Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 38
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 39
Chapter- I
Introduction
1.1 Brief Foreword of Project proponent and Project Site
Mr. E.A Abdulkarim, Directorof Malabar Aggregates Pvt.Ltd. is carrying outbusiness related
to quarry, crushing, trading etcMr. E.A Abdulkarimis aresident of EdathuruthilHouse,
Vadakkekara (P.O),Paravoor, Ernamkulam-683522, Kerala. A Resolution of Board of
DirectorsauthorizingMr. E.A Abdulkarim to file and sign necessary application before the
SEIAA, Trivandrum in connection with the Environmental Clearance Certificate for Malabar
Aggregates Pvt. Ltdis enclosed as Annexure No. 4.
M/s. Malabar Aggregates Pvt. Ltd.pocessed a quarry permit for extraction of granite building
stonefromSy.Nos. 37/1 & 37/3 of MorayoorVillage, KondottyTaluk,MalappuramDistrict of
Kerala Statefor an extent of 1 Acre.
Tax paid receipts and possession certificates is enclosed as Annexure No. 5 & 6
As per the WGEEP report and ESA of HLWG, Morayoor Village does not fall in the sensitive
area.The proposed lease area marked on the cadastral plan is enclosed as Plate No. 1.
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 40
Chapter- II
2.1 Project Description
Project Proponent: E.A Abdulkarim (Director)
Mailing AddressEdathuruthil House,
Vadakkekara–PO
Paravoor,
Ernamkulam District.
Kerala – 683 522
Proposed project: In survey Nos.36/3(pt), 37/1(pt), 37/2, 37/3
Location: Morayoor Village,
KondottyTaluk
Malappuram district
Kerala state
Quarry lease area: 4.2793Ha
Type of land : Private land.
2.2 Salient features of the study area
The said quarry lies towards SW of Nediyiruppu village,andNW of Kuzhimanna village. This
lease area is approachable by road.
The photographs of the Project Site and its surroundings is enclosed as Plate No: 11.
The Location Showing the lease area along with coordinates are given below:-
Latitude 11⁰ 08’ 40.78” N to 11⁰ 08’ 51.19” N
Longitude 75⁰ 59’ 46.94” E to 75⁰ 59’ 55.07” E
Nearest Village Nediyiruppu village –SWboundary of proposed area.
Nearest Town Kondotty- 3.58Km- W(AerialDistance)
Nearest Railway Station Feroke Railway Station -18.5Km -W(Aerial Distance)
Nearest Airport Calicut International Airport - 5Km -NW(Aerial Distance)
Nearest Highway NH 213–1.5Km - S (Aerial Distance)
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 41
Elevation in (M SL) Highest 130m above MSL.
Lowest 55 m above MSL.
Working depth Top most level 130m above MSL
Bottom most level 40 m above MSL
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 42
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 43
The Google Map showing Location of the lease area is given below:-
The Route map showing location of the lease area:-
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 44
2.3 Nature and size of the project
Proponent is presently proposing the quarry project in Survey Nos. 36/3(pt), 37/1(pt), 37/2,
37/3of MorayoorVillage, Kondotty Taluk, Malappuram District ofKerala State for an extent of
4.2793 Ha.
Below table shows the proposed Year wise Production & Development quantities with its
respective strip ratio:
Qty: ‘000 MT
Year ROM Waste Strip
Ratio
1st Year 2014 - 15 38 2 1:0.05
2nd Year 2015 - 16 50 4 1:0.08
3rd Year 2016- 17 80 3 1:0.04
4th year 2017 - 18 108 5 1:0.05
5th year 2018 - 19 139 6 1:0.04
Total 415 20 1:0.05
2.4 Land use plan of the project site
Proposed quarry lease area is 4.2793Ha.Land use pattern of the lease area is shown on the
surface plan (Plate No. 3).
The present, plan period and conceptual land use pattern of the lease area is shown below:
Area in Ha.
Description As on date Plan period Concep.
Period
Area under Quarry pit 0.2800 1.4400 2.0600
Area for infrastructure / plant 0.0052 0.0019 0.0019
Green belt / Plantation 0.0000 2.2174 2.2174
Area for future use / undisturbed 3.9941 0.6200 0.0000
Total 4.2793 4.2793 4.2793
At the end of life of mine, the excavated pit will be 2.06 Ha, in which 1.633 Ha will be
reclaimed with stacked dumping and overburden and rehabilitated by plantation and the
remaining part 0.427 Ha will be used as a water pond. The details of the post mine land use are
given below:
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 45
Sl.
No Type of activities
Extent in
Ha
Post mining land use of
degraded land Extent in Ha.
1 Area under Quarry pit 2.0600 Water Pond 0.4270
Backfilling and Reclamation 1.6330
2 Area for infrastructure 0.0019 Area for infrastructure 0.0019
3 Green belt /
Plantation 2.2174 Green belt / Plantation 2.2174
Total 4.2793 Total 4.2793
Post mining land use plan is enclosed asPlate No. 8.
2.5 Employment Generation
About15peoplewill be employed from nearby villages for the quarry operation. This project
will also create additional employment indirectly.
