Page

Wester Fabrication Facility

27.1.11 11Page

Hastigrow Fabrication Facility

27.1.11 12Page

Welding Firing Lines

27.1.11 13Page

Inner Bundle Fabrication

27.1.11 14Page

Insulation Type

Pipe-in-Pipe System

Passive Insulation System

27.1.11 15Page

Pipe-in-Pipe System

Electrical Active/Trace Heating

Indirect Hot Water Heating

Production Line Insulation

27.1.11 16Page

Applying ITP Izoflex Insulation

27.1.11 17Page

Applying ITP Izoflex Insulation

27.1.11 18Page

Spot Welding Steel Sheet Over ITP Izoflex

27.1.11 19Page

Spot Welding Steel Sheet Over ITP Izoflex

27.1.11 20Page

Bundle System Applicability

1500

2000

Wat

er D

epth

(m)

Pipe-in -Pipe

Wet Insulation

27.1.11 21Page

0

500

1000

0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5

Wat

er D

epth

(m)

U-Value (W/m 2K)

Pipe-in -Pipe

Bundles - Towed Pipeline Systems

Flexibles

Flow Assurance – Geometry of Pipelines

• The environment within the carrier pipe provides an ideal opportunity forinnovative solutions in Flow Assurance.

• The pipelines can be arranged to facilitate heat transfer between product linesor from dedicated heating lines.

• Heat transfer analysis confirmed by experimental results.

27.1.11 22Page

Active Heating Systems

� Warm-up before Start-up

� Increase Temperatures for Low Production Rates

� Keep System Temperature High during Shutdowns

� Reduce Chemical Injection

Six Active Heating Systems installed in the North Sea

Hot Water Circulation over distances of 15 km

Electric Heat Transfer

Carrier Sheathing

27.1.11 23Page

• 27m lengths welded into 500-1000m trains

• All production operations on line

• Trains sheathed to final location

• Final field joint tie-ins

Towheads

27.1.11 24Page

Jura Manifold Beach Landing

27.1.11 25Page

Jura Manifold Beach Landing

27.1.11 26Page

Bulkheads

27.1.11 27Page

Bulkheads

27.1.11 28Page

Towhead Tie-In

27.1.11 29Page

Bundle Launch

• Structures greater than 500Te

• Tidal currents monitored & tug

locations altered accordingly

• Tug bollard pull up to 400Te

• Capstan winch providing

holdback tension up to 70Te

27.1.11 30Page

holdback tension up to 70Te

• A99 road bridge opens to allow

large structures to pass through

Launch

27.1.11 31Page

Control Depth Tow Method

• Chains attached at regular intervals along the bundle.

• Ensures accurate weight control to approximately 0.5%.

• Weight of chain links on seabed is submerged weight of bundle.

• Chains can be easily cut by ROV to trim bundle

27.1.11 32Page

• Chains can be easily cut by ROV to trim bundle for tow if required.

CDTM – in Practice

27.1.11 33Page

A data highway runs thelength of the bundle andallows acoustic commandsmade at one end of thebundle to be implemented atthe other, for example forvalve actuation or acousticspool metrology.

Towmaster’s real-time display of bundle shape and water depth

What We Can Do

• Field Concept Development, FEED Studies

• Tender Engineering

• Detailed Design & Fabrication

• Launch, Tow & Installation Analysis

• Dynamic & Fatigue Analysis

• Failure Investigation Support

27.1.11 34Page

• Failure Investigation Support

• Regional Support (Bundles), Norway & Asia Pacific

Bundle Technologies

Advantages of Bundle Systems

Shell Fram Bundle FEED

Agenda

27.1.11 35Page 35Page 27.1.11

Shell Fram Bundle FEED

Why Bundles? - Advantages

• Eliminate the requirement for heavy lift vessels by incorporating Subsea Structures within a

Towed Production System (Maximum to date 545te).

• Testing and commissioning of complete system onshore therefore reducing offshore time: -

Hydro testing, dewatering, drying, control fluid flushing, valve operations etc.

• Fast hook up and commissioning for early first oil dates.

