16
BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

Embed Size (px)

Citation preview

Page 1: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®1

East Branch Dam Safety Modification Project

PUBLIC INFORMATION MEETING

April 16, 2014

Johnsonburg, Pa

Page 2: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®

WHY WE ARE HERE

• Communicate actions to improve dam safetyWhat’s The Problem

What’s Done

The Way Ahead

Questions

2

Page 3: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®3

FLOW

Soil

Rock

Grouted Cavity

Muddy Seepage Flowing from Rock Drain During Incident

WHAT’S THE PROBLEMRisk of Internal Erosion

Dam failure averted in 1957, but risk for re-initiation of internal erosion remains.

Untreated, Jointed Bedrock in Cutoff Trench Walls

Page 4: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®4

WHAT’S DONE

• 1957 to 2008 – Monitor Dam

• 2008 to 2014 - Interim Risk Reduction

• 2008 to 2010 – Dam Safety Study

• 2010 to 2014 – Preconstruction, Engineering & Design

• 2011 - Initiate Construction

Work Platform

Cutoff Wall

BEDROCK

FOUNDATION SOIL

Page 5: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®5

WHAT’S DONE

Construction Contracts

• 2011 to 2013 - Site Development Contract

• 2012 to 2014 - Building Contract

• 2013 to 2014 - Guiderail & Weir Pond Contract

Page 6: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®6

WHAT’S DONE

Instrumentation• 2012 – Nine new Piezometers Installed

• 2013 – Data Loggers Installation

• 2013 - 2014 – Instrumentation Automation (Ongoing)

Typical Piezometer (PZ)

DataLogger

Page 7: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®7

• 2011 – 2013

Geotech investigations

Acquisition Plan

Plans & specs

Reviews

WHAT’S DONE

Cutoff Wall

Preconstruction

WORK PLATFORM

CUTOFF WALLRESERVOIR

Page 8: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®8

WHAT’S DONECutoff Wall

Work Platform Design

• Maximum Geometry

100 ft maximum width

30 maximum slope (Slope Stability)

• Concrete Work Surface

Page 9: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®9

WHAT’S DONE

Cutoff Wall

Design

Page 10: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®10

THE WAY AHEADCutoff Wall Construction

• May 2013 - Advertise cutoff wall contract

• Oct 2013 - Contractors Submit Initial Proposals

• 2014 – Award Cutoff Wall Contract

• Construct Cutoff Wall

4 years 9 months period of performance

Production work hour limitations

ReverseCirculationDrill

Hydromill

Page 11: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®11

THE WAY AHEADCutoff Wall Construction

Increased Traffic

• Volume and frequency - is contractor, equipment, and construction activity dependent

Average annual traffic on SR 1001 is 164,500 vehicles

3 to 6% more on SR 1001 during construction on average

• Traffic Control Plan

Maintain access to Maple Lane

• Transportation Management Plan

Maintenance Plan, Permits & Bonds

Page 12: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®

Borrow Area and Support Area (~1 Acre as created by excavation) and E&S Pond

Support Area (~1 Acre)

Support Area (~1 Acre) Vehicle

Turnaround

Work PlatformGrouting, Soil Mixing, Cutoff Construction

Overlook Parking Support Area

(~1.8 Acre)

Existing Boat Launch (~0.9 Acre)

16 Sep to 14 Apr

Support Area(~.7 Acre)

THE WAY AHEADCutoff Wall Construction

Public Safety

RE Office

Construction Access Government Road

Maple Lane

Campground

Page 13: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®

• Instrumentation Automated & manual readings

• Visual Inspection Continued 24-hour government presence

• Contractor’s Emergency Plan

• Government’s Emergency Action Plan

Exercises with contractor & emergency responders

THE WAY AHEADCutoff Wall Construction

Dam Safety

Page 14: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®14

Grouting in Critical AreaAllowed 1 Oct – 1 Mar

Grouting in Critical AreaAllowed 1 Oct – 1 Mar

14 April 2014

Page 15: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®

• Comply with Federal, State, and County Environmental Regulations

• Monitor Lake Water Quality

• Monitor Outflow Water Quality

Outflow

THE WAY AHEADCutoff Wall Construction Safety During Construction

Page 16: BUILDING STRONG ® East Branch Dam Safety Modification Project PUBLIC INFORMATION MEETING April 16, 2014 Johnsonburg, Pa 1

BUILDING STRONG®

Website: www.lrp.usace.army.mil/rec/lakes/eastbran.htm

Email: [email protected]

NEW – Community Information System

CONTACT INFORMATIONResourcesEast Branch Dam OperationsMike SetlockEast Branch Park Manager, 814-965-2065E-mail: [email protected]

Media & General InquiriesDan JonesPublic Affairs, 412-395-7500E-mail: [email protected]