Draft, status per 6 March 2012 + modification of 20 March 2012
Page 1 of 23
Translation from the German
Building and Fittings Specifications Residential Units Chausseestrasse 121-122 Berlin-Mitte, formart Berlin-
Brandenburg
Building Specifications
Chausseestrasse 121-122
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 2 of 23
Contents
1.0 Basics ................................................................................................................... 4
1.1 General Details of Property ................................................................................... 4
1.2 General .................................................................................................................. 4
1.3 Alterations and special requests ............................................................................ 4
1.4 Insurance ............................................................................................................... 5
1.5 Basis of calculation of living space ........................................................................ 5
1.6 Initial infrastructural development .......................................................................... 6
1.7 Energy requirement and thermal insulation ........................................................... 6
2.0 Construction ......................................................................................................... 6
2.1 Foundation ............................................................................................................. 6
2.2 Outside walls ......................................................................................................... 6
2.3 Internal walls .......................................................................................................... 6
2.4 Ceilings .................................................................................................................. 7
2.5 Communal stairs .................................................................................................... 7
2.6 Balconies and other external construction elements.............................................. 7
3.0 Facade / Roof ....................................................................................................... 7
3.1 General .................................................................................................................. 7
3.2 Facade ................................................................................................................... 7
3.3 Windows ................................................................................................................ 8
3.4 Shutters / sun shades ............................................................................................ 8
3.5 Building entrance ................................................................................................... 9
3.6 Underground garage entrance ............................................................................... 9
3.7 Roof ....................................................................................................................... 9
3.8 Roof terraces / balconies ....................................................................................... 9
3.9 Ground floor terraces ............................................................................................. 9
4.0 Interior construction residential units .................................................................. 10
4.1 Living rooms, bedrooms and storage rooms ........................................................ 10
4.2 Bathroom / toilet................................................................................................... 10
4.3 Kitchen ................................................................................................................. 11
5.0 Interior construction cellar in individually owned property ................................... 11
6.0 Interior construction communal areas ................................................................. 12
6.1 Technical rooms and cellar aisles/gates .............................................................. 12
6.2 Underground garage............................................................................................ 12
6.3 Storage rooms for prams, pushchairs and wheelchairs; bicycle room ................. 12
6.4 Stairwells ............................................................................................................. 13
6.5 Exterior facilities................................................................................................... 13
6.6 Lifts ..................................................................................................................... 14
7.0 Miscellaneous ..................................................................................................... 14
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 3 of 23
7.1 Locking system .................................................................................................... 14
8.0 Building technical equipment .............................................................................. 14
8.1 Sanitary installations general ............................................................................... 14
8.2 Bathrooms and toilets .......................................................................................... 15
8.3 Kitchens ............................................................................................................... 16
8.4 Watering of exterior facilities ................................................................................ 17
8.5 Heating installation .............................................................................................. 17
8.6 Electrical installation and communications technology ........................................ 17
8.7 Ventilation to protect against moisture ................................................................. 21
9.0 Other general details .......................................................................................... 22
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 4 of 23
1.0 Basics
1.1 General Details of Property
The construction project Chausseestrasse 121-122 is located in Berlin-Mitte. It is an
infill construction with attached courtyard development.
The residential units being thus created will form part of a condominium comprising
approx. 88 residential and approx. 4 commercial units.
Access to the building is by four separate entrances. One entrance is located on
Chausseestrasse. The other entrances are reached via a passage from
Chausseestrasse to the courtyard. There are underground garages, tenants’ cellars
and rooms for technical equipment in the basement level. Four commercial units are
planned for the ground floor, while residential units are planned for the courtyard area
and on floors 1 to 6.
The building is constructed in a solid manner.
1.2 General
The plans adopted as an Annex to the Declaration of Division and these Building and
Fittings Specifications shall be definitive for the execution of the work.
The work shall take place in accordance with the accepted rules of construction
technology.
In accordance with the building permit applied for, the planning and construction of
the project shall be in accordance with the requirements of DIN 4109 in the current
version, ‘Noise Protection in Building Construction’, with Supplementary Sheet 1
thereto. Although the ‘Suggestions for Enhanced Noise Protection’ in Supplementary
Sheet 2 to DIN 4109 are not required for issuing the building permit, they shall
nonetheless be taken into account in the area of dividing walls and ceilings between
storeys where these are located between two immediately adjacent residential units
or next to communal areas or stairwells.
