257
Kwame Nkrumah University of Science and Technology Kumasi – Ghana Institute of Distance Learning BT 358 Construction Estimating and Price Analysis (Credits: 3) Kwame Ofori-Kuragu

BT 358 ConstructionEstimating and Price Analysis

Embed Size (px)

Citation preview

Page 1: BT 358 ConstructionEstimating and Price Analysis

Kwame Nkrumah University of Science and TechnologyKumasi – Ghana

Institute of Distance Learning

BT 358 Construction Estimating and Price Analysis

(Credits: 3)

Kwame Ofori-Kuragu

Page 2: BT 358 ConstructionEstimating and Price Analysis

Course AuthorKWAME OFORI-KURAGU is a lecturer at the Department of Building Technology at the Kwame Nkrumah University of Science and Technology, Kumasi. He holds a Bachelor of Science in Building Technology from the Kwame Nkrumah University of Science and Technology and a Master of Science in Construction Project Management from Loughborough University in the United Kingdom. He is member of the Chartered Institute of Building (CIOB), UK member of the American Association for the Advancement of Cost Engineering (AACE), member of the General Teaching Council (GTC) of Great Britain and the Design and Technology Association (DATA), Great Britain.

His main teaching and research interests are in the areas of Improving Productivity in Construction, Construction Cost Reduction Strategies, Innovation in Construction and Project Management Excellence.

Table of Content

2

Page 3: BT 358 ConstructionEstimating and Price Analysis

sUNIT 1 THE COST ESTIMATING PROCESS..........................................................11

Session 1-1 The Estimating and Tendering Process......................................................121-1.1 Stages in the Estimating and Tendering Process...................................................12

Session 2-1 Preparations for the Estimate.......................................................................18

UNIT 2 PRINCIPLES FOR COMPUTATION OF ESTIMATES...............................40Session 1-2 ‘All-in Rates” and Unit Rate Computation..........................................40

1-2.1 All-in Rates..................................................................................................40

1-2.2 All-in labour rates.................................................................................................44

1-2.3 All in-rate for Plant.........................................................................................47

1-2.4 Composition of net unit rates...............................................................................48

Session 2-2 PC Sums, Provisional Sums and Overheads......................................532-2.1 PC Sums Nominated suppliers..........................................................53

2-2.2 Provisional sums............................................................................................56

Session 3-2 Project Overheads (Stage 8).................................................................603-2.1 Classification of project overheads.......................................................................62

UNIT 3 BID SUBMISSION AND ACTION AFTER SUBMISSION........................66Session 1-3 Completing and submitting the bid...........................................................66 2-3 The Final Review, Mark-up and tender Submission...........................................73

2-3.1 Estimator’s report...........................................................................................73

2-3.2 Final review...................................................................................................75

Session 3-3 Tender submission and beyond............................................................783-3.1 Tender submission..........................................................................................78

3-3.2 Action after Submitting Tender (Stage 10)......................................................78

UNIT 4 BUILDING UP ESTIMATES.........................................................................84Session 1-4 Preparing Estimates for Excavation, Concretework,

1-4.1 Preparing estimates for Excavation.........................................................841-4.2 Estimating for Concrete..................................................................................90

1-4.3 Preparing Estimates for Structural Steelwork.....................................................104

2-4.4 Estimating for Metalwork............................................................................106

Session 2-4 Estimating for Roofing, Walling, Woodwork, Finishes, Painting and Decoration……………………………………………………………………………108

2-4.1 Estimating for Roofing.......................................................................................108

2-4.2 Estimating for Blockwork and Brickwork..........................................................116

2-4.3 Estimating for Woodwork..................................................................................123

3

Page 4: BT 358 ConstructionEstimating and Price Analysis

2-4.4 Estimating for Painting and Decoration..............................................................125

2-4.5 Estimating for Floor, Wall and Ceiling Finishes.............................................127

Session 3-4 Preparing Estimates for Plumbing and Electrical installations, Glazing and Preliminaries…………………………………………………………………….129

3-4.1 Estimating for Plumbing Installation..............................................................129

3-4.2 Estimating for electrical installations..................................................................131

3-4.3 Estimating for Glazing........................................................................................134

Unit 5 ESTIMATING FOR PRELIMINARIES..............................................................136Session 1-5 Preliminary Items...............................................................................136Session 2-5 Pricing Strategy..................................................................................139

Unit 6 PRICE ANALYSIS..............................................................................................151SESSION 1-6 Pricing manipulations.......................................................................151 2-6 Bidding strategy, contract strategy and risk management................................153

2-6.1 Bidding Strategy..........................................................................................153

2-6.2 Risk Management.........................................................................................154

References........................................................................................................................159

4

Page 5: BT 358 ConstructionEstimating and Price Analysis

List of tables Page

1. Table 2.1 Computation of “all-in rates for labour 46

2. Table 2.2 Plant information for estimating 47

3. Table 2.3 Classification of construction material wastes 49

4. Table 2.4 Outputs for different methods of excavation in gravel soil 51

5. Table 2.5 Multipliers for different excavation types and depths 51

6. Table 2.6 Effect of soil type and bulkage effect on excavation output 51

7. Table 2.7 Outputs for different depths of earthwork support 52

8. Table 3.1 Comparison of company’s tenders with competitors 83

9. Table 4.1 Illustration of formwork estimating 96

10. Table 4.2 Reinforcement Requirements 99

11. Table 4.3 Information on timber mould 101

12. Table 4.4 Output per ton for fabrication and erection 104

13. Table 4.5 Output data for metalwork per gang-day 106

14. Table 4.6 Achieved outputs for corrugated sheet roofing 108

15. Table 4.7 Corrugated roofing sheet sizes in use locally 109

16. Table 4.8 Outputs for bituminous felt covering operation 109

17. Table 4.9 Popular sizes of blocks which are commonly used in Ghana 116

18. Table 4.10 Weights and volumes of cement and sand in specified nominal mixes of

mortar

117

19. Table 4.11 Achieved outputs for selected blockwork operation 117

20. Table 4.12 Average covering capacities in m2/gallon/coat 125

21. Table 4.13 Achieved labour output data on works in m2/ gang-day 126

22. Table 4.14 Achieved labour outputs for finishes 127

23. Table 4.15 Output data per gang-day for supply, preparation and fixing fittings and

appliances

129

24. Table 4.16 Showing output per gang-day for pipework inclusive of pipes, fittings and

supports in domestic buildings

130

25. Table 4.17 Estimating for electrical installations 131

26. Table 4.18 Cutting and fixing of sheet glass in m2/gang-day 134

27. Table 5.1 Pricing of site visit 140

28. Table 5.2 Calculation of contractor’s supervision cost 145

5

Page 6: BT 358 ConstructionEstimating and Price Analysis

29. Table 6.2a Cashflow without front loading 152

30. Table 6.2b Cashflow when front loading is used 152

6

Page 7: BT 358 ConstructionEstimating and Price Analysis

List of Figures Page

1. Fig 4.1 Timber formwork support to soffit of suspended slab 96

2. Fig 4.2 Timber moulds for precast concrete works 100

3. Fig 4.3 Bituminous felt roof covering materials and operations 115

4. Fig 5.1 Horse type timber scaffold at 1500mm centres 146

5. Fig 5.2 Site fence with timber frame boarding 147

6. Fig 6.1 Graph of percentage of project costs against percentage of bill items 152

7. Fig 6.2 Risk assessment framework 156

8. Fig 6.3 Risk assessment worksheet 157

Course ContentThis course broadly covers:

1. The Estimating and Bidding process

2. All-in rates determination and materials adjustments

3. Unit rate computation for construction items

4. Price analysis

5. Price and contract strategies

Main Objectives of CourseBy the end of this course, you should be able to:

Understand the step-by-step procedure adopted in practice to establish cost estimates at the tendering stage of construction projects

Acquire the data and methodology required for detailed cost estimation of construction work items

Appreciate the design and development of reports such as adjudication and tender evaluation reports

Appreciate pricing strategies used by contractors to achieve financial objectives

7

Page 8: BT 358 ConstructionEstimating and Price Analysis

PERSONAL ACHIEVEMENT CHECKLIST

The following table could be useful in helping you to keep track of your progress as you

go through the study material. You can use the spaces provided to indicate when you

have achieved a particular objective. The way to check if you have achieved a particular

objective will be by testing yourself using the self-assessment questions.

Course ObjectiveTarget Date for Objective

Date Objective Achieved

Comment

To be able to explain the estimating and bidding process.To be able to compute all-in rates for plant and labour and to be able to compute net unit rates for construction activitiesTo be able to compute estimates for the respective work sections associated with the construction processTo be able to explain the commonly used pricing and contract strategies.To understand fully the reports associated with the estimating and bidding process

8

Page 9: BT 358 ConstructionEstimating and Price Analysis

HOW THIS BOOK HAS BEEN STRUCTUREDThe course has been divided into six main units. Each unit has its own unit objectives.

The unit objectives represent the major achievements which you will be expected to

attain by the time you have finished studying the unit.

Each unit is divided into a number of sessions. In addition to the objectives for the units,

each session has learning outcomes to enhance your learning process and to help you to

effectively assess your learning. Following each session, there are Self-Assessment

Questions. These have a two-fold objective of helping to consolidate your learning whilst

helping you test your knowledge and understanding of the key knowledge areas of each

topic studies.

Much of the material in this book focuses on the Construction Estimating principles and

procedures. In addition to a dedicated unit which focuses on Price Analysis, aspects of

Price Analysis are included throughout the text.

STUDYING THIS COURSE

You may wish to adopt any approach that suits your learning needs and your personal

circumstances. The individual sessions have been structured to be studied as stand-

alones, however if it suits your learning style, you may wish to break down the respective

sessions into manageable bite-size chunks to enhance your learning.

To enable you to assess your progress whilst you study this course, each session is

followed by an activity. The activity consists of assessment questions which seek to

consolidate your learning by helping you assess your learning against the learning

outcomes. These questions should be done within a reasonable time. It is recommended

that you spend about fifteen minutes on the activities. The course material should serve as

9

Page 10: BT 358 ConstructionEstimating and Price Analysis

a useful guide to help you answer correctly any of the assessment activities. Should you

find it necessary, please feel free to refer to relevant sessions.

Finally, the units have been arranged to make it easy to read and may be studied in any

order depending on your specific needs and preferences. In the same way, whilst it will

provide some consistency if the sessions are studied in the order in which they appear in

the book, the presentation of the course material lends itself to any approach that suits

your needs and style. We wish you all the very best as you study this course.

Do enjoy reading.

THE UNITS IN THIS COURSEThe course objectives are achieved through six Study Units as follows:

Unit 1: The Cost Estimating Process

Unit 2: Principles for Computation of Estimates

Unit 3: Tender Submission and Action after Submission of Tender

Unit 4: Building up Estimates

Unit 5: Estimating for Preliminaries

Unit 6: Price Analysis

REQUIRED READINGSHarris F and McCaffer R. MODERN CONSTRUCTION MANAGEMENT 4TH EDITION Professional Book Chapter 9

Hackett M, Robinson I & Statham G, (2007) AQUA GROUP GUIDE TO PROCUREMENT, TENDERING & CONTRACT ADMINISTRATION Chapters 3,4,8-15

Amoah Mensah, K., (1995), MANUAL FOR ESTIMATING

Ashworth, A. & Hogg, K., (2007) WILLIS PRACTICE AND PROCEDURE FOR THE QUANTITY SURVEYOR, Blackwell Publishing, Oxford

10

Page 11: BT 358 ConstructionEstimating and Price Analysis

COURSE STRUCTUREUnit 1 The Cost Estimating ProcessSession 1 The Estimating and Tendering Process

Session 2 Preparations for the Estimate

Unit 2 Principles for Computation of Estimates

Session 1 “All-in Rates” and Unit Rate Computation

Session 2 PC Sums, Provisional Sums and Overheads

Unit 3 Bid Submission and Action after Tender Submission

Session 1 Completion and Submission of Bid

Session 2 The Final Review, Mark-up and Tender Submission

Session 3 Tender Submission and beyond

Unit 4 Building up Estimates

Session 1 Preparing Estimates for Excavation, Concretework, Steelwork and Metalwork

Session 2 Preparing Estimates for Roofing, Walling, Woodwork, Finishes, Painting and Decoration

Session 3 Preparing Estimates for Plumbing and Electrical Installations and Glazing

Unit 5 Estimating for Preliminaries

Session 1 Preliminary Items

Session 2 Pricing Strategy

Unit 6 Price Analysis

Session 1 Price Manipulations

Session 2 Bidding Strategy, Contract Strategy and Risk Management

11

Page 12: BT 358 ConstructionEstimating and Price Analysis

UNIT 1 THE CONSTRUCTION ESTIMATING PROCESSUnit ObjectivesBy the end of this unit, you should be able to:

i. Outline the sequence of activities which make up the Estimating and

Tendering Process for construction projects;

ii. Explain what happens at each stage of the estimating and tendering process;

iii. Explain what strategies contractors use during estimating to improve

cashflow.

Introduction to Tendering and EstimatingThe tendering and estimating phase can be seen as the interface between the design and

the construction phase of a traditionally procured contract.

Tendering is the total processes undertaken by a contractor to estimate the net prime costs

of the works involved in a project, making allowance for head office contribution to the

project and risks associated with the project. The tendering process is sometimes

described as bidding. So tender and bid are used interchangeably in some cases. There

are several different types of bids which may be chosen from for a particular project. The

type of bid process chosen may be determined by the client’s priorities or preferences or

in the case of the public procurement of projects in the Ghanaian construction industry,

by the rules governing procurement as set out by the Public Procurement Act. The first

step in the preparation of a bid by the contractor is to prepare estimates of what is

required for a project and what these will cost. The function of estimating is to establish

the net prime cost of completing the works indicated in the contract documents (exclusive

of head office overheads and profits and allowances for contractors’ risks).

Once the total estimate for a project has been obtained, it can be converted to a tender

figure by adding a charge for head office overheads, profits and allowances for

contractor’s overheads. There are several stages in the estimating process. In the next

session, we look at the different stages of the construction estimating process.

12

Page 13: BT 358 ConstructionEstimating and Price Analysis

Session 1-1 The Estimating and Tendering ProcessLearning Outcomes

By the end of this session, you will be able to explain:

i. The criteria used to select suitable contractors to bid;

ii. The factors considered by the contractor when making the decision to bid; and

iii. What actions should be taken by the contractor if a decision is made to tender

for a project.

1-1.1 Stages in the Estimating and Tendering Process

The process of estimating and tendering for a project usually follows a set of systematic

stages. The following distinct stages can be identified:

i. Development of tender list and invitation to tender;

ii. The contractor’s decision to tender;

iii. Project appreciation;

iv. Enquiries and quotations;

v. Planning and temporary works;

vi. “All-in” Rates and Unit Rate Pricing;

vii. PC and provisional sums;

viii. Project overheads;

ix. Completion, adjudication and submission of tender; and

x. Action after submitting tender.

We will now discuss the respective stages and the series of actions undertaken at each

stage.

13

Page 14: BT 358 ConstructionEstimating and Price Analysis

Stage 1: The Invitation to TenderTender List and Invitation to TenderThe contractor will be expected to formally respond to the client’s invitation to tender. If

the contractor’s response is positive, it will indicate to the client and his consultants

whether the contractor has the necessary expertise, experience, management, resources

(including financial) and knowledge of the location to adequately construct their works in

the time required. Adequate and consistent appraisal of contractors submitting

information is essential. From the written exchange of information, and any interviews

felt necessary by the client and his consultants, a shortlist of contractors will be produced.

This pre-selection procedure will produce a list of companies, any of which will be

capable of constructing the works. Consultants should advice contractors who are

selected that they would be receiving tender documents on the advised date. The

contractor can then reserve appropriate resources to process the tender when it arrives. It

is important that these dates are adhered to and that the contractor is advised of any

changes that occur. Contractors who have not been selected at the pre-selection stage

should also be advised promptly that they have not been successful.

Once a contractor has indicted his intention to submit a tender, it will only be under very

exceptional conditions that such a contractor should decide not to submit a final tender. If

a situation arises which makes a contractor’s withdrawal necessary, adequate notice of

the withdrawal should be given to the client or consultants in order for them to be able to

either invite new contractors to join or abandon the process. This will help prevent undue

delays to the contractor selection process and by extension the project.

Stage 2: Decision to TenderWhen a contractor makes it to onto a client’s tender list and is invited to tender, the

contractor now needs to make a decision whether or not to formally put in a bid for the

project. Some of the factors used to make this crucial decision whether or not to bid are

shown below:

14

Page 15: BT 358 ConstructionEstimating and Price Analysis

Factors Considered when making decision to tender

The following factors are the main points considered when contractors are making a

decision to bid / tender for a project or not. They are:

The conditions of contract for the project;

The contractor’s workload or timetable;

The type of work and resources needed for the project;

The tender information provided;

Commercial factors;

Credit standing of the client;

Source of funding for project;

Knowledge of Client;

Timescale for offer;

Knowledge of competitors also interested in the project;

Importance of the project to the client and the contractor;

Knowledge of local conditions – availability of labour, plant and materials;

Risks involved – cash flow, future business, etc.;

Terms of payment for the project;

The contractor’s overheads, mark up and profit; and

The method of evaluation and award to be used for the project.

Once the contractor has decided to put in a bid for the project, the next thing is to put

together a team for the estimating process. Let us now consider the estimating team

generally and the main parties which usually make up the team.

The Estimating TeamThis is the team put together by the contractor to handle the tendering and estimating

process once the decision to tender has been made. It is important to ensure that the

whole process is a team effort. The natural leader of the team is the estimator and all

other members of the contractor’s organisation may contribute depending on the scale

and complexity of the project in relation to the company’s workload. On a major project,

15

Page 16: BT 358 ConstructionEstimating and Price Analysis

some or all of these functions within the contractor’s organisation may work on the

preparation of a tender. Not all of these will however work on a full time basis depending

on the specific needs and the requirements relating to a particular project.

In general, some of the members who make up the contractor’s estimating team are:

estimator, planner, buying officer, engineer, plant manager, quantity surveyor, insurance

officer and operations manger. Let’s look at the respective roles that each team member

plays and/ or their departments play in the overall estimating process.

The Estimator: The estimator is the team leader and is responsible for pricing the works

which form part of the project.

The Planner: The planner has responsibility for the pre-tender planning process. This

includes the programme of works, method statement and resource scheduling. The

planner must work closely with the estimator so that the estimate produced relates

directly to the pre-tender plan.

The Buying Officer: The buying officer is generally responsible for sending out

enquiries for all bought-in items. These include enquiries relating to materials, sub-

contractors, temporary works and consumables. This department is responsible for

presenting the estimator with a table of comparisons and their recommendations for

inclusion in the estimate.

Engineer: The engineer is responsible for design, quality control and /or quality

assurance proposals. He is also responsible for making recommendations relating to

temporary works.

Plant Management Officer: The plant management officer is responsible for advising

the estimator on the selection, availability, utilisation and cost of specialist plant and

transport required for the project.

16

Page 17: BT 358 ConstructionEstimating and Price Analysis

Quantity Surveyor: The quantity surveyor on the estimating team is responsible for

examining contract documents to identify any areas of commercial risk or opportunity.

Insurance Officer– This is the insurance expert on the estimating team who offers

specialist advice regarding bonds and insurance to the estimating team.

Operations Management Representative: Represents the operations department in the

contractor’s organisation and serves on the estimating team; must be given the

opportunity to examine and approve the proposed contract strategy.

What happens when the tender documents are received?When the estimating department receives the tender documents, the department must

complete a Tender Information Form. Once this has been done, an acknowledgement or

receipt of the enquiry must be sent to the client or his consultant. This form provides

management with a summary of the project and the tender documentation. It must be

circulated to managers in other departments and will be very important in helping to

make the decision to tender. Where an approximate cost of the project is provided, this

must be reconciled against any advice given at the time of pre-selection. If no

approximate cost is given, an early assessment must be made by the estimator to

determine the approximate cost of the project and the scope of works.

Inspection of tender documentsThe inspection of the tender documents must be made by the estimator mainly

responsible for the production of the cost estimate. The estimator must then make a

checklist of all the documents received. In larger construction companies, these

documents may be inspected by the chief estimator as well as other members of the

contractor’s organisation. These may include the tender planner, quantity surveyor,

contracts advisor and contracts manager. Clear lines of communication should be

established to ensure that all viewpoints of all those who examine the documents are

considered. The estimator will have overall responsibility for the co-ordination of the

views of the other parties who examine the documents.

17

Page 18: BT 358 ConstructionEstimating and Price Analysis

Objectives when inspecting tender documentsThe main objectives which should be achieved when inspecting the documents are:

Whether the documents received are those specified in the enquiry;

That the documents and information are adequate for assessing costs; and

That sufficient time is available for the production of a tender.

Information required for the preparation of an estimateIn order to prepare a tender programme, all the information contained during “Pre-

selection” will be required together with additional information. This is supplied in

various forms, including:

Drawings;

Specifications (including performance specifications where possible);

Schedules;

Technical reports;

Programme of work periods for major nominated subcontractors; and

Bills of quantity.

All forms must show the date of original issue as well as the date(s) and nature of any

amendments. The drawings issued in the bills of quantities or the drawing issue forms

will be issued with the tender documents.

Self assessment questions

i. You are part of a client consulting group tasked with selecting a contractor for

a large project. What factors will you consider when deciding which

contractors to invite to bid for the project?

ii. On receiving an invitation to tender, contractors need to make the critical

decision whether to bid for the project or not. What factors should contractors

consider when they are making the decision to bid for a project or not?

iii. What actions should be taken by a contractor after a decision has been made

to tender for a project?

18

Page 19: BT 358 ConstructionEstimating and Price Analysis

Session 2-1 Preparations for the Estimate

Learning Outcomes

By the end of this session, you should be able to:

i. Explain what Project Appreciation means;

ii. Describe the nature of enquiries which contractors may need to make whilst

putting a bid together; and

iii. Describe the type of planning which the contractor makes at this stage.

Stage 3: Project AppreciationHaving decided to tender for the project, the next stage is for the contractor is to gain an

in-depth understanding of the project’s requirements and to devise a strategy for the

timely completion of the complex, interrelated activities involved in the project.

Management of estimates

All projects in an estimating department must be entered in a tender register. Many

companies use the register to evaluate tender performance in relation to their competition.

Co-ordination meetings are needed with management and other departments within the

contractor’s organization to establish key dates, decide on actions necessary and monitor

progress during the production of the cost estimate. The chief estimator will prepare a bar

chart each week to plan the estimator’s work-load showing both present and possible

future tenders. Copies are sent to heads of other departments for their input.

Checking the tender documents

After the contractor has decided to tender for a project, the estimator must ensure that all

the tender documents have been received. A check must be made to see that all drawings

received are those which have any up-to date revisions noted and that all other documents

listed in the invitation letter are provided. Making a checklist for the tender documents

will help the estimator to assess their suitability for the estimate. A letter is then sent to

the client or consultant to acknowledge receipt of the documents and confirm that a

tender will be produced by the due date. This letter sent to the client should also record

any discrepancies in the documents received. It is important to make an accurate record

19

Page 20: BT 358 ConstructionEstimating and Price Analysis

of tender documents received because they will become the basis of a formal offer and

eventually be checked against the contract documents in the case of a successful tender.

This can best be achieved by stamping each drawing and document to show the date

received and the words – “Tender Documents” on them.

Timetable for the production of the estimate and tender

A timetable must be established which highlights the key dates in the production of the

estimate and tender. This is the responsibility of the estimator. When prepared, the

estimating timetable will be an essential document for all those associated with the

tendering function. The following dates should be established without ambiguity:

Latest date for dispatch of enquiries for materials, plant and sub-contracted items;

Latest date for the receipt of quotations;

Bills of quantity production for design and build, drawings and specifications

contracts;

Visit to the site and the locality;

Finalization of the method statement;

Completion of pricing and measured rates;

Finalization of tender programme;

Intermediate coordination meetings within the contractor’s organization;

Review meetings;

Submission of the tender.

Examination of the tender

The conditions of contract, bills of quantity, general arrangement drawings, specifications

and any supporting documents, such as soil reports, site industrial relations policy, or

specialist information must be examined in detail by he estimator or other personnel in

the contractor’s organization, including those associated with purchasing, tender

planning, commercial management, engineering, temporary works, plant and

construction. Any discrepancies in the tender documents must be noted by the estimator

for future reference to the appropriate consultant for clarification.

20

Page 21: BT 358 ConstructionEstimating and Price Analysis

Conditions of contract and appendix

At this stage the estimator must consider in more depth the consequences of such

conditions and note his recommendations for dealing with the situation on the

‘Estimator’s summary’. Any further particulars received during the tender period

concerning the conditions of contract and appendix details, must be noted and entered in

the ‘Estimator’s Summary’. The estimator must ensure that appropriate action is taken

regarding any cost implications of revised or additional information received. When the

conditions of contract and appendix are examined, they must reveal whether:

All forms of contract used are standard forms of contract;

Conditions of standard forms are amended;

Non-standard payments or retention provisions are included and the effects that

such alterations may cause regarding the contractor’s liability for payments to

sub-contractors;

Bid bonds, performance bonds or parent company guarantee are required;

Insurance requirements are met by the contractor’s standard policies, or can be

obtained within the current insurance market at reasonable rates;

Nomination procedures will be followed without amendment;

Liquidated damage requirements are acceptable and whether any allowance

should be made in the tender; and

Amendments to other project information have been reflected in the conditions; of

contract, i.e. items not measured in the bills of quantity in accordance with the

SMM.

Specifications, bills of quantity and drawings

The estimator must have a thorough understanding of the specification. This document

must be examined in detail and compared with the items measured in the bills of quantity

and tender drawings to identify any divergence and discrepancies. The estimator must

ensure that there is consistency and any cross references is accurate. The specification

must be clear and unambiguous and the estimator must prepare a queries list of any

unclear items for discussion with the appropriate consultant.

21

Page 22: BT 358 ConstructionEstimating and Price Analysis

A schedule must be prepared for use in obtaining quotations for various materials and

elements to be sub-contracted. In order to prepare this, the estimator must first of all

group together relevant items from the specifications and bills of quantity into respective

trades and if necessary, individual suppliers. It may be necessary to obtain further

information from drawings, for example lengths of timber may need to be specified. The

estimator should consider any additional quotations that will be required to enable him to

have flexibility when pricing. This could include extra over rates for machine offloading

of bricks. Another example is the extra over charge made by ready mix concrete

suppliers. Such information will be of benefit when pricing the bills in detail at a later

stage. The attention of the consultants must be drawn to any problems, particularly when

an estimator is concerned that poor specifications could make his tender less competitive.

The information provided on tender drawings will be a significant factor in the decision

to tender. At this stage, the estimator will systematically analyse the data shown on the

various tender drawings and schedules and build up a picture of the project’s needs. This

analysis must highlight the cost significant items in the project and demonstrate areas of

caution or risk. Further information may be needed when the site is visited. This

information must be recorded for review purposes in the ‘Estimator’s summary’. The

estimator should look for various factors at this stage which will influence his approach

to pricing such as:

Standard and completeness of the drawn information;

Tolerances required;

Clarity of the specifications requirements and the quality required;

Buildability;

Whether load bearing and non load bearing areas can be identified;

The extent of use of standard details indicating previous construction experience;

Evidence of design coordination of services and structural needs;

The amount of information concerning ground conditions and foundations; and

Problem areas and restraints on construction in the design.

