Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
March 8,2018
Baroau of Saffilf flnd EavirsiESdifli Umm\ [BSEE)
R E C E I V E D MAR 13 2018
Office of Field Operations Pipeline Section
U. S. Department of the Interior Bureau of Safety and Environmental Enforcement 1201 Elmwood Park Boulevard New Orleans, Louisiana 70123-2394
Arena Offshore, LP
4200 Research Forest Dr.
Suite 230
The Woodlands, TX 77381
281-681-9501
281-681-9502 Fax
Attention: Phillip Smith Pipeline Section
RE: Supplement and Amendment to Application Dated December 12, 2017 for Modification to Existing Right-of-Way Easement Associated with Abandoned-In-Place 14-Inch Right-of-Way Pipeline (ROW OCS-G 29378/Segment No. 19785) Originating at Plugged End in Eugene Island Block 297 and Terminating at a Plugged End in Ship Shoal Block 28, OCS Federal Waters, Gulf of Mexico, Offshore Louisiana
Ms. Smith:
The following information is provided as further support of the referenced application, and our subsequent telephone discussion and email correspondence:
• Arena's plan to remediate line restriction: The flow test conducted by Arena in 2017 did show a significant pressure drop over the length of the 14" pipeline. This flow test was conducted by pumping through 300' of 2.5" hose on one end connected to a 14" flange that was subsea. The flow was received at the other end through another 250' of 2" hose connected to a 14" flange subsea. When this configuration is modeled in PIPESIM assuming no restriction in the flow line, the results are almost identical to what was recorded on the flow test chart in the field. Our conclusion is that this pressure drop was later erroneously attributed to a restricted/obstructed pipeline using a very rudimentary orifice calculation. This analysis did not take into account the two hoses on either end which caused this significant pressure drop. The chart below clearly shows that the hoses are where the majority of the pressure differential is occurring. In conclusion. Arena does not believe there is a pig stuck in this line or that it is restricted in any way.
U.S. Department of the Interior Bureau of Safety and Environmental Enforcement March 8, 2018 Page 2
• Proposed testing of new line and riser piping to be installed: The piping will be pre-tested onshore for 4 hours at 1500#.
• Assignment of segment number(s) for entire length of existing line pipe: As reflected in the application. Arena is requesting reactivation of a portion of the line pipe and requesting a 5-year inactive status to the remaining portion ofthe existing pipeline for future utility. As we discussed in our earlier conference call, we have since elected to re-route production from our existing Eugene Island Block 341 A Platform which will include installing new departing line pipe to the south end of the existing 14-inch pipeline's capped end in Eugene Island Block 297. We have completed running the Pipeline Pre-Lay Survey and will be submitting a separate application within the next few weeks will provide for a new 14-inch pipeline originating at Eugene Island Block 341 A Platform and terminating at the existing capped end of the 14-inch pipeline (Segment No. 19785) in Eugene Island Block 297. As such, we would like to maintain the existing Segment No. 19785 as one segment number.
Arena has elected to not install the subsea pig launcher; as such we are requesting removal of the Key Plan at Subsea Tie In Drawing No. 0912 included in our original application.
Correction to wall thickness of existing line pipeline: Attached are the amended documents in support of this correction:
Document Name
Drawing or Page
No. Rev. No.
Document Date
New Pipeline Design Data 1-8 1 3//2018
Maximum Spill Volume Calculations (Worst-Case Discharge) 1-2 1 3/6/2018
Pipeline Safety Flow Diagram 4301 2 3/6/2018
Please continue to direct any questions or requests for additional information to Connie Goers at 281.210.3123 or [email protected].
