Upload
others
View
10
Download
1
Embed Size (px)
Citation preview
Leeds Arena – BIM Time-line
April 2010
Appointed Preferred Bidder
Design Currently 2D
No BIM Requirement
April 2010 to March 2011
Tender Second Stage
Design starting to be developed in 3D
2D Design still being under taken
No BIM Requirement
March 2011
Contract signed
No BIM Requirement
April 2011
BAM Decision to trial BIM on Leeds Arena
- Fabrication Model
Arup M.E.P
Revit 3D
Arup –
Structures –
Revit 3D
Arup 3D Civil
Populous – Rhino
3D & Microstation
2D
Steel – FEL –
Telka 3D M&E – Rotary –
CAD Duct 3D
Precast –
Creagh –
Tekla 3D
Glazing
Contractor 2D
Other design
subcontractors
3D & 2D
• Lifts
• Escalators
• Metalwork
• etc
Envelope –
Lakesmere –
3D DWG
Design Data Model
BAM model co-ordination
Populous Secondary Steel Model FEL Steel Model
Combined Model Lakesmere Stub Model
Example of Supply Chain Design Coordination
Temporary Propping to Wing Wall Edge Protection to Metal Deck Areas
Handrail locations for temporary and Permanent Schemes High Level Duct, Gantry & Steel Coordination
Zero Harm by design
Initial Concrete roof and external Cladding Sequencing
Precast Wall Slabs
Roof decking erection
Roof Truss erection
From the 3D Model it is clear that we need to remove steel to allow the unit to be erected in place
Steel highlighted in Blue is to be left out during Steel erection
ESCALATOR LOCATION
Installation Methodology
Escalator lifted into position from ground floor by means of A frames supported on existing structural steel above
Installation Methodology
Handover & Aftercare
• Snagging & Handover
• O&M Manuals
• Field BIM
• Defects management
• Lifecycle