Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Board Members: Catherine D. Cooke, Chairman • Ellen G. Milligan, Vice-Chairman • Charles W. Miller • Harry E. Lemon, Jr. • Gerald D. Benton, Jr.
Dr. Jerry L. Oates, Superintendent
BRUNSWICK COUNTY SCHOOLS
35 Referendum Drive ∙ Bolivia, North Carolina 28422 ∙ Phone: 910-253-2900 ∙ Fax: 866-291-7891
Date: August 12, 2020
Bid Request No: 153.334.21.CPP.138
Bids Due By: August 24 at 3:00 PM
Project Name and Location: Parking Lot Improvement
South Brunswick High School
Brunswick County Schools is informally requesting bids for the partial repaving of the South Brunswick High School parking
lot. Bids shall be binding for 30 days. Information regarding this Informal Bid Request may be obtained from Larry Smith
at Office (910) 253-1062, Mobile (910) 508-8701 or [email protected]. Bids can be emailed to [email protected].
READ RECEIPT REQUESTED on Emailed bids.
PROJECT DESCRIPTION: See Exhibit 1 for a detailed description of the project scope and requirements. Also included
is the Geotechnical Report by ECS.
PROJECT SCHEDULE: The Contractor shall begin the work upon receipt of the Purchase Order, and expeditiously, with
adequate forces, complete the work within the specified calendar days. The required milestone dates, and completion date
are included in Exhibit 1. The contractor shall coordinate all work with Operations personnel to ensure minimal disruption to
school activities. Should the Contractor fail to substantially complete the Work on or before the date stipulated for Substantial
Completion, or such later date as may result from extension of time granted by Owner, he shall pay the Owner, as liquidated
damages, the sum of Two Hundred and Fifty Dollars ($250.00) for each consecutive calendar day that terms of the contract
remain unfulfilled beyond the date allowed by the Contract, which sum is agreed upon as a reasonable and proper measure of
damages which the Owner will sustain per day by failure of the Contractor to complete Work within time as stipulated; it
being recognized by the Owner and the Contractor that the injury to the Owner which could result from a failure of the
Contractor to complete on schedule is uncertain and cannot be computed exactly. In no way shall costs for liquidated damages
be construed as a penalty on the Contractor.
TERMS AND CONDITIONS
Brunswick County Schools Contract, is included in Exhibit 2. The selected contractor will be required to sign this contract,
and Sexual Offender Registry Check Certification Form, included as Exhibit 2.1, as each are a part of this Request for Bid
and will govern this work.
FORM OF BID
The Form of Bid is included as Exhibit 3
Board Members: Catherine D. Cooke, Chairman • Ellen G. Milligan, Vice-Chairman • Charles W. Miller • Harry E. Lemon, Jr. • Gerald D. Benton, Jr.
Dr. Jerry L. Oates, Superintendent
EXHIBIT 1 – SCOPE OF WORK
PRE-BID MEETING: There will be a pre- bid meeting scheduled for this bid. Pre-Bid meeting will be held at 3:00
PM on August 18, 2020 at South Brunswick High School. Bidding Contractors can also visit the site by contacting
Capital Projects and Planning to receive a Site Visit Authorization Form. Forms may be obtained by emailing
Cherie Suther at [email protected]
SCOPE OF WORK & SCHEDULE
The contractors are responsible for all items required to complete the scope of services, those items being included
in the scope of services even if not listed below. The subcontractor’s workmanship shall be equal to or exceed the
workmanship of reputable contractors performing similar work in the Wilmington Metropolitan Service Area.
Contractor shall perform the following scope of work in compliance with all federal, state, and local codes
and in accordance with any plans, specifications and engineered drawings, design or criteria.
• The general scope involves demolition and replacement of paved surfaces; specifically, all work outlined in the
Bid Documents titled Parking Lot Refurbishment for South Brunswick High School, by McGill Associates
dated July 15, 2020.
GENERAL
• Brunswick County Schools has a policy of No Contact, Socialization, Or Fraternization between contractor
personnel and students or school staff. All Brunswick County Board of Education property is designated as non-
smoking non-tobacco use areas. All employees must sign a Policy Compliance Form prior to mobilization to the
site.
• Lump Sum Bid to include all applicable taxes, shipping costs, and delivery lead time once selections made.
• The contractor shall provide Brunswick County Schools with a list of subcontractors along with subcontractor’s
contact information that will be performing work for the contractor.
• The contractor shall supply submittals for approval prior to work associated with the submittal.
• The contractor shall schedule and perform the work without impeding or interfering with day to day school
activities.
• Contractor shall obtain all required permits and pay all fees associated with this work.
• Contractor will be responsible for having all utilities, power lines, water lines, sewer lines, gas lines, telephone
lines, data lines, communication lines, etc… located by locating service as necessary.
• Contractor shall maintain a safe and clean work environment. Contractor shall maintain a dumpster on site for
duration of the project with periodic hauling off of trash and construction debris. Contractor is responsible for
daily cleanup of any trash and construction debris to maintain a safe and clean job site.
• Contractor shall provide its employees and subcontractors with a portable restroom facility to be maintained,
cleaned and emptied weekly.
• Work area is to be left safe at the close of each workday. Leave no unfilled/protected holes. Coordinate work with
Capital Projects Office.
• Safety: Contractor shall erect barriers as needed, to prevent pedestrians and vehicles from entering the work area.
Contractor to provide and use any and all equipment needed to complete the work following all OSHA guidelines
and requirements.
• Contractor shall complete Architect’s, Engineer’s, or Owner’s punch list before final payments and release of
retainage will be issued.
• Upon completion of the work the contractor is to perform a final construction cleaning of all surfaces and areas
associated with this project.
ALLOWANCES:
1. Each Contractor shall include an allowance of $ 5,000 for a general owner’s allowance in their
Base Bid amount. Allowances will be used for Owner requested and authorized, out-of-scope
work. The contractor will invoice allowance amounts as a separate line item.
Board Members: Catherine D. Cooke, Chairman • Ellen G. Milligan, Vice-Chairman • Charles W. Miller • Harry E. Lemon, Jr. • Gerald D. Benton, Jr.
Dr. Jerry L. Oates, Superintendent
Warranty: Contractor shall warrant work for a period of 1 year.
SCHEDULE:
- Anticipated Project Start Date: September 2
- Project Completion Date: September 20, 2020
- Submittals to be provided upon receipt of PO to assure materials available at project start date
- If work involves weekends or holidays Contractor to have schedule approved in advance by Capital
Projects & Planning. Access into the schools facilities will have to be coordinated three days in
advance.
•Board Members: Charles Miller., Chairman • Catherine Cooke, Vice-Chairman • Ed Lemon, Jr. • John Thompson • Ellen Milligan • Leslie K. Tubb, Superintendent
EXHIBIT C - BID FORM BID REQUEST NO.: 153.334.21.CPP.138
PROJECT DESCRIPTION: Parking Lot Improvement – South Brunswick High School ___________________________________________________________________________________________
Company Name:
Street Address:
City, State, Zip Code:
Contact Person:
Contact Information:
It has been determined that the above specified project is a Capital Improvement as defined in E505 (09-17). Brunswick
County Board of Education will issue a E589-CI, Affidavit of Capital Improvement, upon award of the bid.
It has been determined that the above specified project is:
Subject to NC Sales & Use Tax
Not Subject to NC Sales & Use Tax
________________________________ proposes to do the above specified project for:
Company Name
Project Expense $____________
Sales Tax (If Applicable) $__NA_______
Total Project Cost $____________
Unit Pricing :
Remove unsuitable soil and replace compacted structural fill $________/CY (Qty measure from excavation) Remove unsuitable soil and replace with stone fill $________/CY (Qty measure from excavation)
Unless otherwise noted, the Total Project Cost includes all material, labor, permitting, freight, taxes,
allowances, and other charges. . Bids are to be valid for 30 days. “N.C.G.S. § 133-32 and Executive Order 24 prohibit the offer to, or acceptance by, any State Employee
of any gift from anyone with a contract with the State, or from any person seeking to do business with the State. By execution of any
response in this procurement, you attest, for your entire organization and its employees or agents, that you are not aware that any such
gift has been offered, accepted, or promised by any employees of your organization.
________________________________ ___________________
Name, Position of Company Representative Signature Date
Projects will be awarded based on cost, adherence to Informal Bid Request requirements, contractor’s ability to meet the
schedule, and contractor’s references. Contractor must be able to comply with Brunswick County Schools Terms and
Conditions (attached). The Brunswick County Board of Education has a right to reject any or all bids, pursuant to NC Statute
and Board of Education Policy, and to waive any or all informalities.
Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid
MBForms 2002-Revised July 2010
Identification of HUB Certified/ Minority Business Participation
I, ,
(Name of Bidder)
do hereby certify that on this project, we will use the following HUB Certified/ minority business as construction subcontractors, vendors, suppliers or providers of professional services. Firm Name, Address and Phone # Work Type *Minority **HUB
Category Certified (Y/N)
*Minority categories: Black, African American (B), Hispanic (H), Asian American (A) American Indian (I), Female (F) Socially and Economically Disadvantaged (D)
** HUB Certification with the state HUB Office required to be counted toward state participation goals.
The total value of minority business contracting will be ($) .
Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid
MBForms 2002-Revised July 2010
State of North Carolina AFFIDAVIT A – Listing of Good Faith Efforts
County of
(Name of Bidder)
Affidavit of I have made a good faith effort to comply under the following areas checked:
Bidders must earn at least 50 points from the good faith efforts listed for their bid to be considered responsive. (1 NC Administrative Code 30 I.0101)
❑ 1 – (10 pts) Contacted minority businesses that reasonably could have been expected to submit a quote and that were known to the contractor, or available on State or local government maintained lists, at least 10 days before the bid date and notified them of the nature and scope of the work to be performed.
❑ 2 --(10 pts) Made the construction plans, specifications and requirements available for review by prospective minority businesses, or providing these documents to them at least 10 days before the bids are due.
❑ 3 – (15 pts) Broken down or combined elements of work into economically feasible units to facilitate minority participation.
❑ 4 – (10 pts) Worked with minority trade, community, or contractor organizations identified by the Office of Historically Underutilized Businesses and included in the bid documents that provide assistance in recruitment of minority businesses.
❑ 5 – (10 pts) Attended prebid meetings scheduled by the public owner.
❑ 6 – (20 pts) Provided assistance in getting required bonding or insurance or provided alternatives to bonding or insurance for subcontractors.
❑ 7 – (15 pts) Negotiated in good faith with interested minority businesses and did not reject them as unqualified without sound reasons based on their capabilities. Any rejection of a minority business based on lack of qualification should have the reasons documented in writing.
❑ 8 – (25 pts) Provided assistance to an otherwise qualified minority business in need of equipment, loan capital, lines of credit, or joint pay agreements to secure loans, supplies, or letters of credit, including waiving credit that is ordinarily required. Assisted minority businesses in obtaining the same unit pricing with the bidder's suppliers in order to help minority businesses in establishing credit.
❑ 9 – (20 pts) Negotiated joint venture and partnership arrangements with minority businesses in order to increase opportunities for minority business participation on a public construction or repair project when possible.
❑ 10 - (20 pts) Provided quick pay agreements and policies to enable minority contractors and suppliers to meet cash-flow demands.
The undersigned, if apparent low bidder, will enter into a formal agreement with the firms listed in the Identification of Minority Business Participation schedule conditional upon scope of contract to be executed with the Owner. Substitution of contractors must be in accordance with GS143-128.2(d) Failure to abide by this statutory provision will constitute a breach of the contract. The undersigned hereby certifies that he or she has read the terms of the minority business commitment and is authorized to bind the bidder to the commitment herein set forth.
Date: Name of Authorized Officer:
Signature:
Title:
State of______________, County of
Subscribed and sworn to before me this day of 20
Notary Public
My commission expires
SEAL
Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid Attach to Bid
MBForms 2002-Revised July 2010
State of North Carolina --AFFIDAVIT B-- Intent to Perform Contract
with Own Workforce. County of
Affidavit of (Name of Bidder)
I hereby certify that it is our intent to perform 100% of the work required for the contract.
(Name of Project)
In making this certification, the Bidder states that the Bidder does not customarily subcontract elements of this type project, and normally performs and has the capability to perform and will perform all elements of the work on this project with his/her own current work forces; and
The Bidder agrees to provide any additional information or documentation requested by the owner in support of the above statement. The Bidder agrees to make a Good Faith Effort to utilize minority suppliers where possible. The undersigned hereby certifies that he or she has read this certification and is authorized to bind the Bidder to the commitments herein contained. Date: Name of Authorized Officer: Signature: Title: State of _________ __ , County of ________________________
Subscribed and sworn to before me this day of 20___
Notary Public
My commission expires
SEAL
Do not submit with bid Do not submit with bid Do not submit with bid Do not submit with bid
MBForms 2002-Revised July 2010
State of North Carolina - AFFIDAVIT C - Portion of the Work to be Performed by HUB Certified/Minority Businesses County of
(Note this form is to be submitted only by the apparent lowest responsible, responsive bidder.)
If the portion of the work to be executed by HUB certified/minority businesses as defined in GS143-128.2(g) and 128.4(a),(b),(e) is equal to or greater than 10% of the bidders total contract price, then the bidder must complete this affidavit. This affidavit shall be provided by the apparent lowest responsible, responsive bidder within 72 hours after notification of being low bidder.