U.S. Department of the Interior Bureau of Safety and Environmental Enforcement March 8, 2018 Page 3
Sincerely,
Arena Offshore, LP By: Arena Offshore GP, LLC its Sole General Partner
Michael E. McCauley Operations General Manager
MEM:CJG Enclosures
^*£TRATEGY
PIPELINE PERMIT & CALCULATIONS - KAQ-1030,14" OIL PIPELINE JUMPER
Client: Arena Offshore, LP
REV DATE ISSUED FOR By Chk'd App'd Client Project: Rosefield Pipeline
0 12/5/17 MOC: SS28A-2017-11-28 MDS CJM CJM VN Job No: 17460
1 3/6/18 MOC:SS28A-2017-11-28 MDS CJM CJM RC By/Date: MDS /11-28-17
Doc No: 17460-PLEN-TP-0003
Spec No: —
Page: 1 of 8
RIGHT-OF-WAY PIPELINE MODIFICATION PERMIT APPLICATION
PROPOSED 14" OIL PIPELINE JUMPER
FROM
ARENA OFFSHORE, LP SHIP SHOAL BLOCK 28, EXISTING FOURTEEN-INCH PIPELINE (SEGMENT NO. 19785)
TO
ARENA OFFSHORE, LP SHIP SHOAL BLOCK 28, PLATFORM "A"
OCS-G 01504
GULF of MEXICO FEDERAL WATERS, OFFSHORE LOUISIANA
Submitted By: ARENA OFFSHORE, LP
MARCH 2018
17460-PLEN-TP-0003, R1 - 14in Oil Pipeline Modification Permit Strategy Engineering and Consulting, LLC.
iTECY PIPELINE PERMIT & CALCULATIONS - KAQ-1030,14" OIL PIPELINE
JUMPER Client:
Arena Offshore. LP
Project:
Rosefield Pipeline
Job No: Rev: Date: Issued For: Spec No: Doc No: Page:
17460 1 3-6 18 MOC SS28A-2017-11-28 — 17460-PLEN-TP-0003 2 of 8
GENERAL INFORMATION
Pipeline Tag No.
Pipeline Name
Pipeline Size
Pipeline Length, ft
Water Depth, ft
KAQ-1030
i r OIL PIPELINE JUMPER
Fourteen-inch
126.00
12
Design Pressure, Psig
Design Temperature, °F
Operating Pressure, Psig
Operating Temperature, °F
1,480
100
400
100
Flowrates:
Gas, mmscfd
Oil/Condensate, bpd
Water, bpd
0
3,200
0
Specific Gravities:
Specific Gravity-Gas
Specific Gravity-OII/Condensate
Specific Gravity-Water
0 65
0 83
1 05
(I) DESCRIPTION OF THE CATHODIC PROTECTION SYSTEM
Pipeline Anodes with the following characteristics will be used for cathodic protection of the pipeline.
Anode Type:
Size:
Weight (net):
Number:
Spacing (Max):
Life Expectancy:
Calculations
Number of Anodes Required (N)
N _ Length of Route (ft)
Anode Spacing (Max)
126 N=
500 N= 1
Anode Intervai (i)
!_ Length of Route (ft)
Number of Anodes
126 1=
1
Tapered, Semi-Cylindrical Aluminum Bracelet, Galvalum
Fourteen-inch
92
1
500
252.2 years
Life Expectancy (L)
£ _ 3 . 8 2 x i a ' x W 0
DxIxR Where:
L = Life of Cathodic Protection System (years)
W° = Weight of unit anodes (Ibs)
D = Outside Diameter of pipe (inches)
i = Interval length of pipe (ft)/total no. of anodes
R = Rate of consumption (lbs/amp«year) - The value
of R for Galvalum ill (aluminum-zinc-indium) as
obtained from Table l.B of NACE Standard
RP0176-83 is 8.4 to 7.4; use 7.9. 1= 127 ft L= 38,200 x 92
14.000 x 127 ft x 7.9
252.2 years LIFE EXPECTANCY
17460-PLEN-TP-0003, Rl - 14in Oil Pipeline Modification Pemit Strategy Engineering and Consulting, LLC,
iTECT PIPELINE PERMIT & CALCULATIONS - KAQ-1030,14" OIL PIPELINE
JUMPER e Client:
Arena Offshore. LP
Project:
Rosefield Pipeline
Job No: Rev: Date:
17460 1 3/6/18
Issued For:
MOC: SS2BA-2017-11-28
Spec No: Doc No:
1746a-PLEN-TP-0003
Page:
3 of 8
(II) DESCRIPTION OF EXTERNAL PIPE COATING SYSTEM
Line Pipe:
Coating Type: Fusion bonded epoxy coating, 14-16 mils thick
Risers:
Above Splash Zone:
Splash Zone:
Below Splash Zone:
Three Coat Offshore Paint System
Neoprene rubber base coating (Splashtron), V4" thick, 20 feet long, vulcanized to pipe
Fusion bonded epoxy coating, 14-16 mils thick
(ill) DESCRIPTION OF INTERNAL PROTECTIVE MEASURES
No internal coating is provided. The analysis of the transported products will be monitored and preventive
measures such as inhibiting will be employed as necessary.
