22 BUILD 120 October/November 2010 BUILD RIGHT FORMWORK Many builders have had a concrete and formwork failure that they would rather forget. It’s an area of construction where listening to the wisdom of experienced tradespeople is vital, but the following pointers may also help. By Des Molloy, Freelance Technical Writer, Golden Bay T he construction of formwork is taken for granted by all except those doing it. It is difficult to find information about it – there is no mention in the Building Code, no New Zealand standard to follow (Australia has AS 3610), no ‘how to’ pamphlets in the local merchants’ shelves and of course there is usually no lasting monument to well constructed examples. Finishing carpenters often take the glory when a job is being reviewed, yet the work of the person doing the formwork is equally vital in producing a quality result. Need to be able to build and unbuild The design and build of formwork is usually done by site staff. Unless a proprietary system is being used, it is up to the carpenters on site to plan how to build and support the formwork, and also how to unbuild it. Being able to strip the formwork effectively is an important part of the task. Building formwork is something that is best learned by listening and working alongside more experienced tradespeople. Learning only by experience can result in failures along the way. Huge forces to consider Wet concrete exerts huge forces against the forms. The concrete and reinforcing together weigh approximately 2.4 tonnes/m 3 . Lateral forces are generated in walls creating horizontal bursting pressures, which are increased by Figure 1: Foundation wall formwork – low walls. Figure 2: Foundation wall formwork – walls up to 2 m. Note: 1. Formwork may be either plywood or timber. Plywood is more suitable where a fair-face finish is required. 2. Pegs and plate beside trench should be in place before digging the trench. (If driven after trenching, pegs may cause the side of the trench to collapse.) Note: Double waling and she-bolts may be used to tie the top of the wall together. Note: 1. Formwork may be either plywood or timber. Plywood is more suitable where a fair-face finish is required. 2. Pegs and plate beside trench should be in place before digging the trench. (If driven after trenching, pegs may cause the side of the trench to collapse.) place outside formwork; excavate trench; place steel – erect inside formwork cleat packed off form to keep formwork apart, support reinforcing and holding down bolts and allow trowelling packing (dotted) to form rebate for concrete slab floors double brace – base of boxing is too close to trench edge to peg peg 150 x 50 mm plate boxing constructed of 150 x 25 mm boards closely butted trench outline form ventilation openings in walls that have a suspended floor over pegs to hold base of shutter in place brace at 1200 mm centres 200 x 50 mm plate, set to line before excavation pre-made plywood shutters fixed securely together verticals at 600 mm max. centres for 25 mm thick boxing support cleat to top waling loose spreader – remove as concreting proceeds formwork ties fitted through conduits starter bars from footing double waling required when using she-bolts 150 x 50 mm bottom plate bottom she-bolts at 900 mm centres pour footing with nib to locate boxing brace to foot of wall 100 x 50 mm double waling/strong backs at 700 centres pull nail to remove spreader 100 x 50 mm braces at 1200 mm centres pre-built shutter spacer used to keep forms apart until concrete placed and to tie forms together

BUILD RIGHT FORMWORK · construction joint will form. Keeping formwork in place aids the curing process, so don’t rush to strip it just because the concrete is hard. Finally, remember

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: BUILD RIGHT FORMWORK · construction joint will form. Keeping formwork in place aids the curing process, so don’t rush to strip it just because the concrete is hard. Finally, remember

22 BUILD 120 October/November 2010

BUILD RIGHT

FORMWORKMany builders have had a concrete and formwork failure that they would rather forget. It’s an area of construction where

listening to the wisdom of experienced tradespeople is vital, but the following pointers may also help.By Des Molloy, Freelance Technical Writer, Golden Bay

The construction of formwork is taken for granted by all except those doing it. It is difficult to find information about it – there is no mention in the Building

Code, no New Zealand standard to follow (Australia has AS 3610), no ‘how to’ pamphlets in the local merchants’ shelves and of course there is usually no lasting monument to well constructed examples.

Finishing carpenters often take the glory when a job is being reviewed, yet the work of

the person doing the formwork is equally vital in producing a quality result.

Need to be able to build and unbuild

The design and build of formwork is usually done by site staff. Unless a proprietary system is being used, it is up to the carpenters on site to plan how to build and support the formwork, and also how to unbuild it. Being able to strip the formwork effectively is an important part of the task.

Building formwork is something that is best learned by listening and working alongside more experienced tradespeople. Learning only by experience can result in failures along the way.

Huge forces to consider

Wet concrete exerts huge forces against the forms. The concrete and reinforcing together weigh approximately 2.4 tonnes/m3. Lateral forces are generated in walls creating horizontal bursting pressures, which are increased by

Figure 1: Foundation wall formwork – low walls. Figure 2: Foundation wall formwork – walls up to 2 m.

Note: 1. Formwork may be either plywood or timber. Plywood is more suitable where a fair-face finish is required.

2. Pegs and plate beside trench should be in place before digging the trench. (If driven after trenching, pegs may cause the side of the trench to collapse.)

Note: Double waling and she-bolts may be used to tie the top of the wall together.