2.6 Project Cost
Total Project cost:Rs. 1.5 Crores.
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 46
Chapter- III
3.1 Process description
The Quarrying operation is carried out in different stages. A flow chart depicting the operations
is shown below:
OPENCAST METHOD
DRILLING & BLASTING 32 mm BLAST HOLE.
GELATINE EXPLOSIVE
LOADING BY EXCAVATORS / LOADERS
TRANSPORTATION BY TRUCKS / TIPPERS
The quarry is being worked with conventional open cast with bench system method with
mechanized mode of operation. Based on the mode and method, taking into the consideration
of geological parameters of the charnockite body, the quarry pit will be so designed such that
the height of the bench is kept about 5.00 m max.
DESPATCH TO CLIENT / CUSTOMER
BENCH FORMATION 5.0 m HIGHT & 5.0 WIDTH
EXCAVATION BY EXCAVATORS
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 47
3.2Local Geology
The country rock in the lease area is migmatisedcharnockite. The contact between the
migmatitic patches within charnockite is very graded. A very faint mineral foliation trending
N60ͦW- S60ͦE, dipping sub vertical is observed. Other planar features like Joint planes are also
observed. Two major sets of joints trending in (1) N-S, dipping 65ͦ easterly and (2)
N30ͦW –S30ͦE, dipping vertical is observed.
The soil profile in the area is thin with an average thickness about 0.5m. Sheet rock is exposed
in most part of the lease area.
Sheet rock with no development of soil profile
Sheet Rock
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 48
The geological parameters / features of the ore body as obtained from the field mapping and
exploration studies reveal the following.
Strike: N600 W
Dip:dipping sub vertical
Length of the ore body : ranging from68-332 m. (average 200)
Width of the ore body :ranging from120-240 m. (average 180)
Depth of the ore body : 40m MSL
A geological map showing the different litho units enclosed as Plate No. 4. and the cross
section showing the disposition of the different litho units are marked and enclosed as Plate
No. 5.
3.3 Mineable Reserves
The mineable reserves and total reserves are calculated based on the mineral concession rules.
The quantity of the reserves are arrived as follows.
Insitu reserves Unit : 000’ tones
Cr. Sec. Betn. R O M Waste Rock
N : 300 to N : 350 242 13
N: 350 to N : 400 390 21
N : 400 to N : 450 262 15
N : 450 to N : 500 112 4
Total 1006 53
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 49
Insitu reserves 000’
tonnes
Blocked
reserves
000’
tonnes
Bench
RL R O M
Waste
Rock
Bench
RL R O M
Waste
Rock
130 - - 130 2 -
125 4 - 125 10 -
120 14 - 120 14 -
115 20 2 115 16 -
110 24 2 110 21 2
105 26 2 105 26 2
100 35 2 100 34 2
95 51 2 95 46 2
90 68 3 90 54 3
85 80 4 85 64 3
80 93 4 80 75 4
75 94 4 75 100 6
70 99 5 70 134 7
65 95 5 65 172 10
60 89 6 60 193 10
55 81 5 55 214 11
50 67 3 50 232 12
45 39 3 45 261 14
40 27 1 40 273 14
Total 1006 53 35 301 16
30 301 16
25 301 16
20 301 16
15 301 16
10 301 16
5 301 16
0 154 8
Total 4202 222
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 50
3.4 Method of Quarrying
Currently the said quarry is working with conventional open cast with bench system method
with mechanized mode of operation. Based on the mode and method so adopted and taking
into the consideration of geological parameters of the ore body, the quarry pit is so designed
such that the height of the bench is kept about 5.00 m (2.50 m x 2 sub benches) max., and the
width is also kept 5.00 m, maintaining 45˚ pit slope. Benches are advanced side ward and
lateral to win the material at lower level /depth.
3.5 Extent of Mechanization
List of Quarrying machinery deployed in the quarry along with their capacities, efficiencies and
other details are shown in below table:
Sr.
No
Equipment /
Machinery
No. of
units
Engine
H P
Size/
Capacity
1 Excavator 1 210 2.0M3
2 Excavator 1 120 2.0M3
3 Rock breaker 1 120 2.0M3
4 Tippers 4 130 7 tonnes
5 Compressor 2 100
6 Jackhammer 2
3.6 Quarrying Activity
Presently the quarry is working with conventional open cast with bench system method with
mechanized mode of operation. Based on the mode and method so adopted and taking into
consideration of geological parameters of the Charnockite body, the quarry pit is designed such
that the height of the bench is kept about 5.00 m max., and the width is kept min 5.00 m,
maintaining 45˚ pit slope. Two sub benches are created of 2.50 m height each, when it reaches
its ultimate limit, all the two benches will be joined together to form a height of 5.0 m. Topsoil
is sparsely distributed in the area, this topsoil will be removed separately and it will be used for
plantation purpose.
As the rock is mainly hard to medium hard in nature, drilling and blasting is required to
dislodge/loosen the material from the main rock mass. The broad blasting parameters are
determined in subsequent paragraph:
The operation flow chart of the quarry activity is given in the above chapter – II under head
Process Description.
