Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

Embed Size (px)

Citation preview

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    1/125

    BSC6900 UMTS

    V900R017C10

    Commissioning Guide

    Issue 01

    Date 2015-03-25

    HUAWEI TECHNOLOGIES CO., LTD.

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    2/125

     

    Copyright © Huawei Technologies Co., Ltd. 2015. All rights reserved.

    No part of this document may be reproduced or transmitted in any form or by any means without prior written

    consent of Huawei Technologies Co., Ltd.

     

    Trademarks and Permissions

     and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.

     All other trademarks and trade names mentioned in this document are the property of their respective holders.

     

    Notice

    The purchased products, services and features are stipulated by the contract made between Huawei and the

    customer. All or part of the products, services and features described in this document may not be within the

    purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,

    and recommendations in this document are provided "AS IS" without warranties, guarantees or representations

    of any kind, either express or implied.

    The information in this document is subject to change without notice. Every effort has been made in the

    preparation of this document to ensure accuracy of the contents, but all statements, information, and

    recommendations in this document do not constitute a warranty of any kind, express or implied.

     

    Huawei Technologies Co., Ltd.

     Address: Huawei Industrial Base

    Bantian, Longgang

    Shenzhen 518129

    People's Republic of China

    Website: http://www.huawei.com

    Email: [email protected]

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    i

    http://www.huawei.com/

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    3/125

    About This Document

    Overview

    BSC6900 commissioning is performed after hardware is installed and before services are

     provided. It aims to ensure that the BSC6900 can work properly by performing verification tasks

    related to equipment, board software and data file loading, interfaces, and services.

    Product Versions

    The following table lists the product version and solution version related to this document.

    Product Name Product Version Solution Version

    BSC6900 V900R017C10 RAN17.1

     

    Intended Audience

    This document is intended for:

    l Field engineers

    Organization

    1 Change History

    This section provides information about the changes in different document versions. There are

    two types of changes, including function changes and editorial changes. Function changes refer 

    to changes in functions of a specific product version. Editorial changes refer to changes in

    wording or addition of information that was not described in the earlier version.

    2 Commissioning Prerequisites

    Before BSC6900 commissioning, the status of the equipment and the network to be

    commissioned must meet the conditions required. The software installation packages, licenses,

    and MML scripts required for commissioning must be ready.

    3 Commissioning Process

    BSC6900 UMTS

    Commissioning Guide About This Document

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    ii

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    4/125

    The BSC6900 commissioning can be performed remotely, locally, or remotely with local

    assistance.

    4 Checking Operating Status of Hardware

    Before commissioning the equipment, ensure that the BSC6900 cabinet is powered on and isoperating properly.

    5 Commissioning the OMU

    Before using the OMU for the first time, commission the OMU onsite to check the installation

    of product software and the version of the product software, and configure the IP address, mask,

    and computer  name to ensure the normal communication between the BSC6900 and the LMT

    or U2000.

    6 Logging In to the BSC6900 Using the LMT

    This chapter describes how to log in to the BSC6900 using the LMT and how to establish

    communication between the LMT and BSC6900 to ensure successful BSC6900 commissioningusing the LMT.

    7 Updating the OMU Database

    This chapter describes how to update configuration data in the OMU database by running MML

    scripts.

    8 Activating and Verifying the License

    This section describes how to activate the license and verify the license configuration

    information to enable service commissioning.

    9 Loading BSC6900 Board Software and Data Files

    This chapter describes how to load the BSC6900 board software and data files.

    10 Connecting to the U2000

    This section describes how to connect the BSC6900 to the U2000 for centralized management.

    11 Connecting to Operator's PKI System

    This section describes how to connect the BSC6900 to operator's CA server so that the

    BSC6900 can automatically manage its own digital certificates.

    12 Setting the Connection Mode Between the U2000 and BSC6900 to SSL

    The connection mode between the U2000 and BSC6900 must be set to Secure Socket Layer 

    (SSL) on the U2000 to ensure operation and maintenance (O&M) safety.

    13 Verifying Interfaces

    This section describes how to verify interfaces on the BSC6900 side using the LMT or U2000.

    Select a verification method based on the onsite situation.

    14 Handling the Alarms Generated During the Commissioning

    This section describes how to handle the alarms generated during the commissioning to prevent

    the alarms from affecting service verifications.

    15 Verifying UMTS Services

    BSC6900 UMTS

    Commissioning Guide About This Document

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    iii

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    5/125

    This section describes how to verify that the basic UMTS services and the feature services are

    normal. The basic UMTS services are speech services and data services. Feature services include

    inter-RAT handovers, HSDPA, HSUPA, 64QAM, MIMO, CBS, and DC-HSDPA.

    16 Verifying Network Reliability

    The network reliability can be verified by checking generated alarms and making dialing tests

    after a switchover between the active/standby boards.

    17 Troubleshooting

    This chapter describes how to troubleshoot common problems during the commissioning.

    18 Appendix

    This chapter provides communication ports on and the commissioning checklist of the

    BSC6900.

    Conventions

    Symbol Conventions

    The symbols that may be found in this document are defined as follows.

    Symbol Description

    Indicates an imminently hazardous situation which, if not

    avoided, will result in death or serious injury.

    Indicates a potentially hazardous situation which, if not

    avoided, could result in death or serious injury.

    Indicates a potentially hazardous situation which, if not

    avoided, may result in minor or moderate injury.

    Indicates a potentially hazardous situation which, if not

    avoided, could result in equipment damage, data loss,

     performance deterioration, or unanticipated results.

     NOTICE is used to address practices not related to personal

    injury.

    Calls attention to important information, best practices and

    tips.

     NOTE is used to address information not related to personal

    injury, equipment damage, and environment deterioration.

     

    General Conventions

    The general conventions that may be found in this document are defined as follows.

    BSC6900 UMTS

    Commissioning Guide About This Document

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    iv

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    6/125

    Convention Description

    Times New Roman Normal paragraphs are in Times New Roman.

    Boldface  Names of files, directories, folders, and users are in

    boldface. For example, log in as user root.

     Italic Book titles are in italics.

    Courier New Examples of information displayed on the screen are in

    Courier New.

     

    Command Conventions

    The command conventions that may be found in this document are defined as follows.

    Convention Description

    Boldface The keywords of a command line are in boldface.

     Italic Command arguments are in italics.

    [ ] Items (keywords or arguments) in brackets [ ] are optional.

    { x | y | ... } Optional items are grouped in braces and separated by

    vertical bars. One item is selected.

    [ x | y | ... ] Optional items are grouped in brackets and separated by

    vertical bars. One item is selected or no item is selected.

    { x | y | ... }* Optional items are grouped in braces and separated by

    vertical bars. A minimum of one item or a maximum of all

    items can be selected.

    [ x | y | ... ]* Optional items are grouped in brackets and separated by

    vertical bars. Several items or no item can be selected.

     

    GUI Conventions

    The GUI conventions that may be found in this document are defined as follows.

    Convention Description

    Boldface Buttons, menus, parameters, tabs, window, and dialog titles

    are in boldface. For example, click OK .

    > Multi-level menus are in boldface and separated by the ">"

    signs. For example, choose File > Create > Folder.

     

    Keyboard Operations

    BSC6900 UMTS

    Commissioning Guide About This Document

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    v

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    7/125

    The keyboard operations that may be found in this document are defined as follows.

    Format Description

    Key Press the key. For example, press Enter and press Tab.

    Key 1+Key 2 Press the keys concurrently. For example, pressing Ctrl+Alt

    +A means the three keys should be pressed concurrently.

    Key 1, Key 2 Press the keys in turn. For example, pressing Alt, A means

    the two keys should be pressed in turn.

     

    Mouse Operations

    The mouse operations that may be found in this document are defined as follows.

    Action Description

    Click Select and release the primary mouse button without moving

    the pointer.