22

Page 23: BT 358 ConstructionEstimating and Price Analysis

From his appreciation of the drawn information, the specification and measured items in

the bills of quantity, the estimator will begin to understand how the project is to be

constructed and the quantity and quality of resources needed.

Outstanding information

Having examined the tender documents thoroughly, the estimator will highlight any

concerns or queries relating to the project and the proposed method of construction. It is

important that the estimator puts together queries that are raised by other members of the

contractor’s team who have examined the documents as well. All queries concerning the

tender information should be channeled to the estimator for resolution. It is recommended

that only the estimator should deal with the consultants at this stage to avoid any

problems which may arise from different people communicating different things. Queries

raised will be resolved through meetings and discussions between the estimator and other

members of the contractor’s team and the consultants on the site visit. The estimator must

ensure that all queries raised with the consultants are made in writing and that the

urgency of the information needed is stressed. Any significant decisions communicated to

one contractor by the consultant, must be communicated to all tendering contractors.

How to ensure effective distribution of documents

The estimator has a responsibility to ensure that other members of the contractor’s

estimating team with specialist knowledge or interests are provided with copies of all

relevant information relating to the project. A tender documents’ checklist can be used to

record who in the estimating team receives documents and which documents are sent. In

very large construction organizations, specialist departments will assess the risks and

obligations as have been detailed below:

The insurance department will obtain a quotation for a specific project if it

exceeds a certain value or involves working in a hazardous location.

The legal department or the company secretary may need to comment on the

wording of warranties or performance bonds or arrange directors’ signatures for

parent company guarantees where these are required.

23

Page 24: BT 358 ConstructionEstimating and Price Analysis

The commercial manager or quantity surveyor should be consulted for advice on

the proposed conditions of contract. In particular, his advice on the terms of

payment which are critical to the financial success of a contract should be sought.

The need to visit the site

The visit to the site must be made once the preliminary assessment of the project has been

carried out and a provisional method and sequence of construction established. The

estimator may be accompanied on such a visit by other members of the contractor’s team.

As well as visiting the site itself, the opportunity must be used to examine the general

locality and to establish the extent of construction-related activity in the area. Visits

should also be made to local labour agencies and suppliers in the area. If there are

excavations near the site, it is advisable to visit these too. The local authorities may be

able to give advice on local conditions and of any excavations which may be visibly

adjacent or near to the site.

After visiting the site, a comprehensive report of the site visit must be prepared. Site

photographs can often be a useful way of recording information from the site visit for

discussion and records purposes. Points to be noted when making a site visit would

usually include: transport links to the site, topographical details of the site, access to the

site, security issues, the location of services, local amenities as well as local regulations

etc.

Visits to consultants

The estimator may need to visit the client’s consultants, particularly when further

information is needed which has not been given to tenderers, such as further drawings

and site investigation reports. In some circumstances, these documents may be

confidential. In practice, visits will normally be made to the architect, but it helps to visit

the consulting engineer, services engineer and quantity surveyor, in order to meet the

personalities who will subsequently be involved in the project. Detailed drawings, reports

of site investigations and any other available information must be inspected and notes and

sketches made of all matters affecting either construction method temporary works or the

24

Page 25: BT 358 ConstructionEstimating and Price Analysis

likely cost of work. A critical assessment must be made of the degree of advancement

and quality of the design. The reason for this is that, generally a well-developed and well-

documented design may be indicative of a smooth running and possibly profitable

project. A design which is obviously ill-conceived and incomplete may cause delays

during construction and as a result, allowance must be made for this in the tender. If the

indications are unfavourable at this stage, the decision to submit a tender may be affected.

Although visits to consultants are invaluable, they have become less common in practice

because contractors are usually given copies of all the drawings and specifications which

are going to become part of the contract documents. The more common situation

therefore is that a visit will be seen as an opportunity to show the tenderer’s willingness

to contribute to the scheme, to work closely with the design team and to express an

interest in further work.

Stage 4: Enquiries and QuotationsAfter tender checking and the project appreciation stages, the next phase is to make all

the necessary enquiries needed to sub-contractors and suppliers, obtain quotes and then to

start to plan the work. This takes the estimating process from the preliminary stages

through to its mid-stage when the detailed pricing begins. A contractor’s success in

obtaining a contract depends upon its success in obtaining good quality quotations for

materials, plant and items to be sub-contracted. These elements typically account for over

70% of the value of direct works, and so the importance of accurate and complete quotes

cannot be overstated.

Enquiry Documents

As previously stated, the contractor’s success in obtaining a contract depends upon the

quality of the quotations received for materials, plant and items to be sub-contracted. It is

therefore essential to obtain realistically competitive prices at the time of preparing the

estimate. The responsibility for carrying out this important function will vary from

company to company. In some organizations, the estimator prepares the information for

enquiry purposes, selects the organizations to receive enquiries and reconciles the

25

Page 26: BT 358 ConstructionEstimating and Price Analysis

quotations received. In others, some or all of this will be done by the buying department,

who may provide the estimator with a selection of fully reconciled quotations at the end

of the enquiry stage for his final consideration. Whoever has responsibility, standard

procedures should be established, setting out the responsibilities of the person who is to

carry out the enquiry function and any subsequent negotiations that arise.

The professional manner in which enquiries are sent to suppliers and sub-contractors can

have a considerable effect on the response and the quality of quotations submitted. Lists

of items for which quotations are required are established following the detailed

examination of the contract documents. Enquiry abstract forms should be produced which

enable the estimator or buyer to list the materials and trade packages which need

quotations. If only drawings and specifications are provided, it is necessary for the

contractor to produce additional information to assist with the enquiries. Every

opportunity should be taken to clarify the contractor’s requirements, bearing in mind the

limited time usually available for obtaining quotations. The contractor must ensure that

comprehensive records of the various elements of project information sent to suppliers

and sub-contractors are maintained. These records must list the drawings sent, the

relevant contracts and specification clauses, project preambles and the pages of the bills

of quality. The use of the standardized documentation and procedures assists at this stage

in the methodical preparation of the estimate, and allows an interchange of personnel at

any stage.

Lists and Pre-selection

Contractors must maintain comprehensive records of suppliers, and sub-contractors.

These records must include:

Details of past performance on site;

Previous performance in returning complete quotations on time;

Extent of geographical operation;

Size and type of contract on which previously used;

Information concerning contacts; and

Address, telephone and facsimile numbers.

26

Page 27: BT 358 ConstructionEstimating and Price Analysis

When operating in a new area, a contractor needs information concerning the local

suppliers and sub-contractors. In this case, performance should be verified from other

external sources and any remaining information established from the supplier and sub-

contractor concerned. A questionnaire may be used to establish the resources and abilities

of subcontractors concerning:

Area of operations;

Size and type of work;

Labour and supervision available;

Size and type of work previously carried out;

References from trade, consultant and banking sources;

Insurances carried by the sub-contractor(if relevant); and

Confirmation of holding of relevant sub-contractor’s tax exception certificate (if

relevant).

This questionnaire attempts to establish the supplier or sub-contractor‘s financial

capability to undertake the work in question and to supply the materials and the plant

required. It is necessary to establish that all resources will be available to meet the

requirements of the main contractor’s programme. Pre-selection will be necessary if

dealing with unknown suppliers and sub-contractors. Bearing in mind the particular needs

of the project, the contractor must ensure that the list of suppliers and sub-contractors

who are invited to tender is comprehensive and that bids will be received. Pre-selection

procedures must confirm that quotations will be submitted and establish that the

particular supplier and sub-contractor has the necessary resources and the desire to tender

for the project. The procedures described previously must be applied if sufficient time is

available. In any event, confirmation must be obtained from major suppliers and sub-

contractors that they will be prepared to submit a bid, before enquiry documents are sent

out.

Programme and Method of Construction

The programme of construction is a schedule which shows the activities required to be

undertaken, the required durations, their start and finish dates.

27

Page 28: BT 358 ConstructionEstimating and Price Analysis

The method of construction is a description of how the contractor proposes to carry out

the required activities.

In order to obtain their maximum support and co-operation, suppliers and sub-contractors

must be advised of the programme requirements and any aspects of the method of

construction that are relevant. Programming information must necessarily include:

The anticipated start date for the main contract;

The approximate start dates for sub-contractor, or materials deliveries;

The required completion date(s);

Key information of significance to the progress of the works; and

Phasing.

Enquiries and requests for quotations

The objective of sending out enquiries is to ensure that technically accurate quotations

are received which are compatible with the main contractor’s conditions. Enquiries must

set out clearly the terms and conditions on which quotations are being invited. It is

recommended that limited numbers of suppliers and sub-contractors are invited to quote

for each item or section of the work. This conforms to the principles of selective

tendering and avoids the wasteful use of resources in requesting an excessive number of

quotations which one may not need or may not be able to process effectively. The time

allowed for the preparation of a tender is invariably short. The contractor has only a

limited period of time to distribute enquiries, thus any enquiries made should be relevant

enquiries which will be of benefit to a reasonable number of participants.

Supplier and material enquiries

Enquiries to suppliers of materials must state:

Title and location of the work, and site address;

Specification, class and quality of the material;

Quantity of the material;

Likely delivery programme, i.e. the period during which supplies would be

needed with daily or weekly requirements if these are known;

28

Page 29: BT 358 ConstructionEstimating and Price Analysis

Means of access, highlighting any limitations or delivery restraints; - any traffic

conditions which may affect delivery times;

Special delivery requirements such as pallets or self-unloading transport;

Date by which the quotation is required;

Period for which the quotation is to remain open;

Whether fluctuating or firm prices are required;

the basis for recovery of increased cost and the base date when a formulae is used

for calculation of fluctuations;

Discounts required; and

The person in the contractor’s organisation responsible for queries.

The contractor must record details of all enquiries sent to suppliers on an enquiry register.

Plant requirements

The contractor’s plant requirements should be established in the method statement and

the programme. They will establish the basic performance requirements of plant and in

many cases will have identified specific plant items needed for the works. The duration

for which the plant is needed on site will be established from the tender programme. The

estimator must firstly compile a ‘schedule of plant requirements’, in which the type,

performance requirements and durations for the plant should be listed.

A note must be made of the schedule of any additional requirements associated with a

particular item of plant which must be provided by the contractor. Power supply for a

tower crane, for example could be a significant extra cost and temporary access roads for

erection purposes may be needed together with foundations. Further details are therefore

necessary for certain non-mechanical plant.

With regards to scaffolding, a scaffolding schedule must be drawn up by the estimating

team in order to provide scaffolding contractors with a clear list of requirements. The

contractor may consider the intended method of working and programme requirements in

the specification for plant. In the case of formwork, equipment turnaround time and

29

Page 30: BT 358 ConstructionEstimating and Price Analysis

striking time will dictate the amount of formwork, support and access equipment needed.

A balance must be drawn between the speed of operation and economy in establishing

plant needs and all must be clearly reflected in the plant enquiry. A list of plant suppliers

must be established from companies who can meet the project’s requirements. The

options available for obtaining plant include:

1. Purchasing plant for the contract;

2. Hiring existing company owned plant; and

3. Hiring from external sources.

Let’s briefly explain each of these.

Purchasing plant for the contract

The decision to purchase plant for a particular contract is usually taken by senior

management. Such a decision requires knowledge of plant engineering and would

be made in accordance with the accounting policy of the company. The following

general factors must be considered when plant is to be purchased for a project and

sold on completion:

Purchase price less expected resale value after allowing for disposal costs;

Return required on capital invested;

Cost of finance;

Cost of maintaining the plant and associated overheads;

Stock levels of spares;

The company’s policy on depreciation;

Likely working life of the plant;

Cost of insurances and taxes, e.g. Road fund tax;

Any tax or depreciation allowances that are available;

Availability and cost of plant outside the company; and

Accessibility of he site in relation to company depot and servicing centres.

Hiring existing company owned plant

When plant is already owned by the company, the estimating department will be provided

with hire rates at which plant will be charged to the site or projects. The following list

30

Page 31: BT 358 ConstructionEstimating and Price Analysis

should be regarded - for guidance only - as the items which must be considered in

building up hire rates for company owned plant:

A capital sum based upon the purchase price and expected economic life;

An assessment of the costs of finance (interest for loan taken to acquire plant or if

bought on hire purchase);

The return required on the capital invested in acquiring the plant;

Grants and financial assistance available when purchasing the plant

Administration and depot costs;

Costs of insurances and road fund licenses; and

Maintenance time and cost and also cost of stocks needed for maintenance

purposes.

Hiring from external sources

Hiring of plant becomes an option where company owned plant is not available or where

the company does not have in its fleet the equipment required. In this case, enquiries

must be sent to external suppliers (plant-hire firms) for the plant required. Enquiries for

items of plant must either be sent specifying the particular machines and equipment that

are needed or specifying the performance required from the item of plant. Enquiries must

generally state:

Title and location of the work, and address of the site;

Specification of the plant or the work to be done;

Anticipated periods of hire with start date on site and duration required;

Means of access, highlighting any restraints or limitations;

Any traffic restrictions affecting delivery times;

Anticipated working hours of the site;

Date the quotation is required;

Period the quotation is to remain open;

Whether fluctuating or firm price required. The basis for recovery of fluctuations

and the base date when formulae are used for the recovery of fluctuations should

be stated;

Discounts offered (if any); and

31

Page 32: BT 358 ConstructionEstimating and Price Analysis

The person in the contractor’s organization to be contacted regarding queries.

In addition to the basic hire charge per hour or week, the enquiry must seek to establish:

Cost of delivering and subsequently removal of plant from the site on completion

of hire;

Cost of any operator, over and above the basic hire charge if provided by the

hiring company. ( if however this is provided by the contractor, the estimator

must produce a built-up rate for the operator’s costs);

Whether the hire rates quoted include those for servicing costs;

Any minimum hire periods applicable to the plant and the extent of any

guaranteed time; and

Cost of standing time and insurance cost for cases when the plant is retained on

site and not working for any reason.

Domestic Sub-contractorsSub-contractors will require the same details and information about the sub-contract

works as the main contractor requires for his tender. Selection of sub-contractors will

take into account skill, performance, integrity, responsibility and proven competence in

health and safety matters and for work of similar size and character to the project under

consideration as well as the sub-contractor’s interest in tendering for the particular

project. The principles of selective tendering relating to the main contractor must be

reflected in the number of sub-contract enquiries. The contractor’s enquiry and

information to the sub-contractors must state:

site and location of the works;

name of employer;

names of the consultants;

relevant contract and sub-contract details;

any amendments to the main contract, appendix or sub-contract conditions;

whether a fixing or fluctuating contract stating relevant details and rules

Dayworks rates as required;

dates quotations must be returned;

32

Page 33: BT 358 ConstructionEstimating and Price Analysis

general description of the works;

particulars of access to the site, available site plant, site industrial relations

policy, storage facilities etc.;

whether further details and drawing may be inspected;

contract period, programme, phasing requirements and method statement

details, start date and duration of sub-contract works;

any discounts required;

a copy of the relevant extracts from the preliminaries and the bills of quantity;

drawings, schedules and reports where applicable; and

services or attendances to be provided by the main contractor (if any).

Subcontract enquiriesContractors use a standard format for producing subcontract enquiries comprising a letter

addressed to each sub-contractor, a list of accompanying documents and an abstract of

contract conditions adapted for the project. Opportunity must be provided for sub-

contractors to see all the relevant drawings and project details as well as any assistance

available to ensure that the quotation received is the sub-contractor’s best price and not

unduly inflated owing to inadequate project information. The contractor may seek

quotations from labour-only sub-contractors for certain elements of the work. The

decision to use labour-only sub-contractors will take into account company policy,

availability of labour in the area, any special requirements concerning site labour policy

and market conditions. In this case, all items noted under ‘domestic sub-contractors’

apply. The contractor must gain further information concerning the status of the labour

only sub-contractor and verify if:

the sub-contractor holds a current relevant sub-contractor’s tax exemption

certificate; and

the sub-contractor’s insurances are adequate.

In addition, the estimator must allow for the cost of:

any attendances to be provided by the contractor;

responsibility for unloading, storage and distribution of materials;

supervision to be provided by the contractor;

33

Page 34: BT 358 ConstructionEstimating and Price Analysis

frequency of payments required by the sub-contractor;

retention sums relating to the sub-contracted work;

any additional costs that may arise once the sub-contractor has completed the

works and left the site; and

any additional risks.

The contractor must record all enquiries to the sub-contractors on the resource abstract or

a domestic sub-contractors’ register and then await receipt of the sub-contractors

quotations.

Materials

In relation to materials, any responses from suppliers should be recorded on the resource

abstract sheet or in a materials quotations register. In some practices, rates are entered on

a Materials Comparison Form for use during the pricing stage. Any discrepancies and

divergence from the enquiry must also be recorded on the register for later evaluation,

before selection of the quotation to be used in pricing unit rates. Quotations must be

checked to ensure that:

the materials comply with the specification;

the materials will be available when required in order to meet the requirements of

the construction programme;

no special delivery conditions have been imposed by the supplier;

the method of delivery complies with the contractor’s requirements and the

intended method of unloading and handling on site;

conditions contained in quotations do not amount to an alternative offer being at

variance with terms and conditions of enquiry;

the quotation is valid for the entire duration for which it is required;

prices are given for small quantities and other items if required;

discounts conform to the requirements of the enquiry; and

requirements concerning fixed or fluctuating prices are complied with.

34

Page 35: BT 358 ConstructionEstimating and Price Analysis

Plant

Rates for plant are entered on a Plant Comparison Form for use during the pricing stage.

Any discrepancies and divergence from the enquiry must be identified and also recorded

on the register. It must be borne in mind that where a performance specification was

provide for the plant, quotations must be carefully checked to ensure that the plant

offered meets the requirements defined at the enquiry stage. Quotations must be

scheduled to ensure that:

the plant complies with the project requirements;

the plant is available to meet the needs of the construction programme;

delivery and construction charges can be identified;

where applicable, all operator costs are included and the operators will comply

with the intended working hours of the site;

Any attendance or supplies to be provided by the contractor are clearly identified;

Maintenance responsibilities and charges are identified; in particular, any wear

and tear should be carefully noted;

Maintenance liabilities are identified;

The quotation is valid for the required period;

The quotation conforms to the terms and conditions of the enquiry and does not

represent an alternative offer; and

Requirements concerning fixed or fluctuating prices are complied with.

Stage 5: Planning and Temporary WorksPlanning takes place once enquiries have been made to sub-contractors and suppliers and

quotes obtained. The planning stage outlines how and when activities proposed under the

project will be undertaken.

Principal quantities

The first part of the planning stage is to extract the principal quantities from the bill of

quantity for the main elements of work. This is done by an experienced estimator or

planning engineer who should be aware of the operations likely to form important and

critical items in a programme. The amount of formwork, for example, has more

35

Page 36: BT 358 ConstructionEstimating and Price Analysis

significance to the programme than the volume of concrete to be placed. This is because

concrete can be placed quickly when required using large gangs or using a concrete

pump, whereas formwork outputs are limited by the number of skilled carpenters

employed on the site and the need to re-use materials wherever possible.

Principal quantities are usually provided in bills of quantity for civil engineering work

but rarely for building. It is not too difficult to abstract quantities from any bills of

quantity providing ancillary items and labour items are ignored. Computers on their own

are unable to assist in this appraisal because estimating software are unable to

differentiate between significant and insignificant items. In order to overcome this hurdle,

contractors may add an activity or operation code item entered in estimate file.

Method statements

Method statements are written descriptions of how operations will be carried out and

managed during a project. Method statements should not only deal with the use of labour

and plant in terms of types, gang sizes and expected outputs, but also include the way in

which the project will be organized.

It is essential that an early meeting is held between the estimator and those responsible

for the programming and construction of the project to discuss the method of

construction. In a smaller organisation, all of these roles may be undertaken solely by the

estimator.

In preparing the method statement, a contractor will gain a competitive advantage by

finding innovative and the most cost effective systems for temporary works and materials

handling. This appraisal of the scope of works and method could involve changes to the

design which may be offered as alternative tenders.

The primary purposes of the method statement are as follows:

i. To establish the principles on which the estimate is based; and

ii. To acquaint construction personnel with the resource limits which have been

considered in preparing the estimate and to describe the method of working

envisaged at the tender stage.

36

Page 37: BT 358 ConstructionEstimating and Price Analysis

The normal practice is that Clients or their consultants will request method statements

from contractors at tender stage. This provides the client with confidence in the

contractor’s ability to overcome construction difficulties and above all to deliver the

project on time. Other reasons for seeing a contractor’s method statement include:

satisfying statutory safety requirements, bringing out interface problems which might

exist with other contractors on site, and to demonstrate compliance with client’s overall

objectives such as ensuring production is not interrupted in a factory.

In successful tenders, the method statement will outline the sequence and methods of

construction upon which the estimate is based. It should indicate how it is proposed to

deal with the major elements of work as well as highlighting areas where new or difficult

methods are necessary or intended. This should be supported with details of cost data,

gang sizes, plant requirement and supervision requirements.

A pre-tender health and safety plan drawn up by the planning supervisor will be provided

to all tenderers. This will incorporate an identification of risks arising from the nature of

the work and the design. The design team must attempt to minimize risks to health and

safety during the construction stage and when the building is used and demolished.

The tender programme

The tender programme is the programme which shows a schedule of the works involved

and when the contractor proposes to undertake them. It is a vital document for the

contractor which represents the contractor’s intentions at the time of tender upon which

pricing of the works is based. Many standard forms of contract require the contractor to

submit a copy of his programme at an early stage of the contract. The programmed

submitted at this stage may be the tender programme as it reflects the contractor’s

intentions, based upon the tender information provided.

The contractor will not always be required to submit a tender programme with his tender.

In some cases, the contractor may only be required to confirm by signing the form of

37

Page 38: BT 358 ConstructionEstimating and Price Analysis

tender that all the works will be executed in accordance with the commencement and

completion dates stated in the project information received from the consultants.

However, good estimating practice dictates that the contractor must prepare a tender

programme which amongst other things will help (the contractor) to:

Verify that the date for completion is possible;

Maximise the efficiency of resources;

Price the time-related elements, in particular staff and site accommodation,

temporary works and general plant;

Establish the method and sequence of working;

Determine cost increases for firm price tenders;

Identify work which may be affected by seasonal weather changes such as bulk

excavation, drying the internal fabric of the building and landscaping; and

Consider making an offer with shorter contract duration.

The tender programme usually develops in two stages. First, a preliminary programme is

drawn up at an early stage of the project once the information has been assimilated. This

must take into account:

Contract commencement and completion dates;

Client requirements for phasing or stage completion;

Other stated requirements or sequence of work, i.e. delivery of client’s equipment;

Work to be carried out by directly employed labour;

Work to be carried out by domestic sub-contractors;

Work to carried out by nominated sub-contractors;

Key items to be supplied by nominated suppliers; and

Timing for temporary works items such as scaffolding.

The preliminary programme will identify the parameters of the project and the main

resources needed. It will establish key dates for major portions of the work and provide

basic information which can be used when obtaining quotations for materials, plant and

work to be sub-contracted.

38

Page 39: BT 358 ConstructionEstimating and Price Analysis

The preliminary programme will provide a basis on which construction method and

sequence can be developed. This can be done following the clarification of any queries

by the consultants and the site visit. When such queries and constraints have been

resolved, the tender programme can be produced from the preliminary programme, taking

into account the agreed construction method and sequence. The method statement can

also be finalised.

If design is incomplete at the tender stage, the contractor should incorporate in the tender

programme a series of key dates when design information (or instructions regarding PC

and provisional sums) must be given. It may well be that the contractor’s estimate is

based on early ordering of materials to obtain price advantage and/or long delivery

periods of materials. It is essential that design information is made available to reflect

these intentions and secure the prices contained in the contractor’s estimate.

A project overheads programme is superimposed on the tender programme in order to

quantify the time-related resources. When a client or his consultants require the

submission of a programme with a tender, the contractor produces a simplified version of

his tender programme. The simplified version is for the reasons below:

To make a well-presented submission

To allow opportunities for changes to be made by the site team when the

construction programme is produced

To offer an overall duration which meets the client’s general requirements and in

cases where time is critical, offer early completion; either because it is feasible or

to gain competitive advantage. (With non-adversarial forms of contracting such as

partnering, where co-operation is encouraged, and price is not an overriding

criterion, a contractor can look for alternative methods, sequences and resources

in order to offer an optimum solution)

To establish dates by which design information will be required to meet the

programmed completion date.

39

Page 40: BT 358 ConstructionEstimating and Price Analysis

Temporary works and plant schedules

The temporary works element of a project is designed by the contractor and as such is an

important opportunity for improving the competitiveness of his tender. For example,

innovative solutions adopted by a contractor for supporting structures or access

equipment can make the difference between winning and losing the contract. Another

illustration is this: it may be worth considering mobile access equipment which can be

cheaper to use than fixed scaffolding. This involves a question of scale, and the

advantages will depend on the size and complexity of the scheme.

The estimating team will mark up a site layout drawing to show the position of access

routes, restrictions, areas for storage and accommodation, temporary service connections

and distribution, temporary spoil heaps, carnage, batching plant, hoardings and

scaffolding. Schedules are commonly produced for traffic control and scaffolding, for

which prices are obtained from specialist contractors. The costs for temporary works are

calculated and summarized on the project overheads schedule forms.

Mid-tender review

The estimator should report regularly to management as part of the management of the

tender process. A mid-tender review meeting provides an opportunity for the estimator to

explain his approach and others to give their ideas and expectations for large projects.

Self assessment

i. Explain what you understand by the term Project Appreciation

ii. Describe the sort of enquiries which contractors may need to make whilst

putting a bid together

iii. Distinguish between “Method Statement” and “Tender Programme”

UNIT 2 PRINCIPLES FOR COMPUTATION OF ESTIMATES Unit objectivesBy the end of this unit, you will be able to:

i. Explain “all-in rates”;

40

Page 41: BT 358 ConstructionEstimating and Price Analysis

ii. Compute “all-in rates” for labour and plant;

iii. Explain unit rates;

Session 1-2 ‘All-in Rates” and Unit Rate ComputationLearning Outcomes

By the end of this session, you will be able to:

i. Explain the term “all-in rates”;

ii. Compute “all-in rates” for labour and plant

iii. Describe the main components considered when computing “all-in rates” for

plant and labour; and

iv. Explain how unit rates are developed.

Stage 6: “All-in” Rates and Unit Rate PricingIntroduction

In the pricing of bills, estimators need a clear and coherent strategy for building up their

estimate. Estimators should be able to read and understand drawings and technical

documents, and clearly understand the provisions of construction contracts. In this

session, we consider the processes which estimators go through in the preparation of

estimates. We will start by discussing what all-in rates are and how these are computed.

1-2.1 All-in Rates

Computing all-in rates is a very key component of construction estimating. The estimator,

needs to be able to calculate all-in rates for both labour and plant. We start this session by

explaining what all-in rates are for both labour and plant.

Composition of net unit rates

The steps involved in the building-up of unit rates may classified as follows:

Step 1

The establishment of ‘all-in rates’ for the key items that will be incorporated. It includes:

41

Page 42: BT 358 ConstructionEstimating and Price Analysis

A rate per hour for the employment of labour;

An operating rate per hour (or per day, per week etc) for an item of plant; and

The cost per unit of material delivered and unloaded at the site.

The cost of labour and some plant items are established after the visits to the site and

consultants. It is also necessary to complete the tender programme and method statement

before finalising these prices. It will be necessary to await receipt of quotations in respect

of materials, some plant items and sub-contracted work. With computer-aided estimating

systems, the estimator can use pricing with ‘notional’ rates because they can be adjusted

at any stage in the preparation of an estimate.