(iv) SPECIFIC GRAVITY OF EMPTY PIPELINE PIPE
Specific gravity of 14.000" x 0.438" wt, empty pipe = 0.93
Weight of Bare Pipe In air (W p )
W p = Volume of steel x Density of steel
12 ft3
1728 in 3 W0
n(Do2-Di2)
n (14.000A2-13.124A2) Wp= x
4 Wp= 63.47 lb/ft3
Weight of Pipe Coating (Wc)
12
1728 x 489.6
Weight of Coated Pipe In air (W)
w= wp + wc
W= 63.47 + 0.00 W= 63.47 lb/ft3
Weight of Displaced Seawater (W.) w s = Volume of sea water x Density of sea water
Ws = n(Dof 12 ft3
_ n((Do+2Tc)2-Do2) W c " x
12 ft3
1728 in J
Wc = •n ((0.00+2(0.00))'12 - O.Oi 12 ft3
1728 in'' x 0.0
_ K (14.000)^2 f r 5 — X
4 W s = 68.42 lb/ft3
1728 in 12
1728
— x Pwalor
X64
W c = 0.00 lb/ft3
Specific Gravity (SG)
S G _ Weight of Pipe in Air
SG=
Weight of Displaced Sea Water
63.47 lb/ft3
68.42 lb/ft3
SG= 0.93
PIPE SPECIFIC GRAVITY
(v) MAXIMUM SOURCE PRESSURE (MSP)
MSP (psig): = < 905
Based on: Input from pipeline pumps on departing platform (EI-2521)
Protection: Pipeline will be protected by PSHL's and PSVs installed on input sources.
17460-PLEN-TP-0003, Rl - 14in Oil Pipeline Modification Permit Strategy Engineering and Consulting, LLC.
PIPELINE PERMIT & CALCULATIONS - KAQ-1030,14" OIL PIPELINE JUMPER
Client:
Arena Offshore, LP
Project:
Rosefield Pipeline
Job No: Rev: Date:
17460 1 3/6/18
Issued For:
MOC:SS28A-2ai7-11-28
Spec No: Doc No:
17460-PLEN-TP-0003
Page:
4 of f
(vi) MAXIMUM ALLOWABLE OPERATING PRESSURE (MAOP) AND CALCULATIONS
Pipeline MAOP:
Limiting Component:
1,000 psig @ 100 0F Existing tie in pipeline (Segment No. 19785) MAOP.
Design Pressure & Component Summary
Components Material or Ratina Nominal Size
Line Pipe API 5L x52 14.000" x 0.438" wt 2,343 psig Line Pipe Bends API 5L x52 14.000" x 0.438" wt 2,155 psig
Riser Pipe API 5L x52 14.000" x 0.438" wt 1,952 psig
Riser Pipe Bends API 5L x52 14.000" x 0.438" wt 1,796 psig
Flanges ANSI 900 14" Nominal 2,220 psig
Existing Line Pipe API 5L x52 14.000" x 0.375" wt 2,006 psig
Subsea Valves ANSI 900 14" Nominal 2,220 psig
Formulas
Internal Design Pressure
From: Title 30 CFR, Chapter II, Subchapter B, Part 250, Subpart J, §250.1002
p _2(S)(t) (FETS) Do
Where: P = Internal design pressure in pounds per square inch (psig).
S = Specified minimum yield strength, in psi, will be stipulated in the specification under which the pipe will be
purchased from the manufacturer. S=35,000 psi for API 5L Gr. B
D = Nominal outside diameter of the pipe in inches,
t = Nominal wall thickness of the pipe in inches.
F = Construction design factor of 0.72 for submerged components and 0.60 for riser pipe.
E = Longitudinal joint factor, 1.00 for API 5L seamless (SMLS) and electric resistance welded (ERW) pipe as
obtained from Table 841.115A of ANSI B31.8.
T = Temperature derating factor, 1.00 for temperatures 250°F or less as obtained from Table 841.116A of ANSI
B31.8.
Pipe Thinning on the Outside Bend Radius of Hot Bends:
From: Intemational Pipe Association's Voluntary Standard for Induction Bending of Pipe (IPA-VIBS-86)
R (D) of Bend=
Dn
Where: R = Center Line Radius of Bend, in inches.
Dn = Nominal pipe Diameter, in inches.