    Double-click Press the primary mouse button twice continuously and

    quickly without moving the pointer.

    Drag Press and hold the primary mouse button and move the

     pointer to a certain position.

    BSC6900 UMTS

    Commissioning Guide About This Document

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    vi

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    8/125

    Contents

    About This Document.....................................................................................................................ii

    1 Change History..............................................................................................................................1

    2 Commissioning Prerequisites.....................................................................................................2

    3 Commissioning Process...............................................................................................................5

    4 Checking Operating Status of Hardware..................................................................................7

    5 Commissioning the OMU............................................................................................................9

    5.1 Commissioning an OMU Locally.................................................................................................................................10

    5.2 Commissioning the OMU Using a USB Flash Drive...................................................................................................16

    6 Logging In to the BSC6900 Using the LMT............................................................................27

    7 Updating the OMU Database....................................................................................................29

    8 Activating and Verifying the License......................................................................................34

    9 Loading BSC6900 Board Software and Data Files................................................................36

    9.1 Generating Data Files for the Loading.........................................................................................................................37

    9.2 Setting the Board Loading Mode..................................................................................................................................37

    9.3 Resetting BSC6900 Boards..........................................................................................................................................37

    9.4 Checking the Consistency of the Data and the Version...............................................................................................38

    10 Connecting to the U2000...........................................................................................................40

    11 Connecting to Operator's PKI System...................................................................................4312 Setting the Connection Mode Between the U2000 and BSC6900 to SSL........................46

    13 Verifying Interfaces..................................................................................................................48

    13.1 Verifying Interfaces on the U2000.............................................................................................................................49

    13.1.1 Setting the NE Engineering Mode to TESTING.....................................................................................................49

    13.1.2 Verifying Interfaces Automatically.........................................................................................................................50

    13.1.3 Setting the NE Engineering Mode to NORMAL...................................................................................................52

    13.2 Verifying Interfaces on the LMT................................................................................................................................53

    13.2.1 Verifying Fiber Optic Cable Connections...............................................................................................................54

    13.2.2 Verifying Internal Interfaces....................................................................................................................................55

    BSC6900 UMTS

    Commissioning Guide Contents

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    vii

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    9/125

    13.2.3 Verifying the Iub Interface......................................................................................................................................56

    13.2.4 Verifying the Iu-CS Interface..................................................................................................................................59

    13.2.5 Verifying the Iu-PS Interface..................................................................................................................................63

    13.2.6 Verifying the Iur Interface.......................................................................................................................................67

    13.2.7 Verifying the Iu-BC Interface..................................................................................................................................70

    13.2.8 Verifying the Iur-g Interface....................................................................................................................................71

    13.2.9 Verifying the Iur-p Interface....................................................................................................................................72

    13.2.10 Verifying the Sr Interface......................................................................................................................................73

    14 Handling the Alarms Generated During the Commissioning.........................................75

    15 Verifying UMTS Services........................................................................................................76

    16 Verifying Network Reliability................................................................................................80

    17 Troubleshooting........................................................................................................................8217.1 Checking Transmission Links....................................................................................................................................84

    17.2 Performing a VCL Continuity Check.........................................................................................................................87

    17.3 Verifying the PVC Delay Detection Function............................................................................................................89

    17.4 Unavailable E1/T1 Port..............................................................................................................................................91

    17.5 Unavailable FE/GE Port.............................................................................................................................................92

    17.6 Cell Setup Failure.......................................................................................................................................................92

    17.7 Signaling Link Failure on the Iub Interface................................................................................................................98

    17.8 AAL2/IP Connection Setup Failure.........................................................................................................................103

    17.9 Data Loading Failures on the Board.........................................................................................................................107

    17.10 Performing a Loopback Test on the Local E1/T1 Port...........................................................................................109

    17.11 Performing a Loopback Test on an Optical Port....................................................................................................111

    17.12 Checking the QCIs of the IP Transmission Link....................................................................................................113

    18 Appendix...................................................................................................................................115

    18.1 Communication Ports on the BSC6900....................................................................................................................116

    18.2 BSC6900 Commissioning Checklist........................................................................................................................116

    BSC6900 UMTS

    Commissioning Guide Contents

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    viii

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    10/125

    1 Change HistoryThis section provides information about the changes in different document versions. There are

    two types of changes, including function changes and editorial changes. Function changes refer 

    to changes in functions of a specific product version. Editorial changes refer to changes in

    wording or addition of information that was not described in the earlier version.

    01 (2015-03-25)

    This issue does not include any changes.

    Draft A (2015-01-15)

    This is the Draft A release of the V900R017C10.

    Compared with issue 01 (2014-04-29) of V900R016C00, this issue includes the following

    changes.

    Change Type Change Description

    Function change Added None.

    Modified Modified the description of 13.2.3 Verifying the Iub

    Interface and 17.7 Signaling Link Failure on the Iub

    Interface as a result of the added Self-planning feature.

    Deleted None.

    Editorial change None.

    BSC6900 UMTS

    Commissioning Guide 1 Change History

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    1

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    11/125

    2 Commissioning PrerequisitesBefore BSC6900 commissioning, the status of the equipment and the network to be

    commissioned must meet the conditions required. The software installation packages, licenses,

    and MML scripts required for commissioning must be ready.

    Requirements for Equipment Status

    Before commissioning, ensure that the equipment meets the conditions listed in Table 2-1.

    Table 2-1 Requirements for equipment status before commissioning

    Item Requirement

    BSC6900 hardware The hardware is installed and has passed the hardware

    installation check and power-on check.

    OMU The OMU is configured before delivery. For details, see

    Checklist for the OMU Software Factory Settings in BSC6900

    UMTS OMU Administration Guide.

    LMT PC The LMT PC meets the configuration requirements. For details,

    see Configuration Requirements of the LMT PC in BSC6900

    UMTS LMT User Guide.

     

    Requirements for the Network

    To ensure the smooth commissioning of the Iub, Iu, Iur, Iur-g, Iur-p, and Iu-BC interfaces, the

    network to be commissioned must meet the following requirements:

    l At least one NodeB is connected to the BSC6900. The NodeB must have passed

    commissioning and can provide basic functions.

    l At least one set of CN equipment is connected to the BSC6900. The CN equipment must

    have passed commissioning and can provide basic functions.

    l Other network equipment that is connected to the network equipment to be commissioned,

    if any, must have passed commissioning and can provide basic functions. If an RNC, BSC,

    BSC6900 UMTS

    Commissioning Guide 2 Commissioning Prerequisites

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    2

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    12/125

    or call broadcast center (CBC) is connected to the BSC6900, the RNC, BSC, or CBC must

    have passed commissioning and can provide basic functions.

    l Three single-mode UEs and one dual-mode UE are ready for test and are registered with

    the home location register (HLR).

    Figure 2-1 shows a typical network to be commissioned.

    Figure 2-1 Typical network to be commissioned

     

    Requirements for Software and Data Files

    l Software installation package

    The installation package that is compatible with the version used in the local office must

     be ready before commissioning.

    l License

    The license that is applicable to configurations used in the local office is obtained from the

    Huawei technical support engineers.

    l MML script file

    The initial configuration is complete before commissioning according to BSC6900

    UMTS Initial Configuration Guide to obtain the MML script file. In addition, the

    correctness of the data configuration is checked and ensured based on the MML script

    examples and the onsite negotiated data defined in BSC6900 UMTS Initial Configuration

    Guide.

    BSC6900 UMTS

    Commissioning Guide 2 Commissioning Prerequisites

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    3

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    13/125

    NOTE

    If the CME method is used to configure the data, the MML script file is not necessary.