Step 2

Use standards from the contractor’s data bank or other sources. These standards are net

unit rates which are set against the items in the bills of quantity. Alternatively, rates

received from sub-contractors may be used.

Step 3

This stage involves the incorporation of rates from specialist trade contractors, including

those offering ‘labour-only’ services into producing either the whole or part of a rate.

The calculation and addition of project overheads is a separate and subsequent

operation.

Calculation of net unit rates

Principles

In calculating unit rates for inclusion in the bills of quantities, careful consideration must

be given to every factor which may influence the cost of the work. The establishment of

realistic production standards is a major consideration. There can be no substitute for

comprehensive company data and feedback from previous work of a similar nature to the

project being priced. Unit rates for measured items in the bills of quantity (excluding

preliminaries) consist of any or all of the basic elements:

42

Page 43: BT 358 ConstructionEstimating and Price Analysis

Labour;

Plant;

Materials;

Sub-contractors;

Overheads (site and head office); and

Profit.

It is recommended that each element is analysed and estimated separately and that the

total cost of all elements is considered by management. This approach is sometimes

called ‘analytical’ estimating.

Constituents of a rate build-up

It needs to be explained that not all of the aspects described below will apply to all items

during estimation. For example, the number of times a square metre of formwork can be

re-used is obviously irrelevant to brickwork (and other) items. The important thing

however is to understand the underlying principle and to make the necessary application

whenever required.

A key point to note is that it is essential that estimators’ calculations are coherent.

Sometimes, estimates may be left for an extended period before being referred to again –

and the intervening period can make it difficult to remember exactly what was meant if

terminology or notes which are not clear are used. Again if assumptions were made

which were not properly recorded, it may be difficult to remember exactly the situation

was. For example, the output for a given piece of plant was assumed, it would be difficult

after a long while to remember the original assumed output, say. In addition, estimating

calculations are often referred to by persons other than those who originated them (e.g.

site surveyors, contract managers and so on). To remove any possible ambiguity in the

future, it is essential that rate build-ups are:

Well described/explained;

Detailed; and

Well illustrated (where applicable).

43

Page 44: BT 358 ConstructionEstimating and Price Analysis

The following are essential constituents of a rate build-up:

1. Assumptions

State all the basic facts on which your build-up is based. E.g.:

Cost of all resources (i.e. labour, plant, materials etc.);

Units that resources are costed in (e.g. hours, tonnes etc);

State what is included in these costs. For example, in the case of labour have you

used an ‘all-in’ rate? What category of labour are you using? For materials

costs, who pays for unloading? (i.e. will the supplier do this – or will the main

contractor, have to do it?);

Output/production rates on which you have based your calculations;

Wastage rates for different materials; and

Number of uses for formwork items.

It is generally advised that wherever possible sketches which explain/expand on any

assumptions that may have been made should be provided. It will probably be essential

for you to provide sketches for formwork items and temporary works.

Gang rates

Some of the calculations required to estimate the cost of a bill item may be found in

many items. For example, it’s usual for an estimator to decide on the size of gang for

brickwork when starting work on a ‘Brickwork’ bill. If a gang of two bricklayers and

one labourer is chosen, this gang will probably be used for most brickwork items.

Clearly it makes sense to calculate this rate once – and re-use it many times. The

estimating jargon for this “preliminary” calculation is a “gang rate”. In the context of

this example, note that estimators (and site QS’s, Contract’s Managers etc.) think of

outputs in terms of what one person can produce per day (or per hour). The gang rate

for the 2 + 1 brickwork gang would look like this:

2 bricklayers@ GH¢6.00 GH¢12.00/hr

1 labourer @ GH¢4.50 GH¢ 4.50/hr

44

Page 45: BT 358 ConstructionEstimating and Price Analysis

Total GH¢ 16.50/hr

Divided by 2 GH¢ 8.25/hr

So – for each hour that a bricklayer works, half a labourer hour is allocated (to supply

him with materials, clear up etc). The production rates that construction professionals are

familiar with assume this assistance.

In addition, estimators need to include these associated “servicing” costs so that the rate

they arrive will allow all costs to be recovered.

Gang rates are usually calculated separately before the “main” calculations.

The main calculations

This is the main task of a rate build-up. If the previous sections have been well

documented, this may be a very short section.

1-2.2 All-in labour rates

The all-in-daily rate of any operative may be defined as the total cost to the employer for

employing an operative’s services for “one operative labour day’s” output. It must be

explained that in this case, the employer is the contractor. The all-in rate for labour is

built up from the following:

1. The basic daily wage of the operator involved.

2. Statutory additions such as employer’s contribution to the national provident

fund, workmen’s compensation insurance, rent and leave allowances.

3. Trade union requirements of tools allowances for tradesman using their own tools,

uniform or protective clothes and trade supervision.

4. Social expenses like canteen subsidy, sick pay, death benefits, medical expenses

and transport allowances.

5. Unforeseen expenses such as bad weather days, idleness and overtime

requirements for necessary work required to keep delivery schedules.

45

Page 46: BT 358 ConstructionEstimating and Price Analysis

Illustration of how all-in daily rates are computed for labour

A typical computation of the all-in-daily rate starts with the calculation of the effective

number of working days per year. This is calculated as follows:

For a typical year, number of days per year 365

less number of days for weekends in a year, 2 x 52 days for week-ends 104

National holidays in a year 13

Annual leave 18

Bad weather days 7

Bad weather days 13 155

Hence effective working days/year 210

In computing the typical number of working days in a year, we need to explain here that whilst

the number of weekends in a year is constant, the others have been assumed. The assumptions

ensure a measure of uniformity in computations which use the number of days in a year.

Now that we have calculated the number of effective working days in a year, let’s go ahead to

compute the all-in rate of some operatives. In the example in table 2.1, we will compute the all-in

daily rate of a labourer, carpenter, painter, mason and steel bender. The all-in daily rate is

obtained by applying a set of Multiplying Factors (MFs) to the consolidated daily wage of the

respective operatives. Assume consolidated basic daily wage of each of the operatives to be 1.00.

Now let’s proceed to compute the respective all-in daily rates for each of the operatives.

46

Page 47: BT 358 ConstructionEstimating and Price Analysis

Table 2.1 Computation of “all-in rates for labour

MULTIPLYING FACTOR (Mf)Description Labourer Carpenter Painter Mason Steel

BenderA. Basic daily wage as consolidated to

coveri. wage + rent + leave

allowanceii. canteen subsidyiii. transport

B. MF/month at 27 days pay

C. MF/year (B x 12)

D. MF/working day at 210 days/year = C/210

E. Statutory additions: MF i. social security 0.125 } ii. Workmen’s comp. 0.025 }0.15 F. Social benefits: i. medical expenses 0.200 ii. death expenses 0.294 iii. end of service award 0.533 (1.027) G. Tools allowance H. Sub total I. Direct supervision at: 1.25H = 0.21H 6

1.00

27.00

324.00

1.00

27.00

324.00

1.00

27.00

324.00

1.00

27.00

324.00

1.00

27.00

324.00

1.543

0.150

1.543

0.150

1.543

0.150

1.543

0.150

1.543

0.150

1.027 1.0271.300

1.027

1.300

1.027

1.300

1.0271.300

2.720

0.567

4.020

0.838

4.020

0.838

4.020

0.838

4.020

0.838

J. Total (working day is all-in-day labour Multiplying factor)

K. If daily basic rate (usually recommended government minimum wage) is

3.287

GH¢2.20

4.858

GH ¢2.20

4.858

GH ¢2.20

4.858

GH ¢2.20

4.858

GH¢2.20 L. All-in-daily rate M. Current all-in-daily rates

GH¢7.23GH¢7.20

GH ¢10.69GH ¢10.70

GH ¢10.69GH ¢10.70

GH ¢10.69GH ¢10.70

GH¢10.69GH¢10.70

47

Page 48: BT 358 ConstructionEstimating and Price Analysis

1-2.3 All in-rate for Plant

The all-in daily rate for an item is the cost to the employer (the contractor) of employing the

services of the item of plant for one plant day’s output. This thus represents all the costs

which the employer pays as a result of using the plant for one plant day’s work.

Computation of all in-rate for plant

In the Ghanaian construction context, it is common practice to hire items of construction

plant for projects on a daily rate basis. It is therefore important to be able to compute

accurately the all-in-daily plant rate the plant used on projects. The main components of the

all-in-daily rate for plant are as follows:

1. The daily hiring rate (this normally includes the operator’s wage) ;

2. Delivery and installation (where necessary), maintenance and removal expenses;

3. Running expenses for fuel, oil and other consumables;

4. Administrative charges for co-ordination of services relating to the plant.

Table 2 shows some information relating to different plant items which can be used during estimating.

Table 2.2 Plant information for estimating (Credit: Amoah Mensah, 1995)

(1)

Description

(2)

Achieved economic life years

(3)

Average utilization days/years

(4)

Repair and renewals 5 of

annual depreciation

(5)

Running and consumables % of annual depreciation

(6)

Overhead cost % of

annual depreciation

(7)

A.B.C.D.E.F.G.H.I.J.K.L.

Tipper trucksDumpersBulldozerWheel loaderGraderBoilerConcrete mixerCrane(Mobile)Crane(Static0CompressorWater pumpPoker vibrator

545447457533

1502001001501406015010080808060

252025303310151010203020

252530252525252517252525

101010101010101010101010

48

Page 49: BT 358 ConstructionEstimating and Price Analysis

Building up of unit ratesThe process of building up unit rates for an activity involves the extraction of the resources

content in terms of materials, labour and plant for each bill item. This is followed by a

computation of the respective costs of each of them. We will be considering in more detail

how to build-up unit rates later in this manual.

This will be done under the respective work sections complete with examples. For the

moment however, let us look at the general factors which influence the inputs which are

considered when building-up rates.

1-2.4 Composition of net unit rates

In the composition of net unit rates, the activities may be grouped into three distinct stages.

The stages are as follows:

Stage 1

The establishment of ‘all-in rates’ for the key items that make need to be considered. This

includes:

A rate per hour for the employment of labour;

An operating rate per hour (or per day, per week etc) for an item of plant; and

A cost per unit of material delivered and unloaded at the site.

The cost of labour and some plant items are established after the visits to the site and

consultants. It is also necessary to complete the tender programme and method statement

before finalising these prices. It will be necessary to await receipt of quotations in respect of

materials, some plant items and sub-contracted work. With computer-aided estimating

systems, the estimator can use pricing with ‘notional’ rates because they can be adjusted at

any stage in the preparation of an estimate.

49

Page 50: BT 358 ConstructionEstimating and Price Analysis

Stage 2

Use standard rates from the contractor’s data bank or other sources. These standards rates

may be net unit rates which are set against the items in the bills of quantity. Alternatively,

rates received from sub-contractors are used.

Stage 3

Incorporation of rates from specialist trade contractors, including those offering ‘labour-only’

services in producing either the whole or part of a rate. (The calculation and addition of

project overheads is a separate and subsequent operation).

Principles for calculating net unit rates

In calculating unit rates for inclusion in the bills of quantities, careful consideration must be

given to every factor which may influence the cost of the work. The establishment of realistic

production standards is a major consideration. If comprehensive company data and feedback

from previous work of a similar nature to the project being priced is available, this will be

very helpful. Unit rates for measured items in the bills of quantity (excluding preliminaries)

consist of any or all of the following basic elements:

Labour;

Plant;

Materials;

Sub-contractors;

Overheads (site and head office); and

Profit

It is recommended that each element is analysed and estimated separately and that the total

cost of each of all elements is considered by management. This approach is sometimes called

‘analytical’ estimating.

So far, we have seen how to compute the all-in rates for labour and plant. Let us have a look

at some of the considerations that need to be made when computing the cost of materials

during estimating.

50

Page 51: BT 358 ConstructionEstimating and Price Analysis

Material input and waste

In determining the total material input in a bill of quantities, the net material content and

associated wastes in respect of that material should both be considered. With regard to

material waste, this may be classified into two. These are AVOIDABLE and

UNAVOIDABLE wastes. The classification of waste into these two categories is based upon

the causes of the waste and the potential to minimize its occurrence. A close examination of

each waste type gives an indication that with proper supervision and reporting procedures for

effecting corrective measures promptly, the amount of avoidable wastes can be pushed down

towards total elimination while the extent of the other wastes can be minimized. Table 2.3

shows examples of the two types of waste.

Table 2.3 Classification of construction material wastes

Avoidable waste Unavoidable wastePilfering CarelessnessPoor quality work demolished to be made goodWrong utilization or preparationMistakes in ordering, both in quality and quantityImproper storageIneffective supervision

Cutting wasteDamage in transitStock pile or residual wasteUtilization waste

From this stage, we will be looking at a few examples which will help to illustrate how to

estimate for specified construction activity. But before we start, let’s look at the tables shown

below. Table 2.4 to table 2.7 present information which will be very useful to us in our

estimating work. We will be referring to them from time to time. Please take sometime now

to look at these tables and try to appreciate the information presented in the tables.

51

Page 52: BT 358 ConstructionEstimating and Price Analysis

Table 2.4 Outputs for different methods of excavation in gravel soil Credit: Amoah Mensah (1995)

Item Method used for Excavating in Gravel Soil OutputA 250HP-D8 Bulldozer in oversite excavation 150m deep 500m. sq / plant dayB 250HP-D8 in reduced level excavation 80cubic metres / plant day

C Manual excavation to reduce levels 3 cubic metres / man day

D Load and wheel excavated material 100m away 5 cubic metres / man dayE Load excavated material only- 10 cubic metres/ man dayF Filling excavated material around foundation 5 cubic metres / man day

GSpread, level and compact excavated material in layers not

exceeding150mm thick5 cubic metres / man day

H Spread and level hardcore in layers not exceeding 150mm thick 4 cubic metres / man day

I Compressor breaking through rock or concrete6 cubic metres/plant day

per drillJ Compacting hardcore with mechanical compactor and operator 8 cubic metres / plant dayK Spreading and leveling only 10 cubic metres / man day

Table 2.5 Multipliers for different excavation types and depths. Source: Amoah Mensah (1995)

Item Description ( Manual output)Depth Category

0-1m 0-2m 0-4m 4m

1 2 3 4 5 6

A

B

C

D

Surface not exceeding 30mm deep

Basement

Trenches

Pits

1.000

0.85

0.83

0.75

-

0.75

0.70

0.60

-

0.06

0.30

0.40

-

0.05

0.40

0.30

Table 2.6 Effect of soil type and bulkage effect on excavation output

Item Type of soil Multiplying factor Bulkage factor

1 2 3 4

ABCDE

GravelCompact soil (laterite)

Soft rockHard rock

Loose soil and sand

1.001.000.700.300.60

20.0022.0035.0050.0033.33

52

Page 53: BT 358 ConstructionEstimating and Price Analysis

Table 2.7 Outputs for different depths of earthwork support

Item Description Depth

1 2 3 4

A

B

Fixing timber pooling

boards,

walling and struts

Stripping

0.8 cubic metres/ gang day

1.5 cubic metres/ gang day

0.6 cubic metres / gang day

1.00 cubic metres / gang day

CUnloading and stacking

of timber

4.00 cubic metres / man day or 150 pieces of

50x150x360mm

Methods of Pricing

There are different approaches which estimators use to arrive at the best possible price for

items.

In general, items need not be priced in the order they appear in the bills because a better

understanding of activities can be gained by pricing one trade at a time. This is becoming

increasingly popular, especially with computer estimating systems which readily sort the bill

items into trade order (similar items). Computers also allow resources to be entered either

through a resource build-up screen for each item or with the aid of a ‘spreadsheet’ type

comparison system where like trade items can be viewed in a single table. If it is known that

quotations for materials will be delayed, the estimator can price labour and plant first, and

return to part-priced items later when quotations are available. On the other hand, ‘typical’

materials prices may be used during the pricing stage. Computers allow late adjustments to

be made and all affected items will be changed. All these techniques are derived from manual

pricing methods but with computers are now faster and more accurate.

Self-assessment questions

i. What do you understand by the term “all-in rates”?

ii. Describe the main components considered when computing “all-in rates” for plant

and labour; and

iii. Explain briefly how unit rates are developed.

53

Page 54: BT 358 ConstructionEstimating and Price Analysis

SESSION 2-2 PC Sums, Provisional Sums and OverheadsLearning Outcomes

By the end of this session, you will be able to:

i. Explain how PC Sums are taken care of during estimating

ii. How Provisional Sums are estimated

iii.Identify different types of Overheads and how they are estimated

Stage 7: PC and Provisional Sums

In order to avoid confusion in calculating and analysing an estimate, it is recommended that

prime cost and provisional sums should form a separate section at the end of the measured

work part of the document which is being priced. Since this is not always the case, estimators

must carefully check all the bill pages, including preliminaries, to ensure that the written-in

sums are incorporated in the final tender amount.

2-2.1 PC Sums

Nominated suppliersStandard methods of measurement state that the cost of materials from nominated suppliers is

to be identified in the tender documents as prime cost sums. A separate item is also given for

the contractor to add his profit. PC sums may also be written-in to an item description (such

as a rate for the supply of facing bricks) for the estimator to incorporate the cost in his rate

build-up.

The estimator will produce a list of nominated suppliers at an early stage using a ‘schedule of

PC sums and attendances’. Where details associated with a nominated supplier are unclear,

the estimator must note any concerns in his report for further consideration at the final review

meeting.

If a PC sum has been included for high value materials or large quantities, the estimator must

check the following:

That the terms of the purchase contract provides for the nominated supplier to allow the

contractor a discount (for payment in full within 30days of the end of the month during

54

Page 55: BT 358 ConstructionEstimating and Price Analysis

which delivery is made). Where it is offered, this discount is normally deducted from the

estimate in order to include net costs in the summaries for the final review meeting. Since

this discount is not available through the terms of all main contracts the estimator must

check the relevant contract conditions and not assume a discount is available.

Delivery times and their effect on the programme

Fixing items associated with materials provided by a nominated supplier need to be

adequately described and measured in the items to be priced. Any discrepancies

concerning fixings, such as bolts, screws, brackets, adhesives and sealants, or ambiguity

over the responsibility for supply of these items must be clarified.

Additional costs for unpacking, storage, handling, hoisting and the return of re-usable

crates or other packing, since the contractor may be required to return such items to the

supplier. Due allowance must be made for the collection, storage, handling and

subsequent dispatch of such items back to the supplier.

Where bills of quantity are used, the fixing of materials supplied by nominated suppliers is

measures in the appropriate part of the bill.

Nominated sub-contractors

A nomination arises in construction contracts where the selection of a sub-contractor is to be

made by the client or his representative. When this happens, a prime cost sum is inserted in

the tender documents to cover the nominated sub-contractor’s charge.

There is a right of objection to a particular nominated sub-contractor because it would be

contrary to contract law if a party is forced into a contract unwillingly. Where prime cost

sums are included in bills of quantity, the estimator is seldom given the name of the proposed

sub-contractor and so it is impossible to discuss methods and programming issues.

Nominated sub- contractor information for BOQ

The standard method of measurement gives the items to be included in the bills of quantity

for each nominated sub-contractor, as follows:

The nature and construction of the work;

55

Page 56: BT 358 ConstructionEstimating and Price Analysis

A statement of how and where the work is to be fixed;

Quantities which indicate the scope of the work;

Any employers’ limitations affecting the method or timing of the works;

A prime cost sum;

General attendance item;

An item for main contractor’s profit, to be shown as a percentage; and

Details of special attendance required by the sub-contractor.

Attendances

Attendance is defined as, ‘the labour, plant, materials or other facilities provided by the main

contractor for the benefit of the sub-contractor and for which the sub-contractor normally

bears no cost’. The main character is under the main contract position for the site

establishment and providing attendance. This provides clear responsibility for the support

service and equipment needed on site and duplicate resources for various resources sub-

contractors. For every large contract where a construction manager or management

contractor has overall control, trade constructions are asked to provide certain parts of the

temporary works and facilities themselves. The cost associated with attendance are built into

the main contractor’s tender and consequently become a charge against the client. However,

the associated risks of attendance are borne by the main contractor.

The item for general attendance is the indication of the facilities which are normally available

to sub-contractors where they are provided by the contractor to meet his own requirements.

In assessing any sums to be allowed for general attendance, the estimator must investigate

the facilities which will already be provided for the main contractor’s use and determine any

cost which may arise by the nominated sub-contractor’s use of any such facilities. The

facilities given in SMM7 include:

use of temporary roads, pavings and paths;

use of standing scaffolding;

use of standing power operated hoisting plant;

use of mess rooms, sanitary accommodation and welfare facilities;

providing temporary lighting and water supplies;

56

Page 57: BT 358 ConstructionEstimating and Price Analysis

providing space for sub-contractor’s own office accommodation and for storage of his

plant and materials; and

clearing away rubbish.

Other specific attendances which do not fall under the category of ‘general attendance’ must

be specially measured in the bill of quantity as ‘special attendance’. Items to be measured

include:

special scaffold for addition to the contractor’s standing scaffolding;

the provision of temporary access roads and hardstandings in connection with

structural steelwork, pre-cast concrete components, piling , heavy items of plant and

the like;

unloading, distributing, hoisting and placing in position of items required as part of

“special attendance”, giving in the case of significant items the weight, location and

size;

the provision of covered storage and accommodation including power supply to

these;

power supply giving the maximum load; and

any other attendance not including ‘general attendance’ or listed above.

2-2.2 Provisional sums

“Provisional sum” is as a sum provided for work or for costs which cannot be entirely

foreseen, defined or detailed at the time the tendering documents are issued. Provisional

sums are included in bills of quantity for items of work which cannot be fully described or

measured in accordance with the rules of the method of measurement of the time of tender.

For work measured under the rules of SMM7, there are three types of provisional sum: These

are as follows:

i. Provisional sums for defined works;

ii. Provisional sums for undefined works; and

iii. Provisional sums for works by statutory authorities.

57

Page 58: BT 358 ConstructionEstimating and Price Analysis

Provisional sums for defined works

This describes the situation where all the information required in support of a defined

provisional sum is given in the description of the provisional work attached to the provisional

sum. In this case, the contractor is deemed to have made due allowance in his tender for that

work in programming, planning and pricing preliminaries.

Provisional sums for undefined works

This describes the situation where all the information relating to provisional work is not

provided. In this case, the contractor is deemed not to have made allowance for the costs in

his tender. As a result, it is very important that provisional sums for undefined provisional

work include the necessary allowance to cater for the costs deemed not to have been included

by the contractor in his lump sum. A client’s contingency sum is deemed to be an undefined

provisional sum.

Provisional sums for works by statutory authorities

SMM7 makes provision for provisional sums to be included in a bill of quantities which is

neither ‘defined’ nor ‘undefined’ for work to be carried out by the local authority, suppliers,

sub-contractor or statutory undertakers including private services authorities carrying out

statutory works. Where any of these are mentioned as a result of provisional sums, the

provisional sum inserted must be sufficient to also cover the main contractor’s profit and

attendances, and where required, fixing only of any items supplied.

Incorporating provisional sums in an estimate

With the exception of provisional services provided by statutory authorities, provisional sums

are deemed to include an allowance for main contractor’s head office or overhead profit. All

provisional sums will become the subject of an Architect’s instruction during construction

and the work will be valued according to the appropriate contract rules for measurement and

valuation which include the provision for overheads and profit. Alternatively, if it is

company practice to add head office overheads and profit to the total value of measured and

un-measured work, provisional sums should be discounted before entry in the summary to

avoid duplicating the overheads and profit for this type of work.

58

Page 59: BT 358 ConstructionEstimating and Price Analysis

Dayworks

Dayworks normally occur where variations cannot be valued by measuring using the rates or

comparable rates, nor by negotiation before an instruction is issued. The Dayworks charges

are usually calculated using the definitions for prime cost and overheads. The prime cost of

Dayworks can be defined in other ways, so care must be taken in reading the definition in the

tender documents. It is important that contractors understand the circumstances under which

varied or additional work will be valued on a Dayworks basis.

The composition of the total Dayworks charge will include the following costs:

Labour;

materials and goods;

plant;

supplementary charges (civil engineering contracts); and

incidental costs, overheads and profit (this addition will vary between labour, plant

and materials, and, in order to introduce competition at tender stage, is added to

provisional sums for the prime cost of labour in the bills of quantity by the

contractor).

An alternative method (for labour to be valued on Dayworks basis) is for the contractor to

provide all-in gross hourly rates which are applied to provisional hours. This makes the

calculation of the Dayworks simpler during the course of the project but moves the burden

for anticipating increased costs to the contractor.

Contractors may decide that some of the projects and head office overheads are covered in

the contract price and may be excluded from Dayworks rates. This is mainly true if the

Dayworks to be carried out during the currency of the contract will not result in extension to

the contract but other additional costs to project and head office overheads may still have to

be considered.

It is inappropriate to use this payment method for anything except work which is incidental

to contract work. In the event that significant changes are made to the original scope of

works the valuation rules normally allow additional overhead costs to be recovered, usually

59

Page 60: BT 358 ConstructionEstimating and Price Analysis

when the full effects of changes are known. Decisions concerning allowances for profit and

overheads must be made by each contractor taking into account his own circumstances,

method of working and his assessment of the effects of Dayworks on a particular project. The

contractor must assess each contract on its own merits in producing Dayworks rates and

calculating the percentage addition needed. This will include an assessment of likelihood of

the prime cost being a reasonable pre-estimate of the work which will be valued on a

Dayworks basis.

The contractor’s Dayworks percentages must take into account the rates required by the sub-

contractors used in the tender. Enquiries to sub-contractors must include a request for

Dayworks percentages based on the definition incorporated in the main contract. For

mechanical and electrical installation in building contracts, the contractor is given the facility

to state different percentages for specialists in the bills of quality.

As Dayworks are calculated inclusive of an allowance for overheads and profit, they should,

like provisional sums, be added to the final summary after the application of overheads and

profit.

Self-assessment questions

i. Give examples of PC Sums and explain how these are taken care of during estimating

ii. Identify examples of “Provisional Sum” items. Describe how estimates are obtained for these

items

60

Page 61: BT 358 ConstructionEstimating and Price Analysis

Session 3-2 Project Overheads (Stage 8)

Learning outcomes

By the end of this session, you will be able to:

i. Explain the term “project overheads”

ii. Identify the different types of “overheads” associated with construction projects

iii. Explain how different types of “project overheads” are estimated

The Code of Estimating Practice defines overheads as ‘the cost of administering a project

and providing general plant, site staff, facilities, site-based services and other items not

included in all-in rates’. The contractor’s opportunity to price for these items is in the

preliminaries section of the bill, the section containing the basic background and contractual

conditions of the contract. The pricing of preliminaries is a key factor of the estimating

process, because it is here that the contractor has the opportunity to cover the cost of

operating the site under specified conditions and in accordance with the contractor’s plan for

progress of the work, storage and movement of materials.

The standard method for measuring for civil engineering and building gives the general items

which should be described as part of overheads in bills in two main parts: the specific

requirements of the employer and the facilities which must be provided by the contractor to

carry out work. Items listed in the preliminaries/general conditions section of a bill of

quantities are not exhaustive and are provided to produce a framework for convenience of

pricing. The actual supervision, site facilities, plant and temporary work to be employed will

be decided by the contractor unless it is clearly stated that certain systems must be used.