Affidavit of I do hereby certify that on the (Name of Bidder)
(Project Name)
Project ID# Amount of Bid $ I will expend a minimum of % of the total dollar amount of the contract with minority business enterprises. Minority businesses will be employed as construction subcontractors, vendors, suppliers or providers of professional services. Such work will be subcontracted to the following firms listed below. Attach additional sheets if required
Name and Phone Number *Minority Category
**HUB Certified
Y/N
Work Description
Dollar Value
*Minority categories: Black, African American (B), Hispanic (H), Asian American (A) American Indian (I), Female (F) Socially and Economically Disadvantaged (D)
** HUB Certification with the state HUB Office required to be counted toward state participation goals.
Pursuant to GS143-128.2(d), the undersigned will enter into a formal agreement with Minority Firms for work listed in this schedule conditional upon execution of a contract with the Owner. Failure to fulfill this commitment may constitute a breach of the contract.
The undersigned hereby certifies that he or she has read the terms of this commitment and is authorized to bind the bidder to the commitment herein set forth. Date: Name of Authorized Officer: Signature:
Title:
State of , County of
Subscribed and sworn to before me this day of 20
Notary Public
My commission expires
SEAL
Do not submit with the bid Do not submit with the bid Do not submit with the bid Do not submit with the bid Do not submit with the bid
MBForms 2002-Revised May 2010 -1-
State of North Carolina AFFIDAVIT D – Good Faith Efforts
County of
(Note this form is to be submitted only by the apparent lowest responsible, responsive bidder.)
If the goal of 10% participation by HUB Certified/ minority business is not achieved, the Bidder shall provide the following documentation to the Owner of his good faith efforts:
Affidavit of I do hereby certify that on the (Name of Bidder)
(Project Name)
Project ID# Amount of Bid $ I will expend a minimum of % of the total dollar amount of the contract with HUB certified/ minority business enterprises. Minority businesses will be employed as construction subcontractors, vendors, suppliers or providers of professional services. Such work will be subcontracted to the following firms listed below. (Attach additional sheets if required)
Name and Phone Number *Minority Category
**HUB Certified
Y/N
Work Description
Dollar Value
*Minority categories: Black, African American (B), Hispanic (H), Asian American (A) American Indian (I), Female (F) Socially and Economically Disadvantaged (D)
** HUB Certification with the state HUB Office required to be counted toward state participation goals.
Examples of documentation that may be required to demonstrate the Bidder's good faith efforts to meet the goals set forth in these provisions
include, but are not necessarily limited to, the following:
A. Copies of solicitations for quotes to at least three (3) minority business firms from the source list provided by the State for each subcontract
to be let under this contract (if 3 or more firms are shown on the source list). Each solicitation shall contain a specific description of the
work to be subcontracted, location where bid documents can be reviewed, representative of the Prime Bidder to contact, and location,
date and time when quotes must be received.
B. Copies of quotes or responses received from each firm responding to the solicitation.
C. A telephone log of follow-up calls to each firm sent a solicitation.
D. For subcontracts where a minority business firm is not considered the lowest responsible sub-bidder, copies of quotes received from all firms submitting quotes for that particular subcontract.
E. Documentation of any contacts or correspondence to minority business, community, or contractor organizations in an attempt to meet the goal.
F. Copy of pre-bid roster
G. Letter documenting efforts to provide assistance in obtaining required bonding or insurance for minority business.
H. Letter detailing reasons for rejection of minority business due to lack of qualification.
I. Letter documenting proposed assistance offered to minority business in need of equipment, loan capital, lines of credit, or joint pay
agreements to secure loans, supplies, or letter of credit, including waiving credit that is ordinarily required.
Failure to provide the documentation as listed in these provisions may result in rejection of the bid and award to the next lowest responsible
and responsive bidder.
Pursuant to GS143-128.2(d), the undersigned will enter into a formal agreement with Minority Firms for work listed in this schedule conditional upon execution of a contract with the Owner. Failure to fulfill this commitment may constitute a breach of the contract.
Do not submit with the bid Do not submit with the bid Do not submit with the bid Do not submit with the bid Do not submit with the bid
MBForms 2002-Revised May 2010 -2-
The undersigned hereby certifies that he or she has read the terms of this commitment and is authorized to bind the bidder to the commitment herein set forth.
Date: Name of Authorized Officer:
Signature:
Title: State of , County of
Subscribed and sworn to before me this day of 20
Notary Public
My commission expires
SEAL
BRUNSWICK COUNTY, NORTH CAROLINA
SOUTH BRUNSWICK HIGH SCHOOL
PARKING LOT REFURBISHMENT
FOR
SCHEDULE OF DRAWINGS
JULY 15, 2020
VICINITY MAP
G-001 . . . . . COVER SHEET
C-100 . . . . . EXISTING CONDITIONS PLAN
C-101 . . . . . SITE / GRADING AND EROSION CONTROL PLAN
C-102 . . . . . EROSION CONTROL DETAILS
C-103 . . . . . SITE DETAILS
NOT TO SCALE
P:\2020\20.07063-B
RU
NS
WIC
KC
OU
S-S
BH
S P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T\D
RA
WIN
GS
\20.07063 S
BH
S P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T IS
SU
ED
F
OR
C
ON
ST
RU
CT
IO
N.D
WG
P
LO
T D
AT
E 8/13/2020 11:53 A
M T
ON
Y M
IN
TZ
mcgillassociates.com
712 Village Road SW
Suite 103
Shallotte, NC 28470
910.755.5872
NC Firm License # C-0459
20.07063 S
OU
TH
B
RU
NS
WIC
K H
IG
H S
CH
OO
L P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T
PROJECT INFORMATION
OWNER/DEVELOPER BRUNSWICK COUNTY BOARD OF EDUCATION
35 REFERENDUM DRIVE NE
BOLIVIA, NC 28422
910.253.2900
LOCATION: 280 COUGAR DRIVE
SOUTHPORT, NC 28461
LEGAL:
PARCEL ID: 17300009
PARCEL PIN: 208912968370
ZONING: C-1
DEED BOOK/PAGE: 00276/0426
SITE SUMMARY
TOTAL SITE AREA: 2.6 ACRES
DISTURBED AREA: 2.6 ACRES
FLOOD ZONE
FIRM MAP: 3720208900J, JUNE 2, 2006
ZONE(S): X
RIVER BASIN CAPE FEAR RIVER BASIN
RECEIVING STREAM MOORE CREEK
STREAM INDEX NO. 18-86-1
CLASSIFICATION: C; Sw
DATUM VERTICAL = NAVD88
HORIZONTAL = NAD 83-2011
I
S
S
U
E
D
F
O
R
C
O
N
S
T
R
U
C
T
I
O
N
PROJECT
SITE
G
E
O
R
G
E
I
I
H
W
Y
N
C
8
7
R
I
V
E
R
R
D
.
S
E
N
C
1
3
3
C
O
U
G
A
R
R
D
.
S
U
N
N
Y
P
O
IN
T
R
D
. S
E
7/15/20
EXISTING CONDITIONS PLAN
712 Village Road SW
Suite 103
Shallotte, NC 28470
910.755.5872
NC Firm License # C-0459
mcgillassociates.com
DIVISION VALUE = FEETGRAPHIC SCALE
30 15 30 60
30
0
M. NORTON
A. LAPINSKY
T. MINTZ
A. LAPINSKY 20.07063 N/A
C-100
I
S
S
U
E
D
F
O
R
C
O
N
S
T
R
U
C
T
I
O
N
P:\2020\20.07063-B
RU
NS
WIC
KC
OU
S-S
BH
S P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T\D
RA
WIN
GS
\20.07063 S
BH
S P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T IS
SU
ED
F
OR
C
ON
ST
RU
CT
IO
N.D
WG
P
LO
T D
AT
E 8/13/2020 11:53 A
M T
ON
Y M
IN
TZ
NO. DATE BY DESCRIPTION
SHEET
OFFICE MANAGER
PROJECT MANAGER
DESIGNER
REVIEWER DATE PROJECT # FUNDING #
20.07063 S
OU
TH
B
RU
NS
WIC
K H
IG
H S
CH
OO
L P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T
SOUTHPORT, NORTH CAROLINA
PARKING LOT REFURBISHMENT
FOR
SOUTH BRUNSWICK HIGH SCHOOL
SURVEY BY: LONG SURVEYING
6609 OCEAN HIGHWAY W
OCEAN ISLE BEACH, NC 28469
(910) 754-6300
JULY 15, 2020
7/15/20
61
nnnnnnnnnnnnnnnnnnnnnnnnnn
n n n n n n n n n n n
n
n
n
n
n
n
n
n
n
1
2
3 4
56
7 8 9 10
11
1213
36.0
' M
IN.
CE
40.0'
10.5'
n n n n n n
n
n
n
n
n n n n n n n n n n n n n n n n
n
n
n n n n n
n n n n n n n n n n n n n n n n n
n
n n n
n n
n
n
n
n
n
n
n
n
n
n
n
n
n
n n
n
n
nn
HC HC HC HCHC
1 2 3 45
6 78
910
12 1314 15 16 17 18 19 20 21 22 23 24 25
26
76 75 7473 72 71 70 69 68 67 66 65 64 63 62
27
2930
31 32 33 34
3536 37 38 39 40 41
94 99 100 101 102 103 104 105
106
107
108 109 110
111
24 25 26
80 81 82 83 84 85 86 87 88 89 90 91 9293
144 143 142141 140 139 138 137 136 135 134 133
132 131 130 129 128 127 126 125 124 123 122 121
59 58 57 56 55 5453 52 51 50 49 48 47 46
45 44
20.0
'24
.0'
24.0
'
20.0
'24
.0'
27.2'
18.1'
10.0
'
28.3'
24.1
'
42
60
77
112
145
25.5'
10.0'
10.5'
10.0'
1128
43
78
79
9895 96
97
113 114 115
116
120 119 118 117
150 149 148147 146
151
SITE / GRADING AND
EROSION CONTROL PLAN
712 Village Road SW
Suite 103
Shallotte, NC 28470
910.755.5872
NC Firm License # C-0459
mcgillassociates.com
DIVISION VALUE = FEETGRAPHIC SCALE
30 15 30 60
30
0
M. NORTON
A. LAPINSKY
T. MINTZ
A. LAPINSKY 20.07063 N/A
C-101
I
S
S
U
E
D
F
O
R
C
O
N
S
T
R
U
C
T
I
O
N
P:\2020\20.07063-B
RU
NS
WIC
KC
OU
S-S
BH
S P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T\D
RA
WIN
GS
\20.07063 S
BH
S P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T IS
SU
ED
F
OR
C
ON
ST
RU
CT
IO
N.D
WG
P
LO
T D
AT
E 8/13/2020 11:53 A
M T
ON
Y M
IN
TZ
NO. DATE BY DESCRIPTION
SHEET
OFFICE MANAGER
PROJECT MANAGER
DESIGNER
REVIEWER DATE PROJECT # FUNDING #
20.07063 S
OU
TH
B
RU
NS
WIC
K H
IG
H S
CH
OO
L P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T
SOUTHPORT, NORTH CAROLINA
PARKING LOT REFURBISHMENT
FOR
SOUTH BRUNSWICK HIGH SCHOOL
EXISTING GRADE
SILT FENCE
SILT FENCE OUTLET
LIMIT OF DISTURBANCE
PARKING SPACE
NUMBER
n n n
LEGEND
TOTAL DISTURBED AREA = 2.6 ACRES
VICINITY MAP
NOT TO SCALE
GENERAL NOTES
1. The Contractor shall attend an on-site preconstruction conference with Brunswick County Schools representative(s)
and the Engineer prior to beginning work.
2. Survey data provided by Long Surveying, received June 25, 2020.
3. All work shall be performed in compliance with all applicable local, state, and federal permits, codes, regulations,
and ordinances.
4. The Contractor shall locate underground utilities within the project work area prior to beginning work. He shall be
responsible for any damage to any above-ground or below-ground properties resulting from his activities.
5. Should the Contractor determine that existing conditions/features/factors may be in conflict with the project plans, he
shall immediately contact the Engineer for direction.
6. The Contractor shall take necessary action to minimize the tracking of mud onto paved roadway(s) and/or school
parking/drive areas.
7. The Contractor, to the extent possible, shall minimize the generation of dust or other airborne particulate matter.
8. Litter, construction debris, oils, fuels, building products, and construction chemicals that could be exposed to rainfall
and/or stormwater runoff shall be prevented from becoming a pollutant source in stormwater discharges.
9. Reset existing catch basins and sewer manhole tops as needed to be flush with the finish grade of the new
pavement.
10. Grade (as necessary) and seed all existing grass islands within area of refurbished parking lot.
11. Contractor shall ensure compliance with the Geotechnical Letter by ECS Southeast, LLP titled "Geotechnical
Engineering Letter South Brunswick High School Bus Parking Lot" dated June 26, 2020 throughout all phases of
construction.
CONSTRUCTION SEQUENCE
NOTE: This sequence is provided as a guide for limiting erosion and the loss of sediment to off-site areas. It is not
intended to dictate means and/or methods for the Contractor to perform his work. The Contractor is solely responsible
for preventing eroded soils from leaving the site. He shall use his best judgment in adjusting this sequence as may be
beneficial in meeting this intended goal.
1. Obtain a copy of the NCDEQ/LQS erosion control permit. Review the permit and become familiar with its
contents/requirements.
2. Schedule an on-site pre-construction conference with the NCDEQ/LQS personnel named on the erosion control
permit. Inform Brunswick County Schools and the Engineer about the date and time of the meeting.
3. Install the temporary gravel construction entrance.
4. Install the sediment (silt) fencing along the alignments shown on the plan.
5. Remove all internal handicap signs, concrete wheel stops, and other designated features on this plan. Store all in
a safe location for reuse after paving is complete.