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 51
3.6.1 Explosives Management, drilling and Blasting
Blast hole will be, preferably by jack hammer where the diameter is normally 32 mm and the
depth of the hole is 2.5 – 2.75 m. Blasting pattern is generally square or rectangle or staggered
with burden ranging from 0.75 to 1.00 meters and spacing of 1.00 to 1.20 meters. Usually
single / double row of holes is blasted along free face to achieve optimum powder factor, best
fragmentation and minimized adverse impacts on account of blasting. Maximum numbers of
holes will be blasted at a time in a round are generally limited to 20 to 30 with normal delay
detonators to mitigate adverse impacts such as air blast, throw and the ground vibration. Holes
are electrically detonated using electric detonators.
Gelatine explosives are used for blasting with 20 to 25 percent, proportion of primer/ booster
cartridges and rest as column charge. About 1 to 1.5 kgs of explosives are loaded in 32 mm
diameter holes. And powder factor ranging between 5.0 tons per kgs of explosives is achieved.
3.6.2 Excavation and Crushing
The said quarry is a conventional opencast with bench systems and operating in a mechanized
mode. The bench height and width is kept at 5m maximum with a pit slope of 450.
Subsequent
to the drilling and blasting, the material so dislodged / loosen from the rock mass, the big
boulders are broken in to small boulders with a help of rock breaker. There after the material is
loaded into trucks / tippers of 7 tonnes capacitywith the help of the excavator and thesame will
be dispatched to the buyers also.The proponent owns a crushing unit which is outside the lease
area.
3.6.3 Topsoil:
The amount of topsoil occurs with average thickness of 0.50m.This will be removed separately
as and when it occurs during the course of quarrying. The topsoil so removed will be stacked
separately and will be used judiciously for plantation purpose. Precautions will be taken to
limit the height of the top soil dump to 5-6 m in order to preserve its fertility and shelf life. It
will be suitably protected from soil erosion and infertility by planting fodder grass and
leguminous plants during temporary storage.
The total amount of topsoil existing within the leasehold is calculated as below:
Area - 31,207 sq.m
Depth - 0.50m
Bulk density - 1.50
31207 X0.50 X 1.50 =23405.64(23400)tones.
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 52
3.6.4 Mine Waste Management
About 53,000 tons ofmine waste will be generated throughout the mine life and it will be
stacked in the area earmarked for it. This waste will be utilized for lying of haul road as well as
for backfilling. At the end, this mine waste can be partly utilized as soil base for plantation.
3.6.5 Site Security and Safety
Copies of all safety and management documents will be made available to on site, personnel
and mandatory training for operations at the Quarry will take place. The Area Coordinator will
ensure that operations are consistent with other management plans, terms and conditions of the
issued permits, and safety procedures for the Project.
Security signage will be posted at the entrance to the quarry. The remoteness of the quarry and
the onsite presence of operations personnel will make perimeter fencing unnecessary. Audible
warning systems will be employed for all blasting operations at posted intervals prior to any
detonations.
Loose rocks will be properly dressed and nature of rocks and available structural planes will be
studied to avoid any slip. Explosives will be stored in safe approved and licensed magazine.
Competent blasters (with blasting certificate of competency issued by DGMS) will only handle
explosives to avoid any accident. Proper and full proof security will be provided to the
magazine to avoid any theft, unauthorized entry etc. proper fencing with sign boards will be
provided to separate out the magazine. Blasting and processing operations will be suspended if
incursions into the quarry occur. On site monitors for animals will provide warnings if the
approach of any animals is noted.
Before the onset of monsoon, drains are cut along the toe of the quarry faces to divert the
surface run off. Garland drain is provided at the quarry top to regulate monsoon water and
direct the same to the settling ponds / quarry pit to contain the quarry wash off and to avoid the
same joining to the adjoining surface water bodies / water courses. It also helps to avert
eventual collapses and damages to the quarry faces.
The pit will be fenced by barbed wire, such that no habitats can enter the pit and watch and
ward is provided round the clock.
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 53
Chapter –IV
Environmental Baseline data Description
4.1 Air Environment
The drilling, blasting and dislodging activities certainly capable of generating the respirable
and non respirable dust during operation.
To assess the ambient air quality status, monitoring stations were identified on the
basis of Meteorology in the upwind and downwind direction as well as to represent the cross
sectional scenario of the project site. Based on the production activity,the parameters chosen
for assessment of air quality are Particulate Matter (PM10&PM2.5), Sulphur dioxide (SO2), and
oxides of Nitrogen (NOx).
4.2 Analysis of Baseline Concentrations
The Ambient Air Quality data were collected in the month of22nd
May 2014from the four
corners of the project site .The data have been collected on 8 hourly basis for parameters of
PM10, PM2.5, SO2, NOX.
The PM10 concentration near the north side boundary of the project site is found to be well
below the prescribed limit with the values 53 µg/m3 during the monitoring period and PM2.5
concentrations is 35µg/M3. The Sulphur dioxide(SO2) concentration is 10.4 µg/m
3and Nitrogen
dioxide(NO2) concentrationis 7.3 µg/m3.