    BSC6900 UMTS

    Commissioning Guide 2 Commissioning Prerequisites

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    4

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    14/125

    3 Commissioning ProcessThe BSC6900 commissioning can be performed remotely, locally, or remotely with local

    assistance.

    l Local commissioning is performed by a field engineer (engineer responsible for onsite

    commissioning in the BSC6900 equipment room) who connects a PC to the BSC6900 and

     performs the commissioning on the LMT.

    l Remote commissioning is remotely performed by an engineer (technical engineer 

    responsible for the BSC6900) and multiple BSC6900s can be commissioned

    simultaneously in the central equipment room.

    l Remote commissioning with local assistance is performed remotely by an engineer with

    the assistance of a field engineer.

    Figure 3-1 shows the commissioning process if all commissioning prerequisites are met.

    BSC6900 UMTS

    Commissioning Guide 3 Commissioning Process

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    5

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    15/125

    Figure 3-1 Commissioning flowchart

    BSC6900 UMTS

    Commissioning Guide 3 Commissioning Process

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    6

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    16/125

    4 Checking Operating Status of HardwareBefore commissioning the equipment, ensure that the BSC6900 cabinet is powered on and is

    operating properly.

    Prerequisites

    The BSC6900 cabinet has passed the power-on check.

    Procedure

    Step 1 Check whether the cabinet is powered on.

    If... Then...

    The cabinet is not powered on Go to Step 2.

    The cabinet is powered on Go to Step 4.

    Step 2 Turn on the power switches that control cabinet power supply on the power distribution frame(PDF).

    Step 3 Turn on the power switches on the power distribution box after the RUN indicator on the front panel of the power distribution box blinks 0.25s on and 0.25s off.

    If... Then...

    The cabinet is an MPR Set the corresponding power switches on the power distribution

     box to ON.

    If the cabinet is an EPR/

    TCR 

    Set the power switches that correspond to the subracks

    configured in the same cabinet to ON.

     

    Step 4 Check the power supply to the cabinet components, as listed in Table 4-1. Ensure that thehardware operates properly.

    BSC6900 UMTS

    Commissioning Guide 4 Checking Operating Status of Hardware

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    7

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    17/125

    Table 4-1 Checklist of the power supply to the cabinet components

    Component Normal Power Supply Status

    Board The RUN indicator on the board panel is

    neither steady on nor steady off.

    Fan box The RUN indicator on the fan box panel

     blinks 1s on and 1s off in green after the

    subrack or independent fan subrack is

     powered on.

    Power distribution monitor board The RUN indicator on the board panel blinks

    1s on and 1s off in green. The ALM indicator 

    is steady off.

     

    NOTE

    If a power failure occurs, resolve the problem following the operations provided in step 5 in section Powering

    On the Cabinet in BSC6900 UMTS Site Maintenance Guide.

    ----End

    BSC6900 UMTS

    Commissioning Guide 4 Checking Operating Status of Hardware

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    8

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    18/125

    5 Commissioning the OMUAbout This Chapter

    Before using the OMU for the first time, commission the OMU onsite to check the installation

    of product software and the version of the product software, and configure the IP address, mask,

    and computer  name to ensure the normal communication between the BSC6900 and the LMT

    or U2000.

    Context

    The OMU can be commissioned locally or by using a USB flash drive. In new network 

    deployment, the OMU board has been preinstalled with the operating system and applications before delivery. Therefore, it is recommended that the OMU board be commissioned locally.

    NOTE

    For the definitions of "fixed external IP address", "virtual external IP address", "fixed internal IP address",

    "virtual internal IP address", "IP address of the backup channel between the active and standby OMU boards",

    and "commissioning IP address", refer to OMU IP Address Plan of "Working Principles" in  BSC6900 OMU 

     Administration Guide.

    5.1 Commissioning an OMU Locally

    This section describes how to commission an OMU locally. The commissioning is performed

     by a field engineer by connecting a PC to the OMU over a commissioning Ethernet port. If the

    BSC6900 has been configured with active and standby OMUs, commission both the active OMU

    and the standby OMU.

    5.2 Commissioning the OMU Using a USB Flash Drive

    This section describes how to commission an OMU using a USB flash drive. You can locally

    insert the prepared USB flash drive to the OMU and then perform OMU commissioning with

    cooperation of a remote engineer.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    9

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    19/125

    5.1 Commissioning an OMU Locally

    This section describes how to commission an OMU locally. The commissioning is performed

     by a field engineer by connecting a PC to the OMU over a commissioning Ethernet port. If the

    BSC6900 has been configured with active and standby OMUs, commission both the active OMU

    and the standby OMU.

    Prerequisites

    l The OMU is connected to a local PC using a commissioning Ethernet port.

    l The version installation package or patch installation package that you have obtained is the

    same as the customer version.

    l You have obtained the psftp software and the PuTTY software. For details, see Obtaining

    and Using the psftp Software and Obtaining and Using the PuTTY Software.

    Context

    l If the product software has been installed before delivery, the active workspace of the OMU

    is version_a.

    l If the product software is not installed before delivery, plan items in Information Records

    of OMU Software Installation before installing the product software.

    l For details about the OMU software factory settings, see Checklist for the OMU Software

    Factory Settings.

    l For details about how to commission the OMU locally, see Figure 5-1.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    10

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    20/125

    Figure 5-1 Flowchart for commissioning the OMU locally

     

    Procedure

    Step 1 Connect a PC to the OMU board.

    1. Connect the PC to the ETH2 commissioning port on the OMU board using a network cable.

    2. Set the IP addresses of the PC and ETH2 port so that they are in the same network segment.

    The initial IP address of the ETH2 port is 192.168.6.50 or 192.168.6.60, and the subnet

    mask is 255.255.255.0. The initial IP address of the ETH2 port is the commissioning IP

    address. For details about the commissioning IP address, see OMU IP Address Plan.

    Step 2 Set the link mode of the external OMU Ethernet adapters.

    1. Log in to the OMU by referring to the procedures described in Logging In to the OMU.

    2. Check whether the link mode of the external OMU Ethernet adapters is consistent with that

    of LAN switches.

    For details about how to query the link mode of the external OMU Ethernet adapters, see

    Querying the Link Mode of the External OMU Network Adapters.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    11

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    21/125

    If... Then...

    The link mode of the external OMU

    Ethernet adapters is consistent with that of 

    LAN switches

    Go to Step 3.

    The link mode of the external OMU

    Ethernet adapters is inconsistent with that

    of LAN switches

    Set the link mode of the external OMU

    network adapters to be consistent with that

    of LAN switch by referring to operations

    in Procedure of Setting the Link Mode for 

    External OMU Ethernet Adapters.

     

    Step 3 Install the product software.

    1. Enter /etc/rc.d/omud status to check the running status of the OMU process.

    If... Then...

    running is displayed 1. Enter /etc/rc.d/omud stop to stop the

    omud process.

    2. Go to Step 3.2.

    unused is displayed Go to Step 3.2.

    No such file or directory is displayed 1. Install the product software to the active

    workspace by referring to operations in

    Procedure of Installing the Product

    Software in the Active Workspace.

    2. Go to Step 7, Step 8 and Step 9.

     

    2. Enter cd /mbsc/upgrade to go to the OMU installation directory, and then enter ls to query

    the current version of the product software.

    If... Then...

    The product software version is the same

    as that required by the operator 

    Go to Step 4.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    12

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    22/125

    If... Then...

    The product software version is different

    from that required by the operator 

    1. Uninstall the product software by

    referring to operations in Procedure of 

    Uninstalling the Product Software.2. Upload the product software

    installation package to the OMU by

    referring to operations in Procedure of 

    Uploading the OMU Application

    Installation Package to the OMU.

    3. Install the product software to the active

    workspace by referring to operations in

    Procedure of Installing the Product

    Software in the Active Workspace.

    4. Go to Step 7, Step 8 and Step 9.

     

    Step 4 Modify the OMU IP addresses.