• Installation under existing or temporary floating assets.

27.1.11 36Page

• Reduced number of subsea tie-ins and spool installations.

• Seabed stability using Gravity Based or Piled design.

• Protection incorporated in structure design.

• Improved Flow Assurance / thermal Management (Heated – Hot Water, Trace Heating).

• Leak mitigation in case of internal flowline failure (maintain leaked oil within Carrier Annulus) -

Flowline safety class can be reduced when using DNV-OS-F101 Design Code.

• Use of CRA Lined pipe in place of Clad pipe or solid CRA pipe.

• High Temperature Flowline Design (up to 160°C curre ntly).

• Turn out cost more predictable (reduced exposure to weather/soils risk).

Bundle Technologies

Advantages of Bundle Systems

Shell Fram Bundle FEED

Agenda

27.1.11 37Page 37Page 27.1.11

Shell Fram Bundle FEED

Fram Field Location

27.1.11 38Page

Fram Field Location

27.1.11 39Page

Fram Development Proposed Field Concept

27.1.11 40Page

Fram Development – Proposed Field Layout (Xodus)

27.1.11 41Page

Fram Infield Layout

27.1.11 42Page

Fram FPSO Approaches (Xodus)

27.1.11 43Page

Fram Drill Centre East Towhead & Well Tie-ins (Xodus)

27.1.11 44Page

Fram Drill Centre West Towhead & Well Tie-ins (Xodus)

27.1.11 45Page

Fram Bundle FEED - Principal Design Assumptions

Principal Design Data / Assumptions for Fram FEED:

• 8 Slot towhead manifold at DCE (5 wells initially).

• 6 Slot towhead manifold at DCW (3 wells initially).

• 2 midline SSIV structures required at FPSO (out with swing circle).

• 14” NB Gas Export SSIV located in Midline Towhead (East).

• Shared services between drill centres (single test riser, gas lift riser & riser umbilical).

27.1.11 46Page

• Shared services between drill centres (single test riser, gas lift riser & riser umbilical).

• Mixture of Oil & Gas Wells at both drill centres.

• 345 Barg Design Pressure / 110°C Design Temperature (Production/Test).

• Max CO2 content ~1.1 mol.% in produced fluids.

• Max. H2S ~6 ppmv in produced fluids.

• ~47,000 mg/l Chlorides in produced water.

• Water depth infield ~ 95 m (wrt LAT).

• 20 year system design life

Fram Bundle Cross Section Designs

DCE & DCW Bundle Cross Sections

27.1.11 47Page

Midline Bundle Cross Section (Shared Services)

Fram Bundle Cross Section Designs

27.1.11 48Page

Fram Bundle Cross Section Designs

Pipe-in-pipe Insulation System Performance (both options)

27.1.11 49Page

CRA Lined Pipe (Butting) – Mechanically Bonded (BuBi)

Fram Bundle Production & Test Line Linepipe Design

27.1.11 50Page

The Mechanically bonded Butting Bimetal Pipe (BuBi Linepipe)

Fram Bundle Simplified Configuration (P&ID)

27.1.11 51Page

Fram Bundle - DCE Towhead Pipework (General Assembly)

27.1.11 52Page

Fram Bundle - DCW Towhead (General Assembly)

27.1.11 53Page

Fram Bundle - Midline Structure East (GA)

27.1.11 54Page

Fram Bundle - Midline Structure West (GA)

27.1.11 55Page

Bundle Launch at Subsea 7’s Wester Site

27.1.11 56Page

Bundle Tow Route

27.1.11 57Page

Bundle Tow Configuration

27.1.11 58Page

Bundle Tow Route

27.1.11 59Page

Control Depth Tow Method

• Chains attached at regular intervals along the bundle.

• Ensures accurate weight control to approximately 0.5%.

• Weight of chain links on seabed is submerged weight of bundle.

• Chains can be easily cut by ROV to trim bundle

27.1.11 60Page

• Chains can be easily cut by ROV to trim bundle for tow if required.

Questions?

27.1.11 61Page

27.1.11 62Page

seabed-to-surface

www.subsea7.com