The PM10 concentration near the east side boundary of the project site is found 64.3 µg/m3
during the monitoring period and PM2.5 concentration is 42.5 µg/m3. The SO2concentration is
13.7 µg/m3and NO2concentration is 9.2 µg/m
3 .
The PM10 concentration near the south side boundary of the project site is found 47 µg/m3
during the monitoring period and PM2.5 concentrations is 24 µg/M3. The SO2concentration is
9.6 µg/M3 and NO2concentration is 6.9 µg/M
3 .
The PM10 concentration near the west side boundary of the project site is found 43 µg/m3
during the monitoring period and PM2.5 concentrations is 21 µg/m3. The SO2concentration is
10.1 µg/m3and NO2concentration is 7µg/m
3 .
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 54
The result of above Ambient Air quality analysis is enclosed inAnnexure No. 11. The average
concentrations of various parameters areshown graphically below.
4.3 Water & HydrogeologyEnvironment
The main source of water to theMorayoor Village is from groundwater (open wells and bore
wells) and rain water sources. The area receives rainfall from south western monsoon and
northeastern monsoon with an annual cumulative contribution of about 2793 mm. The
Charnockite forming a part of crystalline group of rocks is the prominent litho-unit in this area.
So the aquifer in theproject site belongs to crystalline type in which occurrenceand movement
of ground water is dominantly controlled by the nature and extent of weathering andthe
presence of structural features like fractures and joints. In this area the groundwater occurs in
the secondary inter-granular pores and voids under unconfined condition. Bore wells and open
wells are the dominant source of groundwater in this area. The yield of these wells ranges from
4 to 5 m3/Hr (CGWB report March 2009).
The depth to the groundwater level in this area ranges from about 7 to10 m during pre-
monsoon and from 5 to 7 m during post-monsoon. Groundwater quality is generally good.
Pollution due to anthropogenic activity is minimum as the district is devoid of any major
industries.
The ground water level measured from the nearest well is about 10 m below the ground
level.The ultimate depth of the working of the quarry is 40m MSL. Since the working is much
above the general ground water table, it does not affect the ground water.
52.9
34.8
10.4 7.3
64.3
42.5
13.79.2
46.7
23.7
9.6 6.9
43.4
21.2
10.1 7
PM 10 PM2.5 SO2 NO2
Baseline Air Quality Data
North East South West
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 55
4.4 Analysis of Baseline Concentrations
Ground water sample were collected from Project site(surface water and open well water) and
pond water,surface water from outside for the analysis of physical, chemical and biological
parameters.
A detailed Analysis report is enclosed in Annexure 12.
The analysis results of ground water are well within the guidelines of IS-10500 standards
except for coliform bacteria and MPN coliform count. The analysis of parameters like pH, Iron,
Chloride, Sulphate, Nitrate, and other parametersare within the site are found to be well within
the prescribed limits except in the case of surface water collected from outside.
4.5 Noise Environment
The exposure to aggregate by mechanical stripping of soil and rock, extraction by digging,
transportation of materials around the site and processing are likely sources of noise.
This Noise generated from quarry activity and vibrations can seriously affect people in noise
sensitive locations and interfere with their ability to relax, sleep, or communicate, causing
stress and annoyance.However, the survey was carried out at the North, South, East and West
direction of the project site.
0100200300400500600700800900
Baseline Water Quality Data
Surface water
Open well water(West side)
Surface water(out side)
Pond water (out side)
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 56
The baseline ambient noise quality at the project site and the surrounding areas where
monitored which was recorded. In daytime, the noise level was measured at 4 locations,
including Quarry / project site on 22/05/2014 to 23/05/2014, the noise levels so observed were
within the prescribed limits / standards with regard to CPCB Standards. The results of above
Noise level is enclosed in Annexure No. 13.
4.6 Biological Environment
Executive Summary
Biodiversity means the diversity or variety of plants and animals and other living thing in a
particular region or area. Biodiversity assessment of the area has been carried out with
appropriate methodology. An observation in the land use shows that the area was barren land
with poor vegetation and some of the surrounding area was covered by coconut plantation
(Cocusnucifera). Faunal diversity is also observed to be not very rich with the occurrence of
some common birds, mammals and reptiles. The mining activity does not seem to have any
deleterious effect on the biodiversity of the region.
Aim of this report
The assessment is conducted to develop a database on the floral and the faunal characteristics
of quarry of the M/s Malabar Aggregates (P) Ltd. The report gives information regarding plants
and animals around the mining site.
Methodology
Preliminary data collection and report preparation was carried out. Species list is developed
after proper identification of the samples collected/ photographs taken and consulting relevant
taxonomic literature. The assessment was focused on all taxonomic groups, such as plants,
birds, fishes, amphibians, insects, reptiles.
Flora:
A detailed survey was carried out in the study area. Only a few number of flora were observed.
Interviews were carried out with local people to collect information about the flora. Based on
this, a detail list is prepared
Fauna:
Mammals: The mammals in the study area were listed along the frequency of occurrence for
sighting, calls, scats / fecal matter, track marks or other indirect signs transects as well as
quadrant.