    Perform either of the following operations to change IP addresses of the OMU:

    l Run the MOD OMUIP command. This operation can be performed only if the Ethernet

    adapter is connected to the OMU over a local commissioning port. For details, see the

    description of the MOD OMUIP command in the MML command reference.

    l Use the omutool to change IP addresses of the OMU. For details, see the following substeps.

    NOTE

    The following restrictions apply when you execute the MOD OMUIP command. Modify OMU IPaddresses based on actual conditions.

    l Only Internal network fixed IP, External network fixed IP, External network fixed IP mask ,

    External gateway IP and Backup network IP of the active OMU can be modified when OMUs work 

    in active/standby mode.

    l After the OMU starts, the system automatically updates the first two network segments of the internal

    fixed and virtual IP addresses to the configured network segments. You can query the configured

    network segments by running the LST SUBNET command.

    1. Enter cd /mbsc/bam/version_a/bin/bam to go to the directory where the omutool program

    is located.

    NOTE

    You can execute ./omutool -h to view the help information of the omutool.

    2. Change the external fixed IP address and subnet mask according to the operator's plan.

    Enter ./omutool extercard The external fixed IP address The subnet mask The gateway IP 

    address (Optional) to change the external fixed IP address and the subnet mask. For 

    example, you can enter the following command:

    ./omutool extercard 10.161.10.100 255.255.255.0

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    13

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    23/125

    NOTE

    l Perform either of the following operations if a gateway IP address needs to be changed while

    you are changing an external fixed IP address:

    l Method 1: Enter ./omutool extercard The external fixed IP address The subnet mask (The

     gateway IP address) to change the external fixed IP address and gateway IP address at thesame time. The following is an example:

    ./omutool extercard 10.161.10.100 255.255.255.0 10.161.10.1

    l Method 2: Enter ./omutool gateway The gateway IP address to change the gateway IP

    address separately. The following is an example:

    ./omutool gateway 10.161.10.1

    l After the external fixed IP address is changed, the OMU can be connected to the operation and

    maintenance (OM) network of the operator over the ETH0 or ETH1 port. In this case, subsequent

    commissioning tasks can be performed remotely.

    3. Change the external virtual IP address and subnet mask of the active and standby OMUs

    according to the plan. Ensure that the external virtual IP address is on the same network 

    segment as the external fixed IP address.Enter ./omutool extervip The external virtual IP address The subnet mask  to change the

    external virtual IP address and subnet mask. For example, you can enter the following

    command:./omutool extervip 10.161.10.102 255.255.255.0

    NOTE

    The external virtual, external fixed and gateway IP addresses must all be in the same network segment.

    If you change either of the first two of these, you will be prompted to check whether the other two

    addresses need to be changed to comply with this rule.

    4. Check whether the internal fixed IP address, internal virtual IP address, backup channel IP

    address, and commissioning IP address of active and standby OMUs are in the same

    network segment as the operator's network.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    14

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    24/125

    If... Then...

    All the preceding IP addresses

    are in the same network segment

    as the operator's network 

    Change the IP address in conflict.

    l Change the internal network segment by referring

    to Follow-up Procedure in 7 Updating the OMUDatabase.

    l Change the backup channel IP address and subnet

    mask of the active and standby OMUs:

    – If OMUa boards are used, enter ./omutool

    backupcard The IP address. For example,

    you can enter the following command:./omutool backupcard 192.168.3.60

    – If OMUc boards are used, enter ./omutool

    backupcard_for_omuc The IP address and ./

    omutool backupcard_for_omua The IP 

    address. For example, you can enter the

    following commands:./omutool backupcard_for_omuc

    192.168.9.60

    ./omutool backupcard_for_omua

    192.168.3.60

    l Enter ./omutool debugcard The debugging IP 

    address to change the commissioning IP address

    and subnet mask. For example, you can enter the

    following command:./omutool debugcard 192.168.6.60

    The preceding IP addresses arenot in the same network segment

    as the operator's network 

    Change the backup channel IP address of the standbyOMU.

    l If OMUa boards are used, enter ./omutool

    backupcard The IP address. For example, you

    can enter the following command:./omutool backupcard 192.168.3.60

    l If OMUc boards are used, enter ./omutool

    backupcard_for_omuc The IP address and ./

    omutool backupcard_for_omua The IP 

    address. For example, you can enter the following

    commands:./omutool backupcard_for_omuc 192.168.9.60

    ./omutool backupcard_for_omua 192.168.3.60

     

    Step 5 Enter ./omutool dispipinfo to check whether the modified OMU IP address and subnet mask are correct based on the query result.

    Step 6 Change the OMU name.

    1. Enter ./omutool computername OMU name to change the name of the OMU.

    For example, you can enter ./omutool computername omu_123.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    15

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    25/125

    NOTE

    The OMU name cannot contain control characters, spaces, or any of the following special characters: / \

    [ ] ( ) ' : | < > + = ; , ?, and the length of the OMU name must range from 1 to 62 characters.

    Step 7 Set the working mode of the OMU.1. Set the OMU backup mode.

    l If only one OMU board is configured, enter ./omutool dualmode single to set the OMU

    to work in independent mode.

    l If two OMU boards (active and standby OMU boards) are configured, enter ./omutool

    dualmode dual to set the OMUs to work in active/standby mode.

    2. Set the office name.

    a. Enter /etc/rc.d/omud start to start the product software.

     b. Run the SET OFFICENAME command to set the office name.

    Step 8 Check the OMU running status.

    1. Enter ps -afx to check the running status of the OMU.

    The OMU is operating properly if all OMU processes exist in the OMU active workspace

    directory /mbsc/bam/version_a/bin/bam/monitor.

    OMU State OMU Processes That Must Exist

    Active OMU host_gate, ems_gate, authority,

    configure, maintain, stat, alarm,

    software, ftp_server, sntp, ems_agent,

    omu_manager, cfa, weblmt, debug_log,

    and cfg_mirror

    Standby OMU software, ftp_server, sntp,

    omu_manager, and debug_log

     

    NOTE

    If some of the preceding processes do not exist, enter /etc/rc.d/omud restart to restart the OMU

    server, and then check whether the processes exist. If some of them still do not exist, uninstall the

     product software and then reinstall it in the active workspace by referring to operations in

    Procedure of Uninstalling the Product Software and Installing the Product Software in the ActiveWorkspace.

    Step 9 Enter exit to stop the PuTTY and then remove the cable to disconnect the PC from the OMU.

    ----End

    5.2 Commissioning the OMU Using a USB Flash Drive

    This section describes how to commission an OMU using a USB flash drive. You can locally

    insert the prepared USB flash drive to the OMU and then perform OMU commissioning with

    cooperation of a remote engineer.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    16

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    26/125

    Prerequisites

    l The preparations for installing software on site are completed. For details, see Onsite

    Software Installation Preparations.

    l You have obtained the planned OMU information and recorded them in Configuration

    Information for Preparing the USB Flash Drive.

    l The capacity of the USB flash drive is at least 4 GB. If the BSC6900 is configured with

    active and standby OMUs, two USB flash drives are required.

    l A USB flash drive has been inserted into an available and uncontrolled (for example, CPM

    control) USB port on a portable computer 

    l Check whether the USB flash drive is usable by referring to the USB Flash Drive

    Verification Guide under the USB Disk Tool (a tool used for preparing the USB flash drive)

    directory. If the USB flash drive cannot be used, replace it with another one. The Netac

    U208 (4 GB), Kingston and Sandisk USB storage devices are recommended.