6. Remove the existing asphalt and base material and/or subgrade material to a depth of at least 8" below the
proposed surface grade of the parking lot. All spoil material from the existing parking lot removal shall be
transported off site immediately and disposed of in a legal manner. Waste site must have a state approved
erosion and sedimentation control plan. Spoil materials are not permitted to be stockpiled on site for any period of
time.
7. Construct the parking lot base by placing and compacting a 6" layer of compacted aggregate base course (ABC).
Refer to General Notes on this drawing.
8. Install pavement section of the parking lot. Refer to General Notes on this drawing.
9. Re-install internal signs, concrete wheel stops, and other designated features.
10. Repair asphalt under temporary construction entrance to match condition of newly installed pavement.
11. Stabilize all disturbed areas as set out in the “Grassing Notes”.
12. Inspect all erosion and sediment control practices weekly and after rainfall events. Make repairs as may be
needed.
13. After the site is stabilized, remove all temporary measures and apply permanent seeding, fertilizer, and mulching.
Water as necessary to establish a vigorous grass cover.
14. Paint crosswalk and all parking stall lines and numbers.
EROSION CONTROL AND STORMWATER NARRATIVE:
Brunswick County Schools desires to reconstruct the on-site parking lot at South Brunswick High School. The project
will entail removing the existing asphalt surface and base materials and replacing with a new base and asphalt surface.
The finished surface will have the same dimensions as the existing one and shall "occupy" the same location. No more
than 2.6 acres will be disturbed during the performance of the work.
Mandarin Fine Sand (Ma) and Leon Fine Sand (Lo) soils are the two types of soils on-site per the Natural Resources
Conservation Service's Web Soil Survey.
The primary temporary means for controlling erosion during construction will be sediment (silt) fencing, and a
construction entrance. The primary means for permanent surface stabilization will be permanent seeding to establish a
vigorous grass cover over the perimeter areas.
The current project entails removing existing BUA and installing new BUA over the same footprint as the old BUA.
This site drains to Moore Creek in the Cape Fear River Basin. The classification of Moore Creek at this location is C;Sw.
The Stream Index number is 18-86-1. No wetlands will be disturbed during the construction of this project.
SILT FENCE (TYPICAL)
PROJECT
SITE
G
E
O
R
G
E
I
I
H
W
Y
N
C
8
7
R
I
V
E
R
R
D
.
S
E
N
C
1
3
3
C
O
U
G
A
R
R
D
.
S
U
N
N
Y
P
O
IN
T
R
D
. S
E
OVERHEAD UTILITY POLE
OVERHEAD
UTILITY POLE
OVERHEAD
UTILITY POLE
ON SITE TRAFFIC FLOW
ARROW TYPICAL 34 PLACES
TEMPORARY
CONSTRUCTION ENTRANCE
NOTES:
1. FINISHED GRADE OF NEW PARKING LOT PAVEMENT
TO MATCH EXISTING PARKING LOT GRADES.
CONTRACTOR TO ENSURE POSITIVE DRAINAGE IN
ALL DIRECTIONS ACROSS PARKING LOT WITH NO
AREAS OF PONDING.
2. SILT FENCE LIMITS EQUAL LIMIT OF WORK AND
LIMIT OF DISTURBANCE
NUMBER ALL PARKING STALLS AS SHOWN ON THIS PLAN.
NUMBERS TO BE 12" TALL x 9" WIDE HIGHWAY GOTHIC
FONT WITH A MINIMUM 2" BAR OR STROKE WIDTH AND 2"
BETWEEN NUMBERS. NUMBERS TO BE CENTERED AT
THE FRONT END OF THE STALLS. ALL NUMBERS ARE TO
BE SOLID WHITE REFLECTIVE TRAFFIC PAINT.
LIMIT OF WORK AND LIMIT OF DISTURBANCE
NEATLY SAW CUT AND REMOVE EXISTING PAVEMENT AND
SUBBASE. REBUILD PARKING LOT TO SAWCUT POINT. SEAL
JOINT BETWEEN NEW AND EXISTING PAVEMENT AT THAT
POINT.
LIMIT OF WORK AND LIMIT OF
DISTURBANCE
NEATLY SAW CUT AND
REMOVE EXISTING PAVEMENT
AND SUBBASE. REBUILD
PARKING LOT ENTRANCE TO
SAWCUT POINT. SEAL JOINT
BETWEEN NEW AND EXISTING
PAVEMENT AT THAT POINT.
REMOVE EXISTING SIDEWALK, BACKFILL AND SEED
SIDEWALK AREA TO MATCH EXISTING GRASS ISLAND
SILT FENCE (TYPICAL)
SILT FENCE
OUTLET (TYP.)
5 EXISTING CONCRETE WHEEL STOPS TO BE
REMOVED AND SAFELY STORED UNTIL
CONSTRUCTION ACTIVITIES HAVE BEEN
COMPLETED. REINSTALL CONCRETE WHEEL STOPS
TO MATCH EXISTING CONDITION AFTER
CONSTRUCTION ACTIVITIES HAVE BEEN
COMPLETED.
SILT FENCE
(TYPICAL)
SILT FENCE
(TYPICAL)
5'x18' HANDICAPPED PARKING STALL AISLE
8'x18' HANDICAPPED PARKING STALL AISLE
SEAL JOINT BETWEEN NEW
ASPHALT SURFACE COURSE
AND EXISTING SIDEWALK
SINGLE WHITE SOLID LINE 4" WIDE TYPICAL ALL
PARKING STALLS UNLESS NOTED OTHERWISE
12'x58' BUS PARKING
STALL (TYP.)
9'x18' PARKING STALL
TYPICAL UNLESS NOTED
OTHERWISE
9'x18' PARKING STALL
TYPICAL UNLESS NOTED
OTHERWISE
5 EXISTING HANDICAPPED PARKING SIGNS TO BE REMOVED AND SAFELY
STORED UNTIL CONSTRUCTION ACTIVITIES HAVE BEEN COMPLETED.
REINSTALL HANDICAPPED PARKING SIGNS TO MATCH EXISTING CONDITION
AFTER CONSTRUCTION ACTIVITIES HAVE BEEN COMPLETED.
9'x18' HANDICAPPED PARKING STALL
TYPICAL 5 PLACES
9 EXISTING CONCRETE WHEEL STOPS TO BE REMOVED AND SAFELY
STORED UNTIL CONSTRUCTION ACTIVITIES HAVE BEEN COMPLETED.
REINSTALL CONCRETE WHEEL STOPS TO MATCH EXISTING CONDITION
AFTER CONSTRUCTION ACTIVITIES HAVE BEEN COMPLETED.
Know what's below.before you dig.CallR
Dial 811 or 1-800-632-4949N.C. One-Call Center
SCALE: 1' = 10'
CROSSWALK INSET
SEE "CROSSWALK INSET",
THIS SHEET
2' TYP.
2' MAX.
10' TYP.
NOTE:
PAINTED PAVEMENT MARKINGS
SHOULD BE OF TYPE AND
INSTALLATION AS REQUIRED
BY THE LATEST REVISION OF
MANUAL OF UNIFORM TRAFFIC
CONTROL DEVICES.
LIMIT OF WORK
PAVEMENT MARKINGS TO BE
PARALLEL WITH TRAVEL LANES
SOLID WHITE REFLECTIVE TRAFFIC
PAINT (TYPICAL)
LIMIT OF WORK
10
10
13
8
8
7
7
18
18
19
19
12
12
6
4
3
JULY 15, 2020
PROPERTY LINE
STOP SILT FENCE AT CORNER
OF EQUIPMENT ENCLOSURE
7/15/20
EROSION CONTROL DETAILS
712 Village Road SW
Suite 103
Shallotte, NC 28470
910.755.5872
NC Firm License # C-0459
mcgillassociates.com
NOT TO SCALE
M. NORTON
A. LAPINSKY
T. MINTZ
A. LAPINSKY JULY 15, 2020 20.07063 N/A
C-102
I
S
S
U
E
D
F
O
R
C
O
N
S
T
R
U
C
T
I
O
N
P:\2020\20.07063-B
RU
NS
WIC
KC
OU
S-S
BH
S P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T\D
RA
WIN
GS
\20.07063 S
BH
S P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T IS
SU
ED
F
OR
C
ON
ST
RU
CT
IO
N.D
WG
P
LO
T D
AT
E 8/13/2020 11:53 A
M T
ON
Y M
IN
TZ
NO. DATE BY DESCRIPTION
SHEET
OFFICE MANAGER
PROJECT MANAGER
DESIGNER
REVIEWER DATE PROJECT # FUNDING #
20.07063 S
OU
TH
B
RU
NS
WIC
K H
IG
H S
CH
OO
L P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T
SOUTHPORT, NORTH CAROLINA
PARKING LOT REFURBISHMENT
FOR
SOUTH BRUNSWICK HIGH SCHOOL
ALL EROSION AND SEDIMENT CONTROL PRACTICES SHALL BE CHECKED FOR STABILITY AND OPERATION
FOLLOWING EVERY RUNOFF PRODUCING RAINFALL BUT IN CO CASE NOT LESS THAN ONCE EVERY WEEK.
ANY NEEDED REPAIRS SHALL BE MADE IMMEDIATELY TO MAINTAIN ALL PRACTICES AS DESIGNED.
SEDIMENT SHALL BE REMOVED FROM BEHIND THE SILT FENCE WHEN IT BECOMES APPROX. 0.5 FEET
DEEP AT THE SILT FENCE. THE SILT FENCE SHALL BE REPAIRED AS NECESSARY TO MAINTAIN A
BARRIER.
ALL SEEDED AREA SHALL BE FERTILIZED, RESEED AS NECESSARY, AND MULCHED ACCORDING TO
SPECIFICATIONS IN THE SEEDING SPECIFICATION TO MAINTAIN A VIGOROUS AND DENSE VEGETATIVE
COVER.
THE CONTRACTOR SHALL MAINTAIN SELF INSPECTION REPORTS AS REQUIRED BY NCDEQ AND THE
NPDES CONSTRUCTION STORMWATER PERMIT. SELF INSPECTIONS ARE TO BE CONDUCTED AFTER EACH
PHASE OF THE PROJECT FOR THE RECORD OF THE INSTALLATION AND MAINTENANCE OF THE EROSION
CONTROL MEASURERS.
1.
5.
2.
3.
4.
MAINTENANCE PLAN
EC
45
CONTACT: CRAIG ECKERT, DIRECTOR OF CAPITAL PROJECTS & PLANNING; BRUNSWICK COUNTY SCHOOLS
ADDRESS: 35 REFERENDUM DRIVE NE
BOLIVIA, NORTH CAROLINA 28422
PHONE: (910) 252-1078 (OFFICE)
EMAIL: [email protected]
GRASSING/SEEDING/MULCHING NOTES
EC
46A
SEEDING NOTES:
1. ALL AREAS DISTURBED BY CONSTRUCTION ACTIVITIES, AS WELL AS SEVERELY ERODED AREAS, SHALL BE STABILIZED BY
ESTABLISHING A PERMANENT GRASS COVER. SEEDING MIXTURES SHALL BE SELECTED BASED ON THE SOIL TYPE PRESENT,
SEASONAL CONDITIONS, AND OTHER FACTORS AFFECTING GROWTH. THE FOLLOWING APPLICATION METHODS MAY BE USED AS
OUTLINED IN THE NCDENR EROSION AND SEDIMENT CONTROL PLANNING AND DESIGN MANUAL. IT IS RECOMMENDED, HOWEVER,
THAT A SPECIALIST BE CONSULTED AND SOILS TESTING PERFORMED TO ENSURE DESIRED RESULTS BASED ON PARTICULAR SITE
CONDITIONS.
A. CULTIVATE AREA TO A 5-INCH DEPTH.
B. APPLY 4,000 LB/ACRE GROUND AGRICULTURAL LIMESTONE (OR IN ACCORDANCE WITH SOIL TESTS).
C. APPLY 10-10-10 COMMERCIAL FERTILIZER AT 1,000 LB/ACRE (OR IN ACCORDANCE WITH SOIL TESTS).
D. MULCH WITH GRAIN STRAW AT 3,250 LB/ACRE TO 4,350 LB/ACRE.
E. ANCHOR BY TACKING WITH ASPHALT EMULSION, ROVING, NETTING, OR BY CRIMPING WITH A MULCH
ANCHORING TOOL.
2. WHEN IT IS NOT POSSIBLE TO ESTABLISH A PERMANENT GRASS COVER IN A REASONABLY SHORT PERIOD OF TIME DUE TO
CONDITIONS, A TEMPORARY GRASS COVER SHALL BE ESTABLISHED. THIS TEMPORARY COVER SHALL INCLUDE ANNUAL
GRASSES OR SMALL GRAINS, SUCH AS RYE GRASS. PERMANENT VEGETATION MUST STILL BE ESTABLISHED. MULCH MUST BE
APPLIED WHEN SEASONAL CONDITIONS DO NOT ALLOW PERMANENT OR TEMPORARY GRASS ESTABLISHMENT, BUT MUST BE
USED FOR THE SHORTEST PRACTICAL DURATION, AND NOT WHEN PERMANENT OR TEMPORARY VEGETATION METHODS MAY BE
USED. TOPSOIL SHALL BE USED WHEN NECESSARY TO ESTABLISH VEGETATIVE COVER.
3. IRRIGATE AS NECESSARY TO OPTIMIZE GROWTH.
4. SLOPES STEEPER THAN 3:1 (H:V) SHALL BE STABILIZED WITH BERMUDAGRASS SOD.
8' MAX. STANDARD STRENGTH FABRIC WITH WIRE FENCE
(MIN. 14 GAUGE 6"X6" WIRE)
6' MAX EXTRA STRENGTH FABRIC WITHOUT
WIRE FENCE
5' STEEL POST (MIN.
