To upload the budget.
Enter Transaction code cj30 and enter
Enter the project definition RR/1001 and enter
Then enter the budget manually against the different WBS elements you want in the budget column
Then press enter
The screen becomes like the one below.
Then save as shown below. Click on the highlighted button.
To supplement the Budget
Enter transaction code CJ36 highlighted in red.
Next Screen will come and we need to put the receiver year.
Receiver year: Current year or Year for which you need to upload budget.
Text name: -
Text: Supplement ENTER
Then next screen comes
Fill in receiver WBS element, the amount, the currency and the year.
Then go to supplement and then click on post
CJ32 - Process to Release the Budget in SAP
Put CJ32 transaction code and Press Enter
Put the controlling Area: CI01
Click on the Continue Button (Tick Mark)
Put the Project Definition: OR/1301. In the below I have selected project definition OR/1301 and Press Enter
Then next screen comes and then go to edit and the select and select all
Then the screen looks like
Click on Edit → Copy View
Click on Edit → Copy View → Current Budget →
Click on Edit → Copy View → Current Budget → Overwrite → 100% → Click on Continue (Enter)
Release → Save
Process to Return Budget in SAP
Go to CJ 32 and De-release the project definition
Then, CJ 35 to return the budget
Then, again CJ 32 to Release the budget in SAP
CJ32 - Process to De-release Budget in SAP
Put CJ32 transaction code and Press Enter
Put the controlling Area: 1000
Click on the Continue Button (Tick Mark)
Put the Project Definition: OR/1301. In the below I have selected project definition OR/1301 and Press Enter
Click on Edit → Select→ Select All
Edit→ Delete → Save
Budget Return: CJ 35 Budget Return
Put transaction code CJ 35 and Enter
Process:
Sender Year: 2015
Text Name: -
Text: Return ENTER
Fill in sender WBS element.
Return → Post
NOTE: Rereleasing is required before posting the Return
DE release (sender) → Post Return → Release (both sender and receiver)
CJ32 - Again Release the Project Definition
Edit → Select→ Select All
Edit → Copy View → Current Budget → Overwrite → 100%
Release → Save
CJ32 - Process to Release the Budget in SAP
Put CJ32 transaction code and Press Enter
Edit → Select→ Select All
Edit → Copy View → Current Budget
Overwrite → 100%
Release → Save
Process to Transfer Budget in SAP
Go to CJ 32 and De-release the project definition
Then, CJ 34 to return the budget
Then, again CJ 32 to Release the budget in SAP
CJ32 - Process to De Release the Budget in SAP
Put CJ32 transaction code and Press Enter
Put the controlling Area: CI01
Click on the Continue Button (Tick Mark)
Put the Project Definition: OR/1301. In the below I have selected project definition OR/1301 and Press Enter
Click on Edit → Select→ Select All
Click on Edit→ Delete → Save
Transfer Budget: CJ 34 Budget Transfer
Put transaction code: CJ34 for Budget Transfer
Process:
Sender Year: 2015
Receiver Year: 2015
Text Name: Leave it blank
Text: Transfer ENTER
Fill in Sender WBS element, Receiver WBS element, Amount and the Currency as mentioned below
Transfer Posting → Post.
Derelease (Sender) → Transfer budget → Release (Both Sender and Receiver)
CJ32 - Process to Release the Budget in SAP
Put CJ32 transaction code and Press Enter
Edit → Select→ Select All
Edit → Copy View → Current Budget
Overwrite → 100%
Release → Save