Birds: The birds on the area were studied by frequency of occurrence for sighting, calls as well
as other indirect signs and road kills along the sector.
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 57
Reptiles and Amphibians: The reptiles and amphibians were studied by direct sighting and
indirect signs like molt as transect as well as quadrants.
Biodiversity of the Study Area
The study area was a barren rocky land with poor vegetation and some of the surrounding area
having coconut plantation. Butterflies, dragon flies and other insects were observed from the
region, however their occurrence was sparse.A total of 22 species were observed from the
region.
Endemic Species
A total of 22 plant species were identified in the study area. The identification of endemics is
based on available literature (Ramesh et al., 1998, Ahmedullah and Nayar (1987) and Nayar
et.al., 1996). There is no endemic species found in the study area.
Table 1. List of plants recorded from the Core & Buffer Zone
Sl.No Botanical Names Family Common Name
Conservation
status (IUCN)
1 Cocosnucifera Arecaceae Tengu Least concern
2 Mangiferaindica Anacardiaceae Mavu Least concern
3 Anacardiumoccidentale Anacardiaceae Kasumavu Least concern
4 Caryotaurens Arecaceae Annapanna Least concern
5 Gliricidiasepium Fabaceae Seemakonna Least concern
6 Tectonagrandis Verbenaceae Thekku Least concern
7 Syzgiumcumini Myrtaceae Njaval Least concern
8 Artocarpusheterophylla Moraceae Plavu Least concern
9 Eupatorium odoratum Asteraceae Kamunistpacha Least concern
10 Desmodiumgangeticum Fabaceae Oorilla Least concern
11 Gliricidiasepium Fabaceae Seemakonna Least concern
12 Sidaacuta Malvaceae Alatta Least concern
13 Canthiumparviflorum Rubiaceae Kaaramullu Least concern
14 Urenalobata Malvaceae Oorakam Least concern
15 Macarangaindica Euphorbiaceae Vatta Least concern
16 Poaannua Poaceae Pullu Least concern
17 Ageratum conyzoides Asteraceae Kattappa Least concern
18 Lantana camara Verbenaceae Arippoo Least concern
19 Sidaalnifolia Malvaceae Kurunthotty Least concern
20 Cyathulaprostrata Amaranthaceae Cherukadaladi Least concern
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 58
21 Bambusaaurundinaceae Bambusaceae Mulla Least concern
22 Mimosa pudica Mimosaceae Thottavady Least concern
FAUNA
Table 2. List of Fauna recorded from the Core & Buffer Zone
Sl.
No
Scientific Name Common name Malayalam
Name
Conservation
Status (IUCN)
Butterflies
1 Euploea core Common Indian Crow - Least concern
2 Neptishylas Common sailor - Least concern
3 Leptosianina Psyche - Least concern
Dragonflies & Damselflies
1 Ceriagrioncerinorub
ellum Orange tailed marsh dart
- Least concern
2 Trithemis aurora Crimson marsh glider - Least concern
3 Orthetrum Sabina Green marsh hawk - Least concern
Birds
1 Corvussplendens House crow Kakha Least Concern
2 Columba livia Rock Pigeon Pravu Least Concern
3 Acridotherestristis Myna Myna Least Concern
4 Haliasturindus Brahminy Kite Krishnaparunthu Least Concern
Reptiles
1 Ptyas mucosa Rat snake Chera Least concern
2 Calotesversicolor Garden lizard Oondu Least concern
3 Sphenomorphus sp. Skink Arana Least concern
Mammals
1 Musmusculus Mouse Chundeli Least concern
2
Bandicotabengalensi
s Bandicoot rat Peruchazi
Least concern
3 Felisdomesticus Cat Pucha Least concern
4 Bosindicus Cow Pashu Least concern
5
Funambuluspalmaru
m Squirrel Annan
Least concern
CONCLUSIONS
The floral and faunal diversity of the area is found to be very low when compared to the
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 59
diversity of the country sides of Kerala. The present study area do not possesses any specific
group of ecological important assemblages. Majority of the surrounding area was planted by
rubber tree and also this region does not come under any conservation reserves. Ecological
important plants were not observed in the buffer zone of the mine site. So any development
activities in the region do not have any direct bearing or significant influences in the ecosystem
stability or biodiversity.
4.7 Socio Economics
The major occupation of the Malappuram and adjacent Kozhikode district is Cultivation,
Household activity, Livestock, Forestry, Mining, Quarrying activities. The quarrying activity
will benefit local villages in both directly and in-directly. Direct beneficiary will be those who
get employed in Quarry as skilled and unskilled workers.
a. Addressing concerns of local inhabitants like health, water, employment,
resettlement / rehabilitation
Proponent shall provide the required Medical facility to all the employees at the quarry such as
first aid, regular checkup, ambulance etc. as per provisions of Indian factories Act. In addition
proponent also provides the medical checkup camps to the local villagers, supply of drinking
water, and contribution of funds for social and cultural program.