1.25 LB/LF)
WIRE
FENCE
PLASTIC OR
WIRE TIES
EXISTING
GRADE
EXISTING
GROUND
24"
8" DOWN & 4"
FORWARD ALONG
THE TRENCH
24"
EXISTING
GROUNDBACKFILL TRENCH
AND COMPACT
THOROUGHLY
FILTER
FABRIC
WIRE
FENCE
STEEL
POST
U
PS
LO
PE
(D
IST
U
R
BE
D
AR
EA
)
8"
MIN.
SILT FENCE
NOTES:
1. FILTER BARRIERS SHALL BE INSPECTED
IMMEDIATELY AFTER EACH RAINFALL AND
DAILY DURING PROLONGED RAINFALL.
REPAIR SHALL BE MADE AS NECESSARY.
2. FABRIC SHALL BE REPLACED PROMPTLY IF
FOUND TO BE IN DISREPAIR.
3. SEDIMENT DEPOSITS SHALL BE REMOVED
AFTER EACH STORM EVENT AND WHEN
DEPOSITS REACH APPROXIMATELY 1/3
HEIGHT OF BARRIER. SEDIMENT SHALL BE
REMOVED IN ACCORDANCE WITH THE
MINIMUM STANDARDS OF THE NORTH
CAROLINA EROSION AND SEDIMENTATION
CONTROL PLANNING AND DESIGN MANUAL.
4. REFERENCE NCDEQ LAND QUALITY SECTION
DESIGN MANUAL: 6.62.
SLOPE
<2%
2 TO 5%
5 TO 10%
10 TO 20%
>20%
SLOPE LENGTH(FT)
100
75
50
25
15
MAXIMUM AREA(SQFT)
10,000
7,500
5,000
2,500
1,500
EC
1A
4"MIN.
18" TO 24"
NOT TO SCALE
SILT FENCE - OUTLET
EC
2A
IF FOUND TO BE IN DISREPAIR.
FABRIC SHALL BE REPLACED PROMPTLY
REPAIR SHALL BE MADE AS NECESSARY.
DAILY DURING PROLONGED RAINFALL.
IMMEDIATELY AFTER EACH RAINFALL AND
FILTER BARRIERS SHALL BE INSPECTED
GROUND
POST
NOTES:
8"
4' O.C.
8'-0" MAX.
ADDITIONAL HORIZONTAL
BRACE AT OPENING
STANDARD HARDWARE
CLOTH - EXTEND 12"
BELOW GRADE
SILT FENCE OUTLET TO BE
LOCATED AT LOW POINT IN
SILT FENCE OR AS SPECIFIED
ATTACH HARDWARE CLOTH TO
POST SECURELY WITH TIES
STANDARD HARDWARE
CLOTH - EXTEND 12"
BELOW GRADE
RIP RAP FACED WITH #57
WASHED STONE - 6" THK. MIN.
12"
MA
X.
OPTIONAL 5' x 10' x 2' DEEP
SEDIMENT TRAP
EXCAVATE 8" x 12" TRENCH
UPSLOPE ALONG LINE OF POSTS.
EXTEND HARDWARE CLOTH INTO
TRENCH. BACKFILL TRENCH AND
COMPACT SOIL.
12"
1.
2.
3.
NOT TO SCALE
LOW POINTS IN CONTINUOUS RUNS OF SILT FENCE.
SILT FENCE OUTLETS SHALL BE LOCATED AT4.
SEDIMENT DEPOSITS SHALL BE REMOVED
AFTER STORM EVENT AND WHEN DEPOSITS
REACH APPROXIMATELY 1/3 HEIGHT OF
BARRIER. SEDIMENT SHALL BE REMOVED IN
ACCORDANCE WITH THE MINIMUM
STANDARDS OF THE NORTH CAROLINA
EROSION AND SEDIMENTATION CONTROL
PLANNING AND DESIGN MANUAL.
EXISTING ROAD
E
X
I
S
T
I
N
G
R
O
A
D
2
0
'
M
I
N
.
NOTES:
1. A STABILIZED PAD OF CRUSHED STONE SHALL BE LOCATED WHERE TRAFFIC WILL
BE ENTERING OR LEAVING A CONSTRUCTION SITE TO OR FROM AN EXISTING ROAD.
2. STONE TO BE 2 - 3 INCH WASHED STONE RAILROAD BALLAST.
3. THE ENTRANCE SHALL BE MAINTAINED IN A CONDITION WHICH WILL PREVENT
TRACKING OR FLOWING OF SEDIMENT ONTO PUBLIC STREETS OR EXISTING
PAVEMENT. THIS MAY REQUIRE PERIODIC TOP DRESSING WITH ADDITIONAL STONE
AS CONDITIONS DEMAND AND REPAIR AND/OR CLEANOUT OF ANY MEASURES
USED TO TRAP SEDIMENT.
4. ALL SEDIMENT SPILLED, DROPPED, WASHED OR TRACKED ONTO PUBLIC STREETS
MUST BE REMOVED IMMEDIATELY.
5. WHEN NECESSARY WHEELS MUST BE CLEANED TO REMOVE SEDIMENT PRIOR TO
ENTERING A PUBLIC STREET, WHEN WASHING IS REQUIRED, IT SHALL BE DONE ON
AN AREA STABILIZED WITH CRUSHED STONE WHICH DRAINS INTO AN APPROVED
SEDIMENT BASIN.
6. REFERENCE NCDEQ LAND QUALITY SECTION DESIGN MANUAL: 6.06.
6" HUMP TO DIVERT RUNOFF
FROM EXISTING ROAD
2"-3" COARSE AGGREGATE
(RAILROAD BALLAST)
6" HUMP TO DIVERT RUNOFF
FROM EXISTING ROAD
50' MIN.
10'
4'
36' MIN.
10' 4' 36' MIN.
6"
6"
6" MIN.
TEMPORARY CONSTRUCTION ENTRANCE
EC
24
FILTER FABRIC
FILTER FABRIC
NOT TO SCALE
7/15/20
SITE DETAILS
712 Village Road SW
Suite 103
Shallotte, NC 28470
910.755.5872
NC Firm License # C-0459
mcgillassociates.com
NOT TO SCALE
M. NORTON
A. LAPINSKY
T. MINTZ
A. LAPINSKY 20.07063 N/A
C-103
I
S
S
U
E
D
F
O
R
C
O
N
S
T
R
U
C
T
I
O
N
P:\2020\20.07063-B
RU
NS
WIC
KC
OU
S-S
BH
S P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T\D
RA
WIN
GS
\20.07063 S
BH
S P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T IS
SU
ED
F
OR
C
ON
ST
RU
CT
IO
N.D
WG
P
LO
T D
AT
E 8/13/2020 11:53 A
M T
ON
Y M
IN
TZ
NO. DATE BY DESCRIPTION
SHEET
OFFICE MANAGER
PROJECT MANAGER
DESIGNER
REVIEWER DATE PROJECT # FUNDING #
20.07063 S
OU
TH
B
RU
NS
WIC
K H
IG
H S
CH
OO
L P
AR
KIN
G LO
T R
EF
UR
BIS
HM
EN
T
SOUTHPORT, NORTH CAROLINA
PARKING LOT REFURBISHMENT
FOR
SOUTH BRUNSWICK HIGH SCHOOL
ST
8F
SUBGRADE COMPACTED TO 98% OF MAXIMUM
DRY DENSITY, STANDARD PROCTOR (ASTM D 698)
SURFACE COURSE CONSTRUCTION NOTES:
1. SURFACE COURSE SHALL BE ALLOWED TO CURE THOROUGHLY BEFORE ANY COLOR
COATINGS ARE APPLIED.
2. FLOOD SURFACE WITH WATER AND PATCH DEPRESSIONS/BIRDBATHS HOLDING MORE
THAN 1/16" WATER WITH ACRYLIC PATCHING MATERIAL PER MANUFACTURER'S
REQUIREMENTS.
SUBBASE COURSE CONSTRUCTION NOTES:
1. GRADE TO HAVE SLOPE OF 0.9% CONSTRUCTED IN ONE CONTINUOUS PLANE.
2. BASE SHALL BE PROOF ROLLED. CONTRACTOR IS RESPONSIBLE FOR CONTRACTING
WITH A 3RD PARTY PROFESSIONAL GEOTECHNICAL ENGINEER FOR SITE TESTING.
3. CONTRACTOR SHALL PROVIDE A STATEMENT SEALED BY A PROFESSIONAL
GEOTECHNICAL ENGINEER CONFIRMING THAT ALL WORK COMPLIES WITH
COMPACTION REQUIREMENTS.
GENERAL PAVEMENT CONSTRUCITON NOTES:
1. COORDINATE WITH ECS SOUTHEAST, LLP "GEOTECHNICAL ENGINEERING LETTER" FOR
SOUTH BRUNSWICK HIGH SCHOOL - BUS PARKING LOT DATED JUNE 26, 2020. FOR
PAVEMENT SECTION, DENSIFICATION, SUBGRADE PREPARATION, AND ENGINEERED
FILL PLACEMENT RECOMMENDATIONS. SHOULD A CONFLICT EXIST, NOTIFY ENGINEER
PRIOR TO CONSTRUCTION.
2. UNDERCUT ANY UNSUITABLE MATERIAL AS REQUIRED AND REPLACE WITH SELECT
MATERIAL AS DETERMINED BY LICENSED GEOTECHNICAL ENGINEER.
3. NO BASE COURSE SHALL BE PLACED ON MULCH, PINE CLAY, ORGANIC MATTER OR
OTHER UNSUITABLE MATERIAL.
4. THE PAVEMENT DESIGN SHOWN REPRESENTS THE MINIMUM THICKNESS OF SURFACE
AND BASE COURSE TO BE USED. SUBGRADE SOILS TESTS MAY DETERMINE HEAVIER
PAVEMENT DESIGNS ARE REQUIRED.
5. ALL MATERIALS SHALL MEET THE REQUIREMENTS SET FORTH IN THE LATEST EDITION
OF THE N.C. STANDARD SPECIFICATIONS FOR ROADS AND STRUCTURES.
6. CONTRACTOR SHALL NOTIFY ENGINEER IF SATURATED SUBGRADE IS ENCOUNTERED
DURING CONSTRUCTION AS ADDITIONAL DRAINAGE MEASURES MAY BE REQUIRED.
PARKING LOT
PAVEMENT SECTION
2'-0"
1'-9"
3'-9"
1'-0"
ON SITE TRAFFIC FLOW
ARROW DETAIL
NOT TO SCALE
NOTE:ALL TRAFFIC FLOW ARROWS ARE SOLID WHITEREFLECTIVE TRAFFIC PAINT AS PER DIMENSIONS SHOWN.
6" AGGREGATE BASE COURSE (ABC) COMPACTED TO 98% OF
MAXIMUM DRY DENSITY, MODIFIED PROCTOR (ASTM D 1557)
MAXIMUM 2% IN ANY
PAINTED STRIPES
PARKING SPACE TO SLOPE
18'
4' WIDE BLUE
HC
DIRECTION
GENERAL NOTES:
1. REGARDLESS OF AGE, ALL ACCESSIBLE SPACES SHALL BE IDENTIFIED BYABOVE- GROUND SIGNS ONLY. (SEE N.C.G.S.)
2. NEW SPACES SHALL NOT USE GROUND-PAINTED SYMBOLS.
9'
1REVISED FOR THIS PROJECT
NOT TO SCALE
STRIPING DETAIL FOR
HANDICAP PARKING STALLS
9'
HC
ST
SEE SITE/GRADING ANDEROSION CONTROL PLANSHEET C-101
STRIPES AT 45°AND 24" ONCENTER
EXISTING HANDICAP PARKINGSIGNS TO BE REINSTALLED
PAINT STRIPEEXISTING CONCRETE WHEELSTOPS TO BE REINSTALLED
HANDICAP PARKING SIGN REINSTALLATION DETAIL
5
NOT TO SCALE
ST
2" ASPHALT SURFACE COURSE S9.5B (PLACE SURFACE
COURSE IN 1" LIFTS. APPLY TACK COAT TO FIRST LIFT
IMMEDIATELY PRIOR TO PLACING SECOND LIFT.)
JULY 15, 2020
7/15/20
SBHS Bus Parking Lot June 26, 2020 ECS Project No. 22:29243 Page 1
June 26, 2020
Mr. Alex D. Lapinsky, P.E. McGill Associates, PA 712 Village Road SW, Suite 103 Shallotte, NC 28470
ECS Project No. 22:29243 Reference: Geotechnical Engineering Letter
South Brunswick High School Bus Parking Lot 280 Cougar Road Southport, Brunswick County, North Carolina
Dear Mr. Lapinsky: Project Description: The proposed project consists of replacing the existing South Brunswick High School Bus Parking lot in Southport, Brunswick County, North Carolina. Based on available overhead imagery it appears that the parking lot is over 20 years old (the design life of asphalt) and is experiencing failures consisting of longitudinal cracking, transverse cracking, fatigue cracking and potholes. Exploration Description: Four (4) hand auger borings with asphalt cores and Kessler Dynamic Cone Penetrometer (DCP) tests were performed in the area of the existing parking lot. The Kessler DCP was continuously driven approximately 2 to 3 feet below the existing ground surface. The Kessler DCP is driven into the soil by dropping a Single-Mass 17.6 lb Hammer from a height of 22.6 inches. The depth of cone penetration is measured at selected penetration or hammer drop intervals and the soil shear strength is reported in terms of the Kessler DCP index. The Kessler DCP index is based on the average penetration depth resulting from one blow of the 17.6 lb hammer. The test locations are shown on the attached exploration diagram. The Kessler DCP index can be correlated to CBR and modulus of rigidity. The individual results of the Kessler DCP tests are attached to this letter. The approximate test locations are attached in Appendix A. Subsurface Description: The hand auger borings encountered asphalt ranging from approximately 1.5 to 3.5 inches, underlain by ABC stone with a thickness of approximately 4.5 to 8 inches. However, no ABC stone was encountered in borings K-2 and K-3. The subgrade soils generally consisted of silty and clean SAND (SM, SP). The hand auger boring logs are attached in Appendix B.