1.3 Alterations and special requests
A contact person will be available to the buyers to discuss any special requests with
regard to the feasibility of such requests and the costs involved. The hourly fees
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 5 of 23
payable to the planners involved and for consultation, preparation of quotes and
sampling will be assumed by the developer up to ten hours in total. The services of
the contact person may of course be used beyond this for an hourly rate of EUR 70
per hour plus 19 % VAT. The developer will then issue a corresponding invoice
irrespective of whether a special request is then realised by way of an order or not.
Additional special requests for fixtures and fittings may delay the completion of the
relevant residential unit. This would be notified at the time of providing the quote for
such work.
Sampling for the interior construction will take place in good time in the course of the
construction process with the firms involved in the construction work.
Certain work will require partition walls and drywall construction cladding in
accordance with the planners’ specifications. Such work will be carried out as needed
and in accordance with the physical building requirements.
Building fixtures which are not described in more detail will be carried out according
to the architect’s specifications and will be based on the building specification and in
compliance with the normal standard.
Items of fittings are drawn into the construction plans merely to show positioning
possibilities and as suggestions for furnishing.
Dimensions for fittings and fixtures should be taken exclusively from the building itself
and not derived from the plans.
1.4 Insurance
The developer will take out a construction and principal’s public liability insurance
policy to cover the entire period of the construction phase.
1.5 Basis of calculation of living space
The living space of a residential unit, based on the Living Space Ordinance (Wo FlV),
covers the ground area of the above-ground rooms belonging exclusively to this
residential unit. Balconies, loggias and (roof) terraces will be taken into account at
half of their respective floor area.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 6 of 23
Areas are calculated on the basis of the relevant planning documents, with the living
space being determined on the basis of the shell construction dimensions less a fixed
deduction of 0.5 % for plasterwork and 3 % for toilets and bathrooms.
Cellars are fitted for use as such, i.e. they are not suitable for residential purposes.
1.6 Initial infrastructural development
The building will be connected to the public supply networks for drinking water, waste
water, district heating and electricity.
Telephone: main connection in the building’s mains connection room, connection
including wiring within the residential units.
Broad-band cables (TV), connection including wiring within the residential units.
1.7 Energy requirement and thermal insulation
The thermal insulation of the building will be carried out in accordance with the
energy savings regulations in force at the time of filing the building permit application.
2.0 Construction
2.1 Foundation
The building will be founded in accordance with the structural requirements on a
foundation comprising a (reinforced) concrete base plate.
2.2 Outside walls
The building’s outside walls will be executed in reinforced concrete or sand lime brick
in accordance with structural specifications.
2.3 Internal walls
Load-bearing internal walls will be executed according to structural requirements in
reinforced concrete or sand lime brick in the relevant noise protection classification
and according to load-bearing capability. Non-load-bearing walls will be constructed
from plasterboard or as double-skinned stud walls.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 7 of 23
2.4 Ceilings
The ceilings from the basement level to the penthouse level will be in solid reinforced
concrete construction (locally poured concrete or prefabricated sections). The ceiling
thicknesses are as necessitated by the structural and building physics requirements.
The clear room height is normally approx. 2.80 m, in the attic level on
Chausseestrasse approx. 3.0 m, in the attic floor of the rear building approx. 2.85 m,
in the ground floor of the commercial units approx. 4.10 m, in the courtyard building
approx. 3.0 m and in the rear building approx. 3.70 m.
On the ground floor and on the upper floors the joints of the reinforced concrete
sections will be filled.
In the basement level, the underside of the reinforced concrete ceiling will remain
untreated; some parts will be insulated as required from a constructional point of
view.
2.5 Communal stairs
The stairways in the stairwells will be soundproofed and constructed in reinforced
concrete.
2.6 Balconies and other external construction elements
Balconies and other external construction elements will be made in a reinforced
concrete and steel construction. Design will be in accordance with the material and
colour concept of the architect.
3.0 Facade / Roof
3.1 General
The building will be thermally insulated in accordance with the energy savings
regulations in force at the time of issue of the building permit.
The design of the facade and roof will follow the architect’s plans.
3.2 Facade
The facade will have a linked thermal insulation system, and will be plastered in a
light colour. The elevated basement level on Chausseestrasse and if need be on the
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 8 of 23
north-west facade will be executed in natural stone or clinker. The architect is
responsible for selecting materials and colour design.