Anticipated wall thinning, in percent, is obtained from Table 1-1 of IPA-VIBS.
17460-PLEN-TP-0003, Rl - 14in Oil Pipeline Modification Pemit Strategy Engineering and Consulting, LLC.
PIPELINE PERMIT & CALCULATIONS - KAQ-1030,14" OIL PIPELINE JUMPER
Client:
Arena Offshore, LP
Project:
Rosefield Pipeline
Job No:
17460
Rev;
1
Date:
3/6/18
Issued For:
MOC:SS28A-2D17-11-2a
Spec No: Doc No:
17460-PLEN-TP-0003
Page:
5 of 8
(vi) MAXIMUM ALLOWABLE OPERATING PRESSURE (MAOP) AND CALCULATIONS - Cont'd
Calculations
Line Pipe internai Design Pressure
Nominal Pipe Size (in): 14
Pipe Outside Diameter (Do) (in) 14
Pipe Schedule Sch. 40
Pipe Inside Diameter (Di) (in) 13.124
Wall Thickness (t) (in) 0.438
Material: API 5L x52
Minimum Yield Strength (S) (psi) 52,000
Construction Type - Line Pipe: A
Construction Factor (F): 0.72
Temperature Selection: 1
Temperature Derating Factor (T): 1.00
Longitudinal Joint Factor (E): 1.00
Line Pipe Bend internai Design Pressure
Nominal Pipe Size (in): 14
Pipe Outside Diameter (Do) (in) 14
Pipe Schedule Sch. 40
Pipe Inside Diameter (Di) (in) 13.124
Wall Thickness (t) (in) 0.438
Material: API 5L x52
Minimum Yield Strength (S) (psi) 52,000
Construction Type - Line Pipe: A
Construction Factor (F): 0.72
Temperature Derating Factor (T): 1.0
Longitudinal Joint Factor (E): 1.0
(D) of Bend (R/D): 5
Wall Thinning (%): 8
P=-
P=-
2(S)(t)(FET)
Do
2(52,000)(0.438)(0.72)(1.00)(1.00)
14.000
P= 2,343 psig
LINE PIPE
W t bendf W. i ) - (thinning % x t^,.,),
W . b , ^ 0.438-(8/100)(0.438)
W t bendf 0 - 4 0 3 i n -
p . 2(S)(t)(FET)
Do
r _ 2(52,000)(0.403)(0.72)(1.00)(1.00)
14.000
P 2,155 psig
LINE PIPE BENDS
Riser Pipe internai Design Pressure
Nominal Pipe Size (in): 14
Pipe Outside Diameter (Do) (in) 14
Pipe Schedule • Sch. 40
Pipe Inside Diameter (Di) (in) 13.124
Wall Thickness (t) (in) 0.438
Material: API 5L x52
Minimum Yield Strength (S) (psi) 52,000
Construction Type - Line Pipe: E
Construction Factor (F): 0.6
Temperature Selection: 1
Temperature Derating Factor (T): 1.00
Longitudinal Joint Factor (E): 1.00
Q There is no Riser
P=- 2(S)(t)(FET)
Do
2(52,000)(0.438)(0.60)(1.00)(1.00)
14.000
P= 1,952 psig
RISER PIPE
17460-PLEN-TP-0003, Rl - 14in Oil Pipeline Modification Permit Strategy Engineering and Consulting, LLC.
P I P E L I N E P E R M I T & C A L C U L A T I O N S - KAQ-1030 ,14" O IL P I P E L I N E
J U M P E R
Client:
Arena Offshore, LP
Project:
Rosefield Pipeline
Job No: Rev: Date:
17460 1 3/6/18
Issued For:
MOC: SS28A-2017-11-28
Spec No: Doc No:
17460-PLEN-TP-00a3
Page:
6 of (
(vi) MAXIMUM ALLOWABLE OPERATING PRESSURE (MAOP) AND CALCULATIONS - Cont'd
Riser Pipe Bend Internal Design Pressure
Nominal Pipe Size (in):
Pipe Outside Diameter (Do) (in)
Pipe Schedule
Pipe Inside Diameter (Di) (in)
Wall Thickness (t) (in)
Material:
Minimum Yield Strength (S) (psi)
Construction Type - Line Pipe:
Construction Factor (F):
Temperature Derating Factor (T):
Longitudinal Joint Factor (E):
(D) of Bend (R/D):
Wall Thinning (%):
Exist ing Line Pipe
Nominal Pipe Size (in):
Pipe Outside Diameter (Do) (in)
Pipe Schedule
Pipe Inside Diameter (Di) (in)
Wall Thickness (t) (in)
Material:
Minimum Yield Strength (S) (psi)
Construction Type - Line Pipe;
Construction Factor (F):
Temperature Selection:
Temperature Derating Factor (T):
Longitudinal Joint Factor (E):
Flanges
ANSI Class
From: ANSI B16.5, Table 2
Temperature =
Flange Sizes
Flange Sizes, Additional
Subsea Valves
ANSI Class
From: API 6D, Table 2.1
Valve Size
14
14
Sch. 40
13.124
0.438
API 5L x52
52,000
E
0 60
1.00
1.00
5
s
W t bend)- in i t ia l ] " ( t h i n n i n g % X t^mtia,,,
W . bendf 0.438-(8/100)(0.438)
W t bendf 0.403 in.