SMM7 defines a Fixed Charge as the cost of work which is to be considered as independent

of duration, and a Time Related Charge as the cost of work which is to be considered as

dependant on duration. Items in bills of quantity for Employer’s requirements and

Contractor’s general cost items are given for both categories. The purpose is to improve the

allocation of values in valuation for interim payments and variations. Some bills of quantity

61

Page 62: BT 358 ConstructionEstimating and Price Analysis

list value-related items for general items such as insurances, bonds and the supply of water to

the site on the bill summary page.

Programme

The tender programme is a vital tool for the calculation lf project overheads. The cost of

many items will vary in direct proportion to the contract period and the length of time that

staff, facilities, plant and temporary words will be required on the site. It is normal for costs

to be built up on a fixed-charge and a time-related basis. For example, in setting up a tower

crane, a high fixed charge is met at the start. There follows a recurring cost related to the time

the equipment is on site. There will then be a subsequent fixed cost for removing the

equipment on completion. By estimating such items in these two distinct forms, changes to

the programme can be evaluated quickly, by reference to the time-related costs. The

estimator will be able to use the tender programme for most of his calculation or develop

project overheads programme. A carefully prepared tender programme will provide a

contractor with the opportunity to reduce the contract duration leading to cost savings for

staff, temporary workers and plant. Since the prices for the measured portion of a bill will be

similar for all contractors, it is the innovative planning skill which produces a competitive

advantage over other tenders. If, on the other hand, the client wishes to retain a longer

contract period (to avoid claims for extension of time, for example) the contract can be at risk

if he allows sufficient staff for only part of the time.

Project overheads schedule

The estimator’s notes must now be brought forward for consideration and entered in the

various sections of the ‘Projects Overheads Schedule’. In addition, other items which have

not been included in unit rates must also be considered and costs established. Items may be

added to or omitted from those listed according to the preferences and policies of individual

companies. Various techniques exist to price these items and in some organisations, the

project overheads are worked back into unit rates. This is a matter for each company to

decide. The total estimate of the cost of project overheads is transferred from the schedule to

the final summary document. Contractors and firms, carrying out small repetitive works,

often apply a fixed percentage for overheads (about 10 – 15%). The pitfall with this approach

62

Page 63: BT 358 ConstructionEstimating and Price Analysis

is the site overheads, particularly the supervision, will be proportionately higher for small

value jobs which are to be carried out to an extended programme. It is also necessary to price

temporary works such as scaffolding separately because they are rarely related to the value of

the works.

3-2.1 Classification of project overheads

Project overheads are usually classified as follows:

Direct overheads – those which relate to a particular project including management and

supervisors, site accommodation, temporary services and plant. They can be calculated on a

weekly or monthly basis and converted to a total cost for the whole project by relating these

costs to the project duration. The total cost is either included as a lump sum or a percentage

addition to the unit rates. It is also usual to include a figure for profit and attendance on sub-

contractors in the preliminaries. This is more logical since attendances are often time rather

than activity related, and often provide for the benefit of several sub-contractors, such as

scaffolding, rubbish disposal, and hoisting etc.

Indirect overheads – these are the general costs relating to the contractor’s business such as

office rent, rates of pay for general staff such as secretaries, pay-roll staff, senior

management and professional support staff (who will have to be paid regardless of the

amount of work that the contractor is winning) and the company’s finance costs. These are

usually calculated for forthcoming years on the basis of previous years’ costs, with every

project contributing towards them.

Project overheads may be divided into employer’s requirements and contractor’s general cost

items. Most contractors will usually lump together the client’s requirements with his own

(e.g. site accommodation will be considered together both for the clients huts and the

contractor’s huts). The following are the main groups of items to be considered as part of

project overheads:

(1) Employer’s requirements - This category of overheads is used for the

accommodation, equipment and services needed by the employer’s representative

63

Page 64: BT 358 ConstructionEstimating and Price Analysis

when based on site. According to SMM7, heating, lighting, cleaning and

maintenance of employer’s accommodation are deemed to be included. The term

‘employer’s requirement’ usually includes other terms such as quality standards,

safety, security, protection, limitations on method and programme, specific

temporary work and services.

(2) Supervisors - Since the management and staff are the largest part of project

overheads, the estimator must propose the smallest team with the skills needed to

produce a successful project. This will include all personnel whose costs have not

been included in unit rates or head office overheads, whatever their method of

remuneration.

(3) Accommodation – The hire-purchase of accommodation should be considered

under this section. Reference to the method statement and programme will be

necessary to determine the intended layout of the site and time period for the

various elements of accommodation.

Transportation, erection, fitting out and decoration, subsequent dismantling and

reinstatement are noted in the fixed cost section of the form.

(4) General labour - General labour can be viewed as a resource to service all trades

and sub-contractors on a site. This can include keeping the site tidy, unloading

materials, distributing materials and driving mechanical plant.

(5) Site facilities - It is sometimes difficult to distinguish between site facilities and

temporary works. Site facilities generally include installation and removal of

services and associated consumable items. Other facilities such as temporary

structures and hardstandings, which are directly associated with the nature of the

works, are entered in the temporary works sheet.

(6) Temporary works - The cost of temporary access roads, hoardings and temporary

structures are determined in this section. Recurring costs to maintain access road

64

Page 65: BT 358 ConstructionEstimating and Price Analysis

and reinstatement of the site. The method of statement and tender programme are

important in establishing the systems and durations for these items.

(7) Mechanical plant - Mechanical plant is included in the project overheads for two

reasons:

Plant which is common to more than one trade can be viewed as common

plant available to all. On a small site, for example, one mortar mixer can

service the bricklayers, drain-layers and plasterers laying screeds. In fact one

mixer may be needed for a large part of contract duration.

To reconcile the plant included in measured rates so that plant resources can

be rationalised. A backacter, for example, would not be used for a few days,

taken off site for a day and then brought back for intermittent periods. By

using the same machine for drainage and earthworks, it may be useful to

employ one machine for an extended period.

(8) Non-mechanical plant - The largest item of non-mechanical plant is scaffolding

and ancillary equipment such as debris netting and rubbish chutes. Small (hand)

tools and equipment may be included in the ‘all-in’ rate for labour since their

value must be in proportion to the amount of labour employed on the works.

(9) Contract conditions – The preliminaries section of the bills of quantity and the

actual conditions of contract must be scrutinised to ensure that all items attracting

a monetary value have been included in the cost estimate. The cost of bonds,

insurance and professional services (where applicable) should be recalculated

after the final review meeting as a percentage of the contract value.

(10) Miscellaneous - Any unusual features associated with the project which do not

fall naturally into the defined categories can be priced in this section. Safety and

quality assurance procedures will be an everyday part of a site manager’s work,

and should not bring about additional costs on small and medium-size contracts.

Pricing preliminaries accurately should involve the following steps:

65

Page 66: BT 358 ConstructionEstimating and Price Analysis

1. Evaluating the requirements of the project and site;

2. Evaluating the likely specific requirements of the client through the project brief

and through discussions with him;

3. Preparing a site layout drawing, accommodation, access, storage and all

services (temporary and permanent). Note any special provisions required (e.g.

traffic management etc.);

4. Preparing a project overheads programme and showing the requirements for staff,

plant and temporary works;

5. Breaking down the preliminary costs into fixed and time-related costs; and

6. Completing the project overhead proformas with prices derived from price books

and other costs sources.

Self assessment questions

i. Explain what you understand by the term “project overheads”

ii. List and explain the different types of “overheads” associated with construction projects

iii. Briefly describe how different types of “project overheads” are estimated

66

Page 67: BT 358 ConstructionEstimating and Price Analysis

UNIT 3 BID SUBMISSION AND ACTION AFTER SUBMISSIONUnit objectivesBy the end of this unit, you will be able to:

i. Explain how the final estimate is obtainedii. Explain the “adjudication process”iii. Describe what happens once the tender has been submitted

Session 1-3 Completing and submitting the bidLearning Outcomes

By the end of this session, you should be able:

i. Explain what actions are taken to arrive at the final estimate;

ii. Explain the term “tender adjudication” and explain what happens during the

adjudication process

iii. Describe what happens during the “final review”

iv. Explain the term “mark-up” and how contractors achieve this

Stage 9: Completion, Adjudication and Submission Having priced the bill, the remaining tasks for the tendering contractor are to complete

the estimate, adjudicate the tender amount and submit the tender to the client’s

representative. Although this stage of the project sounds simple, it can be said to be the

most vital part of the entire estimating process. This is because if an inappropriate

addition is made for instance to the estimate for overheads and profit, the lengthy (and

expensive) work of preparing the tender will have been wasted. We will now look at

some of the actions required in the run-up to the submission of the tender.

Extending bills of quantity

When the net unit rates have been competed, the bills must be extended and added up

before project overheads and other allowances are calculated. This gives the estimator an

overall picture of the elements of the work. Such extensions are made with separate sub-

totals being produced for the four basic elements of labour, plant, materials and domestic

67

Page 68: BT 358 ConstructionEstimating and Price Analysis

sub-contractors. The extension of the bill rates to totals, collections and summaries must

be carried out in a manner that eliminates clerical errors and also allows the establishment

of various sub-totals relating to elements of the work or trades as necessary.

Net cost summaries

The estimator must prepare summaries of the resources which make up an estimate so

that management can assess the source of labour, plant, materials, services, possible

discounts available and price level as well as undertake price comparisons among

suppliers. These forms can be hand-written or produced by a computer-aided estimating

system; whichever method is adopted, when the forms are complete, computer

information should not be changed. Hand-written forms are being superseded by tailor-

made computer reports but are retained by organisations which want their estimators to

thoroughly check the information from computer printouts. Adjustments must be made

on the forms or added to a final review adjustment form. A record must be kept showing

the changes made during the final review stage. The final summary brings all the parts of

an estimate, with costs apportioned between labour, plant, materials, sub-contractors, site

overheads, PC and provisional sums.

Price fluctuations

In times of relatively low and predictable inflation, contractors are expected to submit

tender prices which remain fixed for the anticipated duration of the work. The method of

calculation of fluctuations in costs is set out in the appendix to the conditions of contract.

Fluctuations in cost can be ‘full’, ‘limited’ or none at all. It should be borne in mind that

fluctuations in cost may give rise to both increases and decreases in the final cost and

thus careful consideration is needed to reconcile such changes to the contractor’s cost

estimate.

(i). Full fluctuations

Full fluctuations in cost are intended to provide an equitable means of reflecting

changes in cost throughout the duration of a contract. Although a number of full

fluctuations clauses are available in standard forms of contract, they are rarely used

68

Page 69: BT 358 ConstructionEstimating and Price Analysis

today. Where the formula method of fluctuations recovery is proposed, the estimator

needs to understand the rules and must ensure that any shortfall or non-recoverable

element is identified and also any potential for over-recovery highlighted. Due

allowances should be made on the firm price adjustment form or resource schedules

for any changes needed. Adjustments using the Formula method are limited to

national increases and do not, therefore, reflect market forces.

(ii). Limited fluctuations (Statutory items)

This is normally limited to specific changes to rates of contribution, levies and taxes

in the employment of labour and in the rates and duties and taxes on the procurement

of materials. The extent of fluctuation of such costs is limited and is effectively those

which arise under and by virtue of an Act of Parliament.

(iii). No fluctuations

This is not an option in most standard forms of contract. This is because in all

contracts, situations will arise, such as taxes or statutory levies which may not be

foreseen at the time of tender. In the case of taxes and statutory levies, it will not be

reasonable to include a contingency sum for a new tax or statutory levy which cannot

be predicted at tender stage. This said however, it needs to be pointed out that it is not

uncommon for all fluctuations clauses to be deleted and a statement added that prices

are to be treated as firm in all circumstances.

Value related items

There are a number of costs, normally projected overheads, which will be calculated as a

proportion of the total value of work. Some bills of quantity provide items for these costs

on the final summary page. They are:

Contractor’s insurances;

Performance bond;

Water for the works; and

Professional fees for design.

69

Page 70: BT 358 ConstructionEstimating and Price Analysis

Contractors each have their own method of dealing with these items, either as project

overheads or in the final summary. If the project overheads forms are used, an adjustment

may be needed when the final tender price is known.

Late quotations

Any late quotations that are received for the supply of materials, hire of plant or work of

sub-contractors, must be entered on the appropriate summary sheets and comparison made

with previously received quotations. Following the meeting, the estimator must use the

final review adjustments form after consultation with the review manager. Great care is

needed in comparing quotations due to the following reasons:

There may be qualifications which other suppliers or sub-contractors may not have

made;

The items included in the quotation must be the same as those priced by others;

The net amount of late quotations must be compared with the previous lowest tender,

including any adjustments made before or during the review meeting; and

It may be difficult to contact suppliers or sub-contractors to discuss queries about

their quotations.

Checking procedures

As a general rule, calculations must be ‘self-checking’ through the use of well-designed

forms or otherwise, someone else must repeat the calculations in order to eliminate

mistakes. With computer-aided estimating systems, the number of calculation errors tends

to be less but other problems may arise through wrongly entered data and incomplete

pricing of items. Since most items are judged on price, it is important to check that the

tender figure has been calculated correctly and is sufficient to meet specific requirements of

the client. A badly prepared tender could have the following effects:

Under-priced – may be difficult to achieve the specification for the price and there

would be a potential loss of profit;

Over-priced – the tender will not win the contract in competition; and

Badly priced – unreliable cost data is provided for construction, and it would be

difficult to achieve the desired financial outcome.

70

Page 71: BT 358 ConstructionEstimating and Price Analysis

The total unit rates must be reasonable and correct for the unit of measurement. Particular

attention must be given to the major items in each trade and to those items to in which the

materials specified are usually costly. Any inaccuracy for the rate build-up for these items

will be magnified and have very serious consequences. It is equally important to check the

sub-contractor related items to see items of work, plant and materials not included in their

quotation have been correctly assessed and incorporated in the rest of the item and the unit

rates reflect these factors. It is important to ensure that when time for project is prescribed by

the client, it is realistic in relation to estimated labour cost and number of men required to be

physically working on site. The construction programme must be reviewed critically to

ensure that no major problem has been overlooked and that the method statement represents

the best method of completing the project. The estimator may be able to compare the

estimate and final costs of previous projects of a similar nature in order to form an opinion on

the likely profitability of the project. Once checking is completed, a final summary is

prepared by the estimator.

Cash flow

Cash is a major resource in construction and its use must be anticipated and managed.

Production on construction projects must be planned and the effect upon resources and the

return on assets employed determined. Clearly, the return on capital will be influenced by

the speed at which it is earned. A simple cash flow diagram must be regarded as a useful

aid to decision making and estimator should ensure that such a diagram is produced for

consideration at the final review savage. When a contract has been secured, a fully-detailed

forecast of cash flow, budget and cost control will be essential. However, post-contract

action is outside the scope of this Code. The estimator’s build-ups will have established the

costs of the work and project overheads under the headings of, labour, plant, materials,

domestic sub-contractors, PC sums and provisional sums and Dayworks. In order to

produce a cash flow diagram this financial appraisal must be linked to the tender

programme. Cash resources must be established for each item on the programme. Once this

link between estimate and programme has been established the cash flow position can be

calculated. The following headings must be taken into account when assessing the

contractor’s financial commitments to a project and in making the cash flow forecast:

71

Page 72: BT 358 ConstructionEstimating and Price Analysis

i. The contractor’s own trading accounts;

ii. Contract conditions; and

iii. Banking conditions.

These are briefly explained below:

The contractor’s own trading accounts

This describes the anticipated cost commitments for own labour, plant, materials, sub-

contractors and overheads. This is because in most cases, these may have to be pre-

financed before the client reimburses on presenting a certificate.

Contract conditions

The conditions of contract affect the contractor’s Cashflow. Some of the constituents of the

contract conditions which impact on Cashflow are as follows:

time period before issue of the first certificate;

interval between certificates;

anticipated time of practical completion;

anticipated time for ending of defects liability period ;

delays between issuing of certificates and receipt of cash;

retention during construction;

retention after practical completion; and

period for final measurement.

Banking conditions

The conditions associated with a contractor’s banking operations impact on the Cashflow

position. Theses include:

earning rate of interest; and

paying rate of interest.

Other factors to be considered include when preparing cashflow forecasts:

timing of special payments, for example: special insurances;

bonds, including date of release;

72

Page 73: BT 358 ConstructionEstimating and Price Analysis

the allocation of firm price allowances;

the recovery of fluctuation costs;

an efficient use of experienced staff;

any special weighting that may be incurred on the contract;

provisions for liquidated ascertained damages;

the present financial commitment of the company and effect of the current tender on

that commitment;

turnover and commitment of resources;

statutory requirements, for example: VAT;

level of project overheads and means of recovery of costs;

amount of PC and provisional sums and their likelihood of being spent;

company’s prior experience of the client and his consultants; and

the addition to be made to the net cost estimate for head office overheads and the

manner in which this addition is to be made.

Cashflow calculations will indicate the financial support needed for the contract and the

financial contribution to be made to company. When a client requests a cashflow forecast at

tender stage, the contractor is asked to submit a schedule of gross valuation at the date of

each interim certificate, based on the tender programme. Such a document would have no

contractual standing but assists the client to prepare a funding schedule. The calculations

needed to produce a cashflow forecast can be complicated and takes time. The contract value

graph is based o

n income from rates contained in the priced bills of quantity. These are produced at the end

of the tender period. Computers can be used to produce the data and charts, either using a

computer-aided estimating system or spreadsheets.

2-3 The Final Review, Mark-up and tender Submission

2-3.1 Estimator’s report

The estimator’s report should include all pertinent facts which have influenced the

preparation of an estimate for final review by management. The object of this report is to

highlight to management the various matters which have been identified as having some

significance in relation to costs, especially if alterations have been made to normal

73

Page 74: BT 358 ConstructionEstimating and Price Analysis

production standards or if there are any special or unusual contract conditions or risks. The

way in which information is presented will vary according to company policy and

preference and the guidelines suggested should not be regarded as mandatory. Many of the

resources schedules, project overheads and other summaries are produced by computer-

aided estimating software, often tailored to a company’s procedures. Whichever system is

used, the estimator’s report to management should include:

a description of the site and its location;

a brief description of the project;

a description of the method of production;

a note of any actual risks which are inherent in the project;

any information regarding the client, architect, quantity surveyor, consultants or other

member of the professional team that should be brought to the attention of

management;

the conditions of contract;

employer’s conditions, such as bond and insurances;

any unresolved technical or contractual problems;

an assessment of the state of the design and the possible financial consequences

thereof;

a note of any major assumptions made in the preparation of the cost estimate;

an assessment of the profitability of the project;

any pertinent information concerning market and industrial conditions;

any need for qualification of the tender or for explanatory letter;

the terms of quotations from own sub-contractors which have been included in the

estimate;

the time for which the tender is to remain open for acceptance;

details of other tenders where known; and

future prospects arising from the scheme such as ‘follow-on’ work.

Estimate schedules and summaries

The estimator’s report will include documents which have been produced during the

preparation of the estimate and summaries relating to the cost estimate, including:

74

Page 75: BT 358 ConstructionEstimating and Price Analysis

schedule of prime cost sums and attendance;

schedule of provisional sums and Dayworks;

materials comparison form;

plant quotation register;

domestic sub-contractors’ register;

resource summaries for labour, plant, materials and domestic sub-contractors;

project overheads; and

final summary.

Supporting documents

The cost summaries should be supplemented by supporting documents which will provide

the technical background. These may include:

method statements;

tender programme;

cash flow calculations;

tender drawings;

specifications and ground investigation report;

quotations files for: domestic sub-contractors, materials and plant suppliers;

tender information form; and

site visit report.

This information will then be considered by management at the final review stage.

2-3.2 Final review

The final review of an estimate and its conversion to a tender is the responsibility of

management. This is a separate commercial function based upon the cost estimate and it’s

supporting reports and documents. The accountability of the estimator is limited to the

proper preparation of the predictable cost of a project. The estimator’s must not feel a sense

of obligation or responsibility for securing work for the company. This is the responsibility

of management. The estimator’s role is to lead the process of preparing a good estimate

with a potential to win.

75

Page 76: BT 358 ConstructionEstimating and Price Analysis

Although the final decisions are made by management, those concerned with estimating,

planning, management and buying must be encouraged to communicate the knowledge

they have acquired throughout the estimating stage to the review panel. Their contribution

at this stage can be by attending the meeting or reporting through the estimator. In larger

companies, the final review stage often consists of two meetings: the fist to review the

estimate through a detailed examination of rates and quotations; the second would be for a

director to receive a short briefing and consider commercial matters before settling on a

mark-up. The need for a formal approach to finalising tenders should be regarded as

fundamental to competent tendering. There should be an agenda for the review meetings.

On large projects, the agenda must be circulated to those required to attend, with an

indication of the time for each agenda item. An evaluation of alternatives, scope to improve

profitability and risks which may be encountered will be considered at each stage of the

estimating process and converted into costs at the final review meeting.

Factors which influence the adjudicated figure

Owing to the strong competition faced, contractors need to find opportunities to use products

and processes which will enable the contract to support sufficient overheads and profits to

maintain the company’s objectives whilst satisfying the client. The mark-up shown on the

final summary form comprises scope, risk, head office overheads and profit. Mark-up will be

applied to all costs above this point, and it is assumed that provisional sums and Dayworks

will produce their own contribution to overheads and profit.

Some of the factors considered when deciding on the mark-up to the estimate include:

The desire to win the contract (here the contractor needs to ask if winning the project

will potentially lead to repeat work, or if the contractor has got too much work

already to be able to take on more);

The amount of contract finance required;

The contractor’s knowledge of the client and consultants;

The local market conditions; an evaluation of their previous biding performance;

Intelligence information on the client’s budget and target; and

Risk (technical and contractual).

76

Page 77: BT 358 ConstructionEstimating and Price Analysis

At the end of the review meeting, there may be other decisions to be made before proceeding

to the submission stage, including:

Which documents will be submitted with the tender? Some contractors may wish to

prepare additional information such as a programme, company profile and coloured

brochures, whereas others reserve their efforts, and ideas, until they know that their

tenders are under serious consideration;

If an alternative method (or design) is to be offered, then another price may need to

be settled by the review panel;

Qualifications which vary the requirements of the tender documents are generally not

permitted by clients. On the other hand, and management must decide the form which

a qualified tender will take; and

In order to provide appositive cash flow for the duration of the project, it is important

to decide how rates are apportioned in bill of quantity to be submitted at tender stage.

Since any artificial alteration of price will bring additional risks, it is for management

to agree the strategy.

It is recommended that a record is kept of all tenders submitted. Particular care should be

taken of the final summary form, and all notes and details of the decisions taken at the

review meeting should be fully recorded for future reference.

Preparation of priced bills of quantity

At final review stage, management may alter some of the basic conceptions concerning the

project. For example, a change to the basic labour rate will affect all bill items concerning

labour. This will affect all net rates that have been compiled by the estimator. With

computer-aided estimating system, such changes can be easily accommodated at the end of

the tender period but often there is insufficient time to re-write the net rates when manual

estimating systems are used, if priced bills of quantity are to be submitted at the time of

tender (or if requested later), management must decide how the difference between the total

of the net rates in the draft bills and the agreed tender figure is to be shown. The method

chosen will depend on individual preference. Examples of possible methods are:

77

Page 78: BT 358 ConstructionEstimating and Price Analysis

All amendments being made to the respective elements of the tender. (this may mean

substantial re-pricing of the bills of quantity, and a balance inserted in the

preliminaries bill);

Units rates increased by an agreed percentage so that the whole difference is included

in the measured items;

The unit rates left net with any difference included as an adjustment on the final

summary page – providing this is considered to be acceptable to the client;

The unit rate remains net and the difference inserted in the preliminaries bill ;

Any combination of those methods;

The way in which submitted bills are priced will have a significant effect on income

generated through interim payments and the valuation of variations. Clearly a contractor

would not be able to insert highly inflated prices against early items because a client will

not accept a disproportionable distribution of rates. Contractors also put their position at

risk if under-measured items are under-priced, and over-measured items are over-priced, in

both cases where the work is re-measured a loss will be incurred.

Self-assessment questionsi. Explain what actions are taken to arrive at the final estimate;

ii. Explain the term “tender adjudication”

iii. Describe what happens during the “final review”

iv. Explain the term “mark-up” and how contractors achieve this

78

Page 79: BT 358 ConstructionEstimating and Price Analysis

Session 3-3 Tender submission and beyondLearning outcomes

By the end, you will be able to:

i. Explain the final actions required before contractor submits bid

ii. Outline and explain the actions undertaken following the bid submission

iii. Explain the actions required after a successful tender has been selected

3-3.1 Tender submission

The estimator must ensure that the procedure set out in the tender documents for the

submission of the tender is followed meticulously. The form of tender and any other

declarations must be completed as required and signed by an authorised person from the

contractor’s organisation. A letter should be attached to the forms to list the documents,

and confirm the amendments received during the tender period. Any other remarks about

the technical content or price may be reviewed as a qualification to a tender and so should

be avoided. The codes of procedure for selective tendering, whether for main contractors or

trade contractors, state that a tenderer who submits a qualified tender should be given

reasonable opportunity to withdraw his qualifications without amendment of his tender

price. Failure to do so will lead to the rejection of the whole tender if it is considered that

such qualifications give the tender an unfair advantage. Alternative proposals involving

design, specification or timing may be invited. In this case those contractors who wish to

offer alternatives must submit a separate tender indicating the effect on price and

programme together with an appraisal of any charges needed to other elements of the

scheme. The tenders should be opened as soon as possible after receipt. Submission of

priced bills of quantity may be required with the tender and it is recommended that the

lowest tenderer should be invited to submit priced bills of quantity within four working

days of the opening of the tenders.

3-3.2 Action after Submitting Tender (Stage 10)

The role of the estimating department does not end at the submission of the tender. They

have an important role to play in responding to further requests by the client team, and in

79

Page 80: BT 358 ConstructionEstimating and Price Analysis

evaluating the tender efficiency. We will now focus on these stages, and how the estimator

can advise senior management on future bidding strategy.

Assessing tenders and notifying results

Generally, received tenders should be opened promptly at the expiration of the deadline.

This is usually done in the presence of all bidders who choose to attend. After the initial

assessment for responsiveness, all present should be informed about those tenders which

are responsive and which tenders are not. Thereafter, the consultants can conduct a detailed

evaluation to select the best evaluated bid. They must be notified at once when a decision

to accept a tender has been taken. Once the contract has been let, every tenderer must be

promptly supplied with tender prices. The estimator (chief estimator) should record the

results in the tender register and, if required, in a tender performance report.

Adjustment of errors

The estimator should be prepared to respond to any request for further information or

notification that the submitted tender contains errors in computation. For errors, two

alternative courses of action are responsible:

The tender will be given details of such errors and afforded opportunity of confirming

or withdrawing the offer. The estimator will need to refer to management when the

extent of the computation errors has been determined for a decision as to whether to

confirm the original tender figure or withdraw the tender. It is legally possible to

withdraw the tender at any time before its acceptance

The second option is that the tenderer is given an opportunity of confirming his offer

or of amending it to correct genuine errors. If the contractor elects to amend his offer

and the revised tender is no longer the lowest, the second lowest tender will be

examined with more detail.

Estimators must consult with management to establish whether to amend the tender figure

or to confirm the original offer, once the extent of the computation error has been

determined. In both situations the estimator or the signatory to the original tender must be

prepared to endorse the appropriate tender document to note the acceptance or change to

80

Page 81: BT 358 ConstructionEstimating and Price Analysis

the tender. Such amendments must also be endorsed by employers in the event that a

contract is subsequently awarded. There are many ways to correct errors in a bill of

quantities. The most common is to recalculate the bill and make an adjustment on the final

summary page; either by changing the total for preliminaries or introducing an adjustment

item. Since the latter amount must be adapted to all valuations it is preferable to ask the

contractor to change one or more items in the preliminaries to bring the total to the tender

figure.