3.3 Windows
Windows and balcony doors pertaining to the residential units will be executed as
wooden windows, wood type Meranti, with multi-layer lamination and open-pored
glaze (colour in accordance with architect’s plan). Glazing will be as instructed by the
building physicist. Window rebate ventilators and air inlet elements will be fitted
(where technically necessary) as per the ventilation concept.
The floor level elements allowing access to terraces and balconies will be made from
slip-proof titanium-zinc sheeting with corresponding seals.
External window sills will be made of powder-coated aluminium and will be given an
anti-drumming noise coating if required.
Single casement windows and balcony doors will have turn-and-tilt fittings, while
multi-casement windows will have at least one turn-and-tilt casement. French
windows will as a matter of course be fitted with a turn-and-tilt casement and a railing
in front of them made of galvanised steel as per the architect’s plan.
The ground floor windows and terrace doors can be locked and will be fitted with
mushroom head locking points.
All windows will be fitted with stainless steel handles (brand: Hoppe Amsterdam or a
product with comparable features).
Windows in the basement level will be plastic-framed turn-and-tilt windows or steel
windows with steel frames. If they are located below ground level, plastic light shafts
(made by Mea, or a product with comparable features) with steel grating capable of
being walked on will be fitted.
3.4 Shutters / sun shades
Shutters may be fitted later for all residential units as a special request feature.
Windows proven to require sun shades will be fitted with plastic external roller blinds
in the insulation layer.
Any blinds that need to be fitted on the ground floor will be fitted in such a way that
they cannot be pushed up, awnings on the sixth floor that slide out horizontally.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 9 of 23
3.5 Building entrance
The building entrances comprise an aluminium-frame door with a glazed element.
The doors will be triple-locking with stainless steel fittings.
The letterboxes will be accommodated in the relevant entrance hallways.
3.6 Underground garage entrance
The underground garage will be accessed from Chausseestrasse via a heated
access ramp. A motorised door system will be installed which can be opened and
closed from inside and outside by remote control.
3.7 Roof
The roof construction is made of reinforced concrete as per structural plan with
insulation in accordance with the building physicist’s specifications.
The roof will be sealed with plastic roof sealing sheeting in accordance with technical
requirements. The attic covering consists of unweathered titanium zinc. Water is
drained from the roof via externally and internally mounted drain pipes.
3.8 Roof terraces / balconies
Balconies and roof terraces will be made of reinforced concrete, with the underside of
the ceilings being given a layer of white paint. They will be sealed as required.
The floor covering consists of weather-resistant bankirai hardwood floorboards or a
product with comparable features as per the architectural plan. Any surface water
(rainwater) will be drained off via a drain let into the floor and rainwater drainpipes.
Railings will be welded and powder-coated steel constructions.
If necessary, sight partition screens consisting of a steel frame with filling will be fitted
in accordance with the architectural plan.
Lights, which must be installed by the buyers, can be connected to a lighting
connection.
3.9 Ground floor terraces
Ground floor terraces will be given a covering consisting of weather-resistant bankirai
hardwood boards or concrete terrace panels.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 10 of 23
If necessary, sight partition screens consisting of a steel frame with filling will be fitted
in accordance with the architectural plan.
Lights, which must be installed by the buyers, can be connected to a lighting
connection.
4.0 Interior construction residential units
4.1 Living rooms, bedrooms and storage rooms
All living rooms, bedrooms and storage rooms and hallways will have a floating
screed with footstep damping and thermal insulation as indicated by the building
physics requirements. These rooms, like the open kitchens, will also be provided with
a prefabricated full-floor parquet (natural oak, wear layer at least 3.5 mm thick, oiled)
according to the architect’s sample. There will be a skirting board where it meets the
wall.
The walls will be plastered or rendered and papered with paint substrate and painted
white.
As necessitated by the specialist planning, plasterboard suspended ceilings will be
fitted.
Interior doors in the residential units will be tubular chipboard doors, approx. 1.01 m
or 0.76 m respectively wide, of the brand WIRUS Optima 30 or a product with
comparable features (clear height approx. 2.22 m), with white-coloured coating (RAL
9010) with matching composite wood surrounds (with rubber profile lip seals). All
doors will have an undercut and a handle of stainless steel (made by Hoppe,
Amsterdam, or a product with comparable features) with a ward lock and one key
each. Each residential unit will also have one door with a glass panel, in accordance
with to the architectural plans.