2(S)(t)(FET)
Do
2(52,000K0.403)(0.60)(1 .OOKI .00)
14.000
1,796 psig
RISER PIPE BENDS
• Tliere is no Subsea Assembly
14
14
Sch. 30
13,250
0.375
API 5L x52
52.000
A
0.72
1
1.00
1.00
ANSI 900
-2010 1 0 0 ^
14
ANSI 900
P=-
P=-
2(S)(t)(FET)
Do
2(52,000)(0.375H0.72)(1 00)(1 00)
14.000
P= 2,006 psig
EXISTING LINE PIPE
2,220 psig
FLANGES
2,220 psig
SUBSEA VALVES
1' ;
17460-PLEN-TP-0003, R l - 14in Oil Pipeline Modification Permit Strategy Engineering and Consulting, LLC.
PIPELINE PERMIT & CALCULATIONS - KAQ-1030,14" OIL PIPELINE JUMPER 0
Client:
Arena Offshore, LP
Project:
Rosefield Pipeline
J o b No:
17460
Rev:
1
Date:
3/6/18
Issued For:
MOC:SS28A-2017-11-28
Spec No: Doc No:
17460-PLEN-TP-0003
Page:
7 of 8
(vii) HYDROSTATIC TEST PRESSURE (HTP), TEST MEDIUM, AND PERIOD OF TIME
Hydrostatic test pressure for the pipeline: 1,250 psig
Test Medium:
Test Period:
Calculation
Sea Water
8 Hours
Minimum Hydrostatic Test Pressure (HTP) for the pipeline:
HTP= 1.25 x MAOP
HTP= 1.25x1,000 psig HTP= 1,250 psig
HYDRO TEST PRESSURE
Stress at Hydrotest Pressure
Where:
Limiting pipeline SMYS Component:
SMYS of Limiting Component:
Outside Diameter (Do):
Wall Thickness (t):
Riser Pipe Bends 52,000
14
0.403
S= (HTP)(Do)E
S=-
2(t) 1,250(14.000)(1.00) S= 21,712 psi
2(0.403)
Stress Ratio (SR)
f.R_ Stress at Hydrotest Pressure
SMYS Limit
SR=-21,712
52,000
SR= 42%
Conclusion
The hydrotest will be performed at a pressure that is 42% of the SMYS of the pipeline (based on the wail thickness of the 14.000-inch Riser Pipe Bends).
(viii) MAOP OF TIE-IN PIPING
The MAOP ofthe 14" Oil Pipeline (Segment No. 19785) is 1,000 PSIG.
(Ix) PROPOSED DATE FOR COMMENCING INSTALLATION AND ESTIMATED TIME FOR CONSTRUCTION
Commence Construction Date: May 2018
Estimated Construction Time: 12 days
17460-PLEN-TP-0003, Rl - 14in Oil Pipeline Modification Pemit Strategy Engineering and Consulting, LLC.
0*7 PIPELINE PERMIT & CALCULATIONS - KAQ-1030,14" OIL PIPELINE JUMPER
Client:
Arena Offshore, LP
Project:
Rosefield Pipeline
Job No: Rev: Date:
17460 1 3/6/18
Issued For:
MOC: SS28A-2017-11-28
Spec No: Doc No:
1746D-PLEN-TP-00a3
Page:
8 of 8
(x) TYPE OF PROTECTION TO THE AFFORDED CROSSING PIPELINES, SUBSEA VALVES, TAPS AND MANIFOLD ASSEMBLIES
Pipeline Burial
The proposed pipeline will be buried to a minimum depth of three feet below natural bottom.