Negotiation and award

When the lowest tender received exceeds the client’s budget, changes should be negotiated

with the lowest tenderer. This process is either through recommendations from contractors

for cost savings, or design changes which reduce the scope or specification of the works. If

significant changes are proposed, two or (at most) three tenderers may be asked to re-

tender thereby retaining the lowest market prices for the amended project. If there has been

any delay in acceptance, enquiries should be made to ensure that there have been no

changes which might necessitate reconsideration of the tender. Once an acceptable offer

has been made, the award of a contract should be in clear terms stating that the offer has

been accepted.

Action with a successful tender

When a tender has been successful, the documents must be checked thoroughly to ensure

they reflect the exact content of the documents used to prepare the tender. This may be

carried out by various people within the company’s organisation but it is recommended that

it should be co-ordinated by the estimator who was responsible for the original submission.

Contract documents should be checked to establish that:

the drawings are those which were circulated with the tender documents, if they have

been revised to produce a construction issue, they cannot be used as contract

documents;

the dates, penalties and particulars given in the appendix to the condition of contract

are those stated in the tender document; and

the submission bills have been copied correctly.

81

Page 82: BT 358 ConstructionEstimating and Price Analysis

A standard form may be used to confirm that these checks have taken place. In larger

organisations, this form will accompany the documents until they are signed by the

company’s directors and retuned to the client’s representative.

It is recommended that an internal pre-contract ‘handover’ meeting be held with all persons

so that details are fully discussed and the distribution of information can take place. The

handover meeting is an opportunity for detailed reporting and a discussion on decisions made

at the time of estimating concerning methods of construction, site layout, organization,

suppliers and sub-contractors. Whilst these decisions should not be binding on those

responsible for construction, it is important that the reasons underlying such decisions and

choices should be explained fully and that decisions made at the time of tender should not be

ignored unless it can be demonstrated that a better method of operation is possible.

Feedback Information

It is recommended that a fully operational cost control system be introduced on all successful

contracts. The collection and collation of data is a function involving the use of statistical

techniques. It is important that during construction, information should be obtained on the

labour and plant cost of major items or stages of work, on the quantities of material used, and

the cost of attendance for sub-contractors. This information is essential for control purposes

and guidance in future estimating. These records should be accurate and give all details

including those of the work, the position on the site of the operation, gang sizes, levels of

incentives and bonuses being paid, plant, access, and weather conditions. This information is

needed so that it may be interpreted correctly for future use. Where a substantial proportion

of work is assigned to sub-contractors, a table should be drawn up showing the estimator’s

allowances and actual prices agreed with them at the time of placing their contracts. In

particular, the estimator needs to know the accuracy of risk and firm price provisions in the

tender. A brief report should also indicate the performance of all sub-contractors and a

recommendation on whether they should be employed for future projects.

82

Page 83: BT 358 ConstructionEstimating and Price Analysis

Action with an unsuccessful tender

When the result of a tender is known, the tender performance form should be completed

where possible with a comparison made between the estimator’s organisation and the one

with the lowest (or the accepted) tender. Tender results can be reported at regular

management meetings so that all those who contributed to the estimate can assess their

performance. Suppliers and sub-contractors who submitted quotations should be notified of

the results as promptly as possible. Tender documents should be carefully filed for possible

future reference; except drawings and bills of quantity which are of little use once the

contract has been awarded to another contractor. Quotations received from suppliers and sub-

contractors can provide a useful guide to prices for other tenders but great care is needed to

ensure that the specification and the nature of the work are the same.

Tender performance and efficiency

Estimators must monitor their performance with an analysis of results recorded over a period

of consistent estimating. If data are available from a large number of tenders, it is possible to

evaluate tender performance in relation to; types of work (new build or refurbishment),

clients (public, private), procurement routes (traditional, design and construct, trade

packages), and estimating resources for further tendering.

It is important that the contractor keeps careful track of tender submissions and results. Large

contractors can be submitting many tenders per month, and so their performance over time

must be carefully analysed to ensure that they are winning a proportionate number of

contracts in comparison to submissions (at least 1 in 6 usually). Whilst there is always a

chance that some contractors may submit a tender which undercuts all of the others by a

significant margin, the successful tenders are usually fairly close to each other.

It is important that the contractor uses the information in the notification to establish its

competitors’ profit margins in order that they can be adjusted in the future to increase their

own chances of winning work or increasing their profits. Estimators are usually charged with

monitoring tender performance with regards to the type of work that they win, together with

the size of project, clients, procurement routes etc., in order that they can establish where

their strengths and weaknesses lie.

83

Page 84: BT 358 ConstructionEstimating and Price Analysis

The contractor will keep track of submitted tenders, number of tendering contractors, lowest

tenders submitted, their estimated cost of the project, their tender sum and the maximum

profit potential for the winning contractor. From this information, they can calculate the

approximate % profit used by their competitors and adjust theirs in the future to be more

competitive. An example is shown below.

Example 1

Building Procurement Inc. has tendered for 6 projects in June. Table 3.1 below shows the

break down of the tenders of Building Procurement Inc in comparison with competitors.

Table 3.1 Comparison of company’s tenders with competitors

Project No. Tenders Rank %Over lowest bid % Over mean bid

1 3 1 0 -2.3

2 6 5 11.0 4.9

3 6 1 0 -3.1

4 5 2 5.0 -3.8

5 7 1 0 -7.7

6 14 5 15.0 1.0

By establishing the types of projects where the company seems to be grossly over or under

priced, management can adjust their profit margin on these particular projects to enhance

their competitiveness.

Self-assessment questionsi. What actions should be taken by the contractor’s estimator after the submission of an

estimate?ii. Should errors be detected in a tender, what action should be taken to address them? iii. Explain the term “tender performance”

End-of-unit assessmenti. Outline the steps taken by the contractor’s estimator in completing the estimate before

bid submission.ii. Explain the terms “tender adjudication” and “adjudication report”.

iii. Compare the action taken with a successful tender with the action taken with an unsuccessful tender.

84

Page 85: BT 358 ConstructionEstimating and Price Analysis

UNIT 4 BUILDING UP ESTIMATESUnit Objectives

By the end of this Unit, you will be able to:

Apply the knowledge of estimating principles to prepare complete estimates for excavation,

concretework, steelwork and metalwork

Session 1-4 Preparing Estimates for Excavation, Concretework, Steelwork and Metalwork

Learning Outcomes

By the end of this session, you will be able to:

i. Compute unit rates for different types of excavation

ii. Prepare estimates for concrete work

iii. Prepare estimates for formwork

iv. Prepare estimates for reinforcement

v. Prepare estimates for painting and decoration

1-4.1 Preparing estimates for ExcavationWorked Example

To demonstrate how we compute estimates for excavation, we will look at different types of

excavation. Let’s start with oversite excavation. Let’s assume we are excavating oversite

6000 sq. metres of material to a depth of 150mm. Let’s now consider the required resource

inputs:

Solution

We will first consider the plant which is used for excavation.

Plant

Let’s assume we use a 250HP Bulldozer with an operator and daily output of 500m2

Assume the 250HP Bulldozer with an operator; from a Plant hire firm costs GH 900.00/day

The costs associated with this plant are as follows:

Hiring cost/day GH¢ 900.00

85

Page 86: BT 358 ConstructionEstimating and Price Analysis

Fuel: assume we need 25gallons of diesel @ GH¢4.50 GH¢ 112.50

Lubricants: Assume we use 2gallons@ GH¢ 6.00 per gallon GH¢ 12.00

Banksman @ GH¢ 8.00 GH¢ 8.00

Total daily cost for the plant GH¢ 1,032.50

No. of plant days required:

For the 6000 sq. metres of area to be excavated and given the plant has a daily output of

500m. sq,

Then the number of plant days 6000 / 500 = 12 days

At a GH¢1,032.50daily cost of using the plant, then for the 12 plant days, the total cost is

GH¢1,032.50 x 12 = GH¢12,390.50

Add transport to & from site@ GH¢ 200 GH¢ 200.00

Total cost of using the plant for excavation GH¢ 12,590.50

For the entire site (6,000 sq. m) therefore, the unit cost for using the plant is 12,590.50 / 6000

= GH¢ 2.10 / sq.m

Computing Estimates for Excavation of Pits to Receive FoundationLet’s assume we are excavating 60 No. pits to receive foundations, with a total volume of 80

cubic metres, not exceeding a maximum depth of 2metres

We will make the following additional assumptions:

Soil identification

Method identification

Method of excavation – manual (labour only)

Required resources:

From tables, the multiplying factor for gravel is 1

Multiplying factor for pits not exceeding 2m is 0.6

Multiplying factor for manual (labour) excavation is 3

Therefore, the output for the labourers is 3 x 0.6 x 1= 1.8 cubic metres per man day

86

Page 87: BT 358 ConstructionEstimating and Price Analysis

No. of man days required for the total 80 cubic metres = 80 / 1.8 = 44.44 days

Approximate 44.44 days to 45 days, if labour costs GH¢ 5.20 , then for the 45 days, total cost

of labour is: 45 x GH¢ 5.20 = GH¢ 234.00

If GH¢ 234.00 is the total cost for the 80 cubic metres, then unit cost for this activity is

GH¢ 234.00 / 80 = GH¢ 2.90 / m3

Computing Estimates for Excavating Trenches in FoundationsTo illustrate this, let us look at the example below:

Let’s consider excavation not exceeding 1.00m to receive foundations commencing from

ground level. Assume the total volume to be excavated is 80 cubic metres.

Solution

Soil identification:

Let’s assume soft rock with multiplying factor 0.70

Method identification:

Let’s assume manual methods with multiplying factor 0.83

Required resources

Labourer only with an output of 3 x 0.7 x 0.83 = 1.743 cubic metres per man day

Labour requirementFor the 80 cubic metres to be excavated, No. of man days required

= 80 / 1.743 = 45.897 days

Approximate 45.897 days to 46 days.

If the daily charge for labour is GH¢5.20, then the total charge for 46 days is = 46 days x GH¢5.20 = GH¢239.20

If the total cost for excavation is GH¢239.20 (for 80 cubic metres), then

Unit cost = GH¢239.20 / 80 cu.metres = GH¢2.99 / m3

Computing Estimates for Excavating Trenches in Foundations with Rock DepositsEstimating for areas with some deposits of rock may be treated as an “extra-over” item

We will now illustrate with an example how this type of estimates should be produced.

87

Page 88: BT 358 ConstructionEstimating and Price Analysis

Let’s assume the excavation will not exceed 2.0m and that the total volume of excavation is

15 cubic metres

Soil identification:

Let’s assume the excavation involves hard rock with multiplying factor 0.3

Method identification:

Let’s assume manual excavation with a multiplying factor of 0.7

Required resources

Labourers with an output of 3 x 0.3 x 0.7 = 0.63 cubic metres /man day

No. of man days required 15 / 0.63 = 23.809 days

Approximate the number of days to 24 days,

If labour costs GH¢5.20 per day, then for 24 days, total cost of labour is

24 x GH¢5.20 = GH¢124.80

If this is the cost for the entire 15 metre excavation, then

The unit cost for excavating through rock = GH¢124.80 / 15 cu.m = GH¢8.32 per metre cube

NOTE

Since we are computing the estimate for an “extra over” item on trench excavation, not

exceeding 2.00m maximum depth commencing from original ground level, we need to

deduct the unit cost of the original trench excavation from the GH¢8.32 we just obtained.

From the calculation above, the unit cost of excavation was calculated to be GH¢2.99

Therefore, the unit cost for extra-over item is = GH¢8.32- GH¢2.99

= GH¢5.33 /cubic metre

Estimating for pit excavation which involves excavating through reinforced concrete

Worked Example

Let’s assume the excavation is to a maximum depth not exceeding 2.0m and the total

excavation is 100 cubic metres

88

Page 89: BT 358 ConstructionEstimating and Price Analysis

Solution

Soil identification

Reinforced concrete

Method identification

Assume the use of a compressor

Required resources

Plant compressor, hose and operator/driller at an output of 6m3/plant day

Assume compressor has analysis of daily cost as follows:

Ownership cost

Assume the purchase price for the compressor is GH¢1200.00 with no resale value

Average life of the compressor 80 plant days x 5 years

Depreciation is expressed mathematically as cost price / average life of plant

Depreciation = GH¢1200 / 80 x 5 = GH¢3.00

This means that the depreciation cost per day of the plant is GH¢3.00

Based on this and using the stated assumptions below, we can compute the total cost per day

If interest is 40% of ownership cost, then interest per day = GH¢1.20

If insurance is 10% of ownership cost, then insurance cost per day = GH¢0.30

Operator or driller’s wages (daily-all-in) = GH¢8.00

Then total ownership cost per day = GH¢12.50

Operating cost/day

Repairs and renewals at 25% of daily depreciation cost of GH¢3.00 = GH¢0.75

Running expenses / day

Fuel: assume 5gallons @ GH¢4.00 = GH¢20.00

Lubricants: assume 0.5gallons@ GH¢6.00 = GH¢3.00

Total running costs is therefore = GH¢23.00

Ownership, operating, running cost / day is GH¢12.50+GH¢0.75+GH¢23.00

= GH¢36.25

89

Page 90: BT 358 ConstructionEstimating and Price Analysis

No. of plant days required 100 / 6 = 16.67 = 17 plant days

cost of 17 plant days@ GH¢36.25 per day = GH¢616.25

Add transport to and from site at GH¢120.00/return trip = GH¢120.00

Therefore total cost of plant for the excavation is GH¢736.25

If this is the cost for the entire 100 cubic metres, then the unit cost is:

Unit cost = GH¢736.25 / 100 = GH¢7.36

Estimating for Materials Arising from Excavation

In general, excavated material may be either re-used or disposed off.

Let’s consider the situation where excavated material is re-used,

In such a case, the estimate will cover the excavation, disposal and compacting.

Worked Example

Let’s assume that the compaction is done in layers of 150mm and the total volume of

excavated material is 150 cubic metres.

Solution

Soil identification

Assume the excavated material is gravel

Method identification

Assume manual spreading, leveling and compacting methods are used.

Required resources

Assume labourers used for spreading, leveling and compacting at an output of 5m3/man day

Labour requirements:

Duration required for the activity = 150 /5 = 30 mandays

If 1 manday IS GH¢5.20, FOR 30man-days, total cost is: = 30 x GH¢5.20 = GH¢156.00

If this is the cost of the entire 150 cubic metre excavation, Then the unit cost for the entire

activity is: GH¢156.00 / 150 = GH¢1.04 per cubic metre

90

Page 91: BT 358 ConstructionEstimating and Price Analysis

1-4.2 Estimating for Concrete

Worked Example

Let’s assume we have 7m3 Plain in-situ concrete 1:3:6 (40mm aggregate) used for a 150-

300mm thick foundation .

Solution Method:Machine, transportation, placing and compacting

Materials

Assume the concrete mix requires a nominal volumetric 1m3 of cement.

If we use 1m3 of cement, then for the 1:3:6 concrete mix, we will require 3m3 of sand and

6m3 of aggregate.

Cement

As above, we are assuming a nominal 1m3 of cement.

Cement is approximately 1450 kg / m3

Since 1 m3 of cement is 50kg,

Therefore for the 1450kg contained in 1 m3 contains 1450 / 50 = 29 bags of cement.

Thus, we will need 29 bags of cement for the 1 m3 . If a bag of cement costs GH¢9.50

(ex-site), then the cost for the 29 bags is 29 x GH¢9.50 = GH¢275.50

The output for unloading and stacking of cement is 120bags / man day

Thus the 29 bags of cement will require 29/120 man days = 0.24 man days

If daily wage for unloading and stacking cement is GH¢5.20,

Then unloading and stacking of the cement will cost = 0.24 x GH¢5.20 = GH ¢1.26

From the initial assumption of a nominal volumetric 1m3 of cement,

we will need 3m3 of sand. Assume 1m3 of sand costs GH¢12.50,

Then the 3m3 of sand will cost 3 x GH¢12.50 GH¢ 37.50

From the initial assumption of a nominal volumetric

1m3 of cement, we will need 6m3 of aggregate.

Assuming 1m3 of aggregate costs GH¢22.90,

91

Page 92: BT 358 ConstructionEstimating and Price Analysis

Then 6m3 of aggregate will cost 6 x GH¢22.90 = GH ¢137.40

Adding all together gives GH¢ 451.66

Allow 33% for shrinkage (33% of GH¢451.66) GH ¢ 149.05

GH¢ 600.71

This means the total material cost for 10m3 of concrete is GH¢ 600.71

To get the material cost/ m3, divide GH¢ 600.71 by 10

Therefore the material cost/m3 GH¢ 60.07

Estimating for Plant used for the Production of Concrete

Let’s assume we use a tilting 10/7 diesel concrete mixer with the

following corresponding data:

Output/batch mix 0.20m3

Mixing cycle 10 mins

Operating efficiency 75%

Assume an all-in daily rate of GH¢40.00/plant day

Let’s assume 8working hours a day. This will amount to 60 x 8 minutes

Number of mixing cycles in a day would be 60 x 8 / 10 = 48

Given that the efficiency of the equipment is 75%

The achieved no. of batches/day is: 48 x 75/100 = 3

Since the output per batch is 0.20 m3, then

Concrete output/day is: 36 x 0.20m3 = 7.2m3

No. of working days required for the 7m3of concrete is = 7 / 7.2 = 0.97 days

Approximate the number of days required for the plant, 0.97 days to 1 day

With the all-in daily rate of GH¢40.00/plant day,

This means the cost of using the tilting 10/7 diesel concrete mixer is:

GH¢40.00 / plant day x 1 day = GH¢40.00

Poker Vibrator:

From tables, the output of the poker vibrator is 10 m3 / plant day

Therefore 7m3 of concrete will require 7 / 10 plant days = 0.7 plant-day

Round 0.7 plant days off to 1 plant day

92

Page 93: BT 358 ConstructionEstimating and Price Analysis

Now, Assuming the cost of 1 plant day is GH¢24.21,

The total cost for using plant for concrete mixing is: the cost of using the concrete mixer and

the poker vibrator,

Total plant cost = GH¢40.00 + GH¢24.21 = GH¢64.92

Estimates for Labour

Let’s assume a concrete gang size of 8 comprising:

1 mixer operator at a daily rate is GH¢5.20 GH¢ 5.20

2 masons working on placing and vibrating @ GH¢6.00 GH¢12.00

2 loaders @ GH¢5.20 GH¢10.40

3 transporters @ GH¢5.20 GH¢15.60

All-in-daily rate for labour GH¢43.20

Total Cost Summary:

Materials GH¢ 420.49

Plant GH¢ 64.92

Labour GH ¢ 43.20

Total estimate for concrete GH ¢ 528.61

The GH¢ 528.61 obtained above is the total cost for producing 7m3

Therefore the unit cost for concrete mixing is: GH¢ 528.61 / 7m3 = GH¢ 75.52

Estimating for ReinforcementThe main components when preparing an estimate for reinforcement are the respective costs

for materials and labour.

For material, the reinforcement bars and binding wire should be estimated for separately but

added together once both have been computed.

Let’s now go through an example of how an estimate is prepared for reinforcement.

Example 1

Let’s assume we have 0.37 tonnes of 12 mm diameter Bar reinforcement in arches and beams

Estimates for Materials

93

Page 94: BT 358 ConstructionEstimating and Price Analysis

(i) Quantity of 12mm bars required 0.37 tonnes

Add 15% for waste 0.06 tonnes

0.43 tonnes

If 12mm bars of reinforcement cost GH¢750 per ton,

then 0.43 tonnes cost GH¢750 x 0.43 GH¢322.50

(ii) Binding wire required

Binding wire requirement is 13kg per tonne of reinforcement (for 12mm bars)

Therefore for 0.37tonnes binding wire requirement will be 13 x 0.37kg = 4.81kg

Binding wire is sold in 25kg rolls and hence

Number of rolls required = 4.81 / 25 = 0.19 rolls of binding wire

Let’s take the cost of 1 roll of binding wire to be GH ¢10.00

As just explained, binding wire is sold in 25kg rolls, therefore though we need just 0.19 rolls,

we will still have to buy 1 roll at a cost of GH ¢10.00

Total material cost is therefore GH¢322.50 + GH ¢10.00 = GH¢332.50

Labour for Reinforcement

i. Let’s take the output for unloading and stacking as 5 tonnes/man-day

Therefore for the 0.43 tonnes, the output will be: 0.43 / 5 = 0.084 man-days

The task will therefore take 1 man day (rounding off 0.084 man-days to the nearest day)

If the rate for 1 man day is GH¢6.00,

therefore the rate for unloading and stacking is: GH¢6.00 x 1 = GH¢6.00

Cutting & bending and fixing

We need to compute the estimate for cutting & bending and fixing 0.37 tonnes of

reinforcement in beams and arches.

From data, cutting and bending reinforcement rod in arches and beams has an output of

500kg/gang day, whilst fixing reinforcement in beams has an output of 320kg per gang day.

Therefore the combined output for reinforcement is: 1/500 + 1 / 320 = 0.005

Now, 0.37 tonnes converted into kilogrammes is 0.37 x 103

94

Page 95: BT 358 ConstructionEstimating and Price Analysis

Therefore, gang-days per kg, would require 0.37 x 103 x 0.005 = 1. 85 gang-days

This approximates to 2 gang days

Let’s assume a gang of 2 steel benders and a labourer,

Cost per gang day=2(GH¢6.00) +GH¢5.20 =GH¢17.20

Cost for 2 gang-days @ GH¢17.20 per day GH¢34.40

Total cost of materials and labour GH¢372.90

Since the GH¢372.90 is the cost for 0.37 tonnes,

Therefore the unit cost will be GH¢372.90 / 0.37 = GH¢1007.84/tonne

Example 2In this example, we find the estimates for 10 mm diameter bar reinforcement using in

columns and beams

Let’s assume we have got altogether 0.03 tonnes of reinforcement.

Estimate for materials(i) Quantity of 10mm bars required 0.03 tonnes

Add 15% for waste 0.0045 tonnes

0.0345 tonnes

If a tonne of 10mm bars costs GH¢750.00, then 0.035 tonnes cost GH¢26.25

Binding wire requirements

From data, 1 ton of 10mm reinforcement rods require 13kg of binding wire

Therefore 0.03 tonnes will require 13 x 0.03kg = 0.39kg of binding wire

Binding wire is sold in 25kg rolls, hence number of rolls required = 0.39 / 25 = 0.016

Rounding 0.016 off to the nearest whole number gives 1,

This means that the minimum quantity of rolls that can be purchased is 1

If a roll of binding wire costs GH¢10.00, the total cost of binding wire is

GH¢10.00 x 1 GH¢10.00

Total material cost = cost of reinforcement bars + cost of binding wire

= GH¢26.25 + GH¢10.00 = GH¢36.25

95

Page 96: BT 358 ConstructionEstimating and Price Analysis

Labour

(i) Unloading and stacking 0.035 tonnes at an output of 5 tonnes/man-day requires

0.035 / 5 = 0.007 man-days

Use 1 man days @ GH¢6.00 GH ¢6.00

(ii) Combined output for cutting and bending + fixing in arches and beams is:

(1 / 500 + 1 / 320 = 0.005

Number of gang-days required is 0.03x 103 x 0.005 =0.15

Rounding off to the nearest whole number gives 1 gang day

If the cost of 1 gang-day is GH¢17.20, then cost of gang GH¢17.20

Total cost of materials and labour = 36.25 + 6 + 17.20 GH¢59.45

If GH¢59.45 is the cost for 0.03 tonnes,

Then unit cost for reinforcement is GH¢59.45 / 0.03 = GH¢1981.67/ton

Estimating for FormworkWorked Example

Let’s consider formwork to the slab, staircase and horizontal soffit of a building. If we have

timber formwork with vertical props and horizontal joist to bearers at 750mm centres with

the total area of formwork as 100m2 and room height being 2.7m as shown in Figures 4.1.

Compute an estimate for the formwork used in this building.

Solution Materials:

Timber content calculations;

Assuming the dimensions of area to be supported to be 10 x 10m;

No. of joists required 10 + 1 = 14.3

0.75

Use 15

Hence no. of props required = 15 x 15 = 225

96

Page 97: BT 358 ConstructionEstimating and Price Analysis

Fig 4.1: Timber formwork support to soffit of suspended slab

Table 4.1 Illustration of formwork estimating

Sym

bol

Siz

es(m

m)

Len

gth

(mm

)

Was

te

100%

of

(3)

Tot

al

len

gth

No.

of

3.6m

m

len

gth

Rat

e/

pie

ces

GH

¢

Cos

t in

G

Vol

. (m

3) (

2 x

5)

(1) (2) (3) (4) (5) (6) (7) (8) (9)

a

b

c

c

e

(Wawa)

25 x 300boarding

50 x 100

50 x 100prop

25 x 150 brace

25 x 100 connector

100.3 10.0 =333.33

15 x 10.00 = 150

225 x 2.70 = 607.50

2 x15 x 10.00 = 300.00

225 x 0.30 = 67.50

33.33

15.00

60.75

30.00

6.75

366.66

165.00

668.25

330.00

74.25

102

46

186

92

21

0.35

0.18

0.18

0.18

0.12

35.70

8.28

33.48

16.56

2.52

2.75

0.83

3.34

1.25

0.19

Totals 96.54 8.35

97

Flo

or to

sof

fit h

eigh

t

A

C C

C C

C

E E E

750 750 750 750

E

25 x 100 connector

B B B

DDDD

25 x 100 brace

FLOOR

25 x 300 boarding

D

2700

0mm

Page 98: BT 358 ConstructionEstimating and Price Analysis

Total cost of Wawa timber including waste (from Table 4.1) GH¢96.54

Assuming 3 uses and nail utilization at 0.2kg/m2 first use and 0.1kg/m2 subsequent uses

Weight of nails required for 3 uses for the 100m2 = (0.2 + 2 x 0.1)kg x 100

= 40.00kg

Add 15% for waste 6.00

46.00kg

Cost of 46kg at GH¢ 0.20 GH¢ 9.20

Total cost of timber and nails for 3 uses GH¢105.74

Material cost for (timber + nails) per use 35.25

Mould oil at utilization capacity of 30m2/4.5L requires 100/ 30 (4.5L units)

= 3.33 (4.5L units)

Add 15% for waste = 0.50

3.83

Use 4 (4.5L units) at GH¢ 1.00 4.00

Total material cost/use GH¢39.25

Labour:

Unloading and stacking of 8.35m3 of timber at an output of 400m3/man-day

would require 8.35/4.00 man-days = 2.09 man-days

Use 2man-days at incentive rate of GH¢ 0.34 0.68

Mould oil application at 30m2/man-day required 100 man-days

30

i.e. 3.33 man-days but use 3 man-days @ GH¢ 0.37 1.11

Fabrication + erection + striking of 100m2

At an output of 1 + 1 + 1 = 0.16 gang-days per m2

18 15 30

would require 100 x 0.16 gang-days i.e. 16 gang-days at GH¢ 1.38 22.08

Total labour cost GH¢23.87

98

Page 99: BT 358 ConstructionEstimating and Price Analysis

Total cost summary:

Materials 39.25

Labour 23.87

Plant - .