4.2 Bathroom / toilet
Bathrooms and toilets will have a floating screed with footstep damping and thermal
insulation as indicated by the building physics requirements.
These rooms will have non-slip floor tiles according to the architect’s sample (30 x 60
cm) (net material price € 30 per m² according to dealer’s list).
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 11 of 23
In the shower area, the walls will be approx. 2.0 m high, and in the area of the toilet,
the wash basin and the bath tub approx. 1.20 m high and tiled (30 x 60 cm)
according to the architect’s sample (net material price € 30 per m² according to
dealer’s list). The other walls will be plastered or rendered and papered with paint
substrate and painted white.
The undersides of the ceilings will be papered with paint substrate and painted white.
As necessitated by the specialist planning, plasterboard suspended ceilings will be
fitted.
The doors will be tubular chipboard doors of the brand WIRUS Optima 30 or a
product with comparable features with white-coloured coating (RAL 9010), with
matching composite wood surrounds (with rubber profile lip seals). They will have an
undercut or a ventilation mesh, and stainless steel toilet fittings (brand Hoppe
Amsterdam or a product with comparable features) with a ward lock and one key
each.
4.3 Kitchen
All kitchens will have a floating screed with footstep damping and thermal insulation
as indicated by the building physics requirements. They will be provided with a
prefabricated full-floor parquet (natural oak, wear layer at least 3.5 mm thick, oiled)
according to the architect’s sample. There will be a concave skirting board,
alternatively a straight skirting board, where it meets the wall.
The walls will be plastered or rendered and papered with paint substrate and painted
white.
The undersides of the ceilings will be papered with paint substrate and painted white.
As necessitated by the specialist planning, plasterboard suspended ceilings will be
fitted.
5.0 Interior construction cellar in individually owned
property
The floor will be smoothed concrete or a screed will be applied on a separation layer.
This will be covered or a coating of abrasion-proof paint will be applied as per
technical requirements.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 12 of 23
The ceiling will be concrete, the walls concrete or pointed brick. The walls will have a
coating of washable paint and the ceiling will be painted in white emulsion.
Cellar partition walls will be light metal partition walls (galvanised) (height approx.
2.10 m), of the Käuferle UTS Type S system or a product with comparable features.
6.0 Interior construction communal areas
6.1 Technical rooms and cellar aisles/gates
The floor will be smoothed concrete or a screed will be applied on a separation layer.
This will be covered or a coating of abrasion-proof paint will be applied as per
technical requirements.
The ceiling will be concrete, the walls concrete or pointed brick. The walls will have a
coating of washable paint and the ceiling will be painted in white emulsion.
Cellar aisles and gates will have self-locking doors, if need be fire doors if required
under the fire protection plan. The surface will be painted in silk matt (RAL 9010 pure
white or as specified by the architect). Fittings will be aluminium (plastic coated).
Doors will be marked with clear text labels (foil print).
6.2 Underground garage
The floor of the underground garage will be built in accordance with structural
requirements. The parking spaces in the underground garage will be separated by
coloured markings. All parking spaces will be marked with a number. Access to the
parking spaces will be gained directly via the stairwells and lifts via the basement
level.
Support pillars will be concrete, walls will be concrete or pointed brick. These building
elements will be painted white and will have a base cladding approx. 30 cm high as
required.
Ceiling undersides will be untreated concrete, with sound damping fitted as required.
The undersides will be painted white.
6.3 Storage rooms for prams, pushchairs and wheelchairs; bicycle room
A screed will be applied on a separation layer on the concrete floors. A coating of
abrasion-proof paint will be applied as per technical requirements.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 13 of 23
The ceiling will be concrete, the walls concrete or pointed brick. The walls will have a
coating of washable paint and the ceiling will be painted in white emulsion.
6.4 Stairwells
On the concrete floors of the landings and hallways, a screed will be applied on an
insulation or separation layer (as required). The covering will be natural stone (e.g.
Padang or a product with comparable features) or artificial stone as the architect
chooses. The steps of the stairways will be covered in the same material. A matching
skirting board will be fitted.
Walls and ceilings will be plastered or rendered and painted (to match the architect’s
colour concept). Undersides of stairs (prefabricated concrete elements) will just be
painted.
