Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Building Design Management
Colin Gray and Will Hughes Department of Construction Management & Engineering,
The University of Reading. UK
UTTERWORTH EIN EMA NN
LLRC
OXFORD AMSTERDAM BOSTON LONDON NEW YORK PARIS SAN DIEGO SAN FRANCISCO SINGAPORE SYDNEY TOKYO
Contents
Preface
Introduction
Part One: Design Management Theory
Chapter 1 - Management and organization in design and construction
1.1 Organizational issues
1.2 Environment
1.3 Complexity
1.4 Approaches 10 collaboration
1.5 Conclusions
Chapter 2 - The process of building design
2.1 The characteristics of design
2.2 The nature of the bui lding design problem
2.3 Strategies for solving problems in des ign
2.4 Constraints on the design process
2.5 The drawing process is an essential part of designing
2.6 Summary
Chapler 3 - The process of engineering design
3.1 The scale of the task
3.2 Design practice
3.3 Technology. quality standards and infomlation
3.4 Summary
7
8
9
11
20 23
24
24 27
28 30
3 1
31
33
33
33
35
41
vi Contents
Chapter 4 - Stages, roles and responsibilities
4.1 Streams of activity
4.2 Project and decision stages
4.3 The 'wheel of dominance'
4.4 The network of management
4.5 The effect of procurement options
4.6 Liability
4.7 Summary
Chapter 5 - People and organizations
5.1 Selection processes
5.2 Management of the multi -organizational project
5.3 Compatibility in the multi-organization
5.4 Agreements
5.5 Summary
Part 1\vo: Design Management Practice
Chapter 6 - Tactics for developing a project culture
6.1 Effective communication
6.2 Collaboration
6.3 Technology clusters
6.4 Developing a unified team
6.5 Stan-up meetings
C hapter 7 - Defining the tasks
7.1 Gelling ll taned
7.2 Statement of need
7.3 Business case
7.4 Functional brief
7.5 Concept and scheme design
7.6 Engineering design
7.7 Control of interfaces
7.8 Complete infonmuion fit for purpose
Chapler 8 - Managing information production
8.1 Co-ordination of infonnation and approval of inputs
8.2 Review of design input
43
45
45
49
50
53
55
56
57
57 60
66
68 70
73
73
74 75 79
80
89
90
91
95
96
106
106
109
116
118
119
120
8.3 Computer-aided design
8.4 Issuing infonnalion
8.5 Drawing control
Chapter 9 - Evaluation of information
9.1 Design reviews
9.2 Value engineering
9.1 Buildability
9.4 Hazardous operations
9.5 Life cycle cost
9.6 Maintenance
9.7 External maintenance
9.8 Services maintenance
Chapter 10 - Planning, monitoring and control
10.1 Methods of programming
10.2 The development of an ana lyt ical design planning tool (ADePT)
10.3 Work package design and procurement control
lOA Cost planning and comrol
10.5 Control of change
10.6 Meetings and decision control
Chapter 11 - Design management in action
11.1 The business case
11.2 Outline design
11.3 Scheme design
11.4 Consultant's detailed de!>ign
11.5 Procurement
11.6 Speciali st's detailed design
11.7 Construction
11.8 Final comments
Glossary
References
Index
Contents vii
12 1
122
121
126
126
127 128
129
129
112
III 131
135
135
140
141
144
146
149
152
154
155
157
159
160
16 1
161
164
165
168
173
Index
Activity. streams of, 45 Agreements, see Contracts Analytical design planning tool. 140- 1 Approval. see Design, inputs. approval of Architect. role of, 1-2 Architectural practice. organization of,
62-3 Assembling the team, 58-70 Assembly, 65
Bar charts, 136 Bauhaus. 40 Boundaries, inter-organizational. 66 Brief:
briefing, 65,82,90 dcvelopmcnI of, 45 functionaL 96-8 standard documents. 104-6
Buildabilily, 128-9 Business case, 95-6 Business cycles, 90
Change control , see Control. change Checklists:
1 Action by project initiator. 81 2 Briefing stage start-up meet ing. 83
3 Engineering stage start-up meeting. 85
4 Working party's fi rst meet ing. 91 5 Initial review meeting, 92 6 Infomlation for the statement of
need. 93-4 7 Options stage. 95 8 Functional brief. 97 9 Typical standard brief provision.
105 10 Scheme design. 107-8 II Engineering design, 110-6 12 BuildabililY. 130 13 Hazardous operations. 131 14 Life cycle cost analysis. 132
Client. 1-3, 13-20. et IXlssim.