Total GH¢ 63.12

Unit cost GH¢ 0.63/m2

Worked example: Formwork to Walls and Associated Features Compute the cost of formwork to walls and associated features vertical surface of walls

Materials:

i. Timber:

For 100m2 at an average utilization of 0.09m3/m2 (for one use) would require

100 x 0.09m3= 9m3 including waste, cost of 9m3 of timber at GH¢ 10.00

90.00

ii. Nails:

Assuming 3 uses and utilization as previous in Item 6:5:1;

Cost of nails required (as previous in Item 6:3:3:1) 9.20

Total cost of timber and nails for 3 uses GH¢99.20

Hence cost/use 33.07

iii. Mould oil required (as previous in Item 6:3:3:1) 4.00

Total material cost GH¢37.07

Labour:

i. Unloading and stacking of 9m3 at an output

of 4.00m3 man-day would require 9/4.00 = 2.25 man-days

use 2 days at incentive rate of GH¢ 0.37 0.74

ii. Mould oil application to 100m2/Cost (as previous in Item 6:3:3:1) 1.11

iii. Fabrication + erection + striking of 100m3 at an output of

1 + 1 + 1 = 0.17 gang-days per m2

16 14 28Would require 100 x 0.17 gang-days, i.e. 17 gang-days at GH¢ 1.38 23.46

Sub-total for labour GH¢25.31

99

Page 100: BT 358 ConstructionEstimating and Price Analysis

Total summary:

Materials 37.07

Labour 25.31

Total GH¢ 62.38

Unit cost GH¢ 0.62/m2

Estimating for Pre-cast Concrete WorksWorked Example

Compute the estimate for 100 No. precast reinforced concrete 1:2:4 (18mm aggregates)

rectangular lintel 150 x 250 x2500mm with two 13mmØ mild steel bars on top and bottom

with 10mm Ø stirrups at 150mm centres in cement and sand mortar (1:4) and left rough.

Solution

Materials:

Cost of rods from Table 4.2 GH¢ 115.64

For binding wire use 1 roll of 50kg at GH¢ 3.50 3.50

Cost of rods and binding wire 119.14

Add 15% waste 17.87

Total cost of rods and binding wire GH¢ 137.01

Table 4.2 Reinforcement Requirements

No.Bar Ø

mm

Shapes

Length (m)

No. Required

Total Length

(m)

Weight (kg)

Rate (kg)

¢

Cost ¢1000

Binding wire reqd.

kg

1

2

13

10

-

-

2.65

0.70

400

1700

1060

1190

1071

734

600

700

642.6

513.8

14

15

Total 1805 - 1156.4 29

Figures 4.2 to 4.5 show sections through the timber moulds including details as shown on table 4.3

100

Page 101: BT 358 ConstructionEstimating and Price Analysis

Figure 4.2a Timber moulds for precast concrete works

Fig 4.2b

Fig 4.2d

Fig 4.2c

101

288m

m

288m

m28

8mm

2 5

b bbb

Frame ‘c’ 2No

Frame ‘d’

Frame ‘d’

C C

b b b b

A

A2500mm

Frame ‘d’ 2 No.

150

b b

a

326mm

Page 102: BT 358 ConstructionEstimating and Price Analysis

Table 4.3 Information on timber mould

Sym

bol

Siz

e (m

m)

Len

gth

(m

m)

Was

te %

of

(m

)

Tot

al

len

gth

No.

of

3.6m

pcs

.

Rat

e/p

iece

(m

)

GH

¢

Cos

t(m

) in

GH

¢

Vol

. m2

(2 x

5)

1 2 3 4 5 6 6 8=6x7 9a

b + f

c

d

e

Total

38 x 326

38 x 250

50 x 50

50 x 50

50 x 50

2.60 = 2.60

2 x 2.55= 5.30

2 x 1.10= 2.20

2 x 5.6= 11.2

2 x 0.33= 0.66

0.24

0.53

0.22

1.12

0.07

2.86

5.53

2.24

12.32

0.73

1

2

1

4

-

0.6

0.6

0.1

0.1

-

0.6

1.2

0.1

0.4

-

2.30

0.033

0.063

0.0061

0.031

-

0.1351

Timber Cost/mould GH¢2.30

Nails:

Assuming 10 uses and nail utilization to be 0.02kg/m2

for first use and 0.1kg/m2 subsequent uses, weight of nails

required for 10 uses will be (0.2 + 9 + 0.1) = 1.10kg

But internal area/mould = (0.65 x 2.6 x 0.15)m2 = 1.77m2

Weight of nails for 10 uses of mould = 1.1 x 1.77kg = 1.947kg

Cost of 1.947kg of nails at GH¢ 0.20 = 0.39

Total cost of timber and nails for 10 uses GH¢2.69

Cost/use 0.27

Cost for 100 uses @ GH¢ 0.27 GH27.00

Mould oil required for (1.77 x 100) m2 surface at utilization capacity

of 30m2 / 4.5L units will be 177 (4.5L units) = 5.9 units

30

102

Page 103: BT 358 ConstructionEstimating and Price Analysis

Add 15% for waste = 0.09

6.79 units

Use 7 (4.5L) units at GH¢ 1.00 = GH¢ 7.00

Concrete 1:2:4 (18mm aggregates) volume required = 100 x 0.15 x 0.25 x 2.50 = 9.375m3

Cost of 9.375m3 at GH¢ 6.18 (as in item 6:3:1) = GH¢ 57.94

Materials Cost Collection

Reinforcement and building wire 137.01

Timber and nails 27.00

Mould oil 7.00

Concrete 57.94

Total material cost GH¢ 228.95

Labour:

i. Unloading and stacking of (0.1351 x 10)m3 of timber at an output of

4.0m3/man-day would require 1.351 man-days @ GH¢ 0.32 GH0.11

4.0

ii. Mould oil application to 177m2 at an output of 30m2/man-day

would require 177 man-days = 5.9 man-days

30

use 6 gang-days at GH¢ 0.32 GH1.92

iii. Fabrication + erection + striking of 177m2

at an output of 1 + 1 + 1 = 0.17

16 14 28

gang-days/m2 would require 177 x 0.17 gang-days = 30.08

Use 30 gang-days at GH¢ 0.34 GH¢ 40.80

Sub-Total GH¢ 42.83

Concrete mixing, transportation, placing and vibrating of 9.37m3

at GH¢ 0.71 as in Item 6:3:1 6.65

Reinforcement cutting, bending and fixing, unloading and

stacking of 1.805 tonnes at GH¢ 9.60 (as in item 6:3:2) GH¢ 17.33

Total Labour Cost GH¢66.81

103

Page 104: BT 358 ConstructionEstimating and Price Analysis

Total Cost Summary:

Materials 228.95

Labour 66.81

Plant - .

Total GH¢ 295.76

Add 5% for hoisting to position and

bedding in cement and sand mortar (1; 4) 14.79

310.55

Unit Cost GH¢ 3.11

104

Page 105: BT 358 ConstructionEstimating and Price Analysis

1-4.3 Preparing Estimates for Structural Steelwork

GeneralTwo major considerations which should be made when measuring steelwork are:

i. The provision of steel including any fabrication required; andii. The erection of the steel structure on site.

Structural steelwork is normally undertaken by nominated sub-contractors since it is a specialist activity. However, minor works in this section would normally be handled by the main contractor since they may not be attractive to specialist contractors.Achieved output data in gang-days per tone for fabricating, unloading, hoisting and erection, including setting in position, have been shown in Table 4.4. The plant input cost relates to all other fabrication input outside labour and this has been converted to the equivalent gang-days units based on an average daily gang rate of GH¢ 30.00 (at 2008 rates).

Worked Example in Structural SteelworkIn view of the inter-dependence of the bill item for the provision and erection of steelwork, a set of items covering these two in respect of a building component element are presented in what we describe as items 2.1 – 2.1.9

Table 4.4 Output per ton for fabrication and erection

Component elementFabrication Erection

Labour gang-daysPlant in gang-days equivalent

Labour and plant

Beams ColumnsRoof trusses

Bolting only

34.56.0

630.33 of total input for fabrication

10 gang-days

Typical Bill ItemsProvision of fabricated steel work in built-up members in roof truss at roof level in 5 no. trusses as per location diagram (this will usually be provided)

For components, angles 75.2 x 75.2 x 11mm thick (5kg/m)ITEM 2.1.1

2.1.22.1.3

1.00m long in 10 No.1.50m ditto2.00m ditto

0.05 tonnes0.08 tonnes0.10 tonnes

For components and tees cut from universal beam 102 x 127mm x 13kg/mITEM 2.1.4

2.1.52.1.6

7.00mm long in 10 No.8.00mm dittoFittings

0.91 tonnes1.04 tonnes0.02 tonnes

105

Page 106: BT 358 ConstructionEstimating and Price Analysis

Erection of Fabricated Steelwork:ITEM 2.1.7

2.1.8

2.1.9

Generally in roof trusses, 2.2 tonnes weightBlack bolts with nuts and washers grade designation 4.6Painting of fabricated steelwork 2 coats of red lead oxide primer to surfaces

0.16 tonnes

80m2

Estimating procedure The estimating procedure for steelwork is as follows:

For items 2.1.1 – 2.1.3Material s required 0.230 tonnesAdd 10% for waste 0.023 0.253Buy 0.26 tonnes at GH¢ 400.00 ex-fabricator’s yard GH¢ 104.00Labour and Plant: Fabrication of 0.23 tonnes at 69 gang-days/ton require15.87 gang-days; use 16 gang-days @ GH¢ 30.00 GH¢ 480.00Total cost for provision and fabrication of 0.23 tonnes GH¢ 584.00Unit cost GH¢ 2,539.13/ton

For item 2.1.4 – 2.1.6 Material required 1.97 tonnesAdd 10% for waste 0.20 2.17Buy 2.2 tonnes @ GH¢400.00 GH¢ 880.00Labour and Plant:Fabrication of 1.97 tonnes @ 69 gang-days per tonrequire 1.92 x 92 gang-days = 136.62Use 137 gang-days @ GH¢ 30.00 GH¢4,110.00Total Cost for Material, labour and Plant for 2.17 tonnes GH¢4,990.00Unit Cost GH¢ 2,299.54/ton

106

Page 107: BT 358 ConstructionEstimating and Price Analysis

2-4.4 Estimating for Metalwork

When estimating for metalwork, the main parts covered are as follows:i. Aluminium or galvanized cast iron louvre blade carriers;

ii. Built-up metal burglar proofing and balustrades;iii. Sheet metal wire-mesh insect proofing fixed to hardwood frame with wrought hardwood

cover stripsTable 4.5 Output data for metalwork per gang-day

Collection from stores, fixing carriers and associated hardwood water stoppers for12 blades with 150m wide chips 8 blades with 150m wide chip 4 blades with 150m wide chip

Metal balustrades or burglar proofing of average weight of 10kg/m2

Unloading and fabricatingUnloading and fixing only Painting or priming Wire-mesh with wrought hardwood cover strips

Unloading and fixing with wrought hardwood battens to sheet wire-mesh insect proofing

14 pairs16 pairs24pairs

10 m2

10 m2

50 m2

30m2

Worked Example in Estimating for Metalwork

Estimate for metalwork in composite items in doors and windows with described as follows: Extruded anodized aluminium louvre blade carriers screwed to wrought hardwood frames with matching screws with clips for: 8 blades of 150mm wide with double lever control.

80 pairs

Material:Assume aluminum louvre blade carrier with clips for 8 blades of 150mm wide blades and double lever control cost GH¢ 10.00/pair ex-site, then, Cost of 80 pairs @ GH¢ 10.00 GH¢ 800.00Add 10% for losses, damage and storage, GH¢ 80.00Add 2.5% for fixing screws GH¢ 20.00Total Material Cost GH¢ 900.00Labour:Unloading and fixing of 80 pairs at an output offrom table 4.5, 16 pairs/gang-day would require 80/16 = 5 gang-daysCost of 5 gang-days @ GH¢ 30.00 GH¢ 150.00Total Cost (material + labour) for 80 pairs GH¢1,050.00Therefore Unit Cost GH¢13.13/pair

107

Page 108: BT 358 ConstructionEstimating and Price Analysis

Self-assessment questions

i. Explain the main cost components which are considered when preparing

estimates for excavation and concrete work

ii. Why, do you think, can we not develop just a single unit rate for excavation?

iii. What are the main cost centres which should be considered when preparing

estimates for formwork and reinforcement respectively?

108

Page 109: BT 358 ConstructionEstimating and Price Analysis

Session 2-4 Estimating for Roofing, Walling, Woodwork, Finishes, Painting and Decoration,

Learning Outcomes

By the end of this session, you should be able to:

i. Identify the key components which are considered when estimating for roofing,

walling and woodwork;

ii. Estimate unit rates for a typical wall or any activity relating to wall construction;

iii. Estimate unit rate for a typical roof and woodwork or sections thereof.

2-4.1 Estimating for Roofing

The most common roof form in West Africa is usually of corrugated sheet covering on

hardwood structure. Where felt-sheet covering is used, it has been mainly for water-proofing

purposes. Slate or Tile roofing is very rare and found, if any, on projects designed by

consultant who normally may be non-residents in the West Africa zone. Such woks have

been executed by specialist sub-contractors who normally present their own quotations to the

appointing body. Accordingly, corrugated and bituminous felt sheet roof covering and their

associated operations are considered. Tables 4.6 to 4.8 give outputs for these materials.

Table 4.6 Achieved outputs for corrugated sheet roofing

Roofing sheet covering type

OperationOutput/gang-day for slopes

<50º >50º VerticalGalvanized/aluminum Unloading and fixing

FlashingFixing ridge cupCutting ridges or hipsStraight cutting

70m2

25m55m45m40m

50m2

55m

40m35m

45m2

----

Cement Asbestos

Unloading and fixingFixing ridge cupCutting ridges or hipsStraight cutting

50m2

40m30m35m

45m2

35m30m30m

40m2

---

Table 4.7 Corrugated roofing sheet sizes in use locally

109

Page 110: BT 358 ConstructionEstimating and Price Analysis

Type Width (mm) Length (mm)

Galvanized""

760760760

180024003000

Aluminum 7607607601200

up to 3000mm for0.4mm thickup to 6600mm for 0.5mm thickup to 9000mm for 0.7mm thick

up to 3000mm for 0.7+mm thick

Deep trough and long span are also available

Asbestos:Ordinary

Super 6 and 7

10601060

24001800

10601060106010601060

24003000180024003000

Table 4.8 Outputs for bituminous felt covering operation

Operation Output/gang-day (m2)

Operation Output gang-day

i. Nailing on boardii. Spreading pitch or

bitumeniii. Unloading and fixing

felt to bitumeniv. Spreading chippings

10mm thick

100100

140 100

v. Laying in gutters of 100mm girth

vi. Cutting

vii. Bitumen utilization

60m2

90m 0.15kg/m2

Worked out examples in roofing Example 1. Estimating for corrugated galvanized iron roofingCompute the estimate for corrugated galvanized iron roof covering fixed to hardwood purlins

and having 150 and 200mm side and end laps respectively with 75mm galvanized drive

screws and washes fixed strictly to manufacturer’s instruction if the area covered is 50m2.

110

Page 111: BT 358 ConstructionEstimating and Price Analysis

Solution

Materials:

corrugated galvanized iron sheets: assume the use of a standard

size of 760 x 2400mm in accordance with purlin spacing. Allowing for

the required laps, covering capacity per sheet will be 0.61 x 2.2m2 = 1.34m2

No. of sheets required = 50

1.34

= 37.31

Add 10% for waste = 3.73

41.03

Use 41 sheets at GH¢ 20.00 GH¢ 820.00

75mm galvanized drive screws and washes with an

achieved utilization of 5/m2 would require 100 x 5 = 500 screws

Add 10% for waste = 50

550

But these are sold together in packets of 1,000

no. of packets required = 550 = 0.55

1000

But use 1 packet at GH¢ 25.00 GH¢ 25.00

Total Material Cost GH¢ 845.00

Labour:

Unloading and fixed of 50m2 at an output

of 70m2/gang-day would require 50 = 0.71 gang-days

70

But use 1 gang-days at GH¢ 36.00 GH¢ 36.00

Total cost (material + labour) GH¢ 881.00

Unit cost GH¢ 17.62/m2

111

Page 112: BT 358 ConstructionEstimating and Price Analysis

Example 2: Estimating for corrugated super 7 cement asbestos roofing

Prepare an estimate for the roof of a proposed building made up of corrugated super 7 cement

asbestos roof covering fixed to hardwood purlins with 75mm galvanized drive screws and

washes and having 150 and 200mm side and end laps respectively all in accordance with

manufacturer’s instruction. Take the area covered by the roof as 200m2.

Solution

Materials:

Corrugated super asbestos sheets; in accordance

with purlin spacing given, use sheets size 1060 x 3000mm

giving net covering capacity of 0.91 x 2.80m2 = 2.55m2

No. of sheets required = 200

2.55

= 78.43

Add 15% for waste = 11.76

Total 90.19

Use 90 sheets at GH¢ 30.00 2700.00

75mm drive screws for 200m2 (as previous in Item 8:2:1) 25.00

Total Cost of Materials GH¢ 2725.00

Labour:

Unloading and fixing of 200m2 of asbestos sheet at an output

of 50m2/gang-day would required 200 = 4gang-day

50

Cost of 4 gang-days at GH¢ 36.00 144.00

Total Cost (material + labour) GH¢ 2869.00

Unit Cost GH¢ 14.35/m2

Example 3: Estimating for asbestos ridge cap Worked examplePrepare the estimate for a 2-unit asbestos ridge cap to fit supper 7 corrugated cement asbestos

fixed to hardwood with 75mm long galvanized drive screws and washes to manufacturer’s

specification. Take the length of the ridge cap to be 40m

112

Page 113: BT 358 ConstructionEstimating and Price Analysis

Solution

Materials:

Use 2-unit corrugated asbestos ridge cup of length 1187mm per piece and 200mm end lap

Net covering capacity/piece = (1.187 – 0.200)m

= 0.987m

No. of sets required = 45

0.987

= 40.53

For waste allow 10% 4.05

Sub-Total 44.53

Use 45 sets at GH¢ 10.00 GH¢ 450.00

Drive screws and washes for 40m

at a utilization of 5/m would require

5 x 40 = 200

Add 10% for waste 20

220

Cost of 220 at GH¢ 0.60 GH¢132.00

Total Material Cost GH¢ 582.00

Labour:

Unloading and fixing + straight cutting of

10m asbestos ridge cup at an output of

1 + 1 = 0.042m/gang-days

40 2 x 30

would require 10 x 0.042 = 0.42 gang-days

Use 1 gang-day at GH¢ 36.00 GH¢ 36.00

Total Cost (material + labour) GH¢ 618.00

Unit Cost GH¢ 15.45/m2

113

Page 114: BT 358 ConstructionEstimating and Price Analysis

Example 4: Estimating for Pre-formed Aluminium Sheet FlashingPrepare an estimate for 20m of pre-formed aluminum sheet flashing 0.8mm thick and

1000mm girth fixed to 50 x 50 x 50mm hardwood grounds in blockwall with drive screws

and washers in accordance with the manufacturer’s instructions all inclusive.

Solution

Materials:

The material required for this are: aluminum flashing with screws and washers

as per manufacturer’s quotation GH¢ 10.00/m (net) ex-factory

Cost of 20m at GH¢ 10.00 200.00

Add 15% for transportation to site and storage 30.00

GH¢ 230.00

50 x 50 x 50mm long timber grounds for 20m at a

utilization of 10 No,/m would require

0.05 x 10 x 20m = 10.00

Add 15% for waste 1.50

11.50

But hardwood is sold in 3.6m piece

No. of pieces required = 11.50

3.60

= 3.19

Use 3 pieces at GH¢ 8.00 24.00

Total Cost of Materials GH¢ 254.00

Labour:

Unloading and fixing of flashing

20m long at an output of 20m/gang-day

Would require

114

Page 115: BT 358 ConstructionEstimating and Price Analysis

20 gang-day = 1.0 gang-day

20

Use 1 gang-day at GH¢ 36.00 GH¢ 36.00

Sub-total GH¢ 290.00

i. Fixing of 50 No. of

50 x 50 x 50mm hardwood grounds

in blockwork at an output of 50/gang-day would require

50 = 1.0 gang-day at GH¢ 36.00 GH¢ 36.00

50

Total Cost (material + labour) GH¢ 326.00

Unit cost GH¢ 16.30/m

Example 5: Estimating for bitumen felt roofing

Prepare an estimate for 2 layers of double-layer bitumen felt roof covering of 50kg/30m3 roll

laid on flat hardwood boarding (measured separately) with manufacturer’s recommended

bitumen binder and having 150 and 200mm side and head laps respectively with 9mm granite

chipping finishing layer of 10mm thick, covering a total area of 50m2.

Solution Materials:

Double layer felt required is sold in rolls of 1 x 30m2

and allowing for laps, net covering capacity/roll

will be 0.85 x 29.80m = 25.33m2

No. of rolls required = 50

25.33 = 1.97

Add 15% for cutting waste = 0.30

Sub-Total 2.27

For the 2 layers, buy 2 x 2.5 = 5 rolls @ GH¢ 2.50 GH¢ 12.50

115

Page 116: BT 358 ConstructionEstimating and Price Analysis

Fig 4.3 Bituminous felt roof covering materials and operations (enlarged)

Binder Bitumen:

With utilization of 0.15kg/m2 layer, requirement for

50m2 will be 0.15 x 50kg = 7.5kg/layer including waste

Requirement for 3 layers will be 3 x 7.5 = 22.5kg @ GH¢ 4.00 90.00

9mm granite chippings over 50m2 in 10mm thick layers

would require 50 x 0.01m3 = 0.5m3

Add 50% for voids = 0.25

Sub-Total = 0.75m3

But buy 1m3 at GH¢ 10.00 GH¢ 10.00

Labour:

No. of gang-days required/m2 for:

i. Applying binding bitumen 3 times = 3 x 1/100

ii. Unloading and laying felt in 2 layers = 2 x 1/140

iii. Spreading chippings in 10mm layers = 1/100

116

10mm chippings

Hardcore rafter

Roof boarding

Measured separately

3 stages of bitumen binder application2 layers of double layer bituminous felt

Page 117: BT 358 ConstructionEstimating and Price Analysis

Combined gang-day/m2 for these 3 operations will be

3 + 2 + 1 = 0.054 gang-days

100 140 100

Hence 50m2 would require 50 x 0.054 gang-days = 2.7

But use 3 gang-days at GH¢ 36.00 108.00

Total cost (material + labour) GH¢ 220.50

Unit cost GH¢ 4.41/m2

2-4.2 Estimating for Blockwork and Brickwork

Wall construction may be either sandcrete load bearing or sandcrete non-load bearing walls

and partitions. Blockwork in walls consists of 100mm, 125mm, 150mm or 225mm thick

sandcrete blocks using 1:4 cement mortar mix as binding joints. Sandcrete blocks are made

using cement and sand in the ratio of 1:8.

In Ghana, brickwork is rather uncommon. Until recently, bricks were mostly used as facing

bricks mainly for decorative purposes. In the recent past, a few projects have been

undertaken entirely using bricks or using mostly bricks in walls. In some developed countries

such as the United Kingdom and the USA, the predominant walling material is bricks. We

will now look at examples of how estimates for wall construction using both blocks and

bricks. To start with, let’s have a look at these tables 4.9 to 4.11 below which provide useful

data which will be used when we compute estimates for blockwork and brickwork. Data

from these tables are used in the examples that follow.

Table 4.9 Popular sizes of blocks which are commonly used in Ghana

Size of block (in mm) Type of block in which available

Actual size200 x 212.5 x 437.5125 x 212.5 x 437.5100 x 212.5 x 437.575 x 212.5 x 437.5

Nominal Size225 x 225 x 450150 x 225 x 450125 x 225 x 450100 x 225 x 450

HollowHollowHollowHollow

SolidSolid SolidSolid

117

Page 118: BT 358 ConstructionEstimating and Price Analysis

Table 4.10 Weights and volumes of cement and sand in specified nominal mixes of mortar

Nominal Mix

Cement Sand

Weight in tonnes Volume (in cubic metres) Weight in tonnes Volume (in cubic metres)

1:11:21:31:4

0.970.660.500.40

0.670.460.350.28

1.071.461.671.79

0.670.911.041.12

Table 4.11 Achieved outputs for selected blockwork operations

Operation Output

Unloading and stacking of 100 x 225 x 450mm sandcrete blocksUnloading and stacking of 125 x 225 x 450mm sandcrete blocksUnloading and stacking of 150 x 225 x 450mm sandcrete blocksUnloading and stacking of 225 x 225 x 450mm sandcrete blocksManual mixing of mortarLaying of sandcrete blocks in 100mm thick walls or partitionsLaying of sandcrete blocks in 125mm thick walls or partitionsLaying of sandcrete blocks in 150mm thick walls or partitionsLaying of sandcrete blocks in 225mm thick walls or partitionsLaying of sandcrete blocks in 225mm thick in foundationLaying of sandcrete blocks in 150mm thick in foundationLaying of sandcrete blocks in 125mm thick in foundationStraight cuttingCurve cuttingAllow 1.5 blocks per metre as cutting waste

450 per man day400 per man day350 per man day250 per man day1 m3/ man-day

14 m2/ gang day13 m2/ gang day12 m2/ gang day10 m2/ gang day9 m2/ gang day10 m2/ gang day13m2/ gang day50m /gang day35m/gang day

Brickwork 0.5 B thick (113mm) partitions1 B thick (225mm) partitions

6 m2

4 m2

We will use data from these tables variously as we prepare estimates for walls using blocks

or bricks. Let’s have a look at the example below.

118

Page 119: BT 358 ConstructionEstimating and Price Analysis

Worked Examples in Blockwork and BrickworkExample 1: Estimates for a 225mm thick hollow blockwall

Let’s consider a 225mm thick hollow sandcrete blockwall filled with plain concrete using

cement and sand mortar (1:4) in foundations. The plain concrete filling is measured

separately. Let’s assume the total area of blockwork is 100 m2

Solution Let’s start by estimating for the materials used for the wall construction.

The main materials used are cement and sand.

i. Estimate for the cement and sand mortar (1:4)

Let’s assume a 1m3 volumetric mix of cement

1m3 uses 29 bags of cement. If a bag of cement costs GH¢9, then

Cost of 29 bags of cement, 29 x GH¢9 GH¢ 261.00

If in 1 man day, 120 bags of cement can be unloaded and stacked,

then 29 bags will require 29 / 120 = 0.242,

Rounding off 0.242 man days to 1 man day.