Entrance doors to residential units will be solid core doors (clear height approx. 2.22
m) with a smooth painted surface and a steel frame (colour as per the architect’s
colour concept). They will have a retractable bottom seal and a spyhole. For security
reasons, they will be fitted with a triple locking mechanism and a security profile
cylinder lock incl. steel cover.
The doorbell buttons for the apartments with integrated name plate will be placed
next to the entrance doors.
Banister rails will be painted steel railings (colour per architect’s colour concept).
In the entrance hall to the building, a doormat will be placed as a cleaning zone
according to the architect’s specifications.
6.5 Exterior facilities
External areas will be filled with appropriate ground material and the planting area
covered with topsoil.
The exterior facilities will be laid out in accordance with the landscape architect’s
plans. The green area will be planted with indigenous plants and materials.
Parts of garden that are individually owned will be sown with lawns and will be fenced
in in accordance with the architect’s plans.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 14 of 23
The access footpaths to the buildings will be lit with mast lights and bollard lamps
(with dimming switch and timer clock). The other paths will be lit in accordance with
the open area plans.
The existing fire wall on the neighbouring property will, in consultation with the owner
of the building, be refurbished to have an attractive optical appeal.
6.6 Lifts
Stairwell 1 will have a steel lift. Stairwells 2 – 4 will have glass lifts. The lift entrances
will be fitted with lift doors.
A stainless steel handrail and a clear control panel will be mounted. The floor
covering will match the adjacent stairwell in front of the lift.
An emergency call system with intercom will be installed in the lift.
7.0 Miscellaneous
7.1 Locking system
A central locking system will be installed so that each resident needs only one single
key for the entrance doors to the house and their apartment, the underground
garage, the cellar sector and all doors to the communal property.
Only the caretaker and technical staff will have access to the technical rooms (energy
relay station, meter room, etc.).
8.0 Building technical equipment
8.1 Sanitary installations general
The building will have a water connection to the local water supply mains in the
building’s connection room.
Household water will be heated centrally.
Consumption will be measured via the water meters for cold and hot water mounted
flush in the plastering in each residential unit. The meters are leased.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 15 of 23
Waste water pipes will be made of moulding, SML or PVC and will be laid with
sufficient drop. Raising facilities will be installed as required by the building technical
systems plans.
As far as necessary, the supply and disposal pipes for the residential unit will be laid
in suspended ceilings and under the screed flooring in the storeys. On the residential
floors, the pipes will be run through soundproofed ducts.
In the basement level the pipes will be uncovered. All fixing points will be acoustically
decoupled.
Internally-located bathrooms and toilets will be ventilated via ventilators via the roof.
Ascending pipes that can be shut off will be installed in the basement level.
Water supply and drainage pipes will be mounted above the plaster in the basement
level. If necessary, the pipes will be thermally insulated and insulated against
condensation water. In areas susceptible to frost an electric pipe-heating system will
be installed.
8.2 Bathrooms and toilets
Toilets
WC
Deep-flushing toilet including wall-mounted cistern will be wall-mounted with pressure
plate in Geberit Samba (white) and toilet seat. Makes as per successive
specifications or a product with comparable features.
WC: Villeroy & Boch, Subway 2.0
Seat: Villeroy & Boch
Cistern: Geberit with water saving flush
Wash basins
Wash basins will be fitted with chrome single tap armatures, makes as per
specifications or a product with comparable features.
Wash basin: Villeroy & Boch, Subway 2.0
Mixer armature: hansgrohe Talis S² with pull-up knob, rod and drain fittings
Bathrooms
WC
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 16 of 23
Deep-flushing toilet including wall-mounted cistern will be wall-mounted with pressure
plate in Geberit Samba (white) and toilet seat. Makes as per specifications or a
product with comparable features.
WC: Villeroy & Boch, Subway 2.0
Seat: Villeroy & Boch
Cistern: Geberit with water saving flush
Wash basins
Wash basins will be fitted with chrome single tap armatures, makes as per
specifications or a product with comparable features.
Wash basin: Villeroy & Boch, Subway 2.0
Mixer armature: hansgrohe Talis S² with pull-up knob, rod and drain fittings
Bathtubs
Makes as per specifications or products with comparable features will be installed.