SBHS Bus Parking Lot June 26, 2020 ECS Project No. 22:29243 Page 2 Groundwater Observations: At the time of the exploration, groundwater was encountered at depths ranging from approximately 2 to 3 feet. The highest groundwater observations are normally encountered in the late winter and early spring. Variations in the long-term water table may occur as a result of changes in precipitation, evaporation, surface water runoff, construction activities, and other factors not immediately apparent at the time of this exploration. If long term water levels are crucial to the development of this site, it would be prudent to verify water levels with the use of perforated pipes or piezometers. Pavement Design Considerations: Based on the results of our hand auger borings, it appears that the soils that will likely be exposed as pavement subgrades generally consist of SANDS (SM, SP). Based on the Kessler DCP test results, a CBR value of 10 has been used to model the in place subgrade soils. The pavement design assumes that the subgrades consist of suitable materials evaluated by ECS and placed and compacted to at least 98 percent of the maximum dry density as determined by the Standard Proctor test (ASTM D 698) in accordance with the project specifications. For the design and construction of flexible impervious pavements, the subgrades should be prepared in strict accordance with the recommendations in the “Subgrade Preparation” and “Engineered Fill Placement” sections of this report. An important consideration with the design and construction of pavements is surface and subsurface drainage. Where standing water develops, either on the pavement surface or within the base course layer, softening of the subgrade and other problems related to the deterioration of the pavement can be expected. Furthermore, good drainage should minimize the possibility of the subgrade materials becoming saturated during the normal service period of the pavement. Traffic loading conditions were not available at the time of this proposal. Based on similar projects, a traffic load of 25,000 ESALs was assumed. ECS understands that the existing asphalt will likely be ground onsite and will likely not be hauled off. If the ground asphalt is to be reused, it is recommended that it is mixed in with the existing subgrade material. After the subgrade is proofrolled, it is recommended that the pavement section is constructed and consists of at least 2 inches of surface material underlain by 6 inches of compacted aggregate base course. Subgrade Preparation: The subgrade preparation should consist of stripping vegetation, rootmat, topsoil, existing fill, and any other soft or unsuitable materials from the 5-foot expanded pavement areas. ECS should be called to verify that topsoil and unsuitable surficial materials have been completely removed prior to the placement of structural fill or construction of the parking lot.
SBHS Bus Parking Lot June 26, 2020 ECS Project No. 22:29243 Page 3 After removing unsuitable surface materials, cutting to the proposed grade, and prior to the placement of any structural fill or other construction materials, the exposed subgrade should be examined by the geotechnical engineer or authorized representative. The exposed subgrade should be proofrolled with previously approved construction equipment having a minimum axle load of 10 tons (e.g. vibratory steel drum roller). The areas subject to proofrolling should be traversed by the equipment in two perpendicular (orthogonal) directions with overlapping passes of the vehicle under the observation of the geotechnical engineer or authorized representative. This procedure is intended to assist in identifying any localized yielding materials. In the event that unstable or “pumping” subgrade is identified by the proofrolling, those areas should be marked for repair prior to the placement of any subsequent structural fill or other construction materials. Methods of repair of unstable subgrade, such as undercutting or moisture conditioning, should be discussed with the geotechnical engineer to determine the appropriate procedure with regard to the existing conditions causing the instability. Test pits may be excavated to explore the shallow subsurface materials in the area of the instability to help in determined the cause of the observed unstable materials and to assist in the evaluation of the appropriate remedial action to stabilize the subgrade. Engineered Fill Placement: Prior to placement of structural fill, representative bulk samples (about 50 pounds) of on-site and off-site borrow should be submitted to ECS for laboratory testing, which will include Atterberg limits, natural moisture content, grain-size distribution, and moisture-density relationships for compaction. Import materials should be tested prior to being hauled to the site to determine if they meet project specifications. Materials satisfactory for use as structural fill should consist of inorganic soils classified as SM, SC, SW, SP, GW, GP, GM, and GC, or a combination of these group symbols, per ASTM D 2487. Natural fine-grained soils classified as clays or silts (CL, ML) should not be considered for use as engineered fill, but may be evaluated by the geotechnical engineer to determine their suitability at the contractor’s request. The materials should be free of organic matter, debris, and should contain no particle sizes greater than 4 inches in the largest dimension. Open graded materials, such as gravels (GP), which contain void space in their mass should not be used in structural fills unless properly encapsulated with filter fabric. Suitable structural fill material should have the index properties shown below.
Structural Fill Index Properties
Location with Respect to Final Grade Liquid Limit Plasticity Index
Max % Fines Passing # 200 Sieve
Pavement Area 35 max 9 max 20
Materials that should not be used as engineered fill include topsoil, organic materials (OH, OL), and high plasticity clays and silts (CH, MH). Such materials removed during grading operations should be either stockpiled for later use in landscape fills, or placed in approved on or off-site disposal areas.
SBHS Bus Parking Lot June 26, 2020 ECS Project No. 22:29243 Page 4 Structural Fill Compaction: Structural fill within the expanded pavement limits should be placed in maximum 8-inch loose lifts, moisture conditioned as necessary to within -3 and +3 % of the soil’s optimum moisture content, and be compacted with suitable equipment to a dry density of at least 98% of the Standard Proctor maximum dry density (ASTM D698). Beyond these areas, compaction of at least 95% should be achieved. ECS should be called to document that proper fill compaction has been achieved. Fill Compaction Control: The expanded limits of the proposed construction areas should be well defined, including the limits of the fill zones for the proposed construction area, at the time of fill placement. Grade controls should be maintained throughout the filling operations. Filling operations should be observed on a full-time basis by a qualified representative of the geotechnical engineer or construction testing laboratory to determine that the minimum compaction requirements are being achieved. Field density testing of fills should be performed at the frequencies shown in the table below but not less than 1 test per lift.
Frequency of Compaction Tests in Fill Areas Location Frequency of Tests
Pavement Area 1 test per 5,000 sq. ft. Compaction equipment suitable to the soil type being compacted should be used to compact the subgrades and fill materials. A vibratory steel drum roller should be used for compaction of coarse-grained soils (Sands and Gravels) as well as for sealing compacted surfaces. Fill materials should not be placed on frozen soils, on frost-heaved soils, and/or on excessively wet soils. Borrow fill materials should not contain frozen materials at the time of placement, and frozen or frost-heaved soils should be removed prior to placement of structural fill or other fill soils and aggregates. Excessively wet soils or aggregates should be scarified, aerated, and moisture conditioned.
At the end of each work day, fill areas should be graded to facilitate drainage of any precipitation and the surface should be sealed by use of a smooth-drum roller to limit infiltration of surface water. Drying and compaction of wet soils is typically difficult during the cold, winter months. Accordingly, earthwork should be performed during the warmer, drier times of the year, if practical. Proper drainage should be maintained during the earthwork phases of construction to prevent ponding of water which has a tendency to degrade subgrade soils. Fill material should be placed in horizontal lifts. In confined areas such as utility trenches, portable compaction equipment and thin lifts of 3 inches to 4 inches may be required to achieve specified degrees of compaction.
SBHS Bus Parking Lot June 26, 2020 ECS Project No. 22:29243 Page 5 We recommend that the grading contractor have equipment on site during earthwork for both drying and wetting fill soils. We do not anticipate significant problems in controlling moisture within the fill during dry weather, but moisture control may be difficult during winter months or extended periods of rain. The control of moisture content of higher plasticity soils is difficult when these soils become wet. Further, such soils are easily degraded by construction traffic when the moisture content is elevated. Closure: ECS has prepared this report of findings, evaluations, and recommendations to guide geotechnical-related design and construction aspects of the project. The description of the proposed project is based on information provided by McGill Associates, PA. If any of this information is inaccurate, either due to our interpretation of the documents provided or site or design changes that may occur later, ECS should be contacted immediately so that we can review the report in light of the changes and provide additional or alternate recommendations as may be required to reflect the proposed construction. It has been our pleasure to be of service to McGill Associates, PA during the design phase of this project. We would appreciate the opportunity to remain involved during the continuation of the design phase, and we would like to provide our services during construction phase operations as well to verify the assumptions of subsurface conditions made for this report. Should you have any questions concerning the information contained in this report, or if we can be of further assistance to you, please contact us. Respectfully submitted, ECS Southeast, LLP
Mike Delaney, E.I. Winslow Goins, PE Project Manager Principal Engineer [email protected] [email protected]
6/26/20
APPENDIX A – Drawings & Reports
Site Location Diagram Exploration Location Diagram
6/25/2020
Service Layer Credits: Source: Esri, Maxar, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA,
²
ENGINEER
SCALE
22:292431 OF 1
PROJECT NO.
SHEET
DATE
WEG
MCGILL ASSOCIATES
SOUTH BRUNSWICK HIGH SCHOOL PARKING LOT280 COUGAR ROAD, SOUTHPORT, NORTH CAROLINA
Site Location Diagram0 1,200600
Feet
1 " = 600 '
K-1
K-2
K-3
K-4
6/25/2020
Service Layer Credits: Source: Esri, Maxar, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA,
²
ENGINEER
SCALE
22:292431 OF 1
PROJECT NO.
SHEET
DATE
WEG
LegendApproximate boring locations - Kessler DCP/Hand Augers
MCGILL ASSOCIATES
SOUTH BRUNSWICK HIGH SCHOOL PARKING LOT280 COUGAR ROAD, SOUTHPORT, NORTH CAROLINA
Exploration Location Diagram0 300150
Feet
1 " = 150 '
APPENDIX B – Field Operations
USCS Reference Notes Hand Auger Boring LogsKessler DCP Results
UNIFIED SOIL
CLASSIFICATION
SYSTEM
Unified Soil Classification System
(ASTM Designation D-2487)
Major Division Group Symbol
GW
GP
GM
GC
SW
SP
SM
SC
ML
CL
OL
MH
CH
OH
Pt
Typical Names
Well-graded gravels and gravel-
sand mixtures, little or no fines
Poorly graded gravels and gravel-
sand mixtures, little or no fines
Silty gravels, gravel-sand-silt
mixtures
Clayey gravels, gravel-sand-clay
mixtures
Well-graded sands and gravelly
sands, little or no fines
Poorly graded sands and gravelly
sands, little or no fines
Silty sands, sand-silt mixtures
Clayey sands, sand-clay mixtures
Inorganic silts, very fine sands,
rock flour, silty or clayey fine
sands
Inorganic clays of low to medium
plasticity, gravelly clays, sandy
clays, silty clays, lean clays
Organic silts and organic silty
clays of low plasticity
Inorganic silts, micaceous or
diatomaceous fine sands or silts,
elastic silts
Inorganic clays of high plasticitiy,
fat clays
Organic clays of medium to high
plasticity
Peat, muck and other highly
organic soils
Classification Criteria
Cu = D60/D10 Greater than 4
Cz = (D30)2/(D10xD60) Between 1 and 3
Not meeting both criteria for GW
Atterberg limits plot below “A” line or
plasticity index less than 4
Atterberg limits plot above “A” line
and plasticity index greater than 7
Cu = D60/D10 Greater than 6
Cz = (D30)2/(D10xD60) Between 1 and 3
Not meeting both criteria for SW
Atterberg limits plot below “A” line or
plasticity index less than 4
Atterberg limits plot above “A” line
and plasticity index greater than 7
Highly organic soils
Co
arse
-gra
ined
soil
s
Mo
re t
han
50%
ret
ained
on N
o.
20
0 s
ieve
Fin
e-g
rain
ed s
oil
s
50%
or
mo
re p
assi
ng N
o.
20
0 s
ieve
San
ds
Mo
re t
han
50
% o
f co
arse
frac
tio
n p
asse
s N
o. 4
sie
ve
Gra
vel
s
Mo
re t
han
50
% o
f co
arse
frac
tio
n r
etai
ned
on
No
. 4
sie
ve
Sil
ts a
nd
Cla
ys
Liq
uid
lim
it
gre
ater
th
an 5
0%
Sil
ts a
nd
Cla
ys
Liq
uid
lim
it
50
% o
r le
ss
Cla
ssif
icat
ion o
n b
asis
of
per
centa
ge
of
fines
GW
, G
P,
SW
, S
P
GM
, G
C,
SM
, S
C
Bo
rder
lin
e cl
assi
fica
tio
n
req
uir
ing
use
of
du
al s
ym
bo
l
Les
s th
an 5
% P
ass
No
. 2
00
sie
ve
Mo
re t
han
12
% P
ass
No
. 2
00
sie
ve
5%
to
12
% P
ass
No
. 2
00
sie
ve
Fibrous organic matter; will
char, burn, or glow
Plasticity chart for the classification of fine-grained soils.
Tests made on fraction finer than No. 40 sieve
Note: U-line represents approximate upper limit of LL and PI combinations
for natural soils (empircally determined). ASTM-D2487.