Pipeline Crossings
The proposed pipeline does not cross any existing pipelines.
Subsea Valves, Taps, and Manifold Assemblies
The proposed subsea components (valves, taps or assemblies) will be covered to a minimum of three feet using sand bags.
Riser Protection
A riser guard will be installed on the platform to protect the proposed pipeline.
(xi) ADDITIONAL DESIGN PRECAUTIONS
Additional design precautions will not be required to enable the pipeline to withstand the effects of water currents, storm or ice scouring, soft bottoms, mudslides, earthquakes, perfafrost or other environmental factors.
17460-PLEN-TP-0003, R1 - 14in Oii Pipeline Modification Permit Strategy Engineering and Consulting, LLC.
MAXIMUM SPILL VOLUME CALCULATIONS - KAQ-1030,14" OIL PIPELINE JUMPER
Client: Arena Offshore, LP
REV DATE ISSUED FOR By Chk'd App'd Client Project: Rosefield Pipeline
0 12/6/17 MOC: SS28A-2017-11-28 MDS CJM CJM VN Job No: 17460
1 3/6/18 MOC: SS28A-2017-11-28 MDS CJM CJM RC By/Date: MDS/11-28-17
Doc No: 17460-PLEN-TC-0004
Spec No: —
Page: 1 of 2
GENERAL INFORMATION & CALCULATIONS
The following calculation applies to the total length of the proposed pipeline 14" OIL PIPELINE
(This length includes 14-inch P/L Seg. No. 19785 being placed back into service and proposed 14-inch Jumper to SS-28A) Given
= 0 mmscfd
3200 bpd
0
14. in
0.375 in (304,283 ft of 0.375" wall, 126 ft of 0.438" wall)
13.25 in
304,409 ft (304,283 ft of 0.5" wall, 126 ft of 0.438" wall)
100 ft
400 psig
Gas Flowrate
Oil Flowrate
Gas to Oil Ratio
Pipeline Outside Diameter
Pipeline Wall Thickness
Pipeline Inside Diameter
Pipeline Length
Average Water Depth
Pipeline Operating Pressure
Assumptions
Pipeline Leak Detection Time
Shutdown Response Time
15.00 minutes
0.75 minutes
Find
Worst-Case Spill Volume
Calculations
Use the MMS Pipeline Oil Spill Volume Estimator, OCS Study MMS 2002-033, Sections 1.3.1 through 1.3.5.
Volume of OII Released Prior to Pipeline Shut-In (Vp,)
v = - 2 i i P S 1440
Where:
Q= Pipeline flowrate, bpd
t= Time before shut-in, min
v _ (3,200 x (15.00+ 0.75))
1440 35.00 barrels
Pipeline Volume (Vplp,)
V = r Pipe
'inr . 2 4 , n
Where:
ID= Intemal diameter of pipe, in Lp= Length of Pipeline, ft
Vpipe= 13.250/24)A2 x 304,409 x TI V n l „ = 291602.61 ft3
17460-PLEN-TP-0003, Rl - 14in Oil Pipeline Modification Permit Strategy Engineering and Consulting, LLC.
0,* TECY PIPELINE PERMIT & CALCULATIONS - KAQ-1030,14" OIL PIPELINE
JUMPER
Client:
Arena Offshore. LP
Project:
Rosefield Pipeline
Job No: Rev: Date:
17460 1 3/6/1B
Issued For:
MOC: SS28A-2017-11-28
Spec No: Doc No:
17460-PLEN-TP-0003
Page:
2 of 2
Release Volume Factors based on Relative Pressure Ratio (Pmi)
P „ . „
rel amb
Where:
Ppipe= Pipeline pressure, psi
Pamb= Pressure at water depth, psi
= 0.446533 x water depth
= 44.65 psi
400 P,si=
44.65 P,B,= 8.96
Use Pr8i and Table 1.3 in the MMS Pipeline Oil Spill Estimator to Find:
f r e l= 0.55
Gm a x= 505
Use Table 1.4 in the MMS Pipeline Oil Spill Estimator to Find:
GOR= 0 f g o r= 0.26 GOR<Gmax
Volume Released ( V n l )
Vr0|= 0.1781 x Vpipe x frel x fgor + Vps
V r o l= 0.1781 x 291,602.61 x 0.55 x 0.26 + 35.00
7461.62 barrels
17460-PLEN-TP-0003, R1 - 14in Oil Pipeline Modification Permit Strategy Engineering and Consulting, LLC.
