Bruno Altieri 21-22 Jan. 2009
http://herschel.esac.esa.int/ # 1
Pointing calibration plan
Bruno Altieri (HSC)
PACS PV phase reviewMPE, January 2008
Bruno Altieri 21-22 Jan. 2009
http://herschel.esac.esa.int/ # 2
Pointing Working Group• A pointing working group was set-up early 2008, by the
SciOps WG between Project, MOC (FD), HSC and ICCs.
• A pointing calibration plan was issued– T. Marston, HERSCHEL-HSC-DOC-1139, v1.0, 5/8/2008– Herschel relies on PACS (blue) photometer for spacecraft
pointing performance assessment
• The plan was later de-scoped to only use Star Tracker 1
Bruno Altieri 21-22 Jan. 2009
http://herschel.esac.esa.int/ # 3
Pointing calibration plan• Pointing cal. plan became part of PV phase to a large
fraction, hence now in PACS PV plan– But time budget counted separately– Obviously must be scheduled as early as possible.– Preceded by in commissioning :
• ACMS commissioning in CoP• Photometer bias set-up (BOLO_BIAS_2)• PACS search scan map (CoP)• Check of derived SIAM update (CoP)
• Total estimated time : ~30 hours– In the PVPhotFPG program– Does not include 7.5 hours of spectrometer FPG.
Bruno Altieri 21-22 Jan. 2009
http://herschel.esac.esa.int/ # 4
Pointing calibration CoP• Initial search map
– 40’x40’ scan map: wide search to include STR structure bending, M2 misalignment ..
– M51 ? ISO first light• Advantages:
– Visible 23/04 – 09/08– Hint about orientation
• Drawback– Not point-like, but companion is !
• Derive SIAM• Check SIAM update
– Standard PS mode– HIP 21479 (always visible) 140 Jy
• Already a scan map at the end of BOLO_BIAS_2 ?
Bruno Altieri 21-22 Jan. 2009
http://herschel.esac.esa.int/ # 5
Pointing calibration PV• Pointing cal. plan became part of PV phase to a large
fraction, hence now in PACS PV plan– But time budget counted separately– Obviously must be scheduled as early as possible.– Preceded by in commissioning :
• ACMS commissioning in CoP• Photometer bias set-up (BOLO_BIAS_2)• PACS search scan map (CoP)• Check of derived SIAM update (CoP)
• Total estimated time : ~30 hours– In the PVPhotFPG program– Does not include 7.5 hours of spectrometer FPG.
Bruno Altieri 21-22 Jan. 2009
http://herschel.esac.esa.int/ # 6
Pointing calibration• Stars sample selected by Markus Nielbock
– PACS pointing calibration stars (PICC-MA-TN-003)
• Measure APE statistically with “many” stars– 40 stars, 5mn AORs, for standard SAA range [-10,30]– Duration :~4 hours
• Tune SIAM• Explore the full SAA range after a long stabilisation
– [-20,-10]– [-30, -20]
• SRPE measurement assessment,– Making use of on-ground gyro propagation
Bruno Altieri 21-22 Jan. 2009
http://herschel.esac.esa.int/ # 7
Pointing observation plan (1)
Bruno Altieri 21-22 Jan. 2009
http://herschel.esac.esa.int/ # 8
Pointing observation plan (2)
Bruno Altieri 21-22 Jan. 2009
http://herschel.esac.esa.int/ # 9
Tests and CAP• SOVT-1: standard AORs• SOVT-2
– OD 60, 63 & 64– Only looked at OD 60 so far
• Dithering was not put (gain?)
• SIMS-1– OD 65 already delivered (standard AORs)
• CAP from Dieter• Tested 2D gaussian fitting in dp-pacs
– Though not as robust as in IDL