    Context

    NOTICE

    Back up the OMU data before you install the OMU operating system and product software. This

    is because the OMU hard disk will be formatted during the installation of the OMU operating

    system and product software using the USB flash drive, and all data will be deleted.

    l This section uses the commissioning of active and standby OMUs as an example. The

    commissioning operation differences between the OMU in independent mode and theOMUs in active/standby mode are described separately.

    l Commissioning an OMU using a USB flash drive involves two steps: preparing the USB

    flash drive and commissioning the OMU after inserting the USB flash drive into the OMU.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    17

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    27/125

    Figure 5-2 Flowchart for commissioning the OMU using a USB flash drive

     

    Procedure

    Step 1 Prepare a USB flash drive.

    1. Double-click U_creator_eng.exe to begin installing a Dopra Linux operating system on

    the USB flash drive, as shown in Figure 5-3.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    18

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    28/125

    Figure 5-3 U_creator_eng window

     

    2. Right-click NE List in the left pane of the window shown in Figure 5-3 and choose Add

    NE from the shortcut menu. A dialog box is displayed, as shown in Figure 5-4.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    19

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    29/125

    Figure 5-4 Add NE dialog box

     

    3. Specify NE Name, set Operating System Type to DopraLinux, set Operate type to

    Install. Then click OK . An NE is added.

    NOTE

    l If only the operating system is to be installed on the OMU, do not select Install product software?.

    If the operating system and product software are to be installed on the OMU, select Install productsoftware? and specify External Virtual IP Address of the NE to be added.

    l If only the product software is to be installed on the OMU, set Operate type to Only install product

    software, and specify External Virtual IP Address of the NE to be added.

    l The NE name, used to identify an NE, can include only letters, numerals, dashes ("-"), and underscores

    ("_").

    l The NE name and the virtual external IP address can be changed only after you delete the NE and then

    add it again.

    l If you want to prepare multiple USB flash drives, you are advised to prepare and label the USB flash

    drives one by one.

    4. Double-click the added NE in the left pane. The window is refreshed, as shown in Figure

    5-5.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    20

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    30/125

    Figure 5-5 Configuring information

     

    NOTE

    l The IP addresses shown in Figure 5-5 are required by the U_creator tool by default. Change the IP

    addresses as required. For details about the principles of changing the IP addresses, see OMU IP

    Address Plan.

    l If Operating System Type in Figure 5-4 is set to DopraLinux, select the product type in Figure

    5-5 according to the product where the OMU is to be installed. The rules for checking network 

    segments of IP addresses vary depending on product types. For details about these rules, see OMU IP

    Address Plan.

    l Select the link mode for external Ethernet adapters listed in Figure 5-5 as required. Ensure that the

    link mode for external Ethernet adapters is consistent with that for the onsite LAN switch. Table

    5-1 lists the mapping between the queried link mode for external Ethernet adapters and that selected

    in Figure 5-5.

    l If Install product software? is not selected in Step 1.3, only the names of the active and standby

    OMUs and IP addresses are displayed in Figure 5-5.

    l In independent OMU mode, only the active OMU configuration is effective, whereas the standby

    OMU configuration is ineffective.l The new password policy is as follows:

    l Passwords of admin must contain 8 to 32 characters.

    l The characters must be uppercase letters, lowercase letters, digits, or special characters, or the

    combination of two among these types.

    l Special characters include spaces and the following characters ~!@#$%^&*()_+-{}|[]:?./

    l Modify Debug network IP and Debug network mask  based on actual conditions.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    21

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    31/125

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    32/125

    Step 2 Commission the OMU after inserting the USB flash drive to the OMU.

    1. Insert the USB flash drive into any USB port on the OMU board panel.

    2. Remove and then install the OMU board to reset it. For details, see sections Removing a

    Board and Installing a board in the BSC6900 UMTS Site Maintenance Guide.

    3. Observe the status of the indicators on the OMU board panel and determine whether the

    installation is complete.

    l If only the operating system is to be installed on the OMU, check the indicator status

    according to the conditions described in Table 5-2.

    l If the operating system and product software are to be installed on the OMU, check the

    indicator status according to the conditions described in Table 5-3.

    l If only the product software is to be installed, check the indicator status according to

    the conditions described in Table 5-4.

    NOTE

    l If the status of the indicators differs from this, the OMU cannot identify the USB flash device.

    In this case, prepare another USB flash device. Alternatively, copy the data in the original USB

    flash device to a new one, and then reinstall the OMU operating system.

    l After the OMU operating system and the product software are installed successfully, remove the

    USB flash drive from the OMU board panel. The OMU commissioning is complete. If the value

    of operation type is Only install product software, you need to remove and reinsert the OMU

    to restart the OMU operating system after removing the USB flash drive.

    Table 5-2 Status of the indicators on the OMUa or OMUc board panel during the OMU

    operating system installation

    Board InstallationProcedure SuccessfulInstallation Failed Installation

    OMUa At the beginning:

    l The RUN indicator 

     blinks.

    l The ALM indicator 

     blinks.

    l The ACT indicator 

     blinks.

    l The OFFLINE

    indicator is off.

    After a certain period:

    l The RUN indicator 

     blinks.

    l The ALM indicator 

    is off.

    l The ACT indicator is

    off.

    l The OFFLINE

    indicator blinks.

    l The RUN indicator 

     blinks.

    l The ALM indicator 

    is off or blinks.

    l The ACT indicator 

    is off.

    l The OFFLINE

    indicator is off.

    l The RUN indicator 

    is off.

    l The ALM indicator 

     blinks.

    l The ACT indicator 

    is off.

    l The OFFLINE

    indicator blinks.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    23

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    33/125

    Board InstallationProcedure

    SuccessfulInstallation

    Failed Installation

    OMUc   l The RUN indicator 

     blinks.l The ALM indicator 

     blinks.

    l The ACT indicator 

     blinks.

    l The OFFLINE

    indicator is off.

    l The RUN indicator 

     blinks.l The ALM indicator 

    is off.

    l The ACT indicator 

    is off.

    l The OFFLINE

    indicator blinks.

    l The RUN indicator 

    is off.l The ALM indicator 

     blinks.

    l The ACT indicator 

    is off.

    l The OFFLINE

    indicator blinks.

     

    Table 5-3 Status of indicators on the OMUa or OMUc board panel during the OMU

    operating system and product software installation

    Board InstallationProcedure

    SuccessfulInstallation

    Failed Installation

    OMUa At the beginning:

    l The RUN indicator 

     blinks.

    l The ALM indicator 

     blinks.

    l The ACT indicator 

     blinks.

    l The OFFLINE

    indicator is off.

    After a certain period:

    l The RUN indicator 

     blinks.

    l The ALM indicator 

    is off.

    l The ACT indicator is

    off.

    lThe OFFLINEindicator blinks.

    l The RUN indicator 

     blinks.

    l The ALM indicator 

    is steady on or off.

    l The ACT indicator 

    is steady on or off.

    l The OFFLINE

    indicator is off.

    l The RUN indicator 

     blinks.

    l The ALM indicator 

     blinks.

    l The ACT indicator 

    is off.

    l The OFFLINE

    indicator is off.

    OMUc   l The RUN indicator 

     blinks.

    l The ALM indicator 

     blinks.

    l The ACT indicator 

     blinks.

    l The OFFLINE

    indicator is off.

    l The RUN indicator 

     blinks.

    l The ALM indicator 

    is steady on or off.

    l The ACT indicator 

    is steady on or off.

    l The OFFLINE

    indicator is off.

    l The RUN indicator 

     blinks.

    l The ALM indicator 

     blinks.

    l The ACT indicator 

    is off.

    l The OFFLINE

    indicator is off.

     

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    24

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    34/125

    Table 5-4 Status of indicators on the OMUa or OMUc board panel during only the product

    software installation

    Board InstallationProcedure

    SuccessfulInstallation

    Failed Installation

    OMUa At the beginning:

    l The RUN indicator 

     blinks.

    l The ALM indicator 

    is off.

    l The ACT indicator 

     blinks.

    l The OFFLINE

    indicator is off.