Bathtub: Kaldewei Saniform (white), Excenter drain fittings
Bath and single-lever mixer shower armature set: hansgrohe Talis S² and hand-held
shower head with wall mounting
Shower fittings
Showers will have a shallow shower basin (sanitary acrylic). All armatures will be in
chrome. Makes as per specifications or products with comparable features. Shallow
shower basin: Kaldewei Superplan 900 x 900 mm. The size of the shower may vary
according to architectural plans.
Shower set: hansgrohe Talis S² with metal shower hose, universal wall mount or wall
bar (approx. 90 cm long) and hand-held shower head,
Single-lever mixer: hansgrohe Tallis S²
Shower screens are not included.
8.3 Kitchens
Chrome angle valves are provided for one cold water and one hot water connection
in each kitchen.
Laying water supply and drainage pipes in the residential unit from the supply duct is
the responsibility of the buyer.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 17 of 23
8.4 Watering of exterior facilities
Water delivery points with frost-proof shut-off taps will be provided at suitable points
for watering the communal exterior facilities.
All ground floor residential units with a garden share and attic apartments with roof
terrace shares will have a water delivery point with a tap with screw-thread for
attaching a hose, consumption being metered via the residential unit’s water meter.
Frost-proof taps will be installed.
8.5 Heating installation
The building will be heated with a central system with distance heating in accordance
with building physical calculations.
Where technically necessary, the developer will, however, have the right to select an
alternative heating system.
Heat will be distributed via ducts installed in the building. Heating costs will be
determined by means of thermal energy quantity meters. One meter will be installed
in a distributor box in each residential unit.
A rental and maintenance contract will be entered into on the owner’s behalf for
leasing the consumption metering equipment. The costs will be borne by the
condominium.
Floor heating will be provided in living rooms, kitchens and bathrooms (except in
internally-located storage rooms). The temperature will be regulated room-by-room
using electronically-controlled thermostats. Guest toilets and halls will not be
regulated.
All bathrooms and showers will also be fitted with a heated towel rail of Zehnder
Forma brand or a product with comparable features (RAL 9010 pure white) with a
thermostat valve.
If necessary, the stairwells will be heated with panel radiators with thermostat valves.
8.6 Electrical installation and communications technology
Building connections will be provided in accordance with the terms and conditions of
the local providers.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 18 of 23
The entire electrical system will be installed in compliance with VDE [Association of
German Engineers] regulations or DIN [German Industry Standards]. All wiring in the
residential storeys will be laid under plaster. Installations in the basement level will be
laid above the plaster.
Each residential unit will have a video intercom with a colour monitor (Ritto or a
product with comparable features). Doorbells and intercom speaking points will be
provided at the building entrance. There will also be a doorbell outside each
apartment door. The intercom with door-opener button and signal bell will be installed
inside each residential unit near its entrance door. An additional doorbell panel will be
provided in front of the passageway for entrance doors in the courtyard.
Each residential unit will have a sub-distribution box and will be provided with
sufficient circuits for plug sockets and lights. There will also be separate circuits for
the dishwasher, the stove and the bath.
The switches in the residential units will be Merten M Plan or a product with
comparable features (colour pure white).
The following areas will be fitted as follows:
Master bedroom
2 toggle switches with ceiling lighting point
2 double plug sockets
1 triple plug socket
1 single plug socket (flush with plaster below light switch
1 telephone socket
1 aerial socket
Other bedrooms
2 switches with ceiling lighting point
1 double plug socket
1 triple plug socket
1 single plug socket (flush with plaster below light switch
1 telephone socket
1 aerial socket
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 19 of 23
Living / Dining room
3 toggle switches with ceiling lighting point
2 double plug sockets
1 triple plug socket
3 double plug sockets
2 single plug sockets (distributed around room)
1 telephone socket
1 aerial socket
Kitchen
3 switches with ceiling lighting point
1 stove connection (AC, separate fuse)
1 oven connection (AC, separate fuse)
1 plug socket for extractor hood (only air circulation mode)
1 plug socket for dishwasher (separate fuse)
1 plug socket for microwave
1 plug socket for refrigerator
1 plug socket for work surface lighting (wall-mounted cupboard)
3 double plug sockets in working area
3 single plug sockets
Bathroom
1 switch with ceiling lighting point
Single plug sockets in the wash basin area
1 double plug socket
2 switches with wall lighting point (for mirror light)
1 plug socket next to towel heater rail
Toilet / Shower (separate)
1 switch with ceiling lighting point
1 switch with wall lighting point (for mirror light)
1 single plug socket
2 single plug sockets near wash basin
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 20 of 23
Hallways
2 toggle switches with ceiling lighting point
3 single plug sockets
1 speaking point (for intercom)
1 three-row terminal for apartment under plaster
1 single row low-voltage terminal under plaster
1 telephone socket
Balconies, terraces, roof terraces
2 switches with wall / ceiling lighting point according to building technical
systems plan and architectural plan), switch indoors with control light
1 humidor plug socket (can be switched off from inside room)
3 humidor plug sockets (only roof terraces)
Private cellars (metered via apartment meter)
1 switch with ceiling lighting point
2 plug sockets (can be switched off at sub-terminal)
Other rooms (e.g. storage room)
1 switch with ceiling lighting point
2 double plug sockets
Underground garage
The underground garage is lit by fluorescent lighting (light intensity in compliance
with the Underground Garages Ordinance). The escape routes and signs are lit in
compliance with the current safety standards in force and the fire protection plan.
