Upload
kentdemeterio
View
226
Download
0
Embed Size (px)
Citation preview
8/10/2019 Budgeting and Cost Estimation (2)
1/23
(project Crashing)
8/10/2019 Budgeting and Cost Estimation (2)
2/23
Time/cost trade-off analysis is thecompression of the project schedule toachieve a more favorable outcome in terms
of project duration, cost, and projectedrevenues
Objectives of time/cost trade-off analysis Minimize total project costs
Compress project to an acceptable duration
Done by selectively crashing specificactivities to shorten project duration
8/10/2019 Budgeting and Cost Estimation (2)
3/23
You might think that total project costswill increase when we begin to crashactivities
But, total project costs consist of bothindirect (project-based) costs (PBC) andactivity-based costs (ABC) ABC goes up when we crash activities in an
effort to finish the project early But, PBC (the indirect costs) goes down if we
finish the project early
8/10/2019 Budgeting and Cost Estimation (2)
4/23
Any activity that is on the critical path Activities with relatively long durations Bottleneckactivities (that appear on
multiple critical paths) Activities that relatively low cost to crash Activities that are not likely to cause quality
problemsif crashed Activities that occur relatively earlyin the
schedule and are labor intensive
8/10/2019 Budgeting and Cost Estimation (2)
5/23
1. Estimate project-based (indirect) cost per unittime
2. Identify critical activities that are goodcandidates for crashing
3. Determine activity-based (direct) cost ofcrashing selected activities vs. indirect costsavings
4. Calculate crash cost per period = (crash cost normal cost)(Normal time crash time)
5. Select activities with minimum crash cost perperiod to be crashed
6. Recalculate the forward pass and check forchanges in critical path
8/10/2019 Budgeting and Cost Estimation (2)
6/23
Reduced flexibility and less margin for errorincreased risk of failure to completeproject on time
Raises potential for poor quality Increases potential for staff burnout, stress,
and turnover Raises activity-based costs May negatively affect other projects
8/10/2019 Budgeting and Cost Estimation (2)
7/237
Crashing
reducing project time by expending additionalresources
Crash time
an amount of time an activity is reduced
Crash cost cost of reducing activity time
Goal
reduce project duration at minimum cost
8/10/2019 Budgeting and Cost Estimation (2)
8/238
Activity time
Crashing activity
Crashtime
Crashcost
Normal Activity
Normaltime
Normal
cost
Slope = crash cost per unit time
8/10/2019 Budgeting and Cost Estimation (2)
9/239
Crashing costs increase as project duration decreases
Indirect costs increase as project duration increases
Reduce project length as long as crashing costs are less than indirect
costs
Time-Cost Tradeoff
time
Direct cost
Indirect cost
Total project costMin total cost =
optimal projecttime
8/10/2019 Budgeting and Cost Estimation (2)
10/23
8/10/2019 Budgeting and Cost Estimation (2)
11/23
8/10/2019 Budgeting and Cost Estimation (2)
12/23
8/10/2019 Budgeting and Cost Estimation (2)
13/23
8/10/2019 Budgeting and Cost Estimation (2)
14/23
8/10/2019 Budgeting and Cost Estimation (2)
15/23
8/10/2019 Budgeting and Cost Estimation (2)
16/23
8/10/2019 Budgeting and Cost Estimation (2)
17/23
The network and durations given below shows the normalschedule for a project.
You can decrease (crash) the durations at an additionalexpense.
The Table given below summarizes the time-costinformation for the activities.
The owner wants you to you to finish the project in 110days.
Find the minimum possible cost for the project if you wantto finish it on 110 days. (Assume that for each activity thereis a single linear, continuous function between the crashduration and normal duration points).
8/10/2019 Budgeting and Cost Estimation (2)
18/23
8/10/2019 Budgeting and Cost Estimation (2)
19/23
8/10/2019 Budgeting and Cost Estimation (2)
20/23
8/10/2019 Budgeting and Cost Estimation (2)
21/23
darla/smbs/vit 21
1
12
2
8
412
3
4 5
4
6
4
7
4
8/10/2019 Budgeting and Cost Estimation (2)
22/23
22
Activity Normaltime
Normalcost Rs
Crashtime
Crashcost Rs
Allowablecrash time
slope
1
2
3
4
5
6
7
12
8
4
12
4
4
4
3000
2000
4000
50000
500
500
1500
7
5
3
9
1
1
3
5000
3500
7000
71000
1100
1100
22000
5
3
1
3
3
3
1
400
500
3000
7000
200
200
7000
75000 110700
8/10/2019 Budgeting and Cost Estimation (2)
23/23
23
1
12
2
8
3
4 5
4
6
4
7
4
R400
R500
R3000
R7000
R200
R200
R70012
4
Project duration = 36
From..
To..1
7
2
8
3
4 5
4
6
4
7
4
R400
R500
R3000
R7000
R200
R200
R70012
4
Project
duration = 31
Additional cost =R2000