    After a certain period:

    l The RUN indicator 

     blinks.

    l The ALM indicator 

     blinks.

    l The ACT indicator is

    off.

    l The OFFLINE

    indicator is off.

    l The RUN indicator 

     blinks.

    l The ALM indicator 

    is steady on or off.

    l The ACT indicator 

    is steady on or off.

    l The OFFLINE

    indicator is off.

    l The RUN indicator 

     blinks.

    l The ALM indicator 

     blinks.

    l The ACT indicator 

    is off.

    l The OFFLINE

    indicator is off.

    OMUc  l

    The RUN indicator  blinks.

    l The ALM indicator 

    is off.

    l The ACT indicator is

    off.

    l The OFFLINE

    indicator is off.

    l

    The RUN indicator  blinks.

    l The ALM indicator 

    is steady on or off.

    l The ACT indicator 

    is steady on or off.

    l The OFFLINE

    indicator is off.

    l

    The RUN indicator  blinks.

    l The ALM indicator 

     blinks.

    l The ACT indicator 

    is off.

    l The OFFLINE

    indicator is off.

     

    ----End

    Follow-up Procedure

    Troubleshooting upon Installation Failures

    Check whether the configuration files prepared in the step Prepare the USB flash drive are

    correct according to the Configuration Information for Preparing the USB flash drive for

    Installation recorded during the preparations.

    l If the configuration files are not correct, prepare the USB flash drive again by referring to

    the step Prepare the USB flash drive.

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    25

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    35/125

    l If the configuration files are correct, contact Huawei technical support by referring to

    Contact the Technical Support for Assistance.

    Querying the Operating System Version Using the PuTTY

    1. Double-click putty.exe. Enter the physical IP address of the OMU where an operatingsystem has been installed. An interface for logging in to the Linux operating system is

    displayed. Enter an administrator-level user name and its password to log in to the OMU.

    2. Execute /cat /etc/DL-Release to query the operating system version, as shown in Figure

    5-6.

    Figure 5-6 Querying the operating system version using the Putty

    BSC6900 UMTS

    Commissioning Guide 5 Commissioning the OMU

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    26

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    36/125

    6 Logging In to the BSC6900 Using the LMTThis chapter describes how to log in to the BSC6900 using the LMT and how to establish

    communication between the LMT and BSC6900 to ensure successful BSC6900 commissioning

    using the LMT.

    Prerequisites

    l The OMU commissioning has been complete.

    l The network connection between the LMT and the OMU has been established.

    NOTE

    In the case of the local OMU commissioning, a field engineer performs local commissioning tasks

    and then Log in to the BSC6900 using the LMT to verify the connection between the OMU and

    the external network. In this case, the field engineer needs to enter the IP address for OMU

    commissioning in the address bar of Internet Explorer (IE) to log in to the LMT.

    Context

    JRE is a standard Java plug-in. If JRE is not installed, a message is displayed when you attempt

    to log in to the LMT. In this case, install JRE by following the instructions in the displayed

     prompt message. If the JRE installed in the PC is not of the latest version, a message is displayed

    when you attempt to log in to the LMT, prompting you to update the JRE. In this case, it is

    recommended that you uninstall the JRE and then install the JRE of the latest version

    CAUTION

    When the LMT application is running, do not change the LMT PC system time. Otherwise,

    severe errors may occur on the system. If you have to change the system time, stop all the LMT

    applications first.

    Procedure

    Step 1 Check the configuration of the LMT PC and ensure that it meets the requirements.

    1. Check the hardware configuration of the BSC6900 LMT PC to ensure that the requirements

    described in Configuration Requirements of the LMT PC are met.

    BSC6900 UMTS

    Commissioning Guide 6 Logging In to the BSC6900 Using the LMT

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    27

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    37/125

    2. Check the security settings of the Internet Explorer and ensure that the Java script is

    supported.

    Step 2 Start the IE, and then log in to the BSC6900 using the LMT.

    1. Start the IE and enter the external virtual IP address of the OMU of the BSC6900 on the

    address bar. The login dialog box is displayed, as shown in Figure 6-1.

    Figure 6-1 BSC6900 login dialog box

     

    NOTE

    To log in to the BSC6900 by using the Domain user account, establish the connection between the

    BSC6900 and the U2000 server.

    2. Enter User Name, Password, and Verify Code, and click Login to log in to the LMT.

    ----End

    BSC6900 UMTS

    Commissioning Guide 6 Logging In to the BSC6900 Using the LMT

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    28

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    38/125

    7 Updating the OMU DatabaseThis chapter describes how to update configuration data in the OMU database by running MML

    scripts.

    Prerequisites

    l You have completed the operations provided in section 6 Logging In to the BSC6900

    Using the LMT.

    l The MML command data scripts applicable to the local office are verified and the contents

    are precise and complete.

    Context

    l There are two methods to run MML scripts: by running MML commands or using the GUI.

    The MML script can be executed by using the GUI only when a script is smaller than 4

    MB. It is recommended that you run the MML script by running MML commands, because

    it is more efficient.

    l You can query the active workspace of the OMU through the MML command LST

    OMUAREA. The following procedure assumes that the active workspace is version_a.

    Procedure

    l Run the MML script by running MML commands.

    1. Run the MML command SET CFGDATAINEFFECTIVE to set the MPS to work in ineffective mode.

    NOTICEIf the database has been updated, run the MML command SET

    CFGDATAINEFFECTIVE  to set each configured subrack to work in ineffective

    mode.

    2. Run the MML command RST DATA. Click Yes in the displayed dialog box to

    initialize the BSC6900 configuration data in the OMU database.

    BSC6900 UMTS

    Commissioning Guide 7 Updating the OMU Database

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    29

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    39/125

    3. Run the MML command UPD KEYMATERIAL to update the key material used for 

    local data encryption.

    4. Upload the MML script to the /ftp folder in the OMU active workspace directory. The

    following assumes that the MML script BATCHFILE.txt saved in disk D is uploaded

    to the OMU active workspace /mbsc/bam/version_a/ftp to introduce the twomethods.

    NOTE

    Two methods are available: through File Manager on the LMT or through command lines.

    – Through File Manager on the LMT

    a. Click File Manager on the toolbar of the LMT to start the file manager.

     b. In the displayed window, choose Root > bam > version_a > ftp on the left

    and click Upload on the right. A dialog box is displayed. Select

    BATCHFILE.txt saved in disk D, and then click Open to upload the file.

    Through command linesa. On the local PC, choose Start > Run. Type cmd and click OK .

     b. Input d: and press Enter to switch to disk D.

    c. Input ftp IP address to connect to the OMU. Here, IP address is the IP address

    of the OMU.

    d. Input the LMT user name and password. The connection between the OMU

    and the local FTP is set up after the authentication succeeds.

    e. Input cd /mbsc/bam/version_a/ftp to switch to the OMU active workspace.

    f. Input put BATCHFILE.txt to upload the file.

    g. After the file is uploaded successfully, input quit to disconnect the FTP.

    5. Run the MML command RUN BATCHFILE to run the batch command file. It is

    recommended that you set Finish Type to ANY_ERR_RETURN(Stop at Error),

    Result Recording Type to REC_ERR(Record errors), Source File Name to

    BATCHFILE.txt, and Result File Name to RUN_BATCHFILE_RESULT.txt .

    NOTE

    l The result file RUN_BATCHFILE_RESULT.txt  is saved in the /ftp folder in the OMU

    active workspace installation directory, that is, /mbsc/bam/version_a/ftp.

    l The execution of the script takes a certain period of time. For example, 1-1.5 hours will be

    needed for executing a script with 100,000 commands.

    l If the MML script fails to be executed, open the RUN_BATCHFILE_RESULT.txt  file

    to check the commands that fail to be executed. Then, extract the commands that fail to beexecuted and the commands that have not been executed to generate a new MML script.