The proposed lease area extends over an area of 4.2793 Ha. There are no settlements within the
lease hold area, hence there is no resettlement or rehabilitation of the same.
b. Compensation for loss of land, crops and other adverse impacts on account of
mining
Entire lease area belongs to lessee hence there is no compensation for loss of land.
c.Biological reclamation/Eco-restoration Plan
Around 1500 saplings will be planted in an area of 1.6321 Ha. The main aim of the green belt
development is to restore the ecosystem to its original form to a maximum possible extend by
designing green cover with the same native species.
Ecological restoration for the mined areas by plantation of the species as per the time schedule
suggested below:-
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 60
• First six month - Herbs and grass
• Next six month - Shrubs
• Next six months onwards - Trees
Sl.
No Herbs & Grasses Shrubs Climber Trees
1 Musa paradisiaca
(Vazha)
Lawsoniainermis
(Mylanchi)
Piper nigrum
(Kurumulaku)
Cocosnucifera
(Tengu)
2
Amaranthuspanic
ulatus
(Cheera)
Manihotutilissima
(Kappa)
Piper betle
(Vettila)
Azadirachtaindica
(Arya Veppu)
3
Bambusaarundina
ceae (Mulla)
Adhatodavasica
(Valiyaadalotakam)
Dioscoreaalata
(Kachil)
Mangiferaindica
(Mavu)
4
Colocasiaesculent
a
(Chembu)
Ocimum sanctum
(Tulasi)
Cassia fistula
(Kannikonna)
5
Dactylocteniumae
gyptium
(pullu)
Bougainvillea glabra
(Bougainvillea)
Bauhinia variegate
(chuvannamandaram)
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 61
Chapter- V
5.1 Site Management Measures
The awareness of environment has led to the development of Environmental Management Plan
including minor development projects, wherein anticipated impact are assessed and the
management plan to mitigate these impacts has been stipulated in advance. The proposed
project involves drilling, blasting, and movement of heavy machineries. Thereby this section
will cover the Environmental management of the environmental attributes that may arise due to
the current project in the entire stage of operation.
The Quarry Lease area is an undulated rocky terrain with thin layers of soil as substratum and
shrubby growth of weeds. Since the quarry was operated earlier there is no cutting of large
woody trees, the site is a rocky area with an outcrop of Charnockite (Commercially known as
Granite) without extensive vegetation. The weeds and shrubby growth of plant are cleaned
manually. The loose soil layer is removed and stored in the non-mining area ,which will be
used for plantation purpose. The boulder and the underneath rock bed consist of rock mass,
which is the mother rock where the extraction of products shall be undertaken.
The number of workers for the current production including the machinery operators and
drivers is15 (adult workers). The quarry shall not employ any children below 18 years. Also the
workers are from nearby villages and no migrated laborers are employed for the current quarry
operation. Thus settlement of migrated worker is not involved inside the Quarry Lease area, as
the workers shall be daily waged laborers of the area. The main activity is drilling, excavation,
storage and transportation of final product.
5.2 Drainage Management
Since Kerala falls under coastal region, Western Ghats and Malnad belt, the state receives a
copious amount of rain fall to an extent of 3,000 mm annually. So safety and precaution of the
quarry pit is very much essential.
Before onset of monsoon, drains are cut along toe of the quarry faces to divert the surface run
off. Garland drain is provided at the quarry top to regulate monsoon water and direct the same
to the settling ponds / quarry pit to contain the quarry wash off and to avoid the same joining to
the adjoining surface water bodies / water courses. It also helps to avert eventual collapses and
damages to the quarry faces if any.
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 62
The quarry is currently designed to avoid surface water courses and drainage channels. Sources
of contamination from the operation that could affect water quality include dust from blasting
and refueling for equipment. Blast residues from explosives will be managed by ensuring that
all material is ignited during the blasting process. Vehicle fuelling will be conducted at a
centralized fuelling facility off site that has proper containment and spill response capability.
Fuelling for non-moveable onsite equipment, such as generators, will take place in a secured
area with approved spill containment.
A Drainage plan showing the drainage pattern is enclosed as Plate No. 10.
5.3 Dust Management
The primary sources of dust at the Quarry are blasting and loading. Very little topsoil exists at
the quarry site, and is not considered a primary source of dust. The management of dust will be
accomplished by minimizing the creation of dust at source. Transport of material will be
subject to speed limit restrictions and covered by tarpaulin sheets to help reduce dust.
5.4 Noise Environment
The Noise is the environment attribute associated with the quarrying activity and operation of
heavy machinery operation which causes vibration and noise. The quarrying operation will be
restricted to only day time. To attenuate noise, various measures shall be taken up from the
source point. The activity such as drilling shall be updated to latest technology which involves
wet drilling technology and blasting will be carried out with controlled mechanism.
Persons who are exposed to critical operation like drilling and operation of excavators are
being provided with personal protective equipments (PPEs) as Occupational Safety Measures.
Greenbelt will be developed, which will act as an acoustic barrier for noise transmission
5.5 Solid Waste
The mine waste generated incidental to quarry operation will be partly used for leveling for
road and civil construction works.It will be stacked at designated places during the quarry
operations and will be utilized for back filling during mine closure.