If the cost per man day is GH¢ 6,

Then the cost of labour for the cement used is GH ¢ 6.00

ii. Estimate for sand

The ratio of cement used to sand is 1:4

Since we used a nominal 1 m3 volumetric mix of cement, then the volume of sand

require is 4 m3

If 1 m3 of sand costs GH¢ 50, then the cost for 4 m3 is GH¢ 200

Thus, the total material cost for 5 m3 GH¢ 467.00

Allow for an additional 33% for shrinkage and waste GH¢ 154.11

Therefore the total material cost for 5 m3 GH¢ 621.11

And the material cost per m3 GH¢ 124.22

119

Page 120: BT 358 ConstructionEstimating and Price Analysis

Estimate for mixing

From the table of outputs, mixing 1 m3 will require 1 man day,

If the cost of labour per man day is GH¢ 6, then

Cost of labour for mixing mortar is 1 x GH¢ 6 GH¢ 6.00

Cost of mortar GH¢ 130.22

Estimate for blockwork

The wall is made up of sandcrete block with nominal size 225x225x450mm

The area of 1 block is 225mm x 450mm,

Converted into metres, the area of 1 block is 0.225 x 0.45 = 0.101 m2

Since the total area of blockwork is 100 m2

Then the number of blocks required = total area / area of 1 block

= 100 / 0.101

= 987.65 blocks

Add 10% for waste 98.77 blocks

Total no. of blocks required = 1086.42 blocks

If 1 block is assumed to cost GH¢ 1.20,

Then cost of 1086.42 blocks is GH¢ 1.20 x 1086.42 GH¢ 1,303.70

Estimate for mortar

Assume the volume of mortar used to be V m3

V = (nominal area of block – actual area of block) x no. of blocks x wall thickness,

= (0.225x0.45 -0.2125x0.4375) x 987.65 x 0.225 m3

= 0.0083 x 222.22 m3

= 1.84 m3

Since 1 m3 of mortar costs GH¢ 130.22,

then 1.84 m3 of mortar will cost: GH¢ 130.22 x 1.84 m3 GH¢239.20

Total cost of material = cost of blocks + cost of mortar GH¢1,542.90

120

Page 121: BT 358 ConstructionEstimating and Price Analysis

Estimate for labour

From the table, the output for laying of 225mm sandcrete blocks is per 9 m2 /gang day,

Then the total area of blockwork, 100 m2 will require 100 / 9 = 11.1 gang days

Rounding 11.1 gang days to the nearest whole number gives 11 gang days

If the charge per gang day is assumed to be GH¢ 32.00,

Then total cost of labour is GH¢ 32.00 x 11 GH¢352.00

Therefore total cost for material and labour is GH¢1,894.90

This is the cost for the entire area 100 m2 of blockwork

And the cost per m2 is GH¢ 1,894.90 / 100 m2 = GH¢ 18.95

Blockwork Example 2Preparing estimates for solid sandcrete blockwall

In this example, we consider a 125mm thick sandcrete blockwall in cement and sand mortar

(1:4) in walls and partitions. Let’s take the total wall area to be 50 m2

Solution

Materials

(i) Blocks

For the 125mm thick walls, we use 125x225x450mm nominal size blocks

Area of 1 block in metres is: 0.225x0.45 = 0.101 m2

For the 50 m2 of blockwalls, number of blocks required is 50 / 0.101

= 495.05 blocks

Add 10% waste 49.51blocks

544.56 blocks

Rounding 544.56 blocks to the nearest whole number,

This means we will need 545 blocks.

If 1 block costs GH¢1, then the 545 blocks used will cost GH¢545.00

121

Page 122: BT 358 ConstructionEstimating and Price Analysis

Mortar used

Assume the volume of mortar used to be V m3

V = (nominal area of block – actual area of block) x no. of blocks x wall thickness,

= (0.225x 0.45 – 0.212 x 0.4375) x 495.05 x 0.125

= 0.008 x 61.88

= 0.495 m3

From Example 1, the cost of mortar per m3 is GH¢ 130.22,

Thus for 0.495 m3 of mortar, the cost is 0.495 m3 x GH¢ 130.22 = GH¢64.47

Total material cost for the blockwall GH¢609.47

Labour

We are considering 50 m2 of blockwall at an output of 12 m2 gang man day,

The output for 50 m2 of blockwall is thus: 50/12 = 4.16 gang days

Approximate 4.16 gang days to the nearest whole number, i.e. 5 days

If the charge per gang day is assumed to be GH¢ 32.00,

Then total cost of labour is GH¢ 32.00 x 5 GH¢ 160.00

Therefore total cost for material and labour is GH¢ 769.47

This is the cost for 50 m2

Thus the cost / m2 is GH ¢ 769.47 / 50 m2 GH ¢ 15.39

Example 3 Preparing estimates for brickworkWe will illustrate the estimating process for brickwork using an example.

Let’s consider a 0.5 Brick thick (i.e. 0.113mm) single leaf burnt clay brick wall in cement

and sand mortar (1:4) in walls and partitions. Assume the area of brickwork is 10 m2

Solution

Materials

We assume burnt clay bricks are used (common bricks).

The nominal size of bricks is 113 x 75 x 225mm

The area of a1 brick is 0.075 x 0.225 = 0.0169 m2

122

Page 123: BT 358 ConstructionEstimating and Price Analysis

For the entire area of brickwork, the number of bricks is:

10 / 0.0169 m2 = 591.72 bricks

Add 10% for waste 59.17 bricks

650.89 bricks

Rounding off to the nearest whole number gives us 651 bricks

Assuming a brick costs GH¢ 0.80, then 651 bricks will cost GH¢ 0.80x651= GH¢520.80

Mortar used

Assume the volume of mortar used to be V m3

V = (nominal area of brick – actual area of brick) x no. of bricks x wall thickness,

= (0.075x0.225 – 0.069 x 0.219) x 591.72 x 0.113

= 0.001764 x 66.86

= 0.1179 m3

From previous examples, we found the cost of mortar to be GH¢ 130.22,

Thus the cost of mortar for 0.1179 m3 is GH¢ 130.22 x 0.1179 m3 GH¢15.35

Total cost of material GH¢536.15

Labour

From tables, the output for 0.6 Brick thick walls is 6 m2

Thus 10 m2 will require 10 / 6 = 1.67 gang days

Approximate this to 2 days. If labour costs GH¢ 32 per gang day,

Then for the two days, cost of labour is GH¢ 32 x 2 GH¢ 64.00

Total cost of material and labour GH¢ 600.15

This is the cost for 10 m2

Thus the cost per m2 is GH¢ 600.15 / 10 m2 GH¢ 60.02

Therefore unit cost of brickwork is GH¢ 60.02

123

Page 124: BT 358 ConstructionEstimating and Price Analysis

2-4.3 Estimating for Woodwork

In preparing estimates for woodwork, the main input resources which should be

considered are material and labour. In the following example, we will prepare an

estimate for sawn timber 50 x 50mm surface brushed with. Creosote preservative in

pitched roof carcassing. Let’s take the total area of woodwork as 726m.

The input resources required are as follows:

Material:

i. Timber

ii. Nails

iii. Creosote

iv. Brush

Labour:

i. Creosote application

ii. Unloading, cutting, hoisting and fixing

Material

i. Timber [dimensions 50 x 050]

The number of 4.2m pieces required = 726 / 4.2 = 172.86

Add 15% for waste = 25.93

198.79

Use 199 pieces @ ¢2.50 GH

¢497.50

ii. Nails

Net timber content = 0.05 x 0.15 x 726

= 5.445m3

At a utilization of 12.0kg/m3 of timber

The weight of nails required = 5.45 x 12 =65.34kg

Cost of 65kg @ ¢1.05 GH¢68.25

iii. Creosote

If the area brushed / piece of 4.2m

124

Page 125: BT 358 ConstructionEstimating and Price Analysis

Length will be 2[0.05+0.15] x 4.2 + [2 x 0.05 x 0.15]

= 1.695m2

For the 199 pieces of wood, the total area brushed =199 x 1.695 = 337.31m2

With utilization of 30 / m2 for 4.5L, the number of units required = 337.31/ 30 = 11.24

Add 20% for waste = 2.25 13.49

Use 14 units. Assuming a unit costs GH¢2.50 GH¢35.00

iv. Estimating for Brushes

In general, brushes are allowed for in preliminaries. However if it is required to

estimate specifically

For brushes, let’s see how this can be done. We will illustrate with an example.

Let’s assume we have 150mm width nylon brush, utilization capacity of 120m2

If the average live coverage per brush is 120m2

Then the number of brushes required = 337.31 / 120

= 2.81

Add 1 for losses and misuse = 3.81

Rounding off to the nearest whole number, thus we use 4 brushes

If a brush costs GH¢2.00, then cost of brushes is 4x GH¢2.00

GH¢8.00

Total material cost

Timber GH¢497.00

Nails GH¢ 68.25

Creosote GH¢ 32.50

Brushes GH¢ 8.00

Total material cost GH¢606.25

Estimates for LabourFrom the earlier calculation, volume of timber is 5.45 m3

Unloading, cutting, hoisting and fixing 5.45m3 @ an output of 0.6 m3/gang day

requires: 5.45 = 9.08 gang days

0.6

125

Page 126: BT 358 ConstructionEstimating and Price Analysis

Use 10 gang days @ GH¢22.40 GH

¢224.00

With the calculated area of 337.31 m2 and creosote application @ 30m2/ man day,

Man days required 337.31 / 30 = 11.24 mandays

Use 12 man days @ GH¢5.20

GH¢57.20

Total labour cost GH

¢286.40

Total cost summary

Materials GH ¢ 606.25

Labour GH¢286.40

Total cost GH¢892.65

Since this cost is for 726m, therefore, Unit cost GH¢1.23/m

2-4.4 Estimating for Painting and Decoration

We start this by looking at the average covering capacities of paint on different types of surfaces for both oil and emulsion paint as shown in table 4.12.

Table 4.12 Average covering capacities in m2/gallon/coat (4.5L of paint)

Surface typeEmulsion Oil

New Old New OldRendered walls or asbestosConcrete fair faceHardboard Woodwork Metalwork

404540--

455045--

3540353545

4045404550

Glass paper utilization of 0.25 sheet/m2

Putty for stopping @ 0.025kg/m2

Brushes with life covering capacity of 180m2 for oil workBrushes with life covering capacity of 300m2 for emulsion workWood vanish spray covers 60m2/gallonThe painting gang normally comprises2 painters @ GH¢ 6.50 13.001 labourer @ GH¢ 6.00 6.00 GH¢19.00

126

Page 127: BT 358 ConstructionEstimating and Price Analysis

Table 4.13 Achieved labour output data on works including preparation in m2/ gang-day

Surface TypeEmulsion Paint Oil Paint

Rendered wallRendered soffitScreeded floorHardboard soffitFlat asbestos sheet soffitGeneral wood surfacesStopping and other putty work on paintingHardwood surfaces including glass paper work

6040-

3535---

453540303030

40

Worked-out example in painting and decorationCompute the estimate for the preparation and application of 3 coats of emulsion on rendered walls, total area 100m2

Solution Materials:Emulsion paint:At a utilization of 40m2/gallon/coat,quantity required for 3 coats of 100m2 3 x 100/ 40 = 7.50 gallonsAdd 15% for waste 1.13 8.63 gallonsBuy 9 gallons @ GH¢ 10.00 ex-site GH¢ 90.00Brushes:With life coverage of 300m2/brushNo. of brushes required 3 x 100/ 300 = 1.00For losses, add 1 1.00 2.00Buy 2 of 150mm width brushes @ GH¢ 0.90 GH¢ 1.80 GH¢ 91.80Labour:

Preparation and painting 3 coats of 100m2 at an output of

From table 4.13, 60m2/gang-day/coat would require 100 x 3/ 60 = 5 gang-days

Cost of 5 gang-days GH¢ 35.00 GH¢ 175.00

Total Cost GH¢266.80

Unit Cost GH¢ 2.67/m2

127

Page 128: BT 358 ConstructionEstimating and Price Analysis

2-4.5 Estimating for Floor, Wall and Ceiling Finishes

In estimating for finishes, let us start with in-situ finishes.The major factors affecting resources input of in-situ finishes are:

i. The irregularities of the surface which receives the finishes;ii. Compression of the in-situ materials on trowelling;

iii. Waste mainly on dropping during utilization.

Allowances have to be made for 60% addition to materials content, in respect of wall rendering, floor screeds and ceiling finishes. Let’s take a look at table 4.14.

Table 4.14 Achieved labour outputs for finishes

Manual mixing of mortar13mm thick rendering to walls13mm ditto to soffitsDitto to angles and arisesDitto to small compartments*18mm thick screed*25mm thick screed

Tiling output/gang-dayWalls (glazed) Floors (PVC) Floors (PVC) Terrazzo floor polishing average daily output for a gang of 2 operatives

Ceiling covering output per gang-day Flat asbestos sheet with hardwood battens Plywood ditto Celotex hard board tiles Covering capacity of white cement pointing of joints in glazed wall tiles Covering capacity of Tyrolean finish to rendered wall Covering capacity of PVC floor tile adhesive

1m3/man-day30m2/gang-day

20m2/ " "15m " "10m2 " "30m2 " "25m2 " "

4m2

12m2

6 m2

10m2

20m2

24m2

18m2

40m2/bag of cement/gang-day40m2/bag of cement/gang-day 10m2/4.5L unit

*Deduct output by 12.5% for:i. Each 12.5mm increase in thickness

ii. Trowelling surface to receive floor tiles.

Worked examples in wall, floor and ceiling finishesIn-situ finishes internally:Compute the estimate for 12.5mm thick cement and sand (1:4) rendering on sandcrete blockwall, steel trowelled in one coat on an area of 100m2

128

Page 129: BT 358 ConstructionEstimating and Price Analysis

Solution We will use data from table 4.14 to solve this.Material:For the (1:4) mortar, let’s adopt the rate of GH¢ 130.22 as mixed (from blockwork

example 1)

Since the thickness of the mortar from the question is 12.5mm, then the volume of mortar (1:4) required is 0.0125 x 100 = 1.25m3

Allow 60% for irregularity of surface, compressionon trowelling and utilization waste 0.75 m3

Total volume required 2.00m3

Cost of 2m3 @ GH¢ 130.22 GH¢ 260.44

Labour:100m2 wall rendering at an output of 30m2/gang-day would require100/30 = 3.33 gang-daysUse 3 gang-days @ bonus rate of GH¢ 32.00 GH¢ 96.00

Total Cost Summary:Materials GH¢ 260.44Labour GH¢ 96.00Total Cost GH¢ 356.44Unit cost GH¢ 3.56/m2

Self-assessment questions1. Identify the key components which are considered when estimating for:

a. Roofing;

b. Walling;

c. Woodwork;

d. Wall, floor and ceiling finishes respectively; and

e. Painting and decoration.

129

Page 130: BT 358 ConstructionEstimating and Price Analysis

Session 3-4 Preparing Estimates for Plumbing and Electrical installations, Glazing and PreliminariesLearning Outcomes

By the end of this session, you will be able compute estimates for:

i. Plumbing installations

ii. Electrical installations

iii. Glazing items

3-4.1 Estimating for Plumbing Installation

Generally, plumbing work is mainly undertaken by labour-only sub-contractors. Most of these are small local contractors who operate on a small-scale without the capacity to support full-time plumbing gangs. Tables 4.15 and 4.16 present some average output data used in estimating the cost of plumbing installations.

Table 4.15 Output data per gang-day for supply, preparation and fixing fittings and appliances

Traps in waste connectionsTaps (13 – 25mmØ)Shower rose and connectionsShower tray80L capacity water heater2000L (500 gals) overhead storage tank and overflow fittingsLow level water closet complete with cisternWash hand basinCast iron enamel bath tubChina clay kitchen sinkStainless steel kitchen sink with double drainerBuilder’s work (floor area)Excavating trench and backfilling Jointing compound utilization @ 0.025kg/m of PVC pipes

12 No.15 "20 " 4 " 4 " 4 " 4 " 6 " 1 " 6 " 4 "30m2

10m/man-day

130

Page 131: BT 358 ConstructionEstimating and Price Analysis

Table 4.16 Showing output per gang-day for pipework inclusive of pipes, fittings and supports in domestic buildings

Diameter (mm)Type of Pipe

Asbestos P.V.C Galvanized Copper

1301005038251513

6m4m

12m15m15m20m20m15m15m

15m15m10m

14m12m

Worked Example in Plumbing Installation:

Compute the estimate for laying 10m of 100mmØ pvc pipes as specified in trenches.

Solution Materials:P.V.C pipes 100mmØ are sold in 3.0m lengths locallyNo. of lengths required will be 10/3 = 3.33Add 15% for waste 0.50 3.83Approximate to 4 lengths,Buy 4 lengths @ GH¢ 10.50 GH¢ 42.00Jointing compound for 10m @ a utilization of0.025kg/m would require:

10 x 0.025kg = 0.250Add 10% for waste 0.025 0.275kg

But this is sold in 0.25kg minimum containers.Therefore, buying 2 containers @ GH¢ 6.60 GH¢ 13.20Total Material cost GH¢ 55.20Labour:Trench excavation and backfilling of 10m @ an output of10m/man-day would require 10/10 = 1 man-dayUse 1 man-day @ GH¢ 6.50 GH¢ 6.50Pipework in trenches for 10m @ an output of 15m/gang-day would require 10/15 = 0.67 gang-dayLets use 1 gang-day @ GH¢ 30.00 GH¢30.00Total Labour Cost GH¢ 36.50

131

Page 132: BT 358 ConstructionEstimating and Price Analysis

Total Cost Collection:Materials 55.20Labour 36.50Total cost GH¢91.70Unit cost GH¢ 9.17/m

3-4.2 Estimating for electrical installations

Electrical installation work is mainly undertaken by specialist sub-contractors.

Estimating is done by preparing a comprehensive list of all electrical items required,

documenting and sending for quotes from prospective specialist sub-contractors. The

list of electrical items is prepared from the contract documents.

However, main contractors also prepare their estimates from comparable detailed

itemized list by adjusting the unit cost of the materials component. Usually, most

local contractors use a combination of the rate of work for the average floor area

covered per gang-day in new building types as follows:

Floor area (m2) per gang day

For mass housing of low income units 15

Medium income house 12

High income house 9

Office 18

Builder’s work 45

Open space like factories, etc. 38

The other types include:

1-3 switches and switch socket outlets per gang day

70.0m cable wire length/gang-day

Worked example in electrical installations

Consider electrical installations in a new medium income house of floor 120m2 floor

area with 20 switches and switch socket outlets all as detailed in Table 4.17

Table 4.17 Estimating for electrical installationsItem Description Quantity Rate (GH₵) Cost (GH₵)

DISTRIBUTION BOARDSA Supply, erect and connect a 6 way mix

capacity MCB consumer unit1 60.00 60.00

MCB FOR ABOVE

132

Page 133: BT 358 ConstructionEstimating and Price Analysis

B 5A SP MCB 2 30.00 60.00C 20A SP MCB 2 35.00 70.00D 30A SP MCB 2 40.00 80.00

SUB FEEDER CABLESSupply, erect and connect the following from the worm piece insulator to meter board and onto the distribution board

A 25mm dia. PVC pipe as conduit 20m 2.00 40.00B 1x16mm2 PVC insulated copper cable

drawn into the conduit40m 3.00 120.00

GENERAL POWER OUTLETS AND LIGHTING POINTSSupply, erect and connect the following for general power and lighting points

C 20mm conduit concealed in chases, block work, concrete floor, etc.

200m 2.50 500.00

D 75mmx75mmx 35/50mm square boxes at switch and power points

20m 2.50 50.00

E -Do- but complete with covers as draw points.

3 Nos 2.00 6.00

F 20mm circular boxes of various ways of lighting points

15 Nos 2.50 37.50

WIRING CABLESSupply and draw the following in existing conduits

G 1.5mm2 PVC insulated cable but coloured green as earth continuity cable to serve fluorescent tubes

300m 1.00 300.00

H 1.5mm2 PVC insulated cable for lights 20m 1.00 20.00J 2.5mm2 PVC insulated cable for 13 A

switch sockets100m 2.00 200.00

K -Do- but coloured yellow/green as earth continuity cable

40m 2.00 80.00

L 6.0mm2 PVC cable (Cu) for cooker control unit

10m 2.00 20.00

M 4.0mm2 PVC cable coloured green/yellow as earth wire

10m 2.00 20.00

SWITCHES AND SWITCH SOCKETSSupply, erect and connect the following:

N 13A 240V SP 1 gang switch socket 2 Nos 1.50 3.00P 15A 240V SP switch socket 11 No 1.50 16.50Q 45A DP cooker control unit Nil -R 5A SP 1way 1 gang switch 3 Nos 2.00 6.00S 5A SP 2 way 2 gang switch 2 Nos 2.00 4.00T 5A SP 1 way 2 gang switch 2 Nos 2.50 5.00A Meter Board 1 No 20.00 20.00

LIGHTING FITTINGSSupply erect and connect the following :-

B 1x 40W 1.2m fluorescent fitting C/W tube

2 Nos 10.00 20.00

133

Page 134: BT 358 ConstructionEstimating and Price Analysis

C 1x 40W batten lamp holder 10 Nos 10.00 100.00

EARTHINGSupply, erect and connect the following:-

D 1.2m long 13mm copper earth rod 2 No. 15.00 30.00E 6.0mm2 bare copper as earth lead

bounded to the DB at one end and to the earth rod at other end buried 2m below ground

20m 2.00 40.00

MATERIAL COST 1,908.00Add 10% for transportAdd 5% for storage 286.20TOTAL MATERIALS COST 2,194.20

Labour:20nr of switches and switched outlets at an output of 2/gang-day would require20/2 =10 gang-daysUse 10 gang-days @ GH₵ 25.00 GH₵ 250.00On the other hand, using an output of 12m2 of floor area/gang-day for 100m2 would require 120/12 = 10 gang-daysHence using 10 gang-daysTotal Cost SummaryMaterials GH₵ 2,194.20Labour GH₵ 250.00Plant -Total Cost (Labour and materials) GH₵ 2,444.20

Hence installed total cost as a factor of material input cost is 2,444.20 2,194.00 = 1.114

Rates of each of the items of materials must be multiplied by the factor 1.114 to obtain the unit rate in each case.For builder’s work in connection to this, gang-days required will be 100/45 = 2.22 gang-daysBut use 3 gang-days @ GH₵ 25.00 GH₵ 75.00

3-4.3 Estimating for Glazing

There are different glass types generally used for building projects in Ghana. The popular ones are:

i. Sheet louvre glass fixed in metal louvre carrier clips. ii. Clear or rough cast sheet glass fixed to metal, wood or plastic in opening. In this

type, some of the common sizes normally available in respective thicknesses are:

5.0mm thick5.5mm thick6.0mm thick

2.7 x 1.67m2.7 x 3.33m2.7 x 3.33m

134

Page 135: BT 358 ConstructionEstimating and Price Analysis

Labour output for glazing works:

Figure 4.18 shows the outputs for cutting and fixing sheet glass to timber, metal and plastic respectively.

Table 4.18 Cutting and fixing of sheet glass in m2/gang-day

Area range (m2)

Cutting and fixing to:Timber Metal Plastic

Up to 0.10.1 – 0.50.5 – 1.01.0+

3.503.002.502.00

4.54.03.52.5

5.55.04.53.5

Putty utilization @ 0.70kg/m2 all-in. For cuttings only use 2.00 times output.

Worked-out example for glazingCompute the estimate for 1000No. 150 x 750 x 5mm ordinary quantity obscure glass louvre blades with smooth cut edges and with ends fixed in metal louvre carrier clips.

Solution Materials:150 x 750 x 5mm glass louvers:Net number required 1000Add 10% for waste and damage 100Total no. required 1100Cost of 1100 @ GH¢ 0.80 GH¢ 800.00

Labour:Louvre glass fixing for 1000 @ an output of150 no./gang-day would require 1000/150 = 6.67 gang-daysAdd 10% for minor cuttings 0.67 7.34Use 8 gang-days @ GH¢ 35.00 GH¢ 280.00Total Cost (material + labour) GH¢1,080.00Unit Cost GH¢1.08

Self-Assessment Questions

List the key constituents which make up estimates for:

i. Plumbing installations

ii. Electrical installations

135

Fixing of 150 x 750mm louversFixing of 150 x 900mm louversFixing of 225 x 900mm louvers

150 No./gang-day120 No./gang-day90 No./gang-day

Page 136: BT 358 ConstructionEstimating and Price Analysis

iii. Glazing

(Clue: this refers to the key headings which are covered in preparing estimates for

these worksections)

136

Page 137: BT 358 ConstructionEstimating and Price Analysis

Unit 5 ESTIMATING FOR PRELIMINARIESUnit Objectives

By the end of this unit, you will be able to:

i. Explain what the term “preliminaries” refer to and how these can be estimated

ii. Identify the relevant preliminary items for a project

iii. Prepare a complete estimate for Preliminaries for a project

Introduction

In general, the preliminaries section of a bill of quantities for a specified project relate

to expenses incurred during construction which will not easily fit into any of the other

trade sections when building up unit rates. They relate to works required for the entire

project but nor necessarily associated with any particular work section or any

particular aspect of a project.

Session 1-5 Preliminary ItemsLearning outcomes

By the end of this session, you will be able to:

i. Identify the different items and activities which make up “preliminaries”

v. Understand how preliminary items are handled during estimating

In the Ghanaian construction industry, some of the common items which constitute

“preliminaries” are as follows:

1. Description of the works and particulars of the work.

2. Visit to the site

3. Access roads to the site.

4. Setting out of the works

5. Competent surveyor and any surveying equipment required.

6. Temporary buildings

7. Programme of works

8. Handing over of the completed works

9. Antique items

137

Page 138: BT 358 ConstructionEstimating and Price Analysis

10. Photographs showing the progress of works

11. Office for consultants and the clerk of works

12. Connection of temporary water to the site

13. Connection of temporary telephone facilities for the site office

14. Temporary lighting for the works

15. Contractor’s supervision

16. Resources, labour, materials and plant for the works

17. Provision of general transport for the works

18. Small tools and equipment required

19. Scaffolding

20. Provision of samples of materials required for the works

21. Ordering of materials

22. Testing of materials

23. Checking of schedules and drawings

24. Record keeping

25. Protection of the works

26. Shoring and strutting of the works

27. Protection of persons and property

28. Insurance against injury to persons on site

29. Insurance of the works

30. Watching and lighting of the site

31. Overtime costs

32. Prevention of nuisance

33. Prevention of fly tipping and spoil dumping

34. Health, safety and welfare of workmen

35. First aid box

36. Sanitary accommodation / restroom

37. Making good damage to roads and streets

38. Employer’s signboard.

39. Cleaning up of site

40. Disposal of water away from the works

41. Prime cost and provisional sums

42. Nominated suppliers

43. Nominated sub-contractors

138

Page 139: BT 358 ConstructionEstimating and Price Analysis

44. Attendances required for the works

45. Builders’ work

46. Contingencies

47. Preamble clauses

48. Bid securities and bid bonds required

This list of preliminary items is by no means exhaustive. Other items may be added

where necessary. It must also be pointed out that whilst most of these will be required

for most projects, not all these items listed above will necessarily be present on all

projects. Therefore the estimator’s discretion should be used whenever necessary.

There is a tendency for some contractors to simply put in a lump sum for

preliminaries. However, there is a danger that a lump sum may be an inaccurate

representation of all the works which make up the preliminary items. Where the lump

sum put in for preliminaries exceeds what is required, it may render the resulting

estimate non-competitive. This may eventually affect the contractor’s chances of

winning the project adversely. It is therefore advisable that wherever items which

form part of preliminaries can be calculated or where a close estimate can be

obtained, this should be used.

It must be pointed out too that not all the items listed above will be required in all

projects. In some cases, some of the listed items in the list above may not apply and

will therefore not be priced. There are also some items in the preliminaries section can

be estimated without the need for any complex computation. However, it should be

stressed that some of the items which form part of the preliminaries section are very

important and should be considered in nearly all estimates. Examples of the more

common ones include water for the works, electricity for the works, bonds and

securities, insurance for the works etc. these are a common feature of most bills.

In the next session, we will take you through how to prepare estimates for some of the

sections which can be easily computed.