    Correct the MML script based on the displayed messages, and then go to Step 5 to run the

    new script.

    l Run the MML script by using the GUI.

    1. Run the MML command SET CFGDATAINEFFECTIVE to set the MPS to work 

    in ineffective mode.

    BSC6900 UMTS

    Commissioning Guide 7 Updating the OMU Database

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    30

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    40/125

    NOTICEIf the database has been updated, run the MML command SET

    CFGDATAINEFFECTIVE  to set each configured subrack to work in ineffectivemode.

    2. Run the MML command RST DATA. Click Yes in the displayed dialog box to

    initialize the BSC6900 configuration data in the OMU database.

    3. Run the MML command UPD KEYMATERIAL to update the key material used for 

    local data encryption.

    4. On the LMT, click theBatch tab. The Batch tab page is displayed, as shown in Figure

    7-1.

    Figure 7-1 Batch tab page

     

    5. Click Open....The Open dialog box is displayed. Select the prepared MML script,

    and then click Open. The commands in the script are displayed on the Batch tab page.

    6. Click Set.... The Set dialog box is displayed. Set Sending Commands Interval(s) to

    0, select Save Failed Commands and set the path for saving the failed commands,

    and then click OK , as shown in Figure 7-2.

    BSC6900 UMTS

    Commissioning Guide 7 Updating the OMU Database

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    31

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    41/125

    Figure 7-2 Setting the batch commands

     

    7. On the Batch tab page, select All in the Execution Type area.

    8. Click Go. The system runs the MML commands one by one.

    NOTE

    l Click OK  when the system displays that the current configuration is in ineffective mode

    after you click Go. The execution of the script will take a long time in GUI mode. For 

    example, 2-3 hours will be needed for executing a 4-MB script.

    l If an Error dialog box showing Execution failed. Continue? is displayed during the

    execution of the MML script, the MML script is incorrect. In this case, select Yes to All

    to ignore the error prompt. After the MML script file is executed, extract the commands

    that fail to be executed to generate a new MML script, correct the commands based on the

     prompts, and then go to Step 5 to run the script again.

    9. Click OK  when a dialog box is displayed, indicating that the running of all the MML

    commands is complete.

    ----End

    Follow-up Procedure

    After the OMU database is upgraded, perform the following operations to ensure the normal

    communication between the OMU and BSC6900.

    1. Run the MML command LST SUBNET to query the Subnet No. of the BSC6900.

    2. Check whether the Subnet No. of the BSC6900 is consistent with the network segment of 

    the planned internal IP address of the OMU.

    NOTE

    The planned internal IP address of the OMU is recorded in Configuration Information for Commissioning the OMU Locally.

    BSC6900 UMTS

    Commissioning Guide 7 Updating the OMU Database

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    32

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    42/125

    l If they are consistent, run the DSP OMU command to query the OMU internal network 

    segment and check whether the OMU internal network segment is consistent with the

    network segment of the internal IP address of the OMU.

    a. If they are consistent, perform 3.

     b. If they are inconsistent, run the RST OMU command with Reset Type set to

    SOFT(Soft Reset) to reset the active and standby OMU boards.

    l If they are inconsistent, perform the following operations:

    a. Run the MML command SET SUBNET to change the Subnet No. of the

    BSC6900 so that it is consistent with the network segment of the planned internal

    IP address of the OMU.

     b. Run the RST OMU command with Reset Type set to SOFT(Soft Reset) to reset

    the active and standby OMU boards.

    3. Run the MML command SET CFGDATAEFFECTIVE to set the MPS to work in

    effective mode.

    4. Locally remove the SCU board and then reinsert it into the MPS. Then, reset the MPS so

    that the new IP address of the BSC6900 host takes effect.

    BSC6900 UMTS

    Commissioning Guide 7 Updating the OMU Database

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    33

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    43/125

    8 Activating and Verifying the LicenseThis section describes how to activate the license and verify the license configuration

    information to enable service commissioning.

    Prerequisites

    l You have completed the operations provided in section 6 Logging In to the BSC6900

    Using the LMT.

    l The FTP server is started. For details on how to start the FTP server, see the operations in

    Startup in BSC6900 UMTS LMT User Guide for FTP Server. For the default user name and

     password of the FTP server, see FTP Server in BSC6900 UMTS LMT User Guide. Note

    that the user name or password may be modified.

    l The license file is ready and the license check is passed.

    Context

    The active workspace of the OMU can be queried through the MML command LST

    OMUAREA. The following operations assume that the active workspace is version_a.

    Procedure

    Step 1 Run the MML command DLD LICENSE to download the license to the OMU active workspacedirectory /ftp/license, that is, /mbsc/bam/version_a/ftp/license/software/bam/version_a/ftp/

    license.

    Step 2 Run the MML command LST LICENSE and then set File Name to the name of the license fileto be activated to query the detailed configuration information of the license file.

    If... Then...

    The license is consistent with what you apply for Go to Step 3.

    The license is inconsistent with what you apply for Contact Huawei technical support.

    Step 3 Run the MML command CHK DATA2LIC, and then set File Name to the name of the licensefile to be activated to verify the license information including the equipment serial number 

    (ESN), version, working mode, and configuration.

    BSC6900 UMTS

    Commissioning Guide 8 Activating and Verifying the License

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    34

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    44/125

    If... Then...

    The license information is consistent with

    the OMU information

    Go to Step 4.

    The license information is inconsistent with

    the OMU information

    Modify the inconsistent data and then repeat

    this step.

    Step 4 Run the MML command ACT LICENSE to activate the license file.

    Step 5 Optional: If there are the primary and secondary operators, run the MML command SETLICENSE to reallocate the resources and functions in sequence from the primary operator to

    the secondary operator. If there are multiple secondary operators, run the command for each

    operator.

    ----End

    Follow-up Procedure

    If the license activation fails, the configuration data of the license is inconsistent with that in the

    OMU database. Check the configuration data of the license and the configuration data in the

    OMU database.

    l If the configuration data, such as the product name, ESN, and version number of the license

    is incorrect, apply for a new license.

    l If the configuration data in the OMU database is incorrect, correct the configuration data,

    and then reactivate the license.

    NOTE

    An invalid or expired license file can also lead to a license activation failure. For details, see the online

    help of the MML command ACT LICENSE.

    BSC6900 UMTS

    Commissioning Guide 8 Activating and Verifying the License

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    35

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    45/125

    9 Loading BSC6900 Board Software and DataFiles

    About This Chapter

    This chapter describes how to load the BSC6900 board software and data files.

    Prerequisites

    l The device has been commissioned.

    l The OMU database has been updated.

    Context

    The software of the BSC6900 is generated automatically in the OMU active workspace

    directory /bin/fam during the installation of the product software. For example, if the active

    workspace is version_a, the software is in /mbsc/bam/version_a/bin/fam. The software can

     be loaded directly.

    To make the configuration take effect, format the configuration data in the OMU database to

    generate a .DAT data file, and then reset the BSC6900 boards.

    9.1 Generating Data Files for the Loading

    This section describes how to generate data files, which can be loaded, using the MML datascripts.

    9.2 Setting the Board Loading Mode

    This section describes how to set the loading modes of all the board subsystems before resetting

    BSC6900 boards.

    9.3 Resetting BSC6900 Boards

    This section describes how to load the BSC6900 board software and data files from the OMU

    installation directory to the boards and make them take effect.

    9.4 Checking the Consistency of the Data and the Version

    This section describes how to check whether the board configuration and the software version

    of the BSC6900 are consistent with those on the OMU.

    BSC6900 UMTS

    Commissioning Guide 9 Loading BSC6900 Board Software and Data Files

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    36

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    46/125

    9.1 Generating Data Files for the Loading 

    This section describes how to generate data files, which can be loaded, using the MML datascripts.