5.6 Water Environment
In the mining activity there is no utilization of water for the process / quarrying. The
requirement is mainly for drinking and domestic purposes and that shall be met through water
pond located outside the quarry area and water required for dust suppression and plantation will
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 63
be met through pit water which is accumulated within the existing pit.
It is proposed to construct two ponds and a check dam. One pond is for rain water harvesting
cum silt arresting and the other for collection of decanted water.
Toilets shall be constructed which is of temporary structure. The domestic effluent of the
Quarry workers, drivers, etc shall be treated in septic tank followed by soak pit as per the
approved design by CPCB.
5.7 Air Environment
The pollutants released from the quarrying activity will be from the machineries (Heavy Earth
Movers, Loaders, Rock breaker, etc) and movement of vehicles. For the purpose of the quarry
activity, and to maintain a quality environment, selection of good condition vehicles and quarry
operation shall be undertaken in a controlled mechanism; vehicular servicing shall be carried
out regularly at frequent intervals so as to limit vehicular emission within the standard
prescribed by Motor vehicle Act.
The drilling activity generates comparatively more dust than other activity such as breaking
and loading. Another common source of dust dispersal is from the haulage road. The
movement of vehicles (dumper & tripper) to ferry the rock fragments is one of the source of
dust. The improvement of haulage road is the main remedy to suppress dust during
transportation. Water sprinklers are provided to check the dusty road in the mining area.
The effective plantation will be undertaken as follows:
Year
Area of
plantation
1000/Ha
No of plants Type of species
2014 - 15 0.4435 450 Bamboo, Rubber, Red palm, Mahagani
Bougainvillea and other local species
with thick foliage to arrest dust
dispersion due to movement of
vehicles.
2015 - 16 0.4435 450
2016 - 17 0.4435 450
2017 - 18 0.4435 450
2018 - 19 0.4435 450
Total 2.2174 2250
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 64
5.8 Occupational health and Safety
Since the activity of the project involves drilling, rock breaking, loading and transportation,
primarysafety for the workers is the main concern of the project. Generally Personal Protective
Equipments (PPE) shall be provided to all individuals inside the Quarry Lease area. The
workersinvolved in the activity of drilling work, additional protective equipments shall be
provided such as Thick Gloves, Goggles, ear plugs, thick boot wears, etc.
The secondary safety of workers health shall also be given the same importance. Secondary
health threat arises from disease causing vectors and untidy housekeeping. The workers’ health
can also be at risk from communicable diseases which may be seasonal or pandemic.
Safe drinking water to all the employees and cleanliness in the quarry area will be maintained
to avoid communicable diseases. Rest rooms and first aid facility is provided in the quarry as
per the DGMS guidelines.
5.9 Social Responsibility
The details of CSR activities carried out are:-
Sl.No CSR Activities Amount
1 Supply of construction materials free of cost with delivery for the
needy local people of MorayurPanchayath
1,50,000.00
2 Road tarring work from West Bazar to Colony road 2,50,000.00
3 Financial Assistance for the marriage of poor people 50,000.00
4 Donation to Juma masjid, West bazar 25,000.00
5 Financial assistance to NoorulHudha Arabic College Orphanage,
Pandikkad
10,000.00
6 Provide financial assistance for ‘Annadanamprogramme’ of Ozhukur
Temple on its festival season.
25,000.00
Total 5,10,000.00
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 65
It is proposed to spend Rs5.0 Lakhs/annum for various local development activities. The
detailed list of the proposed CSR activities are:
Sl.
No
CSR Activities Beneficiary Year Amount
1 Supply of construction material free of
cost with delivery for the needy local
people
Morayoorpanchayath Yearly 1,50,000.00
2 Financial assistance to A.M.L.P School Ozhukur Yearly 50,000.00
3 Donation to Ozhukur temple Ozhukur Yearly 20,000.00
4 Donation to OzhukurJuma Masjid Ozhukur Yearly 30,000.00
5 Rennovation of Road work from West
Bazar to Colony road
West Bazar-Colony
Road
Yearly 2,50,000.00
Total 5,00,000.00
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 66
Chapter VI
6.0 Environmental Control Measures
6.1 Environmental Management measures
The entire quarry area is planned systematically and scientific method of mining with 5.0
bench ht and 5.0 m bench width. Once the reserves are exhausted, the quarry pit will be
reclaimed to the extent possible by suitable plantation. Some area of the pit will be retained as
water pondwith fencing around the quarry lease. Qualified Mines Manager will supervise
mined area management. Mines Manager will identify the suitable personnel for
implementation of Environmental Management Plan (EMP).
6.2 Safety and Environment Management measures
• Mitigation measures will be taken in respect to non - compliance.
• Review of the safety practices being followed and additional safety measures
ifnecessary.
• Identification of unsafe conditions/ practices prevailing in the area and mitigation
measures, if any.
• Arrangement of training to develop safety awareness among all staff including laborers.
• Preparation of safety codes/ manuals of operations which will be distributed to workers.
6.3 Occupational Health measures
An occupational health unit will be organized and the proposed measures will be adopted:
• Periodic Medical Checkup program for all the workers.