0
1
2
3
4
5
6
Asphalt Thickness [3.5"]
ABC Stone Thickness [8"]
(SM) SILTY FINE-MEDIUM SAND, brown,moist to saturated
END OF BORING @ 4.0'
CLIENT
McGill Associates
Job #:
22:29243
BORING #
K-1
SHEET
PROJECT NAME
South Brunswick High School - Parking LotEvaluation
ARCHITECT-ENGINEER
Alex D. Lapinsky, P.E.SITE LOCATION
280 Cougar Road, Southport, NCNORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL 3.0 WS WD BORING STARTED 6/25/20 CAVE IN DEPTH
WL(SHW) WL(ACR) BORING COMPLETED 6/25/20 HAMMER TYPE
WL RIG Hand Auger FOREMAN DRILLING METHOD Hand AugerDRILLING METHOD Hand Auger
DE
PT
H (
FT
)
SA
MP
LE
NO
.
SA
MP
LE
TY
PE
SA
MP
LE
DIS
T. (I
N)
RE
CO
VE
RY
(IN
)
SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WA
TE
R L
EV
ELS
ELE
VA
TIO
N (
FT
)
BLO
WS
/6"
10 20 30 40 50+
20% 40% 60% 80% 100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTICLIMIT %
WATERCONTENT %
LIQUIDLIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD% REC.%
STANDARD PENETRATIONBLOWS/FT
1 OF 1
DCP TEST DATA
Project: South Brunswick High School Date: 25-Jun-20
Location: K-1 Soil Type(s): SAND (SM)
No. of Cumulative Type of
Blows Penetration Hammer
(mm)
0 0 1
5 56 1
5 81 1
5 99 1
5 124 1
5 137 1
5 152 1
5 170 1
5 191 1
5 211 1
5 229 1
5 246 1
5 264 1
5 284 1
5 307 1
5 328 1
5 345 1
5 366 1
5 381 1
5 399 1
5 417 1
5 434 1
5 455 1
5 475 1
5 493 1
5 511 1
5 531 1
5 554 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
0
5
10
15
20
25
30
35
40
0.1 1.0 10.0 100.0
0
127
254
381
508
635
762
889
1016
0.1 1.0 10.0 100.0
DE
PT
H, in
.CBR
DE
PT
H, m
m
10.1 lbs.17.6 lbs.Both hammers used
Soil TypeCHCLAll other soils
Hammer
0
127
254
381
508
635
762
889
1016
0 14 28 42 56 69 83
0
5
10
15
20
25
30
35
40
0 2000 4000 6000 8000 10000 12000
DE
PT
H, m
m
BEARING CAPACITY, psi
DE
PT
H, in
BEARING CAPACITY, psf
Based on approximate interrelationshipsof CBR and Bearing values (Design ofConcrete Airport Pavement, Portland
Cement Association, page 8, 1955)
0
1
2
3
4
5
6
Asphalt Thickness [2.75"]
(SM) SILTY FINE-MEDIUM SAND, tan/brown,moist to saturated
END OF BORING @ 4.0'
CLIENT
McGill Associates
Job #:
22:29243
BORING #
K-2
SHEET
PROJECT NAME
South Brunswick High School - Parking LotEvaluation
ARCHITECT-ENGINEER
Alex D. Lapinsky, P.E.SITE LOCATION
280 Cougar Road, Southport, NCNORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL 2.0 WS WD BORING STARTED 6/25/20 CAVE IN DEPTH
WL(SHW) WL(ACR) BORING COMPLETED 6/25/20 HAMMER TYPE
WL RIG Hand Auger FOREMAN DRILLING METHOD Hand AugerDRILLING METHOD Hand Auger
DE
PT
H (
FT
)
SA
MP
LE
NO
.
SA
MP
LE
TY
PE
SA
MP
LE
DIS
T. (I
N)
RE
CO
VE
RY
(IN
)
SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WA
TE
R L
EV
ELS
ELE
VA
TIO
N (
FT
)
BLO
WS
/6"
10 20 30 40 50+
20% 40% 60% 80% 100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTICLIMIT %
WATERCONTENT %
LIQUIDLIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD% REC.%
STANDARD PENETRATIONBLOWS/FT
1 OF 1
DCP TEST DATA
Project: South Brunswick High School Date: 25-Jun-20
Location: K-2 Soil Type(s): SAND (SM)
No. of Cumulative Type of
Blows Penetration Hammer
(mm)
0 0 1
5 48 1
5 76 1
5 94 1
5 122 1
5 150 1
5 173 1
5 196 1
5 216 1
5 236 1
5 257 1
5 279 1
5 297 1
5 315 1
5 335 1
5 381 1
5 399 1
5 419 1
5 445 1
5 470 1
5 503 1
5 533 1
5 561 1
5 592 1
5 627 1
5 660 1
5 699 1
5 737 1
5 775 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
0
5
10
15
20
25
30
35
40
0.1 1.0 10.0 100.0
0
127
254
381
508
635
762
889
1016
0.1 1.0 10.0 100.0
DE
PT
H, in
.CBR
DE
PT
H, m
m
10.1 lbs.17.6 lbs.Both hammers used
Soil TypeCHCLAll other soils
Hammer
0
127
254
381
508
635
762
889
1016
0 14 28 42 56 69 83
0
5
10
15
20
25
30
35
40
0 2000 4000 6000 8000 10000 12000
DE
PT
H, m
m
BEARING CAPACITY, psi
DE
PT
H, in
BEARING CAPACITY, psf
Based on approximate interrelationshipsof CBR and Bearing values (Design ofConcrete Airport Pavement, Portland
Cement Association, page 8, 1955)
0
1
2
3
4
5
6
Asphalt Thickness [1.5"]
(SM) SILTY FINE-MEDIUM SAND, brown,moist to saturated
END OF BORING @ 4.0'
CLIENT
McGill Associates
Job #:
22:29243
BORING #
K-3
SHEET
PROJECT NAME
South Brunswick High School - Parking LotEvaluation
ARCHITECT-ENGINEER
Alex D. Lapinsky, P.E.SITE LOCATION
280 Cougar Road, Southport, NCNORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL 3.0 WS WD BORING STARTED 6/25/20 CAVE IN DEPTH
WL(SHW) WL(ACR) BORING COMPLETED 6/25/20 HAMMER TYPE
WL RIG Hand Auger FOREMAN DRILLING METHOD Hand AugerDRILLING METHOD Hand Auger
DE
PT
H (
FT
)
SA
MP
LE
NO
.
SA
MP
LE
TY
PE
SA
MP
LE
DIS
T. (I
N)
RE
CO
VE
RY
(IN
)
SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WA
TE
R L
EV
ELS
ELE
VA
TIO
N (
FT
)
BLO
WS
/6"
10 20 30 40 50+
20% 40% 60% 80% 100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTICLIMIT %
WATERCONTENT %
LIQUIDLIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD% REC.%
STANDARD PENETRATIONBLOWS/FT
1 OF 1
DCP TEST DATA
Project: South Brunswick High School Date: 25-Jun-20
Location: K-3 Soil Type(s): SAND (SM)
No. of Cumulative Type of
Blows Penetration Hammer
(mm)
0 0 1
5 61 1
5 91 1
5 122 1
5 152 1
5 180 1
5 208 1
5 236 1
5 259 1
5 282 1
5 307 1
5 328 1
5 351 1
5 371 1
5 391 1
5 409 1
5 427 1
5 445 1
5 460 1
5 478 1
5 495 1
5 516 1
5 533 1
5 556 1
5 572 1
5 592 1
5 615 1
5 640 1
5 668 1
5 699 1
5 729 1
5 767 1
5 795 1
5 826 1
1
1
1
1
1
1
1
1
1
0
5
10
15
20
25
30
35
40
0.1 1.0 10.0 100.0
0
127
254
381
508
635
762
889
1016
0.1 1.0 10.0 100.0
DE
PT
H, in
.CBR
DE
PT
H, m
m
10.1 lbs.17.6 lbs.Both hammers used
Soil TypeCHCLAll other soils
Hammer
0
127
254
381
508
635
762
889
1016
0 14 28 42 56 69 83
0
5
10
15
20
25
30
35
40
0 2000 4000 6000 8000 10000 12000
DE
PT
H, m
m
BEARING CAPACITY, psi
DE
PT
H, in
BEARING CAPACITY, psf
Based on approximate interrelationshipsof CBR and Bearing values (Design ofConcrete Airport Pavement, Portland
Cement Association, page 8, 1955)
0
1
2
3
4
5
6
Asphalt Thickness [1.5"]
ABC Stone Thickness [4.5"]
(SM) SILTY FINE-MEDIUM SAND, dark brown,moist to saturated
END OF BORING @ 4.0'
CLIENT
McGill Associates
Job #:
22:29243
BORING #
K-4
SHEET
PROJECT NAME
South Brunswick High School - Parking LotEvaluation
ARCHITECT-ENGINEER
Alex D. Lapinsky, P.E.SITE LOCATION
280 Cougar Road, Southport, NCNORTHING EASTING STATION
THE STRATIFICATION LINES REPRESENT THE APPROXIMATE BOUNDARY LINES BETWEEN SOIL TYPES. IN-SITU THE TRANSITION MAY BE GRADUAL.
WL 2.0 WS WD BORING STARTED 6/25/20 CAVE IN DEPTH 2.0
WL(SHW) WL(ACR) BORING COMPLETED 6/25/20 HAMMER TYPE
WL RIG Hand Auger FOREMAN DRILLING METHOD Hand AugerDRILLING METHOD Hand Auger
DE
PT
H (
FT
)
SA
MP
LE
NO
.
SA
MP
LE
TY
PE
SA
MP
LE
DIS
T. (I
N)
RE
CO
VE
RY
(IN
)
SURFACE ELEVATION
DESCRIPTION OF MATERIAL
WA
TE
R L
EV
ELS
ELE
VA
TIO
N (
FT
)
BLO
WS
/6"
10 20 30 40 50+
20% 40% 60% 80% 100%
1 2 3 4 5+
ENGLISH UNITS
BOTTOM OF CASING LOSS OF CIRCULATION
CALIBRATED PENETROMETER TONS/FT2
PLASTICLIMIT %
WATERCONTENT %
LIQUIDLIMIT %
ROCK QUALITY DESIGNATION & RECOVERY
RQD% REC.%
STANDARD PENETRATIONBLOWS/FT
1 OF 1
DCP TEST DATA
Project: South Brunswick High School Date: 25-Jun-20
Location: K-4 Soil Type(s): SAND (SM)
No. of Cumulative Type of
Blows Penetration Hammer
(mm)
0 0 1
5 25 1
5 33 1
5 43 1
5 56 1
5 76 1
5 99 1
5 135 1
5 183 1
5 226 1
5 272 1
5 323 1
5 391 1
5 472 1
5 612 1
5 691 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
0
5
10
15
20
25
30
35
40
0.1 1.0 10.0 100.0
0
127
254
381
508
635
762
889
1016
0.1 1.0 10.0 100.0
DE
PT
H, in
.CBR
DE
PT
H, m
m
10.1 lbs.17.6 lbs.Both hammers used
Soil TypeCHCLAll other soils
Hammer
0
127
254
381
508
635
762
889
1016
0 14 28 42 56 69 83
0
5
10
15
20
25
30
35
40
0 2000 4000 6000 8000 10000 12000
DE
PT
H, m
m
BEARING CAPACITY, psi
DE
PT
H, in
BEARING CAPACITY, psf
Based on approximate interrelationshipsof CBR and Bearing values (Design ofConcrete Airport Pavement, Portland
Cement Association, page 8, 1955)
APPENDIX C – Supplemental Report Documents GBA Document
Geotechnical-Engineering ReportImportant Information about This
Subsurface problems are a principal cause of construction delays, cost overruns, claims, and disputes.
While you cannot eliminate all such risks, you can manage them. The following information is provided to help.
The Geoprofessional Business Association (GBA) has prepared this advisory to help you – assumedly a client representative – interpret and apply this geotechnical-engineering report as effectively as possible. In that way, clients can benefit from a lowered exposure to the subsurface problems that, for decades, have been a principal cause of construction delays, cost overruns, claims, and disputes. If you have questions or want more information about any of the issues discussed below, contact your GBA-member geotechnical engineer. Active involvement in the Geoprofessional Business Association exposes geotechnical engineers to a wide array of risk-confrontation techniques that can be of genuine benefit for everyone involved with a construction project.
Geotechnical-Engineering Services Are Performed for Specific Purposes, Persons, and ProjectsGeotechnical engineers structure their services to meet the specific needs of their clients. A geotechnical-engineering study conducted for a given civil engineer will not likely meet the needs of a civil-works constructor or even a different civil engineer. Because each geotechnical-engineering study is unique, each geotechnical-engineering report is unique, prepared solely for the client. Those who rely on a geotechnical-engineering report prepared for a different client can be seriously misled. No one except authorized client representatives should rely on this geotechnical-engineering report without first conferring with the geotechnical engineer who prepared it. And no one – not even you – should apply this report for any purpose or project except the one originally contemplated.
Read this Report in FullCostly problems have occurred because those relying on a geotechnical-engineering report did not read it in its entirety. Do not rely on an executive summary. Do not read selected elements only. Read this report in full.
You Need to Inform Your Geotechnical Engineer about ChangeYour geotechnical engineer considered unique, project-specific factors when designing the study behind this report and developing the confirmation-dependent recommendations the report conveys. A few typical factors include: • the client’s goals, objectives, budget, schedule, and risk-management preferences; • the general nature of the structure involved, its size, configuration, and performance criteria; • the structure’s location and orientation on the site; and • other planned or existing site improvements, such as retaining walls, access roads, parking lots, and underground utilities.
Typical changes that could erode the reliability of this report include those that affect:• the site’s size or shape;• the function of the proposed structure, as when it’s changed from a parking garage to an office building, or from a light-industrial plant to a refrigerated warehouse;• the elevation, configuration, location, orientation, or weight of the proposed structure;• the composition of the design team; or• project ownership.