    Prerequisites

    l You have completed the operations provided in section 6 Logging In to the BSC6900

    Using the LMT.

    Procedure

    Step 1 Run the MML command SET CFGDATAEFFECTIVE without specifying any parameter to

    set the subracks configured to work in effective mode.

    Step 2 Run the MML command FMT DATA and set Work Area Flag to Active(Format activearea) to format the configuration data in the OMU database. Do not specify the subrack number 

    when running the MML command.

    ----End

    9.2 Setting the Board Loading Mode

    This section describes how to set the loading modes of all the board subsystems before resetting

    BSC6900 boards.

    Prerequisites

    You have completed the operations provided in section 6 Logging In to the BSC6900 Using

    the LMT.

    Context

    For details about the loading modes, see BSC6900 Loading Management.

    Procedure

    Step 1 Run the MML command SET LODCTRL to set the board loading mode. In this command, setBoard Start Load Control to LFB(Load from OMU and write flash).

    ----End

    9.3 Resetting BSC6900 Boards

    This section describes how to load the BSC6900 board software and data files from the OMU

    installation directory to the boards and make them take effect.

    BSC6900 UMTS

    Commissioning Guide 9 Loading BSC6900 Board Software and Data Files

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    37

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    47/125

    Prerequisites

    l The data file for the loading has been generated.

    l You have completed the operations provided in section 6 Logging In to the BSC6900

    Using the LMT.

    l All the subracks have been powered on.

    Context

    The resetting time is less than or equal to six minutes in the maximum configuration. There is

    no requirement for the sequence. All the subracks can be reset at the same time.

    Procedure

    Step 1 Run the MML command RST SUBRACK , and then set Subrack No. to the number of thesubrack to be reset. A dialog box is displayed, asking you whether to proceed. Click OK . The

     boards in the subrack automatically load the BSC6900 board software and data files from the

    OMU.

    Step 2 Repeat Step 1 to reset all the BSC6900 subracks.

    NOTE

    You can observe the loading process on the Progress tab page on the LMT home page. If this tab page is hidden,

    click Progress in the toolbar on the LMT home page.

    Step 3 Click the Device Maintenance tab on the LMT home page after all the subracks are reset. TheDevice Maintenance tab page is displayed.

    Step 4 Check whether all the boards on the device panel are in the normal state.

    If... Then...

    The device panel shows that all the boards

    are in the normal state

     No further action is required.

    The device panel shows that some boards

    are not in the normal state

    Check the faulty boards and clear the alarms

    according to operations in 17.9 Data Loading

    Failures on the Board.

    ----End

    9.4 Checking the Consistency of the Data and the Version

    This section describes how to check whether the board configuration and the software version

    of the BSC6900 are consistent with those on the OMU.

    Prerequisites

    l All the subracks and boards are running properly.

    l You have completed the operations provided in section 6 Logging In to the BSC6900

    Using the LMT.

    BSC6900 UMTS

    Commissioning Guide 9 Loading BSC6900 Board Software and Data Files

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    38

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    48/125

    Procedure

    Step 1 Run the MML command ACT CRC without specifying any parameter to check whether theBSC6900 board configuration is consistent with the data on the OMU.

    Expected result: The All table data consistent. message is displayed.

    Step 2 Run the MML command CMP BRDVER  without specifying any parameter to check whether the version run by the BSC6900 is consistent with the version information on the OMU.

    Expected result: The Compare consistent message is displayed.

    NOTE

    If the board configuration or software version is inconsistent with the information on the OMU, run the MML

    command RST SUBRACK  reset the subrack where the board with incorrect data or version is located.

    ----End

    Follow-up Procedure

    After the consistency check, restore the loading method of the board: Run the MML command

    SET LODCTRL to set Board Start Load Control to CL(Consult Load).

    BSC6900 UMTS

    Commissioning Guide 9 Loading BSC6900 Board Software and Data Files

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    39

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    49/125

    10 Connecting to the U2000This section describes how to connect the BSC6900 to the U2000 for centralized management.

    Prerequisites

    l The operation and maintenance (O&M) network has passed the commissioning. The U2000

    is operating properly.

    l The version of the U2000 is compatible with that of the BSC6900.

    l The mediation version of the U2000 is compatible with the NE version.

    Context

    l If the BSC6900 and the U2000 are in the same network segment, you do not need to

    configure an IP route to the BSC6900 to the U2000.

    l If the BSC6900 and the U2000 are not in the same network segment, you must configure

    an IP route from the BSC6900 to the U2000.

    Procedure

    Step 1 Connect the BSC6900 to the O&M network.

    1. Connect one end of a straight-through cable to the ETH0 or ETH1 port on the OMU board.

    2. Connect the other end of the straight-through cable to the peer network device, such as a

    hub or a router, to access the O&M network.

    Step 2 Configure an IP route from the BSC6900 to the U2000.

    1. Run the MML command LST OMUIPRT to check whether the IP route to the U2000 is

    configured on the OMU.

    l If the values of Destination Network Address, Destination Address Mask , and

    Forward Route Address are consistent with the planned addresses, the BSC6900 has

    an IP route to the U2000. Go to Step 2.3.

    l If the Destination Network Address, Destination Address Mask , and Forward

    Route Address are not consistent with the planned addresses, the BSC6900 does not

    have a route to the U2000. Go to Step 2.2.

    2. Run the MML command ADD OMUIPRT to configure a route from the BSC6900 to the

    U2000.

    BSC6900 UMTS

    Commissioning Guide 10 Connecting to the U2000

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    40

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    50/125

    3. Verify the configuration of the route from the BSC6900 to the router.

    Log in to the OMU according to the instructions in BSC6900 UMTS OMU Administration

    Guide for Logging In to the OMU, and then run the ping command to check whether the

    network connectivity between the BSC6900 and the router is available. If the OMU can

    receive an acknowledge packet from the router, go to Step 2.4. Otherwise, check whether the OMU and the router are properly connected.

    4. Verify the configuration of the route from the BSC6900 to the U2000.

    Log in to the OMU and run the ping command to check whether the network connectivity

     between the BSC6900 and the U2000 is available. If the OMU can receive a response packet

    from the U2000, go to Step 3. Otherwise, check whether the router and the U2000 are

     properly connected.

    Step 3 Create the BSC6900 on the U2000. For details, see the information about how to create an NEin the U2000 documentation.

    NOTICE

    l If a firewall exists between the BSC6900 and U2000, enable the communication ports

    connecting the BSC6900 and U2000 to ensure proper communication between the

    BSC6900 and U2000.

    l For details on the ports connecting the BSC6900 and U2000, see 18.1 Communication Ports

    on the BSC6900.

    l The MTU value configured for the transmission equipment between the BSC6900 and the

    U2000 must be no less than that configured for the OMU board of the BSC6900. Otherwise,

    the communication between the BSC6900 and the U2000 may be abnormal. The defaultMTU value for the OMU board is 1500.

    l You are advised to run the SET CONNTYPE command with Connection Type set to

    ONLY_SSL(Only SSL Connection) to enhance network transmission security.

    ----End

    Example

    Table 10-1 describes how to configure a route between the BSC6900 and the U2000.

    Table 10-1 Configuring a route from the BSC6900 to the U2000

    Scenar

    io

    The IP address of the U2000 server is 10.11.100.23. The mask is 255.255.255.255.

    The OMU is connected to the U2000 network segment through the router. The IP

    address of the router is 192.168.139.10.

    BSC6900 UMTS

    Commissioning Guide 10 Connecting to the U2000

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    41

  • 8/18/2019 Bsc6900 Umts Commissioning Guide(v900r017c10_01)(PDF)-En

    51/125

    Opera

    tion

    1. Run the MML ADD OMUIPRT command.

    l Set Destination network address to 10.11.100.23.

    l Set Destination address mask  to 255.255.255.255.

    l Set Forward route address to 192