BSBPMG503A Manage Project Time
6.3 Estimate Activity Resources
• The process of estimating the type and quantities of material, people, equipment or supplies required to perform each activity
• Closely related to the Estimate Costs process (7.1) and normally done simultaneously
• Sometimes the resources are captured in project management software, most particularly human resources
• Supplementary registers are often maintained for non human resources
• Occurs during the Planning Phase
Adapted from PMBOK 4th Edition
Initiation Planning Execution Close
Monitor
Control
BSBPMG503A Manage Project Time
6.3 Estimate Activity Resources
• Inputs to Estimate Activity Resources
Activity list and attributes
Resource Calendars
Resource availability and skills
Staffing policies and procedures
Procurement policies and procedures
• Tools and techniques to Estimate Activity Resources
Adapted from PMBOK 4th Edition
Bottom-UpEstimating
ExpertJudgement
AlternativesAnalysis
PublishedEstimating
Data
ProjectManagement
Software
BSBPMG503A Manage Project Time
6.3 Estimate Activity Resources
• Published Estimating Data
Many industries (eg Construction) have standard production rates and unit costs for common activities
• Bottom-Up Estimating
Decomposing activities into more detail to assist with estimation
• Project Management Software
Can assist with planning, organising and managing resources
Different levels of sophistication Initiation Planning Execution Close
Monitor
Control
Adapted from PMBOK 4th Edition
BSBPMG503A Manage Project Time
Practical Tips to Estimate Duration
• Experience has taught me that often the best way to estimate the duration of an activity is to ask the person who will be performing the activity to make an estimate
• I have also learnt that most people are –– Optimistic so that they underestimate the work effort
required;– Assume they are productive for more hours per day than
they really are; and– Fail to include rework and sign off activities as part of
their estimate
• In practice I will double, or sometimes triple, these estimates before putting them in the project schedule
BSBPMG503A Manage Project Time
6.3 Estimate Activity Resources
• Outputs of this process include –
Activity Resource Requirements
– Captured in project management software or supplementary registers
Resource Breakdown Structure
– Hierarchical chart of resources required
– Commonly depicted as the project organisation structure for human resources
Revised Activity List and Attributes
Revised Resource Calendar
– Resources marked as unavailable
Adapted from PMBOK 4th Edition
Initiation Planning Execution Close
Monitor
Control