KAQ-IQ3Q OL PIPELINE
9 ! t . I*" OO
id top iooo pac
ZZZ-9060 PIG RCTVER
3ZE 20 _ i i r
EVERYTHING ON THIS DRAWING IS EXISTING
CLOUDED ITEMS REPRESENT PROPOSED MODIFICATIONS
\ * ' ANS 900
or wm 2 TAP
WT TAP-v MS 900 \
1000 PSC PCH HTOROItST
- E N O or UNE IH
gHERAL NOTTS:
1 THE DESKH CHARACTCRISTKS OF THE PROPOSED RPEUNE EQUALS OR EXCEEDS THE REOU1REUENTS OF DOI TITLE 30 CFR. PART 250 SUBPART J.
2 SEE SECIWN M OF THE RICH I Of WAT PIPEUNE APPUCATION FOfl SPEOFIC DCSKW CHARACTERISTICS OF THE PROPOSED PIPEUNE 1 H 00" PIPEUNE WLL TRANSPORT OL
4 PLATFORU PRESSURE PILOT SENSORS WLL BE SET AS FOLLOWS HI SENSOR. I5» OVER NORMAL OPERATWC PRESSURE RAHCE, NOT TO EXCEED IHE MAOP OF THE SEGMENT THEY ARE PROTECTING
LO SENSOR- 151 UNDER NORMAL OPERATING PRESSURE RAHCE
S. mFQSED UHE PPE. PBOPQgD UNC PUT 5fl flEHOS. fflPfQgD ffigR fVE, PROPQgD BSB 50 Km. 0.0. - l^ f iO'N
KGCHTStHJlLfl/FT API 5L X 5 r - ^ TTPE • SMLS DESGN - 3574 PSK
O.D WT
5) Lfl/FT HDCHT -API SL X TYPE - SMLS OESCN - 2460 PSC
O.D. KT BOOIT •hG^STLD/TT
API SL xsr^ TTPE - SMLS DESW - 2229 PSC
O.D W.T WDGHT Si 63 3)LB/FT API 5L X 5 r - ^ FIPE - SMLS OESim - 2050 PSC
PROPQSffi Fimcs aASS - ANS 900 SZE - 14" SPEC - BG 5 DESGN - 2220 PSG
Ewsmc M' UHC PPE
EXISTING P A SEGMENT PROPOSED 14' 00. PIPEUNE NO 19785 0 SS-2Bj_I0 SS-JflA PLATFORM
APPROX, 126 FT TO 14' SSD « SS-28
WVEUNE SEGMENT NO 19785
EMSPHC M' HTTIWCS a * s s - ANS 900 SZE - H ' SPEC - BG 5 DESGN - 2220 PSIC
I HYDROTESTED EXISTINC 14' P/L SECEMENT NO 1 9 7 t o \ TO 1300 PSG FOR 8 HRS.
PffCLtNE SFOtfWT HO I97H5 PROPOSED MDPFICATIQH I REUSE MAOP PER HYDROTEST TO IOOO PSC. 3 INSTALL PROPOSED 14* 00. PIPELINE JUMPER
FROM PIPEUNE SEGMENT 19785 W 55-28 TO SS-38A.
6 14 00' PIPEUNE MAOP IS IOOO PSC
7 COOES ft SPEPTlCAnONf 60 AHS SI6 5 30 CFR 350 AHS 831 3
VALVES FITTlNCS PIPELINE PLATFORM PWNG
I PROPOSED 8' PA FROM El-2531 CCWRCD UNDER SEPARATE PERMIT APPUCATION
•1 RtMSCD I* MCH m*LL THOOCSI, UOC SS3BA-MI7-11 -W MB CM UflM/lM NC 1 (ssuco ran PCTWI. UOC S S I B A - M I T - M - J B •.m 11/M/17 ^ m
a BSUCD Ttm POtUfl. UOC SS31*-«II7-t1-7B im Mt
oesavpnoN amcss DATt 2 T DATt
0** DSAWINC ISSUE ARENA
O F F S H O R E , L P
worosai H- OIL PA Mmn mai scomr m mn PIPELINE SAFETY a o w DUCRAU
4 INCH OIL PIPELINE JUMPER