Note: 1. Formwork may be either plywood or timber. Plywood is more suitable where a fair-face finish is required.

2. Pegs and plate beside trench should be in place before digging the trench. (If driven after trenching, pegs may cause the side of the trench to collapse.)

place outside formwork; excavate trench; place steel – erect inside formwork

cleat packed off form to keep formwork apart, support reinforcing and holding down bolts and allow trowelling

packing (dotted) to form rebate for concrete slab floors

double brace – base of boxing is too close to trench edge to peg

peg

150 x 50 mm plate

boxing constructed of 150 x 25 mm boards closely butted

trench outline

form ventilation openings in walls that have a suspended floor over

pegs to hold base of shutter in place

brace at 1200 mm centres

200 x 50 mm plate, set to line before excavation

pre-made plywood shutters fixed securely together

verticals at 600 mm max. centres for 25 mm thick boxing

support cleat to top waling

loose spreader – remove as concreting proceeds

formwork ties fitted through conduits

starter bars from footing

double waling required when using she-bolts

150 x 50 mm bottom plate

bottom she-bolts at 900 mm centres

pour footing with nib to locate boxing

brace to foot of wall

100 x 50 mm double waling/strong backs at 700 centres

pull nail to remove spreader

100 x 50 mm braces at 1200 mm centres

pre-built shutter

spacer used to keep forms apart until concrete placed and to tie forms together

Page 2: BUILD RIGHT FORMWORK · construction joint will form. Keeping formwork in place aids the curing process, so don’t rush to strip it just because the concrete is hard. Finally, remember

BUILD 120 October/November 2010 23

internal vibrators during compacting. (This exerts similar pressure to a hydraulic jack.)

Formwork needs to resist lifting and bending in every direction and be able to also support the live loads of people and equipment during the pour. Once things start to shift, you’ll never get it back.

Planning is vital

The formwork may not have to look good (except for the face that is imparting the surface finish) but it has to be strong and yet still able to be stripped. When deciding on what to use for formwork, consider that: ❚ proprietary systems will have all the engineering calculations done and have all the necessary components for the job

❚ using higher grade timbers is often quicker than using ‘boxing’ grade, due to its likelihood of being truer

❚ absorbent form surfaces can draw moisture from the concrete

❚ plywood sheathing of forms should have the outer ply face grain running parallel with the span of the sheet – it is stronger this way

❚ a 90 mm nail will take a lateral load of 360 N in radiata pine.

Designing and building

Wet concrete doesn’t quite act as a fluid, but it does have many of the same attributes, such as

being forced out of gaps and open footings when there is a head of pressure above. Care has to be taken in making sure forms will keep the concrete where it is meant to be until it hardens.

When designing the formwork, think about: ❚ access for placing the concrete, vibrating it and stripping the forms

❚ how to clean out before the concrete pour – specific ports may be needed in high wall forms

❚ how you will screed the top of the concrete accurately – the top of the forms or sometimes a line of nails can be used

❚ how to tie walls together – the use of conduits and through-bolts may be precluded, necessitating snap-ties or she-bolts, which remain in the concrete.

When building the formwork, remember: ❚ any deflection of formwork should be no less than 3 mm or 1⁄₂₇₀ of the span

❚ don’t cut timber to length unless necessary ❚ make sure all formwork running joints are tightly butted together to minimise grinding, stoning or ‘bagging’ work after stripping

❚ sealing cut edges will stop the drawing out of water from the concrete mix

❚ never hammer nails fully home on formwork. Leaving the heads proud aids the taking apart of the forms. Consider using hex-head drive screws.

Make sure it’s very strongIt’s unlikely that anyone has been sacked, injured or killed by making formwork using too many props, strong-backs or holding down fixings… but they have from not using enough.

When the formwork is completed, subject it to a strenuous test of pushing and pulling in all directions. It has to be extremely strong.

And now the pour

The most forces on wall forms are applied at the time of placing. There will be fewer forces if the pour is done in layers (approximately 1–1.5 m), but it is important that there is no more than 30 minutes gap between these otherwise a construction joint will form.

Keeping formwork in place aids the curing process, so don’t rush to strip it just because the concrete is hard.

Finally, remember the easiest time to clean the forms is straight after stripping.

CCANZ have some useful information booklets – IB 29 Formwork for concrete, IB 41 Formwork detailing and IB 64 Surface retarders. See www.ccanz.org.nz, then Publications.

Figure 4: Beam box less than 600 mm.

18 mm plywood

150 x 50 mm joists

ledger

18 mm plywood

100 x 50 mm support

150 x 75 mm ledgers

fork heads

steel props at 900–1,200 centres

distance piece removed when beam ¾ full

raking cut to ease striking

head tree 100 mm

framing wedged up to level

Figure 3: Formwork for thickened edge slab up to 600 mm high.

25 mm thick timber rough-sawn boards closely butted

top plate

brace (typically 25 mm thick at 600 mm centres)

peg

150 x 50 mm sole plate

Note: Place sole plate before excavating trench.

side braces left out for clarity