As a general rule, always inform your geotechnical engineer of project changes – even minor ones – and request an assessment of their impact. The geotechnical engineer who prepared this report cannot accept responsibility or liability for problems that arise because the geotechnical engineer was not informed about developments the engineer otherwise would have considered.
This Report May Not Be ReliableDo not rely on this report if your geotechnical engineer prepared it:• for a different client;• for a different project;• for a different site (that may or may not include all or a portion of the original site); or • before important events occurred at the site or adjacent to it; e.g., man-made events like construction or environmental remediation, or natural events like floods, droughts, earthquakes, or groundwater fluctuations.
Note, too, that it could be unwise to rely on a geotechnical-engineering report whose reliability may have been affected by the passage of time, because of factors like changed subsurface conditions; new or modified codes, standards, or regulations; or new techniques or tools. If your geotechnical engineer has not indicated an “apply-by” date on the report, ask what it should be, and, in general, if you are the least bit uncertain about the continued reliability of this report, contact your geotechnical engineer before applying it. A minor amount of additional testing or analysis – if any is required at all – could prevent major problems.
Most of the “Findings” Related in This Report Are Professional OpinionsBefore construction begins, geotechnical engineers explore a site’s subsurface through various sampling and testing procedures. Geotechnical engineers can observe actual subsurface conditions only at those specific locations where sampling and testing were performed. The data derived from that sampling and testing were reviewed by your geotechnical engineer, who then applied professional judgment to form opinions about subsurface conditions throughout the site. Actual sitewide-subsurface conditions may differ – maybe significantly – from those indicated in this report. Confront that risk by retaining your geotechnical engineer to serve on the design team from project start to project finish, so the individual can provide informed guidance quickly, whenever needed.
This Report’s Recommendations Are Confirmation-DependentThe recommendations included in this report – including any options or alternatives – are confirmation-dependent. In other words, they are not final, because the geotechnical engineer who developed them relied heavily on judgment and opinion to do so. Your geotechnical engineer can finalize the recommendations only after observing actual subsurface conditions revealed during construction. If through observation your geotechnical engineer confirms that the conditions assumed to exist actually do exist, the recommendations can be relied upon, assuming no other changes have occurred. The geotechnical engineer who prepared this report cannot assume responsibility or liability for confirmation-dependent recommendations if you fail to retain that engineer to perform construction observation.
This Report Could Be MisinterpretedOther design professionals’ misinterpretation of geotechnical-engineering reports has resulted in costly problems. Confront that risk by having your geotechnical engineer serve as a full-time member of the design team, to: • confer with other design-team members, • help develop specifications, • review pertinent elements of other design professionals’ plans and specifications, and • be on hand quickly whenever geotechnical-engineering guidance is needed. You should also confront the risk of constructors misinterpreting this report. Do so by retaining your geotechnical engineer to participate in prebid and preconstruction conferences and to perform construction observation.
Give Constructors a Complete Report and GuidanceSome owners and design professionals mistakenly believe they can shift unanticipated-subsurface-conditions liability to constructors by limiting the information they provide for bid preparation. To help prevent the costly, contentious problems this practice has caused, include the complete geotechnical-engineering report, along with any attachments or appendices, with your contract documents, but be certain to note conspicuously that you’ve included the material for informational purposes only. To avoid misunderstanding, you may also want to note that “informational purposes” means constructors have no right to rely on the interpretations, opinions, conclusions, or recommendations in the report, but they may rely on the factual data relative to the specific times, locations, and depths/elevations referenced. Be certain that constructors know they may learn about specific project requirements, including options selected from the report, only from the design drawings and specifications. Remind constructors that they may
perform their own studies if they want to, and be sure to allow enough time to permit them to do so. Only then might you be in a position to give constructors the information available to you, while requiring them to at least share some of the financial responsibilities stemming from unanticipated conditions. Conducting prebid and preconstruction conferences can also be valuable in this respect.
Read Responsibility Provisions CloselySome client representatives, design professionals, and constructors do not realize that geotechnical engineering is far less exact than other engineering disciplines. That lack of understanding has nurtured unrealistic expectations that have resulted in disappointments, delays, cost overruns, claims, and disputes. To confront that risk, geotechnical engineers commonly include explanatory provisions in their reports. Sometimes labeled “limitations,” many of these provisions indicate where geotechnical engineers’ responsibilities begin and end, to help others recognize their own responsibilities and risks. Read these provisions closely. Ask questions. Your geotechnical engineer should respond fully and frankly.
Geoenvironmental Concerns Are Not CoveredThe personnel, equipment, and techniques used to perform an environmental study – e.g., a “phase-one” or “phase-two” environmental site assessment – differ significantly from those used to perform a geotechnical-engineering study. For that reason, a geotechnical-engineering report does not usually relate any environmental findings, conclusions, or recommendations; e.g., about the likelihood of encountering underground storage tanks or regulated contaminants. Unanticipated subsurface environmental problems have led to project failures. If you have not yet obtained your own environmental information, ask your geotechnical consultant for risk-management guidance. As a general rule, do not rely on an environmental report prepared for a different client, site, or project, or that is more than six months old.
Obtain Professional Assistance to Deal with Moisture Infiltration and MoldWhile your geotechnical engineer may have addressed groundwater, water infiltration, or similar issues in this report, none of the engineer’s services were designed, conducted, or intended to prevent uncontrolled migration of moisture – including water vapor – from the soil through building slabs and walls and into the building interior, where it can cause mold growth and material-performance deficiencies. Accordingly, proper implementation of the geotechnical engineer’s recommendations will not of itself be sufficient to prevent moisture infiltration. Confront the risk of moisture infiltration by including building-envelope or mold specialists on the design team. Geotechnical engineers are not building-envelope or mold specialists.
Copyright 2016 by Geoprofessional Business Association (GBA). Duplication, reproduction, or copying of this document, in whole or in part, by any means whatsoever, is strictly prohibited, except with GBA’s specific written permission. Excerpting, quoting, or otherwise extracting wording from this document is permitted only with the express written permission of GBA, and only for purposes of scholarly research or book review. Only members of GBA may use this document or its wording as a complement to or as an element of a report of any
kind. Any other firm, individual, or other entity that so uses this document without being a GBA member could be committing negligent
Telephone: 301/565-2733e-mail: [email protected] www.geoprofessional.org
SAMPLE
OWNER-CONTRACTOR AGREEMENT
THIS AGREEMENT is made this ____ day of ________ 2020 by and between the
Brunswick County Board of Education (herein referred to as the Owner), whose mailing address is
35 Referendum Dr., Bolivia, NC 28422 and _______________ (herein referred to as the
AContractor@), whose mailing address is __________________, North Carolina ______.
Correspondence, submittals, and notices relating to or required under this Agreement shall be sent
in writing to the above addresses unless either party is notified in writing by the other of a change
in address.
WITNESSETH:
WHEREAS, it is the intent of the Owner to obtain the services of the Contractor in
connection with ____________________: and
WHEREAS, the Contractor desires to perform such construction in accordance with the
terms and conditions of this Agreement.
NOW, THEREFORE, in consideration of the promises made herein and other good and
valuable consideration, the following terms and conditions are hereby mutually agreed to, by and
between the Owner and Contractor:
1. Scope of Services. The Contractor shall perform the Work in accordance with the terms
of this Agreement, any plans and specifications prepared for this Project, and the
description of services attached to this Agreement as Exhibit A, all of which are
incorporated into and made a part of this Agreement. The Contractor agrees that any
general terms and conditions that are attached to Exhibit A that are inconsistent with this
Agreement shall not be applicable to this Agreement, and any such provisions shall be
deemed null and void.
a. The Contractor shall provide and pay for all materials, tools, equipment, and labor, and
shall perform all other acts and supply all other services and things necessary to fully
and properly perform and complete the Work as required by this Agreement.
b. The Contractor shall perform the Work in compliance with all governmental laws and
regulations, including all applicable local, state and federal rules and regulations.
c. The Contractor shall, unless otherwise specified, supply and pay for all labor,
transportation, materials, tools, apparatus, lights, power, fuel, sanitary facilities, and
incidentals necessary for the completion of his work, and shall install, maintain and
remove all equipment of the construction, other utensils or things, and be responsible
for the safe, proper and lawful construction, maintenance and use of same, and shall
construct in the best and most workmanlike manner, a complete job and everything
incidental thereto, as shown on the plans, stated in the specifications, or reasonably
implied therefrom, all in accordance with the Agreement documents.
Small Project Construction Contract Form v.2
d. All materials shall be new and of quality specified, except where reclaimed material is
authorized herein and approved for use. Workmanship shall at all times be of a grade
accepted as the best practice of the particular trade involved, and as stipulated in
written standards of recognized organizations or institutes of the respective trades
except as exceeded or qualified by the specifications.
e. Products are generally specified by ASTM or other reference standard and/or by
manufacturer's name and model number or trade name. When specified only by
reference standard, the Contractor may select any product meeting this standard, by
any manufacturer. When several products or manufacturers are specified as being
equally acceptable, the Contractor has the option of using any product and
manufacturer combination listed. However, the Contractor shall be aware that the cited
examples are used only to denote the quality standard of product desired and that they
do not restrict bidders to a specific brand, make, manufacturer or specific name; that
they are used only to set forth and convey to bidders the general style, type, character
and quality of product desired; and that equivalent products will be acceptable.
Substitution of materials, items or equipment of equal or equivalent design shall be
submitted to the architect or engineer for approval or disapproval; such approval or
disapproval shall be made by the architect or engineer prior to the opening of bids.
f. The Contractor shall designate a foreman/superintendent who shall direct the work.
g. If at any time during the construction and completion of the work covered by this
Agreement, the conduct of any workman be adjudged a nuisance to the Owner or
considered detrimental to the work, the Contractor shall order such parties removed
immediately from the Owner’s property.
h. The Contractor shall keep the sites and surrounding area reasonably free from rubbish
at all times and shall remove debris from the site from time to time or when directed to
do so by the Owner. Before final inspection and acceptance of the Project, the
Contractor shall thoroughly clean the sites, and completely prepare the Project and site
for use by the Owner.
i. Temporary electricity and water shall be arranged by the Contractor at the Contractor’s
expense.
2. Compensation. Provided that the Contractor shall strictly and completely perform all of
its obligations under this Agreement, the Owner shall pay the Contractor the amount of
_______ dollars ($______) (herein referred to as the AContract Sum@). No compensation
shall be paid for any additional work that is not approved in advance by the Owner. One
progress payment, if any, may be made by the Owner to the Contractor only after
certification that the Work is complete and will be based upon the completion of the
identified interim work agreed to by the Owner. Under no circumstances will the Owner
make more than one interim payment. The Owner will retain five percent (5%) of the
amount of any progress payment and/or the Contract Sum until all of the Work is finally
completed and accepted, whether or not the Owner has occupied any or all of the Project
Small Project Construction Contract Form v.2
before such time. Final payment will be withheld until the Contractor’s North Carolina
sales and use tax report is received. The report shall accurately list any and all sales and
use tax paid on materials for the entire Project.
3. Time. The Contractor shall commence the Work promptly upon the date established in
the Notice to Proceed, the date of this Agreement, or such other date as may be established
by the Owner. Time is of the essence. The Contractor shall perform work in a timely
manner.
4. Codes, Permits and Inspections.
a. The Contractor shall obtain the required permits, give all notice and comply with all
laws, ordinances, codes, rules and regulations bearing on the conduct of the work under
this Agreement. If the Contractor observes that the drawings and specifications are at
variance therewith, he shall promptly notify the architect or engineer in writing. If the
Contractor performs any work knowing it to be contrary to such laws, ordinances,
codes, rules and regulations, and without such notice to the Owner, he shall bear all
cost arising therefrom.
b. All work under this Agreement shall conform to the North Carolina State Building
Codes and other state and national codes as are applicable.
5. Safety Requirements.
a. The Contractor shall be responsible for the entire site and the construction of the same
and provide all the necessary protections as required by laws or ordinances governing
such conditions and as required by the Owner, architect or engineer. He shall be
responsible for any damage to the Owner's property or that of others on the job, by
himself, his personnel or his subcontractors, and shall make good such damages. He
shall be responsible for and pay for any claims against the Owner arising from such
damages.
b. The Contractor shall adhere to the rules, regulations and interpretations of the North
Carolina Department of Labor relating to Occupational Safety and Health Standards
for the Construction Industry (Title 29, Code of Federal Regulations, Part 1926
Construction and Part 1910 General Industry).
c. The Contractor shall provide all necessary safety measures for the protection of all
persons on the work, including the requirements of the AGC Accident Prevention
Manual in Construction as amended, and shall fully comply with all state laws or
regulations and North Carolina State Building Code requirements to prevent accident
or injury to persons on or about the location of the work. He shall clearly mark or post
signs warning of hazards existing, and shall barricade excavations and similar hazards.
He shall protect against damage or injury resulting from falling materials and he shall
maintain all protective devices and signs throughout the progress of the work.
6. Warranties. The Contractor guarantees and warrants to the Owner all Work as follows:
that all materials and equipment furnished under this Agreement will be new and the best
of its respective kind unless otherwise specified; that all Work will be of good quality in
Small Project Construction Contract Form v.2
accordance with the industry standards for reputable contractors; that the Work will be free
of omissions and faulty, poor quality, imperfect and defective material or workmanship;
that the Work, including but not limited to, mechanical and electrical machines, devices
and equipment, shall be fit and fully usable for its intended and specified purpose and shall
operate satisfactorily with ordinary care; that the products or materials incorporated in the
Work will not contain asbestos; and that all agents or employees of Contractor who will
provide services under this Agreement will be fully qualified, possess any requisite
licenses, and otherwise be legally entitled to perform the services provided; and that the
person(s) executing this Agreement on behalf of Contractor have authority to do so as an
official, binding act of Contractor.