Clusters. :>'ee Technology clusters Collaboration, 20-23. 58, 74-5 Co-location. 79-80 Commitment. 79 Communication, 15- 16,60,63-4,73-4 Compatibility, organizational. 66 Competence, 34 Complexity. 1, 11-20, 35. 39, 74, Component. 35. 38 Conflict management. 19-20 Confrontation , 19
174 Indell
Construction (Design and Management) Regulations. 119
Constructivism. 40 Consultanls:
roles of. see Roles selection of. 58-9
Contmct: general. 52 designer. 68-70 main contractor. 52 specialist. 60
Control: general. 19-20. 135-51 change. 146-9 cost. 144-6 decision. 149-51 procurement, 141-4
Construction. see Stages. construction Controversy, 19-20 Convention, 34 Co-operative design. 3 Co-ordinating Commillee for Project
Information. 118-9 Co-ordination, 16-18
see Information. co-ordination of Cost effectiveness, 38 Cost planning. see Control, cost Craft. 34
Decisions. 45 Delegated direct output. 62 Design:
art. as. 25-26 characteristics of, 24-7 computer-aided. 121-2 concept. 106 constrainls, 30- I creativity. 24. 26-7 detai ls, 33-4, 37. 65 development. 147 drawing. role of. 31 engineering. 33-42, 65. 106-9 industrialization of. 2 inputs. approval of. 119-20 inputs, review of. 120-1
nalUre of. 27-8 philosophy. 20 process. 140 relationship with management, 3 reviews, 126-7 scheme, 106 techniques. 30
Design management: function of. 2 in action. 152-64 need for, 43 practice. 73-164 process map, 153 theory. 7 - 70
Design manager. see Roles. design manager
Design team: involvement of. 49 selection. 65
Design-construction interface. 49. 68 Designer:
motivation of, 25 liabili ryof. 119 selection of, 58
Detail, level of. 42 Differentiation, 14-16,20 Drawing:
generally, 31 control, 123-5 co-ordination, 120 demand for. 2 number of. 39
Engineering. see Design. engineering Environment:
control of. 17-18 see also Organization. environment of
Fitness for purpose. 55 Fragmentation. 12-14 Functional brief. see Brief, functional Functional depallmenls. 65
c
Globalization, 34 Group size. 66
Hazardous operations, 129 Health and safety law, 67 Hierarchy, 17
Industrialization. 39 1nfonnation:
generally. 35-42 accuracy, 3 completeness of, 116-7 co-ordination of, 3. 119-20 evaluation of. 126-34 issuing. 122-3 managing production of, 11 8-25 processing. 18 requests from site. 147 ~chcdules, 137-8 systcms. 18
Integration, 15-16,64,77-9 Interfaces:
control of. 109-16 Inter-finn networks, 21-22
Japan, 37 Jargon, 64 Joint Contr.tcts Tribunal 98. 52
Languagc, 64 Lmeral relations. 18, 66 Leadership. changing pattem of. 47-8 Liability. 55-6 Life cycle cost, 129-32 Location, 77
Maintenance, 132-4 Management:
definition of, 8 design. influence on, 7 hierarch ies of. 61
levels of. 60 network. of. 51-2 organization, compared. 8 related to design. 3 separate task, as :to 7 structure of, 60
Manufacturing, 34 Materials science. 34 Meetings, 149-5 1 Metaphors, 64 Modemism. 39 Monitoring. 135-5 1 Multi-organization. 60
Neo-vemacular, 39 Network analysis, 136
Objectivity. 12 see also: Rationality
Organization: appropriateness of. 10 boundary. 9 contingency theories. 8-9 definition of. 8 environment of, 9-11 environmental fit, II environmental scanning. 10 management, compared. 8 structure. 58 temporary. 8-9
Out-soureing, 21
Partnering. 21 Planning. 17 Planning. 135-5 1 Post-modem ism, 39 Prefabrication . 1 Problem-solving:
group size. and. 66 strategies. 28-30
Procedures, 17
Index 175
Procurement control , see Control, procurement
•
176 Index
Procurement schedule, 136 Procurement system:
general, 46-7. 52-4 construction management. 53 design-and-build, 38 design-and-manage. 53 general contrJcting, 53 management contracting. 53
Product differentiation. 36 Professionalism. 12 Programming. methods of. 135-9 Project:
initiation of, 89-90 cuhure. 73-88 design office. 79-80
Project stages. see Stages
Quality: standards, 35-42
Quality function deployment. 101 - 4
Ralionality: generally. 12 excessive rationality. dangers of. 8
Relationships. inter-fInn, 67-8 Repetition, 38 Resources. 67 Responsibilities. 43-56 Risk. apponionment of. 69 Risk-taking. 38 Roles:
generally, 43-56 co-ordinator, 19 cost adviser. 144 fragmentation of, 13 progressive reduction of. 20 institutionalization of, 7-8 integrator, 19 design manager. 7-8. 19.23.25.32.
61,70,87,90,96,119,121,123, 147
project manager, 11. 15.44,46.49-52. 70,75,80,82,84,86-8, 119, 121, 123,144,146. 154-5, 163
specialist contractor: genemlly, 49. 65, 67 involvement of, 74 selection of. 58-60
specialist designer. I
Salisficing. 27 Scheme design, 84 Self-contained units, 17 Sign-ofT points. 43-4 Simplicity, 38 Skill and care, 55 Skills. 77 Slack resources. 17 Specialist knowledge. 64 Specialization. 12- 14,52.74 Stages of work:
generally, 43-56 briefing. see Brief, business case. 154-5 conceptual and scheme, 45 construction. 163-4 consultant's detailed design, 159-60 engineering design. 46, 84 getting staned. 90 outline design. 155-7 procurement. 160- 1 scheme design, 84, 157-8 specialist's detailed design, 161 -3
Standard briefing documems, see Brief. standard documents
Standardization. 17.36.39 Stan-up meetings:
generally, 80-8 agenda for, 86 design manager's role. 87 organizing, 88 structure. 86
Statement of need , 82. 91 -5 Strategic alliance. 21 Sub-contracting, 53 Subjectivity, 12 Supply chain man:lgement. 21-2
Task autonomy, 18 Tasks. definition of. 89-117 Team building. 58-70. 77. 79-80 Teamwork. 73 Technology, 11, 14,34 Technology clusters, 75-9 Tolerances. 40 Tort, 55 Traditional approach:
inadequacy of, 23, 69 Transact ion cost econom ics, 21
USA, 37
Value engineering, 127-8 Value management, 98-101 Variations. see Control, change
Wheel of dominance, 49-51 Whirling, continuous, 29 Work package design , 141-4 Working party brief. 89- 90
Zones, 108- 16
Index 177