• Compulsory medical checkup program for risk group
• Training for workers regarding occupational hazards.
• Lung function test for workers exposed to dusts.
6.4 Post Environmental Clearance Monitoring Programme
An environmental monitoring cell will be constituted for constant monitoring of environmental
parameters like air, water, noise and soil to assess the status of environment during mine
operations and other activities.The environmental monitoring cell will conduct routine
monitoring as given below to ensure the protection of environment from any degradation.
Besides, the compliances to all environmental clearance conditions and consents from KSPCB
/ MoE&F will be monitored and reported periodically.
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 67
SI
No
Potenti
al
Impact
Actions to be Followed Parameters for
Monitoring
Frequency
of
Monitoring
Location
1. Air
Emissio
ns
Ambient air quality
within the project site
from four corners.
PM10,PM2.5, SO2
and NOx
Seasonal At the four
direction of
the Project site
Good conditioned
vehicles shall be used to
ferry the rock fragments
by making minimum
number of trips from the
project site. Periodic
vehicular servicing shall
be carried out to limit the
vehicular emission within
the standard prescribed by
PCB
Systematic
maintenance of
Vehicle logs
Daily
Records
Main Entrance
The main source of the
dust emission is from
haulage road and quarry
site.
To minimize the dust
emission, periodic
maintenance of the
haulage road, sprinkling
of water along the haulage
road and the quarry site,
shall be carried out.
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 68
2. Noise Noise is mainly generated
from quarrying activities
and operation of heavy
machineryand vehicular
movements.
To minimise noise
disturbance the quarrying
operations shall be
restricted to day time,
vehicular movements
shall be minimised, the
drilling technology shall
be updated to the latest
and blasting shall be
carried out with
controlled mechanism and
green belt can be
developed which act as an
acoustic barrier for noise
transmission.
Spot noise level
recording during
and after
blasting.
Seasonal At the four
direction of
the Project site
3. Waste
water
and
solid
waste
dischar
ge
Waste water and solid
waste generated from the
domestic activity will be
disposed through septic
tanks and soak pits.
The quarry wash off will
be directed to the quarry
pit.
No untreated discharge to
be made to the surface
water, ground water or
soil.
No discharge
will be made in
to or in the
vicinity of water
courses.
Periodic
during
operational
phases.
-
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 69
4. Drainag
e
manage
ment.
Drains will be cut along
toe of the quarry faces to
divert the surface runoff.
Garland drain shall be
provided at the quarry top
to regulate monsoon -
storm water and direct the
same to the settling
ponds.
Visual
inspection of
drainage
mitigation
measures
Periodic
during
operation
phase.
-
5. Water
quality
and
Water
levels.
Used water and ground
water shall be monitored
for assessing the quality
and the ground water
level will be checked.
Comprehensive
monitoring as
per IS 10500
Seasonal 2 Ground
water &2
surface water
6 Energy
usage
Energy usage will be
minimised as possible.
Consumption of
conventional energy will
be reduced by utilising
renewable energy sources.
Energy audit
report.
Annual
audits and
periodic
checks
during
operational
phases
-
7 Emerge
ncy
prepare
dness
such as
fire
fighting
Assessment of fire
protection and safety
measures to take care of
fire and explosion hazards
and steps taken for their
prevention
Mock drill
records and
onsite
emergency
plans
Periodic
during
operational
phases
-
8 Mainten
ance of
flora
and
fauna.
Vegetation, green
belt/green cover
development
No. of plants,
species
Periodic
during-
operation
phase
-
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 70
9 Waste
Manage
ment
Implement waste
management plan that
identifies and
characterizes every waste
arising associated with
proposed activities and
which identifies the
procedures for collection
,handling and disposal of
each waste arising
Records of solid
waste
generation and
disposal.
Periodic
during-
operation
phase
-
10 Health Periodical Medical check-
up programmes
Training for workers
regarding occupational
hazards
Occupational
health checkup
As per the
mine act
-
6.5 Environmental control cost estimate
S. No. Description of item Recurring cost
(in lac)
1 Air Pollution Control - Water sprinkling 1.0
2 Water Pollution Control 1.0
3 Environmental Monitoring and Management 3.0
4 Green belt Development 1.0
Total 6.0
Additionally, 1% of annual profit shall be given to concerned Panchayat for Biodiversity
Management Committee toward eco-restoration.
Building Stone Quarry of M/s. Malabar Aggregates Pvt. Ltd.
Prepared by Metamorphosis Project Consultants Pvt. Ltd., Bengaluru/Trivandrum 71
7.1 CONCLUSIONS
It is predicted that socio-economic impact due to this project will positively bring prosperity
and improvements in physical and social infrastructure in the area. It will increase the chance
of more employment to local people. There is no resettlement and rehabilitation involved in
this project. Revenue of the state government and central government will be increased through
collection of various taxes. The entire project area is devoid of any endangered flora and fauna.
It is proposed to reclaim the land to a maximum possible extent by providing green belt in
refilling and surrounding areas. In addition to this 10% of the total area is converted to water
pond. Thus the proposed project is not likely to affect the environment or adjacent ecosystem
adversely.
***********