If, within one year after the Date of Substantial Completion of the Work or designated
portion thereof or within one year after acceptance by the Owner of designated equipment
or within such longer period of time as may be prescribed by law or by the terms of any
applicable special warranty required by this Agreement, any of the Work is found to be
defective, not in accordance with this Agreement, or not in accordance with the guarantees
and warranties specified in this Agreement, the Contractor shall correct it within five (5)
working days or such other period as mutually agreed, after receipt of a written notice from
the Owner to do so. For items which remain incomplete or uncorrected on the date of
Substantial Completion, the one year warranty shall begin on the date of Final Completion
of the Work.
7. Contractor-Subcontractor Relationships. The Contractor agrees that the terms of these
Agreement documents shall apply equally to a subcontractor as to the Contractor, and that
the subcontractor is bound by those terms as an agent of the Contractor.
8. Hold Harmless. The Contractor shall indemnify and hold the Owner harmless from and
against any and all losses, liabilities, claims, lawsuits, judgments, and demands
whatsoever, including costs of investigation (including reimbursement of reasonable legal
fees and all costs) caused solely by any negligent act or omission or intentional
wrongdoing of the Contractor or its agents, employees or subcontractors, or caused solely
by the maintenance, presence, use, location or removal of any equipment or other property
owned or operated by the Contractor or its agents, employees or subcontractors. The
parties agree that this indemnification clause is an “evidence of indebtedness” for purpose
of N. C. Gen. Stat. § 6-21.2. The Owner shall not be responsible for any damage to the
Contractor=s property, business, agents or employees, unless said damage is due solely to
the negligence of Owner.
9. Insurance. The Contractor shall obtain and maintain in effect during the term of this
Agreement, general liability and automobile liability insurance in which the Owner and the
Contractor shall each be named as insured parties, which insurance shall protect the Owner
and the Contractor from claims in an amount not less than $1,000,000 for personal injury,
including death, to any one person and in an amount not less than $1,000,000 for any one
occurrence, and from claims for property damages in an amount of not less than
$1,000,000 for each occurrence arising from any act or omission of Contractor, its agents,
employees or subcontractors. The Contractor shall obtain and maintain in effect during
the term of this Agreement, a policy of workers compensation liability insurance in which
Small Project Construction Contract Form v.2
the policy shall protect the Owner and the Contractor from claims in an amount not less
than the statutory amount.
The Contractor shall promptly furnish to the Owner certificates of insurance evidencing
such insurance coverage. Insurance required hereunder shall be maintained by insurance
companies properly licensed by the Insurance Department of the State of North Carolina
and rated A or better by Best Insurance Guide.
10. Termination for Convenience. The Board may terminate this Agreement at any time in its
complete discretion upon twenty (20) days written notice. In the event of a termination
for convenience, all finished or unfinished work and materials pursuant to this Agreement
shall be turned over to the Board and become its property. If the Agreement is terminated
by the Board in accordance with this section, the Board shall only be responsible for paying
Contractor for all Work performed and accepted and all materials delivered to the site as of
the date of termination.
11. Termination by the Owner for Cause. The Owner may terminate the Agreement upon five
(5) days written notice if the Board is dissatisfied with the quality or timeliness of the Work
performed. If the Owner becomes dissatisfied with the Work, the Owner may without
prejudice to any other rights or remedies of the Owner and after giving the Contractor five
days’ written notice, terminate employment of the Contractor and may:
1. Exclude the Contractor from the site and take possession of all materials,
equipment, tools, and construction equipment and machinery thereon owned by
the Contractor;
2. Accept assignment of any subcontracts; and
3. Finish the Work by whatever reasonable method the Owner may deem
expedient. Upon written request of the Contractor, the Owner shall furnish to
the Contractor a detailed accounting of the costs incurred by the Owner in
finishing the Work.
If the Owner terminates the whole or any part of the Work, the Owner may procure, upon
such terms and in such manner as the Owner may deem appropriate, supplies or services
similar to those so terminated, and the Contractor shall be liable to the Owner for any
excess costs for such similar supplies or services. The Contractor shall continue the
performance of the Agreement to the extent not terminated hereunder.
When the Owner terminates the Agreement, the Contractor shall not be entitled to receive
further payment until the Work is finished. If the unpaid balance of the Contract Sum
exceeds costs of finishing the Work, including compensation for the Architect’s and legal
services and expenses made necessary thereby, and other damages incurred by the Owner
and not expressly waived, such excess shall be paid to the Contractor. If such costs and
damages exceed the unpaid balance, the Contractor shall pay the difference to the Owner.
The amount to be paid to the Contractor or Owner, as the case may be, shall be certified by
the Architect and this obligation for payment shall survive this Agreement.
Small Project Construction Contract Form v.2 6
12. Lunsford Act/Criminal Background Checks. The Contractor shall conduct or arrange to
have conducted at its own expense sexual offender registry checks on each of its owners,
employees, agents, or subcontractors (“contractual personnel”) who will engage in any
service on or delivery of goods to school system property or at a school-system sponsored
event, except checks shall not be required for individuals who are solely delivering or
picking up equipment, materials, or supplies at: (1) the administrative office or loading
dock of a school; (2) non-school sites; (3) schools closed for renovation; or (4) school
construction sites. The checks shall include at a minimum checks of the State Sex
Offender and Public Protection Registration Program, the State Sexually Violent Predator
Registration Program, and the National Sex Offender Registry (“the Registries”). For the
Contractor’s convenience only, all of the required registry checks may be completed at no
cost by accessing the United States Department of Justice Sex Offender Public Website at
http:// www. nsopw.gov/. The Contractor shall provide certification that the registry
checks were conducted on each of its contractual personnel providing services or
delivering goods under this Agreement prior to the commencement of such services or the
delivery of such goods (Registry Check Certification Form – Exhibit B). The Contractor
shall conduct a current initial check of the registries (a check done more than 30 days prior
to the date of this Agreement shall not satisfy this contractual obligation). In addition,
Contractor agrees to conduct the registry checks and provide a supplemental certification
before any additional contractual personnel are used to deliver goods or provide services
pursuant to this Agreement. Contractor further agrees to conduct annual registry checks
of all contractual personnel and provide annual certifications at each anniversary date of
this Agreement. Contractor shall not assign any individual to deliver goods or provide
services pursuant to this Agreement if said individual appears on any of the listed
registries. Contractor agrees that it will maintain all records and documents necessary to
demonstrate that it has conducted a thorough check of the registries as to each contractual
personnel, and agrees to provide such records and documents to the school system upon
request. Contractor specifically acknowledges that the school system retains the right to
audit these records to ensure compliance with this section at any time in the school
system’s sole discretion. Failure to comply with the terms of this provision shall be
grounds for immediate termination of the Agreement. In addition, the Owner may
conduct additional criminal records checks at the Owner’s expense. If the school system
exercises this right to conduct additional criminal records checks, Contractor agrees to
provide within seven (7) days of request the full name, date of birth, state of residency for
the past ten years, and any additional information requested by the school system for all
contractual personnel who may deliver goods or perform services under this Agreement.
Contractor further agrees that it has an ongoing obligation to provide the school system
with the name of any new contractual personnel who may deliver goods or provide services
under the Agreement. The Owner reserves the right to prohibit any contractual personnel
of Contractor from delivering goods or providing services under this Agreement if the
Owner determines, in its sole discretion, that such contractual personnel may pose a threat
to the safety or well-being of students, school personnel or others.
Small Project Construction Contract Form v.2 7
13. Governing Law. This Agreement and the relationship of the parties shall be governed by
the laws of the state of North Carolina.
14. Entire Agreement. All of the representations and obligations of the parties are contained
herein, and no modification, waiver or amendment of this Agreement or of any of its
conditions or provisions shall be binding upon a party unless in writing signed by that
party. The waiver by any party of a breach of any provision of this Agreement shall not
operate or be construed as a waiver of any subsequent breach of that provision by the same
party, or of any other provision or condition of the Agreement.
15. Severability. If any section, subsection, term or provision of this Agreement or the
application thereof to any party or circumstance shall, to any extent, be invalid or
unenforceable, the remainder of said section, subsection, term or provision of the
Agreement or the application of the same to parties or circumstances other than those to
which it was held invalid or unenforceable, shall not be affected thereby and each
remaining section, subsection, term or provision of this Agreement shall be valid or
enforceable to the fullest extent permitted by law.
16. Compliance with Applicable Laws. Contractor shall comply with all applicable laws and
regulations in providing services under this Agreement. In particular, Contractor shall not
employ any individuals to provide services to the Owner who are not authorized by federal
law to work in the United States. Contractor represents and warrants that it is aware of
and in compliance with the Immigration Reform and Control Act and North Carolina law
(Article 2 of Chapter 64 of the North Carolina General Statutes) requiring use of the
E-Verify system for employers who employ twenty-five (25) or more employees and that it
is and will remain in compliance with these laws at all times while providing services
pursuant to this Agreement. Contractor shall also ensure that any of its subcontractors (of
any tier) will remain in compliance with these laws at all times while providing
subcontracted services in connection with this Agreement. Contractor is responsible for
providing affordable health care coverage to all of its full-time employees providing
services to the School System. The definitions of “affordable coverage” and “full-time
employee” are governed by the Affordable Care Act and accompanying IRS and Treasury
Department regulations.
17. Restricted Companies List. Contractor represents that as of the date of this Agreement,
Contractor is not included on the Final Divestment List created by the North Carolina State
Treasurer pursuant to N.C. Gen. Stat. § 147-86.58. Contractor also represents that as of
the date of this Agreement, Contractor is not included on the list of restricted companies
determined to be engaged in a boycott of Israel created by the North Carolina State
Treasurer pursuant to N.C. Gen. Stat. § 147-86.81.
18. Anti-Nepotism. Contractor warrants that, to the best of its knowledge and in the exercise
of due diligence, none of its corporate officers, directors, or trustees and none of its
employees who will directly provide services under this Agreement are immediate family
Small Project Construction Contract Form v.2 8
members of any member of the Brunswick County Board of Education or of any principal
or central office staff administrator employed by the Board. For purposes of this provision,
“immediate family” means spouse, parent, child, brother, sister, grandparent, or
grandchild, and includes step, half, and in-law relationships. Should Contractor become
aware of any family relationship covered by this provision or should such a family
relationship arise at any time during the term of this Agreement, Contractor shall
immediately disclose the family relationship in writing to the Superintendent of the
Schools. Unless formally waived by the Board, the existence of a family relationship
covered by this Agreement is grounds for immediate termination by Owner without further
financial liability to Contractor.
19. Applicable School Board of Education Policies. Contractor acknowledges that the
Brunswick County Board of Education has adopted policies governing conduct on School
System property and agrees to abide by any and all relevant Board policies while on School
System property. The Contractor acknowledges that Board’s policies are available on the
School System’s website.
20. Exhibits.
Exhibit A: Scope of Services
Exhibit B: Sexual Registry Check Certification Form
Small Project Construction Contract Form v.2 9
IN WITNESS WHEREOF, the Owner has caused these presents to be signed and the
Contractor has caused these presents to be signed by a person with the authority to enter this
Agreement, as hereinafter attested, all as of the day and year first above written.
BRUNSWICK COUNTY BOARD OF EDUCATION
By: _____________________________________________________________(Seal)
__________________, Chairperson
Attest: _____________________________________________________________(Seal)
__________________, Superintendent
[INSERT CORPORATE NAME OF CONTRACTOR]
By: ____________________________________________________________(Seal)
[INSERT NAME OF CORPORATE PRESIDENT OR VICE PRESIDENT]
Attest: _____________________________________________________________(Seal)
[INSERT NAME OF CORPORATE SECRETARY]
This instrument has been preaudited in the manner required by the School Budget and Fiscal
Control Act.
________________________________________________
(Date)
________________________________________________
(Signature of finance officer)
BUDGET CODE: _____________________
Small Project Construction Contract Form v.2 10
SAMPLE
Sexual Offender Registry Check Certification Form
Check the appropriate box to indicate the type of check:
□ Initial
□ Supplemental
□ Annual
I, _______________ (insert name), ______________ (insert title) of ____________ (insert
company name) hereby certify that I have performed all of the required sexual offender registry
checks required under this Agreement for all contractual personnel (employees, agents, ownership
personnel, or contractors ) who may be used to deliver goods or provide services under this
Agreement, including the North Carolina Sex Offender and Public Protection Registration
Program, the North Carolina Sexually Violent Predator Registration Program, and the National
Sex Offender Registry. I further certify that none of the individuals listed below appears on any
of the above-named registries and that I will not assign any individual to deliver goods or perform
services under this Agreement if said individual appears on any of the sex offender registries. I
agree to maintain all records and documents associated with these registry checks, and that I will
provide such records and documents to the school system upon request. I specifically
acknowledge that the school system retains the right to audit these records to ensure compliance
with this section at any time in the school system’s sole discretion. I acknowledge that I am
required to perform these checks and provide this certification form before any work is performed
under the Agreement (initial check), any time additional contractual personnel may perform work
under the Agreement (supplemental check), and at each anniversary date of the Agreement (annual
check).
Contractual Personnel Names Job Title
1. ________________________ ________________________
2. ________________________ ________________________
3. ________________________ ________________________
4. ________________________ ________________________
5. ________________________ ________________________
(attach additional page(s) if needed)
I attest that the forgoing information is true and accurate to the best of my knowledge.
_____________________ (print name) _____________________ (signature)
_____________________ (title) ______________________ (date)