Budgeting and Cost Estimation (2)

Embed Size (px)

Citation preview

  • 8/10/2019 Budgeting and Cost Estimation (2)

    1/23

    (project Crashing)

  • 8/10/2019 Budgeting and Cost Estimation (2)

    2/23

    Time/cost trade-off analysis is thecompression of the project schedule toachieve a more favorable outcome in terms

    of project duration, cost, and projectedrevenues

    Objectives of time/cost trade-off analysis Minimize total project costs

    Compress project to an acceptable duration

    Done by selectively crashing specificactivities to shorten project duration

  • 8/10/2019 Budgeting and Cost Estimation (2)

    3/23

    You might think that total project costswill increase when we begin to crashactivities

    But, total project costs consist of bothindirect (project-based) costs (PBC) andactivity-based costs (ABC) ABC goes up when we crash activities in an

    effort to finish the project early But, PBC (the indirect costs) goes down if we

    finish the project early

  • 8/10/2019 Budgeting and Cost Estimation (2)

    4/23

    Any activity that is on the critical path Activities with relatively long durations Bottleneckactivities (that appear on

    multiple critical paths) Activities that relatively low cost to crash Activities that are not likely to cause quality

    problemsif crashed Activities that occur relatively earlyin the

    schedule and are labor intensive

  • 8/10/2019 Budgeting and Cost Estimation (2)

    5/23

    1. Estimate project-based (indirect) cost per unittime

    2. Identify critical activities that are goodcandidates for crashing

    3. Determine activity-based (direct) cost ofcrashing selected activities vs. indirect costsavings

    4. Calculate crash cost per period = (crash cost normal cost)(Normal time crash time)

    5. Select activities with minimum crash cost perperiod to be crashed

    6. Recalculate the forward pass and check forchanges in critical path

  • 8/10/2019 Budgeting and Cost Estimation (2)

    6/23

    Reduced flexibility and less margin for errorincreased risk of failure to completeproject on time

    Raises potential for poor quality Increases potential for staff burnout, stress,

    and turnover Raises activity-based costs May negatively affect other projects

  • 8/10/2019 Budgeting and Cost Estimation (2)

    7/237

    Crashing

    reducing project time by expending additionalresources

    Crash time

    an amount of time an activity is reduced

    Crash cost cost of reducing activity time

    Goal

    reduce project duration at minimum cost

  • 8/10/2019 Budgeting and Cost Estimation (2)

    8/238

    Activity time

    Crashing activity

    Crashtime

    Crashcost

    Normal Activity

    Normaltime

    Normal

    cost

    Slope = crash cost per unit time

  • 8/10/2019 Budgeting and Cost Estimation (2)

    9/239

    Crashing costs increase as project duration decreases

    Indirect costs increase as project duration increases

    Reduce project length as long as crashing costs are less than indirect

    costs

    Time-Cost Tradeoff

    time

    Direct cost

    Indirect cost

    Total project costMin total cost =

    optimal projecttime

  • 8/10/2019 Budgeting and Cost Estimation (2)

    10/23

  • 8/10/2019 Budgeting and Cost Estimation (2)

    11/23

  • 8/10/2019 Budgeting and Cost Estimation (2)

    12/23

  • 8/10/2019 Budgeting and Cost Estimation (2)

    13/23

  • 8/10/2019 Budgeting and Cost Estimation (2)

    14/23

  • 8/10/2019 Budgeting and Cost Estimation (2)

    15/23

  • 8/10/2019 Budgeting and Cost Estimation (2)

    16/23

  • 8/10/2019 Budgeting and Cost Estimation (2)

    17/23

    The network and durations given below shows the normalschedule for a project.

    You can decrease (crash) the durations at an additionalexpense.

    The Table given below summarizes the time-costinformation for the activities.

    The owner wants you to you to finish the project in 110days.

    Find the minimum possible cost for the project if you wantto finish it on 110 days. (Assume that for each activity thereis a single linear, continuous function between the crashduration and normal duration points).

  • 8/10/2019 Budgeting and Cost Estimation (2)

    18/23

  • 8/10/2019 Budgeting and Cost Estimation (2)

    19/23

  • 8/10/2019 Budgeting and Cost Estimation (2)

    20/23

  • 8/10/2019 Budgeting and Cost Estimation (2)

    21/23

    darla/smbs/vit 21

    1

    12

    2

    8

    412

    3

    4 5

    4

    6

    4

    7

    4

  • 8/10/2019 Budgeting and Cost Estimation (2)

    22/23

    22

    Activity Normaltime

    Normalcost Rs

    Crashtime

    Crashcost Rs

    Allowablecrash time

    slope

    1

    2

    3

    4

    5

    6

    7

    12

    8

    4

    12

    4

    4

    4

    3000

    2000

    4000

    50000

    500

    500

    1500

    7

    5

    3

    9

    1

    1

    3

    5000

    3500

    7000

    71000

    1100

    1100

    22000

    5

    3

    1

    3

    3

    3

    1

    400

    500

    3000

    7000

    200

    200

    7000

    75000 110700

  • 8/10/2019 Budgeting and Cost Estimation (2)

    23/23

    23

    1

    12

    2

    8

    3

    4 5

    4

    6

    4

    7

    4

    R400

    R500

    R3000

    R7000

    R200

    R200

    R70012

    4

    Project duration = 36

    From..

    To..1

    7

    2

    8

    3

    4 5

    4

    6

    4

    7

    4

    R400

    R500

    R3000

    R7000

    R200

    R200

    R70012

    4

    Project

    duration = 31

    Additional cost =R2000