Entrances and exterior facilities
An adequate number of lights, the positioning and number of which is in accordance
with the landscape architect’s specifications, is planned for the external facilities and
will be controlled by motion detectors and dimmer switches.
The light switches are located in the entrance area on the doorbell panel and time
switch clock.
Stairwells
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 21 of 23
The electrical plans provide for lighting in the stairwells in the required number with at
least one switch on each floor, linked by automatic timer.
In the basement level, fluorescent lighting with motion detectors will be installed in
accordance with the building technical system plan.
Escape route lights will also be installed in accordance with the fire protection plan.
Bicycle rooms
Ceiling lights (fluorescent lighting) with motion detectors will be installed.
Cellar aisles
Cellar aisles will be provided with energy-saving lighting with switches and automatic
timer system.
8.7 Ventilation to protect against moisture
The internally-located bathrooms and guest toilets will each have air extractor
ventilators as individual room ventilators in line with the features of the guideline
brand Helios. Connection to vertical ventilation shafts integrated into the installation
ducts, fed out over the roof in compliance with fire regulations. Decentral ventilation
system. Air replaced via suitable external air inlets. The minimum flow volume of air
constantly being extracted in accordance with DIN 18017 Part 3 permanently
guarantees ventilation to protect against moisture in accordance with DIN 1846 Part
6. The arrangement of the external air inlets in the form of self-regulating window
pane ventilators, air inlet elements in window panels or frames or air ducts integrated
into external walls therefore takes places evenly in all living rooms and bedrooms.
The internal doors in the residential unit will have undercuts to allow air to circulate.
The basic ventilation to control moisture, which is user-independent, operates
automatically 24 hours per day, while ventilation as needed will be switched when
sanitary facilities are being individually used by a fully automatic, moisture-activated
control system. Technical ventilation measures in accordance with specialist
planner’s ventilation plan.
Buyers’ kitchen extractor hoods must be used in air circulation mode. There will be
no separate wall ducts to the outside.
Draft, status per 6 March 2012 + modification of 20 March 2012
Page 22 of 23
The underground garage will be ventilated and aired in accordance with the
requirements of construction law and/or in accordance with the stipulations of the
safety concept.
Stairwells will be aired via the windows as far as possible. Smoke extraction will take
place as required.
9.0 Other general details
Consumption-related meters such as water meters and electricity meters will be
ordered in due course by the buyers at their own expense from the relevant
providers.
Thermal energy meters are not part of the scope of services and will be leased by the
building management for individual residential units and taken into account in the
statement of account for the operating costs.
Licence fees etc. for radio and television reception must be paid by the buyer.
Because of residual moisture in the residential units and possible slight settling of the
building, hairline cracks may develop. To the extent that these do not exceed the
tolerances prescribed under DIN, they do not represent material defects.
It is not advisable to store items which react sensitively to damp in unheated cellar
rooms due to damp from the initial phase of the construction period which is only
slowly drying out. The drying of washing in the cellar air may in particular be of limited
effectiveness in this phase.
All acrylic and / or silicon seals are maintenance joints and require regular,
professional care by the buyer.
For safety reasons, visits to the building site will only be possible by prior
appointment with the site supervisors and accompanied by them, subject to
compliance with safety regulations such as the wearing of safety shoes, hard hats,
etc. Insurance cover for visits to the building site is a matter for the visitor to the
building site.