139

Page 140: BT 358 ConstructionEstimating and Price Analysis

Session 2-5 Pricing StrategyLearning outcomesBy the end of this session, you will be able to:

i. Identify the main components which make up the total cost of preliminary itemsii. Prepare a complete estimate for Preliminaries for a project

In general, preliminary items are considered on the basis whether they are time-

related or otherwise. The main components which make up the total cost of

preliminary items are usually as follows:

i. Cost of bringing and installation to site and / or erection as a fixed cost, X;

ii. Utilization and maintenance cost as a time-dependent variable cost, Y; and

iii. A fixed cost, Z, for removal and making perfect.

We will illustrate these with a few worked examples of preliminary items. By their

very nature, preliminary items tend to vary depending on the nature and

characteristics of the project under consideration. We can therefore not present a set

of comprehensive worked examples representing all possible preliminary items. These

worked examples are meant to simply illustrate the principles used when estimating

for preliminary items. We will focus on some of the more commonly occurring

preliminary items.

Worked out Examples for PreliminariesItem 1: Estimating for Description of the works

“Description of the works” gives general information on a project with regards to the

type of structure(s), the volumetric content, area on plan, roof form, finishes, project

location and expected mode of completion on projects involved until completion.

Generally this should not involve any expense to the contractor and hence this item is

not normally priced.

Note: Description of works is quite distinct from the signboard which also describes

the project but involves some expenses.

140

Page 141: BT 358 ConstructionEstimating and Price Analysis

Item 2: Site Visit

Generally, the time spent by the estimator and contractor’s manager is allowed for in

the general overhead cost. However other expenses relating the site visit are priced as

show in table 5.1 below.

Table 5.1 Pricing of site visit

Fixed Cost X

GH¢

Variable Cost

Y GH¢

Fixed Cost Z

GH¢

i. Vehicle for trip. Say 2 days

@ GH¢100.00200.00 - -

ii. Hotel and other incidentals

@ GH¢ 15.00 a day per

person for 3 persons for 3

days

135.00 - -

iii. Stationary 20.00 - -

Total 355.00 - -

Overall Total GH¢ 355.00

Item 3: Access Roads

These are highly dependent on the site conditions and the available infrastructure. But if it

becomes very necessary to construct temporary roads, then the total expenses to be computed

should cover the following:

i. Fixed cost ‘X’ for initial construction

ii. Variable cost ‘Y’ for maintenance

iii. Fixed cost ‘Z’ for removal and leaving perfect/cleaning up.

Item 4: Setting Out

The following items which constitute general supervisory labour: Site Agent, General

Foreman, etc, engaged on this are covered under the project overheads. The remaining cost is

estimated as follows:

Use a profile girth of 2(L + B + 2)m where L and B are dimensions of the least

rectangular enclosure of the building. Hence for a building of 20 x 25m on plan, the

required profile girth = 2(20 + 25 + 2)m = 94m

141

Page 142: BT 358 ConstructionEstimating and Price Analysis

Material:

i. Using 50 x 50 x 100mm sawn redwood pegs at 1.0m centres would require

94/1 + 1 = 95pegs

Add 10 for waste = 10

A. Total no. of pegs = 105

B. Cost of 105 pegs @ GH¢ 1.00 GH¢ 105.00

ii. Using 25 x 150mm Wawa as profile board

Length required = 94.0m

Add 10% for waste = 9.4

C. Total length = 103.4m

D. No. of 3.6m length, 103.4/3.6 = 28.7

use 29 length @ GH¢ 15.00 GH¢ 435.00

c/fwd GH¢ 540.00

iii. 75mm long wire nails used at 5/m girth

Work up to 0.033kg/m

Weight required will be 94 x 0.033kg

= 3.1kg

Add 10% for waste = 0.3

Total weight 3.4kg

But buy 4kg @ GH¢1.00 GH¢ 4.00

Sub-total for materials GH¢ 544.00

Material cost/m girth GH¢ 5.79/m

Using a carpentry gang of 2 carpenters and 2 labourers with a daily gang output of

100m at a rate of 2(8 + 6) = GH¢ 28.00

Labour cost/m GH¢28/100 = GH¢ 0.28

Total erection cost/m girth for materials and

labour will be (5.79 + 0.28) = GH¢ 6.07

(this becomes the fixed cost ‘X’ for erection)

The maintenance cost/m is time dependent and allowing

GH¢ 0.01/month for the first 3 months of the 12 months

contract gives GH¢ 3.36

142

Page 143: BT 358 ConstructionEstimating and Price Analysis

(Such setting out boards are removed after substructure works)

This becomes variable cost ‘X’

For the cost of profile removal, disposal and making good the

site, allow 1.5 times erection labour cost as fixed sum ‘Z’ i.e. 1.5 x 0.28 GH¢ 0.42

Total cost/m girth GH¢ 9.85

Expenses on the surveyor’s team and their equipment will be covered under item 5.

Item 5: Competent Surveyor and Equipment

For general building works, such expenses are allowed for in the overheads. But

where specialist surveying services are required, the duration of the surveying team’s

involvement must be estimated. This is a time-related item and from the computation

of the all-in-rate for the surveyor and his team members on the projected duration of

the works, the cost can be estimated.

For example, a month’s total duration for 3 man team earning 3 x GH¢10.00 all-in

monthly requires

3 x GH¢ 150.00 = GH¢ 450.00

For example, add GH¢ 20.00/month for 1 month = GH¢ 20.00

Total cost for item = GH¢ 470.00

Item 6: Temporary Site Building

The site layout shown in the site visit report and the firm’s policy on such temporary

buildings would help identify the type and space allocation required. With this, cost of

erection and furnishing can be built up from historical records as in the following example for

a large project:

i. Office, conference and drawing rooms – 60m2 floor

area of timber on raised platform at GH¢ 40.00 = GH¢ 2400.00

ii. Construction of stores 20m2 at GH¢ 120.00 GH¢ 240.00

iii. Canteen: 30m2 at GH¢ 30 GH¢ 90.00

iv. Workshops and toilet 28m2 at GH¢ 20 GH¢ 560.00

v. Sheds: 40m2 at GH¢ 30.00 GH¢ 120.00

= GH¢3,410.00

143

Page 144: BT 358 ConstructionEstimating and Price Analysis

vi. Furnishing:

Furniture GH¢ 500.00

Stationary GH¢ 500.00

Office Equipment GH¢ 2000.00

Fridge GH¢ 500.00

Air Conditioner GH¢ 2,500.00 = GH¢ 6,000.00

Total erection and furnishing GH¢ 9,410.00

Utilization and maintenance for 12 months

at GH¢50.00/month GH¢ 600.00

Removal and leaving perfect at 33% of erection

cost 1/3 x 3,410 GH

¢1,136.67

Total expenses = GH¢11,146.67

Item 7-9: Programme of works, Handing over of the completed works and Antique items.

These are normally not priced but deemed to be covered in overheads.

Item 10: Progress Photograph

This may be a lump sum based on, say a set of 5 snaps every 2 months for the contract period

of any 12 months.

Hence no. of snaps required will be = 5 x 12/2 = 30

Cost of 30 snaps @ GH¢ 2.00 = GH¢ 60.00

Item 11: Office for consultants and clerk of works

This item has already allowed for in the computation of item 6(temporary buildings).

Item 12-14: Temporary Water or Telephone or Electricity for the Works.

The cost constituents for water are:

1. Bringing and storing the water comprising:

i. Pipe works including excavation at

GH¢ 2.00/m for, say 100m distance = GH¢ 200.00

ii. Fittings at an average of 50% of (i) GH¢ 100.00

iii. Block storage tank 4m3 at GH¢ 6.00 GH¢ 24.00

iv. Labour using 2 plumber gang days @ GH¢ 10.00 GH¢ 20.00

144

Page 145: BT 358 ConstructionEstimating and Price Analysis

v. Connection to mains + recording meter statutory

charges by GWSC currently (March 2008) rate GH¢ 100.00

Total fixed cost ‘X’ GH¢ 444.00

2. Utilization and maintenance allowance of GH¢ 5.00/month

for contract period of 12 months GH¢ 60.00

3. Removal and leaving perfect allowance of 50% installation

labour 50% of GH¢ 20.00 GH¢ 10.00

Total cost GH¢ 514.00

Item 15: Contractor’s Supervision

This is a good example of time related items. It covers the expenses on general site

staff that have not been allowed for elsewhere in the preliminaries unit. It starts from

the preparation of the outline works programme to determine the projected contract

period and then setting out the site organization structure. The latter is extracted from

the project’s general staff and the duration of their services during the projected

contract period. The data so collected should then be tabulated as shown in table 5.2,

to calculate the contractor’s cost.

Table 5.2 Calculation of contractor’s supervision cost

Designation No.Time on Project

(months)

All-in-rate (months)

GH¢Total Cost

Site AgentGeneral ForemanGeneral ArtisanSite Records ClerkStorekeeper Time-KeeperTypist Watchman

11211113

1212101212121213

18.0012.0011.008.007.006.006.005.00

216.00144.00220.0096.0084.0072.0072.00195.00

Total Cost GH¢ 1099.00

Item 16: Resources, labour, material and plant for the works

This item is not priced.

Item 17: Provision of general transport for the works

This is expected to be in the form of, say a Pick-up vehicle and allowance is made as

follows

i. Fixed cost for provision of vehicle comprising:

145

Page 146: BT 358 ConstructionEstimating and Price Analysis

Daily all-in-rate of vehicle, say 0.0035 of purchase

price of GH¢ 25,000.00 GH¢ 87.50

Daily all-in-rate of driver, say GH¢ 15.00

Total fixed cost GH¢ 102.50

Hence fixed cost/month GH¢ 102.50 x 27 GH¢ 2767.50

For contract period of 12 months x 12

GH¢ 33,210.00

It should be noted however that the item has no allowance for removal and making

perfect after completion.

Item 18: Small Tools and Equipment Provision

Ideally, a comprehensive list of small tools and equipment envisaged for the project

could be prepared and priced accordingly at rates that allow for expected price

increases. This might include such major items as cranes and dumpers and minor ones

like shovels and pick-axes. However analysis of local historical site cost data

indicates that where no heavy equipment like cranes, central batching plant and their

likes are needed, an allowance of 0.8% of cost of works has been found reasonable.

Heavy equipment should be estimated for in terms of the costs of:

i. Bringing to the works and installation including its operator’s wages

ii. Utilization and maintenance

iii. Removal and making good

Item 19: Scaffolding

In general, ordinary buildings up to 3.0m high do not require any special scaffolding.

From historical data, 0.1% of cost of works appears to be a reasonable figure. Thus,

an allowance of 0.1% should be made for scaffolding for such buildings. Buildings

above the 3.0m high up to about 12m high, require these and timber scaffold of the

horse type shown in Figure 4.1 is normally provided

Solution

Analysis of local site data indicate the following resources input per meter perimeter

of building requiring scaffolding for external surface work at elevations up to 3.5m

high. This is for erection only and subject to 12 repetitive uses.

i. Material utilization of 0.12m3 sawn hardwood and 0.25kg of 75mm wire nails

146

Page 147: BT 358 ConstructionEstimating and Price Analysis

ii. Labour input of 0.20 carpenter gang days

Removal and making good cost is in the region of 1.5 times labour cost for erection.

These estimates increase by 40% for subsequent 1.5m increase in height up to 12m

where specialist attention would be required. In the latter case, tabular scaffolding

would be required and enquiries for quotations for purchasing, erection and removal

would be necessary for first users to facilitate further pricing using historical data as

basis for subsequent uses. This is resorted to because all such tubular scaffolds where

required would have to be imported in the first instance.

Figure 5.1 Horse type timber scaffold at 1500mm centres

Item 26: Shoring and Structuring required

The two types commonly found at local sites are 50 x 100mm sawn hardwood frame

structure with either 25 x 300mm hardwood vertical boarding of corrugated metal

sheet cladding along the site boundary as shown in Figure 4.2.

Figure 4.2a Site fence with timber frame and corrugated metal sheet cladding.

147

5 011 50

11 505 0

5 0

57 557 5

3600

mm

A

C

C

1000 mm

3 No. of 50 x 100 x 1100 beams

3 No. of 50 x 100 x 3600 boarding

2 No. of 50 x 100 x 3600 posts

2 No. of 50 x 100 x 3600mm brace

A

Page 148: BT 358 ConstructionEstimating and Price Analysis

Figure5. 2a Site fence with timber frame boarding

Figure 5.2b

Details from analyses local site data on timber shoring of this type show the following

as cost per metre girth of shoring.

i. Materials:

Timber input utilizing 0.025m3 for frame work

Timber input utilizing 0.040m3 for cladding.

Nails input utilizing 0.08kg of 75mm long for frame work.

Nails input utilizing 0.06kg of 50mm long for cladding.

Creosote preservation utilization at 0.10 gallon.

ii. Labour:

Framework at 0.05 carpenter gang day.

Cladding at 0.40

Preservative brushing at 0.01 labourer day

iii. Maintenance cost achieved at local sites per month is of the order of 1.5% of total

erection cost of shoring:

iv. Removal and making good cost is in the region 1.5 times total erection labour cost.

Item 25: Protection of Works

This is allowed for in the trade units of the bill. If specific requirements are necessary,

this can be priced accordingly on the cost of provision maintenance and removal.

148

50 5050

150150 150 150

15001500

2 No. 50 x 100 horizontal beamsat 1000mm centres 50 x 100mm post at 1500 centres

Corrugated metal sheet cladding

50 x 100 horizontal beam

25 x 150mm boarding 50 x 100 post

Page 149: BT 358 ConstructionEstimating and Price Analysis

Item 27 and 28: Protection of persons and property / Insurance against injury to persons

on site.

These are usually not priced as part of the preliminaries since they would have been allowed

for in the workmen’s compensation insurance in building up the all-in-labour rates.

Item 29: Insurance of the work

This is value-related and hence depends on the contract sum with the premium paid in

the order of 0.2% of contract sum. The premium paid is usually re-imbursed in full

without mark-up for overhead expenses which must be allowed for elsewhere. Details

must be cleared from reliable insurance firms concerned.

Item 30: Watching and lighting have been allowed for in computing expenses for items

12-15.

Item 31: Overtime and Completion

Local climate conditions and project resources supply situations are such that the need

for overtime work to keep to works schedule cannot be ignored. Reasonable

allowance for this is in the region of 1.5 days per month operative for a minimum of

10% contract period.

Hence for a 12 month contract with anticipated labour force of 60 operatives, due

overtime should be:

1.5 x 12 x 0.10 x 60 = 100man-days

At 1.35 times normal time = 135 man-days (normal)

Use 135 man-days at GH¢ 6.00 = GH¢ 810.00

Item 32 and 33: Prevention of nuisance / prevention of fly tipping and spoil dumping.

$These are not normally priced except where very specific precautions are required. An

example is an area where there is a high incidence or potential for their occurrence. In such

cases, detailed estimates can be prepared after thorough examination of the situation.

Item 34: Health, Safety and welfare of workmen

This item is allowed for in computing all-in-labour rates.

149

Page 150: BT 358 ConstructionEstimating and Price Analysis

Item 35: First-Aid Box.

This is generally of 13mm thick plywood of 300 x 300 x 600mm size with door,

hinges and lock. It is stuffed with pain-killing and other first-aid drugs. Pricing is

pursued as follows:

i. Provision of box at fixed cost;

ii. Utilization of drugs and replenishing stock; and

iii. Removal expenses.

Item 36: Sanitary Accommodation / Restroom

This is allowed for in item 6 (temporary buildings)

Item 37: Making Good Damage to Roads and Streets

Whilst in principle this item needs to be included, in practice, it is hardly enforced and thus

most contractors do not price this.

Item 38: Employer’s Sign Board

This is allowed for in terms of:

i. Cost per month for provision and erection;

ii. Cost per month for maintenance; and

iii. Removal expenses

Item 39-47

These cover details of project information and are normally not priced. In the case of

items 41 and 46, specific amounts to be directed by architect and their inclusion in the

sub-total must be noted.

Item 48: Bid Securities and Bonds

The premium charged for bid securities and bonds is usually at the rate of 0.5% of

contract sum. The associated on-cost is also about 0.5%. Thus the total allowance for

bid securities and bonds is usually of 1% of the contract sum.

Self-assessment questions

i. Identify 10 items which comprise preliminaries when preparing an estimate.

ii. Which of the items listed in (1) will incur an expense to the contractor and

which of them will not?

150

Page 151: BT 358 ConstructionEstimating and Price Analysis

End of Unit Assessment

i. Explain the terms “all-in rate for labour” and “all-in rate for plant”

ii. In computing the “all-in rate” for labour and plant respectively, what are

the respective sets of constituents which are considered?

iii. Explain the pricing strategy which is followed when pricing preliminary

items.

iv. Make a list of as many preliminary items as you can. Briefly describe how

the cost for each of these is computed.

151

Page 152: BT 358 ConstructionEstimating and Price Analysis

Unit 6 PRICE ANALYSISUnit objectivesBy the end of this unit, you will be able:

i. Explain the different pricing strategies used by contractors when pricing their estimates

ii. Explain the term “bidding strategy”iii. Explain how “risks” are managed through the contract

SESSION 1-6 Pricing manipulationsLearning outcomesBy the end of this session, you will be able to:

i. Identify different pricing strategies which may be employed by contractors to achieve their financial objectives

ii. Explain the terms: “front-end loading” and “unbalancing of tenders”.

The s-curve suggests that a typical building project does not become self financing

until it is near completion and in addition, requires the contractor to provide

considerable amounts of capital in both working capital and long-term capital. As cost

is associated with the provision of capital, contractors often seek ways of improving

their cash flow at the initial stages of project.

The two common methods which are often used by contractors to improve their

cashflow during the early stages of a project are:

i. Front-end loading; and

ii. Unbalancing of Tenders.

Front-end loading

It is generally expected that project costs rise as the percentage of bill items covered

increases (fig.6.1). Front-end loading occurs when items of work which the contractor

expects to be executed early in the project have prices which contain

disproportionately large content of overheads and profits and items of work to be

executed in the later stages of the project have their prices reduced accordingly. This

situation is of further benefit to the contractor due to the time value of money. The

client’s quantity surveyor should generally be able to detect if front-end loading has

been used by a contractor through rigorous checking. Table 3.3a and fig.3.3b illustrate

152

Page 153: BT 358 ConstructionEstimating and Price Analysis

the cashflow for a project without front loading and one that uses front loading

respectively.

80% of the value of work will be 20% of Bill items

Fig 6.1 Graph showing percentage of project costs against percentage of bill items

Table 6.2a Cashflow without front loading

Item Quantity Unit Mark-up Bill RatePrice in

GH¢

Excavation

Concrete

Block

Proof

1000

100

500

200

5

50

50

25

10

10

10

10

5.5

55

55

27.50

5500

5500

27500

5500

44000

Total Cost = GH¢40,000

Total mark-up = GH¢ 4,000

Total GH¢ 44,000

Table 6.2b Cashflow when front loading is used

Item Quantity Price in GH¢

ExcavationConcrete

BlockProofTotal

1000100500200

75007500230002000

40,000

Unbalancing of TendersThis normally occurs where the contractor expects variations in the contract. In this

case the contractors will price low those items they expect to be increased. Again

153

100

100 % of Bill Items20

Page 154: BT 358 ConstructionEstimating and Price Analysis

systematic checking by the consultants Quantity Surveyor acts as a restriction upon

such manipulations.

Contract StrategiesThe development of an appropriate contract strategy requires consideration of:

i. Effective organizational structure to control design and construction and their

influences;

ii. Selection of the contract, extent and sequences of work packages;

iii. Choice of type of contract;

iv. Method of contractor selection; and

v. Selection of method of preparation of Tender documents.

Adopting the most appropriate contract strategy can help save project costs. Research

suggests up to 5% of project cost savings by using the most appropriate type of

contract.

2-6 Bidding strategy, contract strategy and risk managementLearning outcomesBy the end of this session, you will be able:

i. Explain the term “bidding strategy” and identify some useful strategies used in the

bidding process

ii. Explain the main considerations involved in contract strategies

iii. Explain how risks associated with a construction project can be handled using the

appropriate contract strategies

2-6.1 Bidding Strategy

Bidding strategy constitutes a set of arrangements which bidders put in place in order

to enhance their chances of winning more projects which are tendered for. To enhance

the chances of success, a contractor, or specialist trade contractor, will formulate aims

and a framework to win contracts at prices which will produce profitable work. An

evaluation of tendering performance itself is not enough to meet this aim, because

although a contract may be won with a reasonable anticipated profit, it may be found

that the particular type of work seldom achieves or improves margins when the final

results are known. A bidding strategy must recognise the need to decline invitations to

154

Page 155: BT 358 ConstructionEstimating and Price Analysis

tender for work or procurement arrangements which fail to meet the organization’s

objectives. When contractors set tender margins, they consider all the points discussed

in the Final Tender Review meeting. In addition, they may be influenced by tenders

submitted by their competitors and budgets set by clients. It is clear that neither of

these criteria will help achieve optimum margins in a highly competitive market. It is

difficult to avoid low margins where competition is strong but, if prices fall below

economic levels, it is time to look for other markets where the company can employ

its strengths more effectively.

Developing a Successful Bidding Strategy

The first step is the development of a probability of winning if the company bids at a

certain mark-up. E.g. if you bid at 15% you have 40% chance of winning. The second

step is the setting up of optimum mark-up which in the long term will produce the

maximum profit. It is assumed that the contractor first estimates his costs and then

adds a mark-up to cover profits and company overheads. It must be noted that there

exists a relationship between the tender sum and the probability or chance of winning

the contract.

2-6.2 Risk Management

Risk management involves identifying what the risks are, taking appropriate efforts to

control them and taking the necessary actions to effectively mitigate the likely effects

of the identified risks. The extent of risk and uncertainty associated with construction

projects are the important things to consider when it comes to estimating, establishing

pricing policies and contract strategies. In dealing with risks, a systematic process

needs to be followed.

Factors to be considered in managing risks include:

1. The extent of risk; and

2. Uncertainties associated with the cost of projects

The risk involved will form the basis of making pricing policies and contract

strategies.

Risks can also be categorized into two: recognized risks and assumed risks.

155

Page 156: BT 358 ConstructionEstimating and Price Analysis

156

Page 157: BT 358 ConstructionEstimating and Price Analysis

Risks associated with construction

We can identify at least 6 types of risks in construction. These are:

1. Risk associated with Construction

- These include inclement weather, accidents and acts of God

2. Physical Risks

- These include those risks due to surface conditions

3. Performance Risks

- These cover the risks associated with workmanship and materials

4. Legal and Construction Risks

- These are dictated by the form of contract and the legal system of the

nation

5. Economic Risks

- Examples of these include strikes, tax rate changes, inflation

6. Political and Public Risks

- These are the risks that come as a result of political and social pressure e.g. public

disorder, war, labour union related problems, religious or racial factors

Sources of Risk

Some of the common sources of risk in construction are:

1) Technical factors;

2) Environmental factors;

3) Economic factors – inflation;

4) Contractual;

5) Productivity of labour and subcontractors etc; and

6) Establishing accuracy.

Systematic risk management

Systematic risk management involves taking measures to mitigate the impact of

identified risks on a project. This can be achieved through the following stages:

Identification of risk sources;

Assessment of their effects (risk analysis);

Development of management response to risk; and

Providing the residual risk in the project estimate.

157

Page 158: BT 358 ConstructionEstimating and Price Analysis

Fig 6.2 Risk assessment framework

No

No

158

Step 1Know the Contract

Step 2Risk Identifiction

Step 3Impact Assessment

Step 4Risk Assessment

Is Maximum Possible Loss Service?

Yes

Analyze Factors Affecting possible Losses Prepare your Tender

Estimate using the Firm’s Normal mark up percentage

Can some of the Losses be Transferred or Controlled?

Yes Increase your mark up to cover the Losses

Does Risk Pose a Problem?

Eliminate

Source of

Losses

Transfer

Risk to Sub-

contractors

Insurance Set a site

Control

Process In

Motion

Page 159: BT 358 ConstructionEstimating and Price Analysis

159

No Yes TenderDo Not Tender

Page 160: BT 358 ConstructionEstimating and Price Analysis

Table 6.3 Risk assessment worksheet

Risk Assessment Worksheet No:

Project: Date:

Possible RiskTarget

Quality or Amount (A) Expose (S)

Assessment of Impact

Percent of Impact (B)

Prob. Of Risk Occ. (C)

Expect. Value (D) of Risk

Substructure

Superstructure 1.

2.

3.

Other Risk Not Associated with any work Section.1.

2.

3.

4.

HighMediumLow

HighMediumLow

HighMediumLow

High MediumLow

HighMediumLowHighMediumLowHighMediumLowHighMediumLow

Total Expected Value of Risk = GH¢ (A*B*C) = GH¢ (D)

160

Page 161: BT 358 ConstructionEstimating and Price Analysis

In some cases, the extent of risk associated with a project will lead to questions as to whether the estimating process should proceed unto bid submission or not if an appropriate risk management strategy cannot be found. Fig 6.2 and fig 6.3 shows a risk assessment worksheet which can be used to assess the extent of risk and the action required to be undertaken.

Factors to consider in choosing risk transfer policy through contract strategy:Some suggested factors to consider when choosing an appropriate policy for risk

transfer using contract strategies are as follows:

i. Which party can best control events that may lead to the risk occurring;

ii. Which party can best control risk if it occurs;

iii. Whether or not it is preferable for the client to retain an involvement in the control of

risk;

iv. Which party should carry the risk if it cannot be controlled;

v. Premium to be charged for the risk; and

vi. Whether risk if transferred may lead to the possibility of risk of a different nature

being transferred to client control.

Self assessment questions

i. What happens usually within the contractor’s organisation after the final

estimate has been agreed?

ii. Once a winning bid has been selected, what follows?

iii. Explain the term “bidding strategy”

iv. Explain what adjudication is.

v. Explain what considerations are made in arriving at the adjudicated figure

vi. Explain how price fluctuations are catered when preparing an estimate

vii. Give some examples of construction risks

END OF UNIT ASSESSMENT

i. List the various stages which make up the estimating and bidding process.

ii. Explain the terms risks and risk management in relation to construction

projects. Identify the different types of construction risks

iii. Describe how pricing policies can be utilized to offset project risk

iv. Describe the types of price manipulations usually used by contractors

when estimating for projects.

161

Page 162: BT 358 ConstructionEstimating and Price Analysis

References and Bibliography 1. Valence, G de and Huon, N. (1999) Procurement strategies in Best, R. and

Valence, G de (Eds) Building in value: pre-design issues. Arnold Publishers, London.

2. McGeorge, D. and Palmer, A. (1997) Construction Management New Directions, Blackwell Science, Oxford

3. Turner, A. 2nd Edition 1997: Building Procurement, Macmillan Press Ltd., London

4. James Franks 3rd Edition 1998: Building Procurement Systems – A Client Guide, The Chartered Institute of Building, Ascot.

5. The Aqua Group and Bagnall, B. (1999) Tenders and Contracts for Building, Blackwell Publishing, Oxford

6. Chartered Institute of Building 1992: Code of Practice for Project Management for Construction and Development, CIOB, Ascot

7. John F. Woodward 1997: Construction Project Management – Getting it right first time.

8. Harris, F and McCaffer, R. (2001), Modern Construction Management 5TH EDITION Blackwell Publishing, Oxford

9. Hackett M, Robinson I & Statham G, (2007) Aqua Group Guide to Procurement, Tendering and Contract Administration Chapters 3,4,8-15, Blackwell Publishing, Oxford

10. Amoah Mensah, K., (1995), Manual for Estimating, Parcom Ghana Ltd, Kumasi

11. Ashworth, A. & Hogg, K., (2007) Willis Practice and Procedure for the Quantity Surveyor, Blackwell Publishing, Oxford

162